Schedule of Tariffs *Tariff Details *LT Service Charges *Miscellaneous Charges Karthik Arumugham Final Year BE EEE July 15, 2009

Page |1 TARIFF RATES AS APPROVED BY THE T.N.E.R.C. WITH EFFECT FROM 16-3-2003, IN TARIFF ORDER DATED 15-3-2003 HIGH TENSION SUPPLY

TARIFF

Demand Energy charges Charges Rupees per Paise per KVA per KWH (unit) month

HT TARIFF I-A HT Industries including Railway traction

350

300

TARIFF II-A Recognised Educational Institutions

350

200

TARIFF II-B Actual place of Public worship.

280

125

TARIFF III Commercial and all categories of consumers not 500 covered under HT Tariff I, II, IV & V

300

TARIFF IV Lift Irrigation, Cooperative Societies for Agriculture 50 TARIFF V Supply to Pondicherry State

300

LT Tariff IA Domestic Tariff Consumption Slab range Description in KWHr (Units) and billing period (One or two months) LT Tariff IA Consumption up to 25 units Domestic per month or 50 units for two months Consumption from 26 units to 50 units per month/ from 51 units to 100 units for two months Consumption from 51 units to 100 units per month/ from 101 units to 200 units for two months Consumption from 101 units to 300 units per month/ from 201 units to 600 units for two months Consumption above 300 units per month/600 units for two months Tariff -IB – Hut Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months) LT Tariff IV Till installation of energy Agriculture meter On installation of energy meter

Fixed charges per service for two months NIL

Energy Charges Paise/Kwhr (unit)

Monthly Minimum in Rupees

110 NIL 130

Rs.10/-

260 20 per month or 40 for two months

Rs.10/-

350

Rs.10/-

475

Fixed charges per service for two months

Energy Charges Paise/Kwhr (unit)

Monthly Minimum in Rupees

Rs.10 per month NIL

50

10 per month or 20 for two months

Page |2 Tariff -IC - LT bulk supply for railway colonies, plantation worker colonies, defense colonies, police quarters. Tariff Description Fixed charges Energy Charges Monthly Minimum in Rupees per service for Paise/Kwhr (unit) two months LT bulk supply for Railway NIL 350 50 per month or 100 for two months Colonies, plantation worker colonies, defense colonies, police quarters. LT Tariff II-A : Street Light and Water supply for Panchayats, Municpalities and Corporations, TWAD Board, CMWSB Tariff Fixed Energy Monthly Minimum in Rupees Description charges per Charges service for Paise/Kwhr two months (unit) LT Tariff II-A : Village/Town Panchayat 50 per month or 100 for two Street Light NIL 340 months and Water supply 50 per month or 100 for two Municipality/ NIL 350 months Corporation LT Tariff II-B : Educational Institutions Tariff Fixed charges per service Description for two months LT Tariff II-B Recognised Educaitonal Institutions

Rs.40/-

LT Tariff II-C : Actual Places of worship Tariff Fixed charges per service Description for two months LT Tariff II-C Actual places of worship

Rs.20/-

Energy Charges Paise/Kwhr (unit)

Consumption from 251 units to 750 Units per month / 501 units to 1500 units for

50 per month or 100 for two months

440

Energy Charges Paise/Kwhr (unit)

Monthly Minimum in Rupees

50 per month or 100 for two months

300

LT Tariff III-A(1) : Cottage and Tiny industries Tariff Consumption Slab range in Fixed Description KWHr (Units) and billing charges per period (One or two months) service for two months LT Tariff III-A Consumption from 0 units to (1) 250 units per month/ 0 Cottage and units to 500 units for two Tiny industry months Rs.60/-

Monthly Minimum in Rupees

Energy Charges Paise/Kwhr (unit)

Monthly Rupees

Minimum

in

60 per month or 120 for two months 180

60 per month or 120 for two months Rs.60/-

270

Page |3 two months Consumption From 751 units and above per month / 1501 units and above for two months LT Tariff III-A(2) : Power looms Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months) LT Tariff III-A (2)

Fixed charges per service for two months

Energy Charges Paise/Kwhr (unit)

LT Tariff III-B: For industries not covered Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months)

Consumption from 0 units to 750 units per month/ 0 units to 1500 units for two months Consumption from 751 units and above per month/ 1501 units and above for two months

LT Tariff IV: Agriculture Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months)

60 per month or 120 for two months

Monthly Rupees

Minimum

in

60 per month or 120 for two months Rs.60/-

Consumption from 251 units to 750 Units per month / 501 units to 1500 units for two months Consumption from 751 units and above per month / 1501 units and above for two months

LT Tariff IV Agriculture

310

Consumption from 0 units to 250 units per month/ 0 units to 500 units for two months

Power looms

LT Tariff III-B Industries

Rs.60/-

140 60 per month or 120 for two months

Rs.60/-

225

Rs.60/-

250

60 per month or 120 for two months

under LT Tariff III-A (1) & III -A(2) Fixed Energy Monthly Minimum charges Charges Rupees per service Paise/Kwhr for two (unit) months

Rs.60/-

400

Rs.60/-

470

Fixed charges per service for two months

Energy Charges Paise/Kwhr (unit)

Till installation of energy meter

Rs.250 per HP per Annum

On installation of energy meter

NIL

20

LT Tariff V: Commercial and Others not covered under Tariff I to IV Tariff Consumption Slab range in Fixed Energy Description KWHr (Units) and billing charges per Charges

in

Rs.40/KW or part thereof of the contracted load.

Monthly Rupees

Minimum

in

25 per month or 50 for two months

Monthly Rupees

Minimum

in

Page |4

LT Tariff V Commercial

period (One or two months) Consumption from 0 units to 100 units per month/ 0 units to 200 units for two months Consumption from 101 units and above per month/ 201 units and above for two months

service for two months

40 per month or 80 for two months Rs.60/-

530 40 per month or 80 for two months

Rs.60/-

LT Tariff VI: Temporary supply Tariff Description Description LT Tariff VI

Paise/Kwhr (unit)

Supply to temporary activities and construction activities other than residential building/ Residential complexes for combined lighting and power loads*

580

Energy Charges Paise/Kwhr (unit)

Minimum in Rupees

700 50 per KW or part thereof per day

700 Lavish illumination *For LT supply for construction activities of residential building/complex, LT Tariff V is applicable.

Reduced tariff with effect from 16-6-2004 Tariff Consumption Slab range in Fixed Description KWHr (Units) and biling charges per

Energy Charges

Monthly Rupees

Minimum

in

Page |5 period (One or two months)

service for two months For consumers consuming up to 100 units bi-monthly LT Tariff IA Consumption up to 25 units NIL Domestic per month or 50 units for two months Consumption from 26 units to NIL 50 units per month/ from 51 units to 100 units for two months For consumers consuming more than 100 units bi-monthly Consumption up to 25 units per month or 50 units for two NIL months Consumption from 26 units to 50 units per month/ from 51 units to 100 units for two NIL months Consumption from 51 units to 100 units per month/ from 101 units to 200 units for two Rs.10/months Consumption from 101 units to 300 units per month/ from 2011 units to 600 units for Rs.10/two months Consumption above 300 units per month/600 units for two Rs.10/months Tariff -IB - Hut Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months)

LT Tariff I-B Huts in panchayats

Fixed charges per service for two months

Paise/Kwhr (unit)

65

20 per month or 40 for two months

75

20 per month or 40 for two months

75

20 per month or 40 for two months 20 per month or 40 for two months

85 20 per month or 40 for two months 150 20 per month or 40 for two months 220

305

Energy Charges Paise/Kwhr (unit)

20 per month or 40 for two months

Monthly Rupees

Minimum

in

Minimum

in

Till installation of energy meter Free with effect from1-4-2004 On installation of energy meter

LT Tariff II-A : Street Lights and Water Supply With effect from 12-4-2007 Tariff Fixed Description charges per service for two months LT Tariff II-A Village Panchayat Street Lights NIL and Water supply Town Panchayat NIL Municipality/ Corporation

NIL

Energy Charges Paise/Kwhr (unit)

300 330 330

Monthly Rupees

50 per month or 100 for two months

Page |6

LT Tariff II-C : Actual Places of worship With effect from 1-1-2006 Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months) LT Tariff II-C Actual places of worship

Consumption up to 60 units per month or 120 units for two months Consumption above 60 units per month/120 units for two months

LT Tariff III-A(2) : Power loom With effect from 1-8-2006 Tariff Consumption Slab range in Description KWHr (Units) and billing period (One or two months) LT Tariff III-A (2)

Fixed charges per service for two months

Energy Charges Paise/Kwhr (unit)

Rs.10/-

150

Rs.10/-

300

Fixed charges per service for two months

Energy Charges Paise/Kwhr (unit)

Monthly Rupees

Minimum

in

50 per month or 100 for two months

Monthly Rupees

Minimum

in

Consumption from 0 units to 250 units per month/ 0 units to 500 units for two months

Power loom

Free Consumption from 251 units to 500 Units per month / 501 units to 1000 units for two months Consumption from 501 units to 750 per month / 1001 units to 1500 units for two months Consumption from 751 units and above per month / 1501 units and above for two months

LT Tariff IV: Agriculture Tariff Consumption Slab range Description in KWHr (Units) and billing period (One or two months) LT Tariff IV Till installation of energy Agriculture meter On installation of energy meter

Rs.30/-

100

Rs.30/-

225

Rs.30/-

250

Fixed charges per service for two months

Energy Charges Paise/Kwhr (unit)

60 per month or 120 for two months

Monthly Rupees

Minimum

in

Free for Farmers other than SFS with effect from 1-42004 Free for SFS farmers with effect from 1-4-2006

Tamil Nadu Electricity Board

Page |8

Different Charges for LT Services to be Paid from 01.10.2004 as per TNERC Order No. 41/2003 SL . N O

Tariff

New Service Connection * Registration 1 Fees Service 2 Connection Charges Meter 3 caution Deposit Development 4 Charges Current 5 Consumption Deposit Meter Board shifting Registration 1 Fees 2 Testing Fees Meter Board 3 shifting

IA(Domestic )

II - A(St. Light)

II - A(Over Head Tank)

I Ph III I Pha III I Phas III ase Phase se Phase e Phase

50

50

50

250 500 250

50

50

50

500

250

500

II - C(Place of Worship)

I Ph III I Phas III ase Phase e Phase

50

50

250 500

III - A1(Cottage Industries) I Phase

III Phase

III A2(Power Loom)

III IV(Agricu V(Commerci B(Industrial lture) al) )

I III I Ph III Phase Phase ase Phase

50

50

50

50

50

250

500

250

500

250

2500

700

2500

50

50

50

50

I Ph III ase Phase

50

50

250 500

700 2500 700 2500

Nil

700 2500

400/ 200/K 400 200/ 400/s 200/K 200/K 400/ 200/K 200/ 400/sc NA sc W /sc KW c W W sc W KW

Nil

400 200/ /sc KW

2500 700 2500 700

500 250 500

III Phase

Nil

700 2500 700 2500 700 400 1400 300 Per /sc /sc Location

II - B

200 600/ 200/ 600/ 200/ 600/K 200 600/ 200/s 600/K 600/K 200/ 600/K 200 600/ 200 600/ 200/sc 125/HP /sc KW sc KW sc W /sc KW c W W sc W /sc KW /sc KW

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

150

150

150

150

150

150

150

150

60

60

60

60

60

60

60

60

150 150 150

Disconnectio n/ 4 60 Reconnection (OH)/cut out

60

60

150 150

60

60

150 150 150

60

60

60

150 150

60

60

Page |8 Reduction of Load Registration 1 50 Fees 2 Testing Fees 75

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

75

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

50

75

75 200/K W

75

75 200/K W

75

75 75 75 200/K 200/ Nil Nil W KW

75

75

Additional Load Registration 1 Fees 2 Testing Fees Development 3 Charges Current 4 Consumption Deposit Tariff Change

50

50

75 75 75 400/ 300/Per Nil sc Location

75

1 Testing Fees

75

50 75

Nil

600/ Nil KW 75

75

Nil

600/ KW

Nil

75

75

75 75 75 200/K 200/ Nil W KW 600/K 600/ Nil W KW 75

75

75

Nil

Nil

Nil

600/K W

Nil

600/K W

Nil

75

75

75

75

75

Nil

75 200/ Nil KW

600/K 600/ 600/ Nil 125/HP Nil W KW KW 75

75

75

Dishonoured Cheque Service 1 Charges/Serv 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 250 ice Name Transfer Fees Legal 1 Succession / 200 200 200 200 200 200 200 200 200 200 200 200 200 200 200 200 Sale Deed * Other variable charges like Labour charges,cable charges,road cut charges etc will be caluculated depending on site condtions

75

75

250 250

200

200 200

TAMIL NADU ELECTRICITY BOARD

Page |9

TAMIL NADU ELECTRICITY BOARD MISCELLANEOUS CHARGES 1.0. Sl. No.

Service Connection Charges for Metering

Category

Tariff

Charges Single Phase

Three Phase

Rs.250/ service

Rs.500/service

1

Low Tension Service

i

Domestic

I(a)

ii

II (a)

iii

Street Lights & Public Water Supply Tiny Industries

iv

Industries

III(b)

v

Agriculture

IV

Exempted

vi

Hut

I(b)

Exempted

vii

viii

Recognised Educational II(b) Institutions Laboratories, Cinema Theatres, Hospitals, etc. Actual Places of Workship II(c)

ix

Commercial

III(a)

Rs.250/ service Rs.500/service

V 2.0 Meters

Sl.

No.

Category 1. Meter Rent

a

Charges Single Phase

Three Phase

Nil

Nil

Meter Rent (Low Tension) All LT Services

b

Meter Rent (High Tension)

i

ii

Demand or special type meter (applicable for Electro mechanical trivector meter) Demand or special type meter (Applicable for Electronic Trivector Meters)

Rs. 1000/ service/month or part thereof Rs. 1500/ service/ month or part

thereof

Rs. 2000/- per service per month or part thereof

P a g e | 10 c

Time switches

Nil

Low Tension (III)

Rs. 150/-

Rs. 150/-

Changing of meter at the request of the consumer not due to increase in consumption or demand

a.

Low Tension

Rs. 50/-

b.

HT meters

(iv)

For testing of Rs 100/- per service meter, if it is proved to be incorrect within the prescribed limit(challenge test) Installation Testing

1

LT Services

a.

First test and

Rs. 50/Rs. 200/-

Rs 300/- per service`

inspection b.

2

3

Further test on inspection due to faults in installation (if needed as per statutory requirement) HT Services For the first and subsequent test and inspections Attending faults by officials of TNEB

Free

Free

Rs. 75/-

Rs/ 75/Rs. 75/-

Rs. 2000/- per visit

Rs. 2000/- per visit

3.0. Meter Caution Deposit Sl. Category No.

Tariff

Charges Single Phase

Three Phase

Low Tension Service 1

Domestic

1(a)

2

Street Lights & Public Water Supply Tiny Industries

II(a)

3

III(a)

Rs. 700/meter

Rs. 2500/meter

P a g e | 11 4

Industries

III(b)

5

Agriculture

IV

Nil

Nil

6

Hut

I(b)

Nil

Nil

7

II(b)

Rs. 700/meter

8

Recognised Educational Institutions, Laboratories, Cinema Theatres. Actual Places of Worship

9

Commercial

V

Rs. 2500/meter II(c)

High Tension Service 1

Industries

I

2

Recognised Educational Institutions Laboratories, Cinema Theatres

II

3

Commercial

III

Rs. 40000/service for 11/22/33 KV levels and Rs 100000/service for EHT levels

4.0. Reconnection Charges Sl. No.

Category

Charges

Tariff CUT OUT Single Phase

a 1. 2.

Low Tension Service Domestic

I(a) II(a)

3.

Street Lights & Public Water Supply Tiny Industries

4.

Industries

III(b)

5.

Agriculture

IV

6

Hut

I(b)

7.

II(b)

9.

Recognised Educational Institutions Laboratories, Cinema Theatres, Hospitals etc. Actual Places of Workship Commercial

b.

High Tension

1

Industries

8.

Three Phase

Rs.60/-

Rs.60/-

Rs.60/-

Rs.60/-

OVERHEAD Single Phase Rs.60/-

Three Phase Rs.60/-

UNDER GROUND Single Phase Rs.300/

Three Phase

Rs.300/

III(a)

II(c) V

I

Rs.60/-

Rs.60/-

Rs.300/

Rs.300/

P a g e | 12 2

3

Recognised Educational Institutions Laboratories, Cinema Theatres, Hospitals etc. Commercial

II Rs. 3000/-

III

5.0 Replacement of white meter card if lost or damaged Sl. No.

Category

Charges

Any Service

Rs. 5/6.0 Service charges for dishonoured cheques

a

Low Tension Services

Rs. 250/-

b

High Tension Services

Rs. 250/-

7.0 Charges for Name Transfer of Service Sl. No.

Category

Charges

Tariff

Legal succession I

Low Tension Service

1

Domestic

I(a)

2

Street Lights & Public Water Supply

II(a)

3

Tiny Industries

III(a)

4

Industries

III(b)

5

Agriculture

IV

6

Hut

I(b)

7

II(b)

8

Recognised Educational Institutions Laboratories, Cinema Theatres, Hospitals, etc. Actual Places of Worship

9

Commercial

V

II

High Tension

1

Industries

I

2

II

3

Recognised Educational Institutions, etc. and Places of Public Worship Commercial

III

Windmills

1

Upto 250 KW

II(c)

III

Rs. 200/-

Sale of property

Rs. 200/-

Rs. 50/-

Rs. 50/-

Rs. 200/-

Rs. 200/-

Rs. 2000/-

P a g e | 13 2

More than 250 KW to 500 KW

3

More than 500 KW to 75 KW

4

More than 750 KW to 1000 KW

5

More than 1000 KW

Rs. 1,00,000/-

8.0 Development Charges Sl. No.

Category

Tariff

Charges Single Phase

Three Phase

Rs. 400/service

Rs. 1400/service

I 1

Low Tension Service Domestic

I(a)

2

Street Lights

II(a)

3

Public Water Supply

II(a)

Rs. 400/service

Rs. 200/KW**

4

Tiny Industries

III(a)

Rs. 400/service

Rs. 200/KW **

5

Industries

III(b)

Rs. 300/location

N.A.

Rs. 200/KW **

N.A.

Rs. 200/KW **

6

Agriculture

IV

Nil

Nil

7

Hut

I(b)

Nil

Nil

8

Recognised Educational

II(b)

Rs. 400/service

Institutions

Rs. 200/KW **

9

Actual Places of Worship

II(c)

Rs. 400/service

10

Commercial

V

Rs. 400/service

II

High Tension

1

Industries

2

Recognised Educational II Institutions, Laboratories, Cinema Theatres, Hospitals, etc. and Actual Places of Public Worship Commercial III

3

Note: ** The KW rate mentioned above is the demand applied/sanctioned and not the connected load. I Rs. 350/ per KVA without ceiling limit

P a g e | 14

9.0 Registration Charges Sl. No

Category

Tariff

Charges Single Phase

I

Three Phase

Low Tension Service

1

Domestic

I(a)

2

Street Lights &

II(a) Rs. 50/ service

Public Water Supply 3

Tiny Industries

III(a)

4

Industries

III(b)

5

Agriculture

IV

6

Hut

I(b)

7

Recognised Educational Institutions Laboratories, Cinema Theatres, Hospitals, etc. Actual Place of

II(b)

8

Rs. 5/service

N.A.

Rs. 50/ service II(c)

Worship 9

Commercial

II

High Tension

1

Industries

2

Recognised II Educational Institutions Laboratories, Cinema Theatres, Hospitals, etc. and Places of Public Worship Commercial III

3 III

Captive Power Plant

V

I Rs. 500/ service

N.A. now

P a g e | 15

10.0 Earnest Money Deposit Sl. No.

Category

Tariff

Charges Single Phase

I 1 2

3 4

Low Tension Service Domestic Street Lights & Public Water Supply Tiny Industries Industries

Three Phase Nil

I(a) II(a)

III(a) III(b) N.A

5 6 7

8 9 II 1 2

3

Agriculture Hut Recognised Educational Institutions, Laboratories, Cinema Theatres, Hospitals, etc. Actual Places of Worship Commercial

High Tension

IV I(b) II(b)

Rs. 600/KW **

Nil

II(c) V Note: ** The KW rate mentioned above is the demand applied/sanctioned and nor for the connected loaded I Rs. 800/KVA II

Industries Recognised Educational Institutions, Laboratories, Cinema Theatres, Hospitals, etc. and Actual Places of Public Worship Commercial III

P a g e | 16

11.0 Initial Current Consumption Deposit Sl. Category No.

Tariff Charges Single Phase

I

Low Tension Service

1

Domestic

I(a)

2

Street Lights & Public Water

II(a) Rs. 200/service

Supply 3

Tiny Industries

III(a)

4

Industries

III(b)

5

Agriculture

IV

Free Supply

Rs. 600/KW **

Nil

SFS

Nil Rs. 125/HP

6

Hut

I(b)

7

II(b)

8

Recognised Educational Institutions, Laboratories, Cinema Theatres, Hospitals, etc. Actual Places of Worship

9

Commercial

V

II

High Tension

1

Industries

I

2

Recognised Educational Institutions, Laboratories, Cinema Theatres, Hospitals, etc. and Actual Places of Public Worship Commercial

II

3

Three Phase

Nil

N.A

Rs. 200/service

Rs. 600/KW **

II(c)

Note: ** The KW rate mentioned above is meant for demand applied/sanctioned and not the connected load.

Rs. 800/KVA

III

TAMIL NADU ELECTRICITY BOARD