Arrow Consulting
Project Management Plan
Version 3.0 December 10, 2013
Presented by: Kirsten Rivera, Project Manager
December 10, 2013
Project Management Plan
Page 1
ASSUMPTION AND CONSTRAINT LOG Project Title: New Kitchen Heaven Retail Store
ID
Category
Date Prepared: 12/10/2013
Assumption/Constraint
Responsible Party
Due Date Actions
Status
01
Planning
Only 24 construction workers are necessary
Project Manager
N/A
Closed
02
Executing
Build phase includes cleaning the facility after construction is complete
Project Manager
N/A
Open
03
Planning
Construction workers are paid wages based on average salary of construction workers in Colorado Springs according to indeed.com
Dirk Perrier
N/A
Closed
04
Planning
Grand opening prep includes training and setting up materials
Jill Overstreet
N/A
Open
05
Planning
Materials will be ordered or purchased at local hardware store as needed. For example, paint it not needed initially and so it will be purchased when necessary.
Construction workers
N/A
Pending
07
Planning/ Executing
A store build-out usually takes 120 days.
Everyone Involved
Jan. 15
Open
08
Executing
Everyone involved in project
Feb. 1
Closed
Completion date: Feb 1
December 10, 2013
Assumption and Constraint Log
Comments
Page 2
09
Executing
Jill Overstreet will help with the initial store stocking.
Jill Overstreet
N/A
Pending
10
Planning
Retail product line will be delivered two weeks prior to grand opening The retail product line must be displayed throughout the store in a way that is easy for customers to find what they want and consistent with other stores in the country
Marketing Department
Jan. 18
Pending
11
Executing
Jake Peterson will provide supplies for the stores that aren’t retail products, such as store furnishings, shelving, and so on, and can help with store build-out as well.
Jake Peterson
N/A
Open
12
Planning/ Executing
The budget for the project will be between $1.5 and $2 million.
Project Manager
Feb. 1
Closed
13
Planning/ Executing
Procurement of TI connection takes 30-45 days and will have on going costs of $3,000 per month
IT Manager: Ricardo
Jan. 21
Pending
14
Planning/ Executing
Running Ethernet cable throughout the building will take 16 hours at $100 per hour
IT Manager: Ricardo
Sept. 18
Closed
15
Planning/ Executing
Purchasing router, switch, server, and rack will cost $17,000
IT Manager: Ricardo
Pending
16
Planning/ Executing
Installing router and testing connection will take 8 hours and cost $78 per hour
IT Manager: Ricardo
Pending
December 10, 2013
Assumption and Constraint Log
Page 3
17
Planning/ Executing
Installing switch will take two hours and cost $78 per hour
IT Manager: Ricardo
Pending
18
Planning/Executing
Installing server and testing it will take six hours at $84 per hour
IT Manager: Ricardo
Pending
19
Planning/Executing
Web team will add new store location and phone number to lookup function on the internet site which will take two hours and cost $96 per hour
IT Manager: Ricardo
Pending
20
Planning/Executing
Interviews for store positions will take place before the 22nd when shelves need to be stocked
Jill Overstreet
December 10, 2013
Jan. 16-19
Assumption and Constraint Log
Open
Page 4
INTER-REQUIREMENTS TRACEABILITY MATRIX Project Title: New Kitchen Heaven Retail Store ID
Business Requirement Cable Vendor
Date Prepared: 12/10/2013
Priority Source High
KHCS-1001
ID
Technical Requirement
Priority Source
WBS
KHCS10011
Electrical lines run and dry-wall work in progress
High
WBS
KHCS-1002 TI Connection
High
WBS
KHCS10012
Build-Out Complete
High
WBS
KHCS-1003 Build-Out Begins
High
WBS
KHCS10013
Install and Test Hardware
High
WBS
KHCS-1004 Sign Lease
High
WBS
KHCS10016
Order Retail Products
High
Activity List
KHCS-1005 Signed Contract
High
WBS
KHCS10017
Hire Retail Products and Stock Shelves
High
Activity List
KHCS-1006 Ethernet Cable Run
High
Activity List
KHCS10018
Build-out behind Schedule
High
Activity List
KHCS-1007 Build-Out Started
High
Activity List
KHCS10019
Store Installation not completed
High
WBS
Build-Out Work In KHCS-1008 Progress
High
Activity List
KHCS10020
Store Opening
High
Activity List
KHCS10021
Cabling Work Check
High
Activity List
KHCS-1023 Store Shelf Installation
High
Activity List
KHCS10022
Build-Out Work Check
High
Activity List
KHCS-1024 Order Retail Products
High
Activity List
December 10, 2013
Inter Requirements Traceability Matrix
Page 5
MILESTONE LIST Project Title:
50th Kitchen Heaven Store in Colorado Springs & GrandOpening Celebration
Milestone
Date Prepared: 12/10/2013
Milestone Description
Type
Hold stakeholder meeting
Project charter kickoff meeting
Project management
Identify property for store
Find appropriate Colorado Springs property for store
Property
Kickoff meeting held with key project team members
Marking project planning stage completion, and start of Project management executing stage
Sign procurement documents
Product
Sign lease
Property
Gomez contract signed
Staffing
Ethernet cable run
Construction
Purchase router, switch, server, and rack
For equipment room and four POS terminals
Construction
Install switch
Construction
T1 cabling installed
Construction
Build-out started
Construction
Hardware installed and tested
Dependent on T1 connection
Construction
Independent inspection
Contracted independent inspector performs inspection prior to city and county inspections
Construction
Personnel hired
Staff hired for new store
Staffing
December 10, 2013
Statement of Work
Page 6
Receive shipments of products
Have all products needed in stock for grand opening shipped to store
Product
Shelves stocked
Products are stocked on shelves in store
Product
Build-out finished
Construction
Add new store location and phone number to website
Added to the lookup function
Marketing
Hold grand opening celebration
50th store opening celebration for community, including chef demonstrations
Marketing
Hand off ongoing operations
Jill Overstreet’s team will oversee ongoing operations
Project management
December 10, 2013
Statement of Work
Page 7
STATEMENT OF WORK Time and Materials Client’s name Client’s administrator Project name Engagement duration Begin date End date
Kitchen Heaven Dirk Perrier, VP of Marketing 50th Kitchen Heaven Store in Colorado Springs & GrandOpening Celebration 6 months August 1, 2013 February 1, 2013
Schedule of rates Item description
Delivery schedule (Business days)
Cost (estimate)
Labor
Payroll every 14 days (8.57 pay periods for 120 day project)
$15.00/hour, per person $1,200.00/pay period, per person $10,284.00/per person for 120 day project $246,816.00 for 24-man construction crew
Materials
Pay as you go
$200.00/sq. ft. $500,000.00 for 2,500 sq. ft. retail space
Furnishings/Shelving
$100,000 approx. budget
Inventory Stock Contractor
Payroll every 14 days (8.57 pay periods for 120 day project) Upfront fees paid immediately
$45.00/hour $3,600.00/pay period $30,852.00 for 120-day build project
Lease, Monthly Rent
Approx. every 30 days, beginning when lease is signed (around one month into project)
$13.00/sq. ft. per year $2,708/month rent $13,540.00 for 5 months of the project
Festivities Costs
December 10, 2013
Statement of Work
Page 8
Payment terms Phase
Completion date
Payments due
Administrative/Planning
Feb. 1, 2013
Consulting fees paid bimonthly, beginning with pay period for August 1-15
Build
Jan. 1, 2013
Payment 1: Sept. 1, 2013
Furnishing/Stocking
Jan. 31, 2013
Payments made as needed, made from and recorded in facilities and retail products budgets
Grand Opening Prep and Execution
Feb. 1, 2013
Payments made as needed, made from and recorded in marketing budget
December 10, 2013
Statement of Work
Page 9
Statement of Work Assumptions ● Only 24 Construction workers are necessary ● Construction workers are paid wages based on average salary of construction workers in Colorado Springs according to indeed.com. ● Build phase includes cleaning the facility after construction is complete ● Furnishing/Stocking includes shelving, seating, setting up cash registers, gathering materials to run store (for example, shopping carts), and stocking the shelves with product and setting up displays. ● Grand Opening Prep includes training and setting up materials. ● Materials will be ordered or purchased at local hardware stores as needed. For example, paint is not needed initially and so it will be purchased when necessary.
Change management process Any major change to the scope will need to be verified by all of the stakeholders to make sure that it is approved. The project manager first will decide if they think the change is necessary and they will then approach all stakeholders and make sure they approve the change. If there is just a scope revision it will be brought to the attention of the project sponsor for refinement first, and then considered for approval by the stakeholders. Scope changes will be anticipated and budgeted for accordingly.
Engagement related expenses All expenses incurred as a cost of doing business for the project will be received, and reviewed by the Project Manager before being passed to the sponsor for approval. The sponsor is responsible for all expenses identified in the budget.
Professional services agreement Once the project is complete, there will be a two month transitional phase in which the project manager will help with any upgrades or maintenance. After this two month phase the building will be under full ownership and responsibility of Kitchen Heaven.
December 10, 2013
Statement of Work
Page 10
Acceptance and authorization The terms and conditions of the Professional Services Agreement apply in full to the services and products provided under this Statement of Work. IN WITNESS WHEREOF, the parties hereto each acting with proper authority have executed this Statement of Work, under seal.
Dick Perrier_______________________________
Kirsten Rivera___________________________
Full Name
Full name
VP of Marketing, Kitchen Heaven_______________
Project Manager, Arrow Consulting__________
Title
Title
__________________________________________
______________________________________
Signature
Signature
August 1, 2013______________________________
August 1, 2013_________________________
Date
Date
December 10, 2013
Statement of Work
Page 11
PROJECT CHARTER Project Title: 50th Kitchen Heaven Store in Colorado Springs & Grand-Opening Celebration Project Sponsor: Dirk Perrier
Date Prepared: August 1st, 2013
Project Manager: Kirsten Rivera, Arrow Consulting Projected Customer: Kitchen Heaven Project Purpose or Justification: Purpose: To open a new store in Colorado Springs on February 1, 2013. Justification: Company data concludes that the Kitchen Heaven consumers have incomes of more than $150,000 a year. The Colorado Springs area is home to a large number of people with that income. Currently, there is no Kitchen Heaven in the area, but there appears to be a demand for one. Additionally, sales are up, and Kitchen Heaven’s new line of ceramic cookware is selling well, which indicates that Kitchen Heaven is in a good financial position to open a new store. Project Description: The 50th Kitchen Heaven store, located in Colorado Springs, will open February 1 with a grand-opening celebration. The project will involve: procuring the property, negotiating the lease, procuring the shelving and associated store furnishings, getting a contractor on the job, and preparing the 50th store festivities in collaboration with the marketing department. High-Level Requirements: - Property will be located in Colorado Springs, in an affluent area - The new store should occupy from 1,500 to 2,500 square feet of retail space - Use local contractors for the build-out - Store will carry full line of products from utensils to gourmet food items - Grand opening celebration for 50th store opening - Store is open in time for the Garden and Home Show conference in Colorado Springs, in early February - Offer new line of gourmet food products - Have classroom space in back of store for cooking demos and classes
December 10, 2013
Project Charter
Page 12
High-Level Risks: - Project management risks (improper schedule and resource planning, poor project planning, and improper or poor project management disciplines or methodologies) - Technical, quality, and performance risks (unproven technology, complex technology, changes to technology anticipated during the course of the project, and unrealistic performance goals) - Organizational risks (resource conflicts because of multiple projects occurring at the same time in the organization; scope, time, and cost objectives that are unrealistic given the organization’s resources or structure; and lack of funding for the project or diverting funds from this project to other projects) - External risks (new laws or regulations, labor issues, weather, changes in ownership, and catastrophic risks) - Market competition - IT risks (TI line availability and installation, contractor availability for Ethernet installation, POS and server hardware availability) - Facilities risks (desirable location in the right price range, contractor availability for build-out, availability of fixtures and shelving) - Retail risks (product availability, shipment dates for product)
December 10, 2013
Project Charter
Page 13
PROJECT CHARTER
Project Objectives
Success Criteria
Person Approving
Scope: New Kitchen Heaven store in Colorado Springs
Opens on-time, at/under budget
Dirk Perrier
Completion date: Feb. 1
Dirk Perrier
Project cost = $2 million
Dirk Perrier
Time: Six months to completion Cost: $2 million
Summary Milestones
Due Date
Procure property
August 14
Negotiate lease
August 14
Procure shelving and store furnishings
January 16
Run Ethernet cabling at property
September 20
Finish build-out
January 16
Hire personnel
February 1
Stock shelves
February 1
Prepare grand-opening celebration
February 1
December 10, 2013
Project Charter
Page 14
PROJECT CHARTER Estimated Budget: $2 million
Stakeholder(s)
Role
Dirk Perrier
VP of Marketing, Project Sponsor
Jake Peterson
Facilities
Jill Overstreet
Director of Retail Products, Ongoing Operations
Ricardo
Stakeholder
Gomez Construction
Build-out contractor
Arrow Consulting
Project Consultants
Colorado Springs community members
New store audience
Kitchen Heaven Marketing Department
Grand Opening Celebration planners
Project Manager Authority Level - Medium Staffing Decisions: - Jill Overstreet will help with the initial store stocking - Jake Peterson will provide supplies for the stores that aren’t retail products, such as store furnishings, shelving, and so on, and can help with the store build-out as well - Ricardo will serve as lead for IT and build-out processes and management - Gomez Construction will oversee the build-out - The Kitchen Heaven Marketing Department will plan the Grand Opening Celebration for the 50th store
December 10, 2013
Project Charter
Page 15
PROJECT CHARTER Budget Management and Variance: Activity cost estimates were created, including basis of estimates, using the following: - Parametric estimates (Ricardo) - Analogous and parametric estimates (Jake) - Reserve analysis including contingencies for unplanned changes in involving vendor deliveries (Jill) - Assumptions made about vendor deliveries and availability of the T1 and assumptions made regarding when lease payments begin - The range of possible estimates is stated as plus or minus 10 percent Since the project occurs fairly quickly, only two funding requirement periods are needed Technical Decisions: Key stakeholders will be responsible for monitoring and controlling the technical aspects of their respective expertise – for example, the Director of Retail Products will ensure that incoming products are up to specification, and will handle any concerns of unacceptable quality. Conflict Resolution: Conflicts should be brought to the attention of the Project Manager first, who will either escalate the issue up to the appropriate level (applicable stakeholder or Project Sponsor), or will address and work through the issue with the person(s) bringing it forth. Approvals:
_________________________________ Project Manager Signature
_________________________________ Sponsor or Originator Signature
Kirsten Rivera______________________ Project Manager Name
Dirk Perrier________________________ Sponsor or Originator Signature
August 1, 2013 _____________________ Date
August 1, 2013_____________________ Date
December 10, 2013
Project Charter
Page 16
CHANGE MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Change Management Approach: Changes involved in the project scope, schedule, or baseline will be documented in order to maintain accurate and reliable performance measurement baselines. All processes impacted as a result of changing project variables will mean revisiting Planning and Executing processes as needed, as well as updating the project scope to reflect these changes.
Definitions of Change: Schedule change: A schedule change is usually the result of a revision to the project scope, activity estimations, or an update in the project baseline. A delay in the schedule can significantly impact the project outcome if there is little variance/float in the schedule. In fact, it can even change the critical path. Budget change: A budget change may result from incorrect estimating techniques, predetermined budgets that had little flexibility, schedule changes (such as crashing), changes in suppliers, failure to provide procedures to review and revisit cost estimates made during the planning phase of the project, etc. Scope change: A scope change requires changes to the project scope as defined by the WBS. Depending on the nature of the scope change, there may need to be updates to a variety of documents such as, project objectives, costs, quality measurement controls, performance measurements baselines, or even schedule revisions. In the event in which a scope change is not documented properly, the project requirements may not align with the desired deliverables. Project document changes: Project document changes may occur throughout the project. It is important that all the stakeholders are aware of such changes and that the project manager is informed and required to sign off on them. For a change to occur, it must first pass through the change control board who meet periodically. Requests for change are always submitted in writing and are detailed to prevent confusion. Documentation will be submitted in a change request form and then processed by the Change Control Board (CCB). The CCB will then track, approve, or deny proposed changes.
December 10, 2013
Change Management Plan
Page 17
CHANGE MANAGEMENT PLAN Change Control Board: Name
Role
Responsibility
Authority
Dirk
Project Sponsor
Attend CCB meetings
Provides input and asks questions regarding proposed changes.
Main Character
Project Manager
Determine impacts
Makes final decision on the approval process by signing off on the change request.
Change Control Process: Change request submittal
October 8th: (APPROVED) Jill submitted a change request regarding the costs associated with the purchasing of retail products from the new gourmet supplier, as their prices are higher than the original vendor. This affects the project budget, but not by too much. October 13th: (APPROVED) Ricardo submitted a change request regarding the purchase of an upgraded version of the company’s current operating system. Ricardo is in charge of upgrading the company’s operating systems in all the stores. Buying the new hardware with the upgraded operating system preinstalled would save time and energy for his future project.
Change request tracking
Gomez - T1 connection issues because the phone company is not returning calls about hardware
Change request review
October 13th: Ricardo’s new operating system questions were answered and approved. Chapter 10: Jill’s cost change request has been approved because her first contracted vendor went out of business, the second vendor failed to meet quality control standards, and her current vendor charges higher retail prices for their gourmet cookware. This change approval doesn’t significantly impact the project budget, but will still require revisions in the cost/budget related documents.
Change Chapter 10: Ricardo’s change request was submitted in writing through the change request control system. disposition Chapter 10: Jill’s change request was submitted through a cost change request to the CCB
December 10, 2013
Change Management Plan
Page 18
COMMUNICATIONS MANAGEMENT PLAN Project Title:
Date Prepared:
New Kitchen Heaven Retail Store Stakeholder
Information
October 27, 2013 Method
(555) 456-7654
[email protected] (555) 324-5644
[email protected] (555) 385-4677
[email protected] Same as ab ove
Email, Phone, & Meetings Email, Phone, & Meetings Email, Phone, & Meetings Email & Phone
Leasing Agent Marketing Department
(555) 853-4575
Email & Phone
(555) 456-7654
[email protected]
Colorado Springs Community
N/A
Garden and Home show conference attendees
N/A
Famous chefs whose cookware will be featured in store Grand opening caterers Local chefs featured at grand opening
Dirk Perrier Jake Peterson Jill Overstreet Jill Overstreet's Group
December 10, 2013
Timing or Frequency
Sender
Weekly & as important updates or changes occur Weekly & as important updates or changes occur Weekly & as important updates or changes occur Weekly & as important updates or changes occur When necessary
Project Manager
Email & Meetings
Initial meeting with weekly correspondences following
Dirk Perrier
N/A
Marketing department
N/A
Jill Overstreet
TBD
Through marketing Through garden and home show Email
Notifications
Jill Overstreet
(555) 505-6575
Phone
Jill Overstreet
(555) 366-4575
Email and Phone
Weekly & daily the week prior to the event A few reminders leading up to event
Communications Management Plan
Project Manager Project Manager Project Manager Jake Peterson
Jill Overstreet
Page 19
Assumptions
Constraints
Only 24 construction workers are necessary
payroll every 14 days (8.57 pay periods for 120 day project) $15.00/hour, per person $1,200.00/pay period, per person $10,284.00/per person for 120 day project $246,816.00 for 24-man construction crew
Construction workers are paid wages based on average salary of construction workers in Colorado Springs according to indeed.com
$15.00/hour, per person Wages could potentially increase
Build phase includes cleaning the facility after Build phase may take longer due to this and could hold up other aspects. construction is complete Furnishing/Stocking includes shelving, seating, setting up The storefront look must be consistent with all of the other 49 stores throughout the country. cash registers, gathering materials to run store (for This will need to be approved and signed off by someone in the Marketing department. example shopping carts), and stocking the shelves with product and setting up displays Grand opening prep includes training and setting up The building and everything must be complete for this step to happen. materials Materials will be ordered or purchased at local hardware store as needed. For example, paint it not needed initially Materials may end up costing more by using this method. and so it will be purchased when necessary. A store build-out usually takes 120 days.
Completion date: February 1st
Retail product line will be delivered two weeks prior to grand opening The retail product line must be displayed throughout the store in a way that is easy for customers to find what they want and consistent with other stores in the country Jake Peterson will provide supplies for the stores that Retail product line will be delivered two weeks prior to grand opening aren’t retail products, such as store furnishings, shelving, The retail product line must be displayed throughout the store in a way that is easy for and so on, and can help with store build-out as well. customers to find what they want and consistent with other stores in the country Jill Overstreet will help with the initial store stocking.
The budget for the project will be between $1.5 and $2 million.
Things may end up costing more than expected.
Glossary of Terms or Acronyms TBD: To Be Determined N/A: Not Applicable
December 10, 2013
Communications Management Plan
Page 20
COST MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Level of Accuracy:
Units of Measure:
Control Thresholds:
Round costs to Hundreds, plus or minus 10%
Hours Dollars
Plus or minus 10%
Rules of Performance Measurement: Parametric and analogous estimating techniques will be used. Reserve analysis will be used to include contingencies for unplanned changes involving vendor deliveries. Budget will be determined using cost aggregation.
Cost Reporting and Format: A cost report will be produced twice throughout this project in a written format. One report at the half and the other one at the end of the project.
Process Management: Estimating costs
Labor: $246,800; Materials: $500,000; Furnishing: $100,000; Contractor: $30,800; Lease, Monthly Rent: $13,540 for 5 months Activity 1: $3000 per month; Activity 2: $1600; Activity 3: $17,000; Activity 4: $624; Activity 5: $156; Activity 6: $504; Activity 7: $192
Developing the budget
Aggregate activity costs: $23,076 Total costs (including labor, materials, rent, etc): $914,216
Updating, monitoring and Every month controlling
December 10, 2013
Cost Management Plan
Page 21
BOTTOM-UP COST ESTIMATING WORKSHEET Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
WBS ID
Labor Hours
Labor Rates
Total Labor
Material/Supplies Equipment
1.2
240.0
$12.5/hour
$3000
$3000
1.3
16.0
$100/hour
$1600
$1600
1.5
960.0
$15.00/hour, per person $1,200.00/pay period, per person $10,284.00/per person for 120 day project
$246,816.00 for 24-man construction crew
$246,816
2.1
Router, switch, server, and rack
Indirect Costs
Reserve
Estimate
$17,000
2.2
16.0
Router install = $78/hour Switch Install = $78 Server Install = $84
$624 for router installation/testing $156 for switch installation $504 for server installation/testing
$1284
2.3
2.0
$96/hour
$192
$192
3.1
Retail Products
$500,000
3.2
400.0
$9 per hour for 40 hour for 10 employees
$3600
$3600
3.3
400.0
$9 per hour for 40 hour for 10 employees Training personnel $20
$4,400
$10,000
December 10, 2013
Bottom-Up Cost Estimating
Page 22
ACTIVITY COST ESTIMATES Project Title: New Kitchen Heaven Retail Store WBS Resource ID
Direct Costs
Indirect Costs
1.1
Leases, contractors
Lease, Contractors
Paperwork
1.2
Contractors, IT Personnel
Procurement costs
1.3
Ethernet Cable, Cable installers
Labor
1.4
Contractors, Gomez
Contractors
1.5
Construction workers
Labor
2.1
Management approval to purchase equipment
Router, switch, server, and rack for the equipment room
2.2
Construction workers, IT Personnel
Labor
Tools, Snacks
2.3
IT Personnel
Labor
Tools, Snacks
December 10, 2013
Ethernet ports, any specific hardware
Tools, Snacks
Reserve Estimate
Date Prepared: 12/10/2013 Method
Assumptions/ Constraints
Additional Information
Range Confidence Level
$2704
Expert Judgment/Analogous
When lease payment begins
plus or High minus 10%
$3000
Expert Judgment/Analogous
When lease Takes 30 to payment begins 45 days to procure
plus or High minus 10%
$1600
Parametric
plus or High minus 10%
Expert Judgment/Analogous
plus or High minus 10%
$15 per hour Expert Judgment $246,816 total cost
plus or High minus 10%
$17,000
Expert Judgment
plus or High minus 10%
$624 for router installation/testing $156 for switch installation $504 for server installation/testing
parametric
plus or High minus 10%
parametric
plus or High minus 10%
$192
Activity Cost Estimates
Page 23
3.1
Management approval to purchase retail products
3.2
3.3
$500,000
Expert Judgment
plus or High minus 10%
Workers for the labor store, need laborers to stock shelves
$9 per hour for 40 hour for 10 employees $3600 total cost
Expert Judgment
plus or High minus 10%
Store management, HR personnel, general store staff
$4,400
Expert Judgment
plus or High minus 10%
December 10, 2013
Retail products
Training, labor
Activity Cost Estimates
Page 24
COST ESTIMATING WORKSHEET Project Title: New Kitchen Heaven Retail Store Date Prepared: 12/10/2013 Parametric Estimates WBS ID
Cost Variable
Cost per Unit
Number of Units
Cost Estimate
2.1 - Procure T1 Connection
Monthly Payments
3000
1-1.5
3000-4500
2.2 - Run Ethernet Cable Throughout Building
Hourly Wage Rate
100
16 hours
1600
2.3 - Purchase the Equipment
Purchases
Variant
Router, Switch, Server, Rack, Service Terminals
17000
2.4.1 - Installations of Equipment (Router and Test Connection
Hourly Wage Rates
78
8
624
2.4.2 - Install Switch
Hourly Wage Rate
78
2
156
2.4.3 - Install Server and Test
Hourly Wage Rate
84
6
504
2.5 - Testing and Adding Location and Phone to lookup function
Hourly Wage Rate
96
2
192
Analogous Estimates WBS ID
Previous Activity
Previous Cost
Current Activity
1.1
None
None
Procure Lease
2704
1.2
Procure Lease
2704
Procure T1 Connection
3000
1.5
Procure T1 Connection
3000
Pay Construction workers
15 per hour 246,816 total cost
3.1
Pay construction workers
15 per hour 246,816 total cost
Management approval for purchasing equipment
17, 000
3.2
Management approval for purchasing equipment
500,000
Workers for the store, need laborers to stock shelves
$3600 total cost
3.3
Workers for the store, need laborers to stock shelves
$3600 total cost
Store management, HR personnel, general store staff
$10,000
December 10, 2013
Activity Cost Estimates
Multiplier
Cost Estimate
Page 25
COST BASELINE Project Title: New Kitchen Heaven Retail Store Date Prepared: 12/10/2013
December 10, 2013
Cost Baseline
Page 26
HUMAN RESOURCE MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Roles, Responsibilities, and Authority
Role
1. Project Sponsor 2. Project Manager 3. Construction Manager 4. Retail Products Manager 5. Facilities Manager 6. Marketing Team 7. IT Manager
Responsibility
Authority
1. Sign off on important 1. High documents, work with project 2. High manager 2. Coordinate project team, manage deadlines, communicate between all stakeholders
3. Moderate
3. Oversee build-out of store
6. Low/Moderate
4. Oversee ordering, receiving, and stocking of products for store
7. High
4. High 5. High
5. Oversee ordering, receiving, and setup of store furnishings 6. Oversee planning and execution of grand-opening celebration 7. Oversee building, installing, and testing of technology
December 10, 2013
Human Resource Management Plan
Page 27
HUMAN RESOURCE MANAGEMENT PLAN Project Organizational Structure
December 10, 2013
Human Resource Management Plan
Page 28
HUMAN RESOURCE MANAGEMENT PLAN
Staffing Management Plan Staff Acquisition
Staff Release
External resources to needed to run Ethernet cable, procure a T1 line, and purchase routers and switches. Personnel to staff new store. Local chefs for cooking demonstrations at grand-opening celebration.
Resource Calendars Key project staff - including Jill Overstreet, Jake Peterson, Ricardo, and Gomez Construction are available for substantial time commitment to this project to ensure project deadline is achieved.
Training Requirements Personnel hired to staff new store will need two weeks training with Jill Overstreet and team.
Rewards and Recognition Project manager takes key project staff to lunch once per month to foster team unity and communication. Project manager rewards those resources occupying the roles listed at the beginning of this Plan with $100 gift cards to [nice Colorado Springs restaurant] for holiday gift. Upon completion of project, key project staff are awarded 20 hours PTO, to schedule at their will. Upon completion of project, project sponsor sends company-wide email announcing success of project, and includes his gratitude to key project staff by name.
December 10, 2013
Human Resource Management Plan
Page 29
HUMAN RESOURCE MANAGEMENT PLAN Regulations, Standards, and Policy Compliance - Lease terms will be negotiated with agent. - Inspections of site will be performed by independent contractor hired by New Heaven, as well as by city and county inspectors. - Procurement of external resources will be under a time and materials contract. - IT equipment specifications and gourmet product and cookware line specifications are documented in Quality Management Plan.
Safety Gomez construction is responsible for ensuring safety standards are upheld by and for its contractors at all times at Kitchen Heaven’s site.
December 10, 2013
Human Resource Management Plan
Page 30
Ricardo Ramirez
I
I
Project Objective
A
C
I
Project Charter
A
I
C
C
I
CCB
Jill Overstreet
C
R
Independent Inspector
Jake Peterson
A
City Inspector
Project Manager
R
Shelly
Dirk Perrier
RACI Definitions: R esponsibility = person or role responsible for ensuring that the item is completed A ccountable = person or role responsible for actually doing or completing the item C onsulted = person or role whose subject matter expertise is required in order to complete the item I nformed = person or role that needs to be kept informed of the status of item completion INITIATE Project Initiator
PLANNING Furnisih, Shelving, StoreSupplies
I
A
R
I
Retail Products
I
A
A
R
I
IT Equipment
I
A
C
I
R
Store Build-Out
I
A
R
I
C
Grand Opening
A
R
I
A
C
IT Task Risk
I
R
I
I
C
Risk
I
R
C
C
I
Ratail Risk
I
R
C
C
I
Project Costing
I
R
C
C
C
I
A
I
I
R
I
A
I
I
R
I
A
R
R
I
Human Resource Needs
I
A
R
R
I
Building and Cabling
I
A
R
C
R
I T hardware
I
A
A
C
R
Store
I
A
R
R
C
Cable Vendor
I
A
I
I
R
IT Connection Status
I
A
I
I
R
Sign Lease
I
R
C
C
C
Intial Retail Product Calls
I
A
C
R
I
Website Announcement
I
A
C
C
R
Forecast
I
R
C
C
C
C
Project Inspection
I
A
A
A
A
I
Website Announcement
I
A
C
C
R
Forecast
I
R
C
C
C
C
IT Quality control and testing
I
A
I
I
R
I
Store Project Quality Status
I
A
I
R
I
I
Contract Payment
I
A
C
C
C
R
Site Inspection
I
A
A
C
I
I
Each Project Monitoring
I
A
R
R
R
I
Project Updates
I
R
A
A
A
IT Quality control and testing
I
A
I
I
R
Store Project Quality Status
I
A
I
R
I
I
Change Request
I
A
A
A
A
A
Project Closeout
R
A
C
R
I
Porject Ends
I
A
A
R
I
Final Closing
R
A
A
A
A
Facilities
IT Installation and Switches IT Testing Hire Store Personnel
EXECUTING
I
R
MONITOR & CONTROLLING R
I R R
CLOSING
December 10, 2013
RACI Chart
Page 31
ROLES AND RESPONSIBILITIES Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Resource Role Description 1. Project Sponsor: The project sponsor has the authority to assign resources and enforce decisions regarding the project, and is a stakeholder. 2. Project Manager: The project manager is responsible for managing the project processes and applying the tools and techniques used to carry out the project activities. The project manager coordinates and communicates between the functional managers and project sponsor, as well as other project stakeholders. 3. Construction Manager: The construction manager is the project vendor overseeing the build out of the new retail store. The construction manager coordinates his team of builders to meet contractual obligations, including completion of build out on schedule in terms of project timeline. He also coordinates with the facilities manager and IT manager. 4. Retail Products Manager: The retail products manager is responsible for overseeing the selection, ordering, and receiving of all retail products for the new store. She is also involved with ensuring a smooth transition of project into her team’s operational care at end of project. 5. Facilities Manager: The facilities manager is responsible for overseeing selection, ordering, and receiving of all furnishings for the new store that are not retail products. He also coordinates with the IT manager and construction manager. 6. Marketing Team: The marketing team is responsible for planning and executing the grand-opening celebration for the new retail store. 7. IT Manager: The IT manager is responsible for overseeing the purchasing, installation, and testing of all technical equipment for the new store. He also coordinates with the facilities manager and construction manager.
December 10, 2013
Roles and Responsibilities
Page 32
Authority 1. Project Sponsor: The project sponsor has a high level of authority, has ultimate decision-making power, and holds a high degree of power and influence in the project. 2. Project Manager: The project manager has a high level of authority, and is recognized as the main contact for questions and issues related to the project. The project manager reports to the project sponsor, and works collaboratively with the functional managers involved in the project. 3. Construction Manager: The construction manager has moderate authority, because he has a high level of authority over his team but low-level authority in the context of project decision making. 4. Retail Products Manager: The retail products manager has a high level of authority, as she is responsible for all decision making with regards to store retail products. 5. Facilities Manager: The facilities manager has a high level of authority, as he is responsible for all decision making with regards to store furnishings. 6. Marketing Team: The marketing team has a low-to-moderate level of authority in the context of the project, as it coordinates grand-opening celebration activities and plans with the project manager and functional manager stakeholders. 7. IT Manager: The IT manager has a high level of authority, has he is responsible for all decision making with regards to technology needs for the store.
Responsibility 1. Project Sponsor: The project sponsor is ultimately responsible for overseeing the project at a high level, ensuring that the project meets deadlines, and financial and other requirements. 2. Project Manager: The project manager is responsible for meeting stakeholder expectations, including the expectations of the project sponsor. The project manager is additionally responsible for managing the project team, their team of consultants, and adhering to the PMI standards and code of ethics. 3. Construction Manager: The construction manager is responsible for communicating with the project manager and functional managers involved in the project who are concerned with the build out. The construction manager is responsible for the conduct of his team. 4. Retail Products Manager: The retail products manager is responsible for ensuring the store retail products meet stakeholder expectations. 5. Facilities Manager: The facilities manager is responsible for ensuring the store furnishings meet stakeholder expectations.
December 10, 2013
Roles and Responsibilities
Page 33
6. Marketing Team: The marketing team is responsible for ensuring the grand-opening celebration meets stakeholder expectations. 7. IT Manager: The IT manager is responsible for ensuring the store technology meets stakeholder expectations.
Qualifications 1. Project Sponsor: The project sponsor’s qualifications for overseeing this project were determined by Kitchen Heaven executive leadership. 2. Project Manager: The project manager is qualified for this project based on past project successes from previous employment. 3. Construction Manager: The construction manager is qualified to serve on this project because this vendor has been engaged with Kitchen Heaven on three of the last five projects, to great success. 4. Retail Products Manager: The retail products manager is qualified to work on this project due to her experience and her role as manager of ongoing operations for this store once the project has been successfully completed and closed. 5. Facilities Manager: The facilities manager is qualified to work on this project due to his successful supervision of eight previous store build outs. 6. Marketing Team: The marketing team is qualified to work on this project based on past event coordination success for other Kitchen Heaven store openings. 7. IT Manager: The IT manager is qualified to work on this project based on past success overseeing technical processes and needs for past store opening projects.
December 10, 2013
Roles and Responsibilities
Page 34
Requirements 1. Project Sponsor: The project sponsor is required to be accessible by the project manager for decision making and other needs, and will communicate necessary project information to the project manager as the need arises. 2. Project Manager: The project manager is required to document project processes and outcomes according to agreements with project stakeholders, and is required to lead project team, including fostering communication between project stakeholders. 3. Construction Manager: The construction manager is required to meet contractual obligations, and to communicate issues and questions to project manager and the necessary functional managers. 4. Retail Products Manager: The retail products manager is required to fulfill project expectations assigned to her to the best of her abilities, and to communicate problems and limitations to meeting these expectations to the project manager as they arise. 5. Facilities Manager: The facilities manager is required to fulfill project expectations assigned to him to the best of his abilities, and to communicate problems and limitations to meeting these expectations to the project manager as they arise. 6. Marketing Team: The marketing team is required to execute a grand-opening celebration for the new retail store on Feb. 1. 7. IT Manager: The IT manager is required to fulfill project expectations assigned to him to the best of his abilities, and to communicate problems and limitations to meeting these expectations to the project manager as they arise.
December 10, 2013
Roles and Responsibilities
Page 35
TEAM OPERATING AGREEMENT Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Team Values and Principles 1. Good communications 2. Good Documentation 3. Meet deadline 4. Deliverable 5. Meet quality status Meeting Guidelines 1. Deadline are important and should be met by everyone 2. Once a week meeting for project update and change notification 3. Extended meetings when necessary 4. Each member would give briefs on the progress and what need to be addressed Communication Guidelines 1. Verbal and written 2. Project documentation update 3. Check regular email every for update Decision-Making Process Responsible parties include the Project Manager, Stakeholders and any team member who is concerned
December 10, 2013
Team Operating Agreement
Page 36
TEAM OPERATING AGREEMENT Conflict Management Approach Use meeting and change management as well as Alternative Conflict Resolution methods.
Signature:
Date:
Dirk Perrier, project sponsor
12/10/13
Kirsten Rivera, project manager
12/10/13
Jake Peterson , construction and facilities manager
12/10/13
Jill Overstreet, retail products and marketing manager
12/10/13
Ricardo Santiago , information technology manager
12/10/13
December 10, 2013
Team Operating Agreement
Page 37
TEAM MEMBER PERFORMANCE ASSESSMENT Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Technical Performance – Ricardo Santiago Scope
Meets Expectations Yes
Needs Improvement
Exceeds Expectations
Meets Expectations Yes
Needs Improvement
Exceeds Expectations
Meets Expectations Yes
Needs Improvement
Meets Expectations Yes
Needs Improvement
Exceeds Expectations
Comments: IT Cable Install by Ricardo’s team Quality Comments: Install Schedule
Comments: Cable Install and Lease Cost
Exceeds Expectations
Comments: Project Cost
December 10, 2013
Team Member Performance Assessment
Page 38
TEAM MEMBER PERFORMANCE ASSESSMENT Interpersonal Competency Communication
Exceeds Expectations Yes
Meets Expectations
Needs Improvement
Exceeds Expectations Yes
Meets Expectations
Needs Improvement
Exceeds Expectations
Meets Expectations Yes
Needs Improvement
Exceeds Expectations
Meets Expectations Yes
Needs Improvement
Exceeds Expectations Yes
Meets Expectations
Needs Improvement
Comments: Project Communication Collaboration
Comments: Very collaborative other team members Conflict Management Comments: Good at conflict resolution Decision Making Comments: Firm decisions Leadership Comments: Good Leadership Strengths Communication, documentation and project execution
Weaknesses Negotiations and enforcing deadlines
December 10, 2013
Team Member Performance Assessment
Page 39
TEAM MEMBER PERFORMANCE ASSESSMENT Areas for Development Area
Approach
Actions
Negotiations project
Be firm
Strong negotiations deals needed
Ramp-up time
Improvement
Negotiate better deadlines and enforce it
Additional Comments N/A
December 10, 2013
Team Member Performance Assessment
Page 40
PROCESS IMPROVEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Process Description Conduct Procurements process for obtaining responses to bids and proposals from potential vendors, selecting a vendor, and awarding the contract for the construction of Kitchen Heaven store. Process Boundaries Process Starting Point
Process Ending Point
Determine store location.
Award construction contract.
Inputs
Outputs
Lease RFP Cost Baseline Qualified Sellers List References Previous Work
Agreement Selected Seller Resource Calendars Change Requests PMP Updates Project Document Updates
Stakeholders Process Owner: Jake Peterson Other Stakeholders Dirk Perrier Jill Overstreet Ricardo Bryan (Ricardo’s team lead) Marketing Department Stakeholder
December 10, 2013
Process Improvement Plan
Page 41
PROCESS IMPROVEMENT PLAN Process Metrics Metric
Control Limit
1. Estimated Time from Begin Buildout to Complete Buildout (days)
1. Acceptable: 120 days Upper Control Limit: 132 days Lower Control Limit: 108 days
2. Contract Procurement Time, including negotiation (days)
2. Acceptable: 14 days Upper Control Limit: 15.4 days Lower Control Limit: 12.6 days
3. Vendor Weighted Score (out of 60)
3. Acceptable: 53 Upper Control Limit: 58.3 Lower Control Limit: 47.7
Targets for Improvement
Metric
Current or Target?
Acceptable
Upper
Lower
Estimated Time from Begin Buildout to Complete Buildout
Current
120 days
132 days
108 days
Estimated Time from Begin Buildout to Complete Buildout
Target
108 days
118.8 days
97.2 days
Contract Procurement Time, including negotiation
Current
14 days
15.4 days
12.6 days
December 10, 2013
Process Improvement Plan
Page 42
Contract Procurement Time, including negotiation
Target
12.6 days
13.86 days
11.34 days
Vendor Weighted Score
Current
53
58.3
47.7
Vendor Weighted Score
Target
56
61.6
50.4
Process Improvement Approach
Current Process:
Intended Future Process:
December 10, 2013
Process Improvement Plan
Page 43
PROCUREMENT MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/13
Procurement Authority Ricardo – Drafted procurement statement of work for IT deliverables Jill – Drafted procurement statement of work for Gourmet & Cookware lines purchases Roles and Responsibilities: Project Manager
Procurement Department
1. Ricardo
1. IT
2. Jill
2. Inventories
3. Jake
3. Furnishings
4. Gomez
4. Build-out
Standard Procurement Documents 1. 2. 3. 4.
Procurement statement of work Fixed-Price Contract Time and Materials Contract Lease Agreement
Contract Type Fixed-Price Contract: Purchase of routes & switches will be accomplished through fixed-price contract Time & Materials Contracts: Human Resources for running Ethernet cable procuring the T1 line. Procurement Assumptions and Constraints Assumptions: The lease will signed by the end of the week. Constraints: The lease must be signed by the lease signing date.
December 10, 2013
Procurement Management Plan
Page 44
PROCUREMENT MANAGEMENT PLAN Integration Requirements WBS
The WBS and WBS dictionary identify the deliverables and describe the work required for each element of the WBS. Procurement of the resources necessary to complete these deliverables by the due date is the purpose of this plan.
Schedule
The schedule influences the procurement process and vice versa because they are both dependent on timing. Availability of resources can significantly impact the outcome of the project. For example, a contract being canceled or failing to procure a seasonal product or service could cause delays later in the project.
Documentation The documentation process involves a procurement document. The document must (1) state the description of the work requested, (2) include the contract SOW, and (3) an explanation of how the seller should format their responses. Risk
The risk register is a useful tool in determining the types of goods or services trying to be procured. Integrating risk into this process is essential to maintaining appropriate levels of risk as defined by the organization’s policies, the stakeholders’ risk appetite, and other external environmental factors. Tool used to procure resources in regards to risk may include: (2) Perform a Make or Buy Analysis, (2) Market Research, and/or (3) Contract Types
Performance Reporting
Throughout the project lifecycle, there will be a need to track and evaluate the progress being made in the various procurement processes. The use of performance metrics will be used in order to insure that the schedule and risk levels are aligned with the WBS and WBS dictionary.
Performance Metrics Domain
Metric Measurement
Statistical Sampling of Cost of quality will help determine if the procured resources are at an Supplies Ordered from adequate level of quality. Acceptable levels of quality may be found in Vendors the quality management plan. Jill ran into issues procuring the gourmet food supplies due to an external and internal failure cost of quality. The first vendor went out of business and the second vendor sold too low of quality supplies for the grand opening.
December 10, 2013
Procurement Management Plan
Page 45
SOURCE SELECTION CRITERIA Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Criteria 1
1 Purchase Price
2 Purchase Price
3 Purchase Price
4 Purchase Price
5 Purchase Price
Criteria 2
Delivery Cost
Delivery Cost
Delivery Cost
Delivery Cost
Delivery Cost
Criteria 3
Financial Capacity
Financial Capacity
Financial Capacity
Financial Capacity
Financial Capacity
Criteria 4
Production Capacity Production Capacity
Production Capacity Production Capacity Production Capacity
Criteria 5
Overall Cost
Overall Cost
Weight
Overall Cost
Candidate 2 Rating
Overall Cost
Criteria 1
.10
3
Candidate 1 Score .3
Criteria 2
.10
2
.2
3
.3
1
.1
Criteria 3
.10
2
.2
1
.1
3
.3
Criteria 4
.10
1
.1
3
.3
2
.2
Criteria 5
.60
3
1.8
1
.6
2
1.2
Totals
1
11
2.6
10
1.5
9
1.9
December 10, 2013
Candidate 1 Rating
Overall Cost
2
Candidate 2 Score .2
1
Candidate 3 Score .1
Source Selection Criteria
Candidate 3 Rating
Page 46
QUALITY MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/13
Quality Roles and Responsibilities Role 1. Project Manager
Responsibilities ➔ Documenting stakeholder expectations and consensus quality management objectives at a project-level that supports the implementation of the PMP. ➔ Utilizing the expertise of the project staff to determine the procedures necessary to achieve the target level of quality. ➔ Ensuring stakeholders endorse quality objectives stated in the QMP. ➔ Understanding the stakeholders’ roles in project success. ➔ Working with the stakeholders early in the project lifecycle to determine needs, and refining those requirements in light of constraints. ➔ Considering the cost/benefit of all quality improvements.
2. Project Staff
➔ Delivering a quality product. ➔ Performing an active role to ensure quality objectives are clearly articulated and that the stakeholder understands the essential professional standards, laws, and codes which must be incorporated into the project. ➔ Monitoring the quality of their work. ➔ Keeping the commitments for completion of their portion of the project as documented in the QMP.
3. Jill Overstreet
➔ Monitoring the quality of her work and the work of her staff. ➔ Serving on an independent review team, when appropriate.
4. Ricardo
➔ Monitoring the quality of his work, and the work of his staff. ➔ Serving on an independent review team, when appropriate.
December 10, 2013
Quality Management Plan
Page 47
QUALITY MANAGEMENT PLAN Quality Planning Approach What
Define quality on the project and how quality will be measured
When
Planning
Processes
Develop Project Management Plan Define Scope Collect Requirements Develop Project Team Estimate Activity Resources Estimate Activity Durations Estimate Costs
Quality Assurance Approach What
Determine if measurement of quality is appropriate by evaluating overall performance on a regular basis to insure the project will satisfy customer quality expectations
When
Executing, Monitoring & Controlling
Processes
Perform QA
Quality Control Approach What
Monitor specific project products to determine if they meet performance measurement thresholds defined in the quality management plan
When
Executing, Monitoring & Controlling, Closing
Processes
Perform QA Manage Communications (lessons learned meetings) Close Project or Phase (lessons learned meetings)
Quality Improvement Approach What
Increase the effectiveness and efficiency of the project when corrective actions such as Change Requests are identified. Changes to the QMP and the PMP may be required
When
Planning, Executing, Monitoring & Controlling
Processes
Develop Project Management Plan Perform Integrated Change Control
December 10, 2013
Quality Management Plan
Page 48
QUALITY METRICS Project Title: New Kitchen Heaven Retail Store ID
Item
Metric
Date Prepared: 12/10/2013 Measurement Method
1
Project Schedule
Time
Schedule Performance Index (SPI) = Earned Value ÷ Planned Value
2
Budget
Cost
Cost Performance Index (CPI) = Earned Value ÷ Actual Cost
3
Project Schedule
Resources
Amount of hours overspent per installations/construction
4
Change Management
Scope
Number of Change Requests
5
Quality Management
Quality
Number of defects fixed per user acceptance test
6
Project Schedule
Action Items
Number of action items behind schedule for resolution
December 10, 2013
Quality Metrics
Page 49
REQUIREMENTS MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store Date: 12/10/13 Collection
Store property must be located in Colorado Springs, CO. Store must open February 1, 2014 to coincide with Garden and Home Show conference in Colorado Springs. The store should have between 1,500 and 2,500 square feet of retail space. Local contractors should be used for the build-out. Project requires team to sign a lease within 14 days. Store must offer new line of gourmet food products. Store must have classroom space in back of store for cooking demos and classes. Project must cost less than $2 million. Jill Overstreet needs 14 days to hire personnel and stock shelves. Signed lease Order T1 connection Ethernet Cable Run Contract with Gomez Build-Out Install and Test Hardware Order Retail Products Hire Retail Products and Stock Shelves Grand Opening
Analysis
There is an overlapping relationship between these requirements. If there is to be a change to any of the requirements it must be reported to the Project Manager with a plan of action moving forward.
Categories
Building and Cabling Store Budget Human Resources Schedule Products
Documentation
Requirements are to be documented and monitored in the Requirements and Traceability Matrix
Prioritization
Ordinal prioritization (high, medium, low)
December 10, 2013
Requirements Management Plan
Page 50
REQUIREMENTS MANAGEMENT PLAN Metrics
These requirements will be traced in hours.
Traceability Structure
Requirements will all have a priority level, category, source, and objective and will be organized this way in the traceability matrix.
Tracking
These requirements will be tracked by weekly progress reports given to the Project Manager and necessary stakeholders.
Reporting
Progress of the requirements will be tracked on and reported on a weekly basis. The project manager must be notified when tasks are completed and if they are running behind schedule.
Validation
Once a requirement is completed the project manager must be notified and will validate that the requirement is completed to the proper standard and that it is okay to move onto that party’s next requirement.
December 10, 2013
Requirements Management Plan
Page 51
REQUIREMENTS TRACEABILITY MATRIX Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Requirement Information
ID
Requirement
Priority
KHCS1001
Signed Lease
High
Building and Cabling
Dirk Perrier
Phase 2
yes
hours
complete
KHCS1002
Order T1 Connection
High
Building and Cabling
Activity List
Phase 2
yes
hours
complete
KHCS1003
Ethernet Cable Run
low
Building and Cabling
Activity List
Phase 2
yes
hours
complete
KHCS1004
Contract With Gomez
high
Building and Cabling
Activity List
Phase 1
yes
hours
complete
KHCS1005
Build-Out
high
Building and Cabling
Activity List
Phase 1
yes
hours
complete
KHCS1006
Build-Out Complete
high
Building and Cabling
Activity List
Phase 1
yes
hours
Not complete
KHCS1007
Instal and Test Hardware
high
Hardware
Activity List
Phase 1
yes
hours
KHCS1008
Order Retail Products
high
STORE
Activity List
Phase 3
yes
hours
Not complete
KHCS10010
Hire Retail Products and Stock Shelves
high
STORE
Activity List
Phase 3
yes
hours
Not complete
KHCS10011
Grand Opening
high
STORE
Activity List
Phase 3
yes
hours
Not complete
December 10, 2013
Category
Relationship Traceability
Source
Risk Management Plan
Objective
WBS Deliverable
Page 52
Metric
Validation
complete
REQUIREMENTS DOCUMENTATION Project Title: New Kitchen Heaven Retail Store Date Prepared: 12/10/2013 ID
Requirement
Stakeholder
Category
Priority
Acceptance Criteria
Validation Method
KHCS-1001
Signed Lease
Dirk Perrier
Building and Cabling
High
Signed within 14 days
Signed lease document
KHCS-1002
Retail Product Line
Dirk Perrier
Store
High
Delivered 14 days prior to opening
Inventory receipt and confirmation
KHCS-1003
In-Store Classroom
Dirk Perrier
Building and Cabling
High
Completed by grand opening
Approval by Dirk
KHCS-1004
Project Cost
Dirk Perrier
Budget
High
Project is completed at or below $2 million budget
Written Confirmation from Accounting
KHCS-1005
Jill’s Time Requirement
Jill Overstreet
Building and Cabling
Medium
Jill has 14 days to to hire personnel and stock shelves
Hiring and stocking completion notification from Jill
December 10, 2013
Risk Management Plan
Page 53
RISK MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store Date Prepared: 12/10/2013 Methodology The Risk Management Plan will be used to define, monitor, and control risks throughout the project. Defining risk will be accomplished through identifying the risk attitudes of the organization and its stakeholders using techniques such as: 1. Regular documentation reviews 2. Gathering information 3. Checklist analysis 4. Assumptions analysis 5. Diagramming 6. Strengths-weaknesses-opportunities-threats (SWOT) analysis 7. Expert judgment After risks have been identified and properly documented in risk register, a qualitative analysis will be performed by utilizing a risk probability impact matrix and a risk data quality assessment. Once the risks have been evaluated from a qualitative perspective, a quantitative analysis will be performed to determine the overall impact of these risks. The quantitative analysis will look at: 1. Possible outcomes and probabilities 2. Identify risks that need the most attention 3. Identify realistic and achievable schedule, cost, or scope targets 4. Determine the best project management decisions possible when outcomes are uncertain Quantitative analysis of risks will be performed by gathering data from probability distributions, performing various modeling techniques (such as EMV, decision tree, simulation, or sensitivity) and documented on the risk register. Once this part of the process has been completed, developing a risk response plan will be necessary to determine which actions to take for the risks that have the highest probability of occurring and highest impact to the project. Strategies are developed in the risk response plan process to address negative and positive risks, as well as contingency plans. Role and Responsibilities Ricardo - Risks associated with IT tasks Jill and Jake - Risks related to store stocking and furnishings Risk Categories IT Risks (Account ID: 1000’s): 1. T1 line availability and installation. Risk ID: 1001. Risk Score: Very Low 2. Contractor availability for Ethernet Installation. Risk ID: 1002. Risk Score: Medium 3. POS and server hardware availability. Risk ID: 1003. Risk score: Medium Facilities (Account ID: 2000’s): 1. Desirable location in the right price range. Risk ID: 2001. Risk score: High 2. Contractor availability for build-out. Risk ID: 2002. Risk score: Low 3. Availability of fixtures and shelving. Risk ID: 2003. Risk score: Low Retail (Account ID: 3000’s): 1. Product availability. Risk ID: 3001. Risk score: Medium 2. Shipment dates for product. Risk ID: 3002. Risk score: Low
December 10, 2013
Risk Management Plan
Page 54
Risk Management Funding Contingency reserves will need to be accounted for based on the likelihood and impact of a risk in relation to the remaining balance of the reserve account. The reserve account should include all the quantified risks in order to maintain an accurate budget. Contingency Protocols Contingency protocols help determine alternative methods of dealing with certain risks. When a risk event occurs, the contingency plan reserve strategy will be in place for that particular event. This protocol may include setting aside funding, resources, and adding project time to the project schedule. In the development of each contingency protocol, it is important to consider the impact the contingency will have on the project. Frequency Timing Risk management documents will be reviewed and evaluated when a risk becomes an issue, needs to be modified, or a new risk has been identified. Documents associated with risk must be monitored and updated to accurately reflect the projects current risks every couple of days, or as needed. Stakeholder Risk Tolerance Stakeholder risk tolerances change throughout the life of the project, new risk tolerances will be documented in this section. In the interview with Ricardo, the risk tolerance for the T1 Line Availability and Installation became a higher priority as Ricardo identified that a risk of delay could postpone the T1 line for up to 3 to 4 months, with a low possibility of it being 6 months. Tracking and Audit Once risks have been identified, they will need to be subsequently tracked throughout the remainder of the project. Tracking the risks will start by referencing the frequency timing section in the Risk Management Plan to ensure that the risks are still applicable to the current project. To determine if risks are still relevant, an audit of the risks will be done by assessing the pending deadlines and current project resources.
December 10, 2013
Risk Management Plan
Page 55
RISK MANAGEMENT PLAN Definitions of Probability Very high
When the probability of an event is from 80%-100%
High
When the probability of an event is from 60%-80%
Medium
When the probability of an event is from 40%-60%
Low
When the probability of an event is from 20%-40%
Very low
When the probability of an event is from 0%-20%
Probability Impact Matrix Very High
.64
.48
.32
.16
.04
High
.48
.36
.24
.12
.03
Medium
.32
.24
.16
.08
.02
Low
.16
.12
.08
.04
.01
Very Low
.04
.03
.02
.01
.0025
Very High
High
Medium
Low
Very Low
Definitions of Impact Objective Scope
Quality
Time
Cost
Very High
.8
Product Not Usable
More than 18% increase
More than 18% increase
High
.6
Unacceptable quality
13%-18% increase
13%-18% decrease
Medium
.4
Significant impact requiring customer approval to proceed
7%-12% increase
7%-12% decrease
Low
.2
Few components impacted
Less than 6% increase
Less than 6% increase
No significant impact
No significant impact
No significant impact
Very Low
December 10, 2013
.05
Risk Management Plan
Page 56
PROBABILITY AND IMPACT MATRIX Project Title: New Kitchen Heaven Retail Store Date Prepared: 12/10/2013 Very High:
.04
.16
.32
.48
.64
.03
.12
.24
.36
.48
.02
.08
.16
.24
.32
.01
.04
.08
.12
.16
.0025
.01
.02
.03
.04
.8 High .6 Medium .4 Low .2 Very Low .05 Very Low: .05
December 10, 2013
Low: .2
Medium : .4
Risk Register
High: .6
Very High: .8
Page 57
RISK REGISTER Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013 Impact
Risk ID
Risk Statement
Scope 1001
T1 Line
.2-.4
Low
1002
Contractor Availability: Ethernet Installation
.4-.6
Medium
1003
POS and Server Hardware Availability
.4-.6
Medium
2001
Desirable location in Price Range
60%
High
2002
Contractor Availability for .2-.4 build out
Low
2003
Availability of fixtures and shelving
.2-.4
Low
3001
Product availability
40%
Medium
3002
Shipment dates for product
.4-.6
Medium
December 10, 2013
Score
Response
Schedule
Cost
Probability
Risk Register
Quality
Mitigation
Loss of $1.3 Million Expected Income per year
125000 Loss
Page 58
SCHEDULE MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Schedule Methodology The methodology is based on Schedule Net-work analysis, Milestone Charts.
Schedule Tools Project Management Software : Microsoft Project; Cost of Quality; Reserve analysis; Vendor bid Analysis; Group decision - making techniques Excel
Level of Accuracy
Units of Measure
95%
Hours
Variance Thresholds +/- 5%
Schedule Reporting and Format Schedule baseline and the reporting format is Milestone Method in time, Finish-to-start (FS)
Process Management Activity identification
Activity List; Project Schedule Plan with analogous estimating and rolling wave planning.
Activity scheduling
Milestone Chart and schedule compression
Estimating resources
Activity list; Leads and lags
Estimating effort and duration
Expert judgment based on Top - down Techniques and Days for duration were used
Updating, monitoring and controlling
Project documentation updates .This would be done on share drive Project Plan
December 10, 2013
Schedule Management Plan
Page 59
ACTIVITY DURATION ESTIMATES Project Title: 50th Kitchen Heaven Store in Colorado Springs & Grand-Opening Celebration Date Prepared: 12/10/2013
WBS ID
Activity Description
Effort Hours
Duration Estimate
1.0
BUILDING AND CABLING
1.1
Sign Lease
8
Days by 8hrs of work
1.2
Order T1 Connection
360
Days by 8hrs of work
1.3
Ethernet Cable Run
16
Days by 8hrs of work
1.4
Contract With Gomez
16
Days by 8hrs of work
1.5
Build-Out
960
Days by 8hrs of work
1.6
Build-Out Complete
0
Days by 8hrs of work
2.0
IT HARDWARE
2.1
Purchase Hardware
112
Days by 8hrs of work
2.2
Install and Test Hardware
24
Days by 8hrs of work
2.3
Add Store to Website
8
Days by 8hrs of work
2.4
It Tasks Complete
0
Days by 8hrs of work
3.0
STORE
3.1
Order Retail Products
120
Days by 8hrs of work
3.2
Hire Retail Products and Stock Shelves
112
Days by 8hrs of work
3.3
Train Store Personnel
16
Days by 8hrs of work
3.4
Grand Opening
16
Days by 8hrs of work
3.5
Project Closeout
40
Days by 8hrs of work
3.6
Project Ends
0
Days by 8hrs of work
December 10, 2013
Activity Duration Estimates
Page 60
ACTIVITY ATTRIBUTES Project Title: New Kitchen Heaven Retail Store
ID: 30100
Date Prepared: 12/10/2013
Activity: Sign Lease
Description of Work: Complete leasing by signing lease contract for retail space.
Predecessors
Relationship
1.2
Lead or Lag lead
Successor
Relationship
1.0
Number and Type of Resources Required:
Skill Requirements:
Personnel, Legal information
Expert knowledge, legal knowledge
Lead or Lag lead
Other Required Resources:
Type of Effort: Time and meeting dead lines
Location of Performance: Real estate office, Colorado Springs, CO
Imposed Dates or Other Constraints: Must be completed by 1/15/2013.
Assumptions: Assuming everything will be on schedule
December 10, 2013
Activity Attributes
Page 61
ACTIVITY RESOURCE REQUIREMENTS Project Title: New Kitchen Heaven Retail Store Date Prepared: 12/10/2013 WBS ID
Type of Resource
Quantity
Assumptions
1.0
BUILDING AND CABLING
1.1
Sign Lease
2
People
1.2
Order T1 Connection
2
People
1.3
Ethernet Cable & IT works
24 bundles + 8 Peoples
1.4
Cement
100
Bags
1.5
Build-Out
50
People
1.6
Ground work equipment
5 + 10 People
1.7
Purchase Hardware
6
People
1.8
Install and Test Hardware
15
People
1.9
Add Store to Website
3
People
1.10
IT Tasks Complete
3
People
2.0
STORE
2.1
Order Retail Products
4
People
2.2
All Other hardware and Equipment
5
People
2.3
All Other hardware and Equipment
7
People
Comments: The is based on what is needed and at low cost
December 10, 2013
Activity Resource Requirements
Page 62
DURATION ESTIMATES WORKSHEET Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Three Point Estimates WBS ID
Optimistic Duration
Most Likely Duration
Pessimistic Duration
Weighting Equation
Expected Duration Estimate
1.0
1360
1300
1400
1326.67
2.0
144
140
160
3.0
304
300
290
(O + (4*ML) + P) / 6 (O + (4*ML) + P) / 6 (O + (4*ML) + P) / 6
December 10, 2013
Duration Estimates Worksheet
144 299
Page 63
RESOURCE BREAKDOWN STRUCTURE Project Title: New Kitchen Heaven Retail Store 1.
Date Prepared: 12/10/2013
Project 1.1. People 1.1.1. Quantity of Role 1: IT: 20 people 1.1.1.1. Quantity of Level 1: Build Out: 50 People 1.1.1.2. Quantity of Level 2: Store: 10 people 1.1.1.3. Quantity of Level 3: Interior and Exterior Decorations- 8 peoples 1.1.2. Quantity of Role 2: Closeout- 5 peoples 1.2. Equipment 1.2.1. Quantity of Type 1: Ladders, Stoves, Shelve, water filters 1.2.2. Quantity of Type 2: Lifts and Forklifts 1.3. Materials 1.3.1. Quantity of Material 1: Cement, IT and Electrical cables, paints and wood 1.3.1.1. Quantity of Grade 1: Tables, Chairs, decorations 1.3.1.2. Quantity of Grade 2: Store retail items 1.4. Supplies 1.4.1. Quantity of Supply 1: 50 Shelves, 24 bundles of IT and electrical Cables, 25 Tables and Chairs 1.4.2. Quantity of Supply 2: 20 tons retail supplies 1.5. Locations 1.5.1. Location 1: Kitchen Heaven Site 1.5.2. Location 2: Store front
December 10, 2013
Resource Breakdown Structure
Page 64
PROJECT SCHEDULE Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Task Name
Duration (Days)
Start Date
Finish Date
Kitchen Heaven Project
178.25
Mon. 8/21/2013
Wed. 2/7/2014
BUILDING AND CABLING
152.5
Mon. 8/21/13
Mon. 1/15/14
Sign Lease
1
Mon. 8/21/2013
Mon. 8/21/2013
Jill, Project Manager
Order T1 Connection
45
Mon. 8/21/2013
Mon. 10/2/13
Ricardo
Ethernet Cable Run
2
Mon. 9/18/2013
Tue. 9/19/2013
3
Ricardo
Contract With Gomez
2
Mon. 9/11/2013
Tue. 9/12/2013
3
Jill, Project Manager
Build-Out
120
Wed. 9/20/13
Mon. 1/15/14
Build-Out Complete
0
Mon. 1/15/14
Mon. 1/15/14
IT HARDWARE
17.5
Mon. 1/8/14
Wed. 1/24/14
Purchase Hardware
14
Mon. 1/8/14
Sat. 1/20/14
Install and Test Hardware
3
Sat. 1/20/14
Tue. 1/23/14
Add Store to Website
1
Tue. 1/9/14
Tue. 1/9/14
It Tasks Complete
0
Wed. 1/24/14
Wed. 1/24/14
December 10, 2013
Project Schedule
Predecessors Resources Names
Page 65
Contractor 7
Ricardo 5,10
Ricardo Ricardo
11
STORE
28.5
Mon. 1/8/14
Fri. 2/2/14
Order Retail Products
15
Mon. 1/9/14
Mon. 1/22/14
Jill, Project Manager
Hire Retail Products and Stock Shelves
14
Tue. 1/10/14
Mon. 1/29/14
Jill, Project Manager
Train Store Personnel
2
Tue. 1/30/14
Wed. 1/31/14
Grand Opening
2
Thu. 2/1/14
Fri. 2/2/14
Project Closeout
5
Fri. 2/2/14
Wed. 2/7/14
18
Jill, Project Manager
Project Ends
0
Wed. 2/7/14
Wed. 2/7/14
19
Project Manager
December 10, 2013
Project Schedule
Page 66
11, 18
Jill, Project Manager Jill, Project Manager
ACTIVITY LIST Project Title: New Kitchen Heaven Retail Store ID
Date Prepared: 12/10/2013
Activity
Description of Work
1.0
BUILDING AND CABLING
1.1
Sign Lease
Signing the lease agreement
1.2
Order T1 Connection
T1 cable procurement
1.3
Ethernet Cable Run
Installation of the Ethernet cable
1.4
Contract With Gomez
Signing the Contract
1.5
Build-Out
Start of renovation and grounds work
1.6
Build-Out Complete
When to complete the build out
2.0
IT HARDWARE
2.1
Purchase Hardware
All hardware purchasing
2.2
Install and Test Hardware
Installation activities
2.3
Add Store to Website
Website development and testing
2.4
IT Tasks Complete
when to complete IT stuff
3.0
STORE
3.1
Order Retail Products
Retail stuff
3.2
Hire Retail Products and Stock Shelves
workers for the store
3.3
Train Store Personnel
Training activities
3.4
Grand Opening
Preparations and activities for the grand opening
3.5
Project Closeout
When the project closes out
3.6
Project Ends
Time to complete and hand over
December 10, 2013
Activity List
Page 67
SCOPE MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store
Date Prepare: 12/10/2013
Scope Statement Development Project objectives: Open 50th store by Feb. 1 in Colorado Springs Project Deliverables: ● Build out storefront, including shelving ● Retail product line will be delivered two weeks prior to grand opening ● Have grand opening party with cooking demos Project Requirements: ● Sign lease within 14 days ● Offer new line of gourmet food products ● Have classroom space in back of store for cooking demos and classes Constraints: Feb. 1 date will coincide with home and garden show Fund Limitations: Spend no more than $2 million on the project Assumptions: ● A store build-out usually takes 120 days ● Jill Overstreet will help with the initial store stocking ● Jake Peterson will provide supplies for the stores that aren’t retail products, such as store furnishings, shelving, and so on, and can help with the store build-out as well. ● The budget for the project will be between $1.5 and $2 million WBS Structure Level 1: The Project: Building the New Store Level 2: Subproject or deliverables (demolition, design, bridgework, and paving) Level 3: Deliverable: (location, store build-out, furnishings, product) Level 4: Time and cost estimate (Constraints: February 1 date will coincide with home and garden show. Fund limitations: Spend no more than $2 million for the project. )
December 10, 2013
Scope Management Plan
Page 68
WBS Dictionary Code of account identifier: Description of the Work of the component: 1. Buildout and ground preparations 2. IT Work on Cable installations 2.1 Procure The T1 connection 2.2 Run Ethernet Cable Throughout the building 2.3 Purchasing of Routers, switches servers and racks 2.4 Installations of Switches, Routers and Racks 2.5 Testing and adding location and phone to lookup function 3. Personnel Hiring and Shelves stocking List Schedule Milestones: Milestone 1: Construction and IT’s jobs - Ricardo’s Team done by Sept 20 Milestone 2: Build-out, Personnel Hiring by Jill’s Team done by January 26 Milestone 3: Grand Opening Preparation done by January 30 Organization responsible for completing the component: 1. Jake’s Team - General Construction of store Build-out, furnishing, Shelving installation and storage room 2. Jim’s team - Retail Product: Sign Lease, Gourmet Product, Cookware line and Store Stocking 3. Ricardo’s team - IT Equipment hardware Procurement, installation and Testing 4. Jim’s team - Grand Opening: refreshment and Chef’s Demos Cost Estimates: Total Project cost: Estimate $ 1.5 to $2.0 million Addition $10,000 for Ricardo’s Team Contract or Agreement information Constraints and Assumptions: 1. February 1st date coinciding with home and garden show. Assumptions: 1. A store build-out usually takes 120 days. 2. Jill Overstreet will help with the initial store stocking. 3. Jake Peterson will provide supplies for the stores that aren’t retail products, such as store furnishings, shelving, and so on, and can help with the store build-out as well. 4. The budget for the project will be between $1.5 and $2 million.
December 10, 2013
Scope Management Plan
Page 69
SCOPE MANAGEMENT PLAN Scope Baseline Maintenance The scope baseline maintenance will be used to monitor the status of the scope of the project. The team will utilize the WBS Dictionary as a framework for the project and ensure that they perform only the work described in the WBS Dictionary. This is measurable by generating deliverables for each WBS element. Maintenance must be timely so that the project is not tracking obsolete or other goals unmentioned in the WBS Dictionary. If there is a scope change, the corresponding cost baseline and schedule baselines must be adjusted to reflect the changes. See Sections: 1. Scope Statement 2. The WBS 3. WBS Dictionary Scope Change Any major change to the scope will need to be verified by all of the stakeholders to make sure that it is okay. The project manager first will decide if they think the change is necessary and they will then approach all stakeholders and make sure they approve the change. If there is just a scope revision it will be left to the project manager’s best judgment whether or not the revision is necessary for the success of the project. Scope changes will be anticipated and budgeted for accordingly. Deliverable Acceptance Project Deliverables: ● Build out storefront, including shelving ○ The storefront look must be consistent with all of the other 49 stores throughout the country. This will need to be approved and signed off by someone in the Marketing department. ● Retail product line will be delivered two weeks prior to grand opening ○ The retail product line must be displayed throughout the store in a way that is easy for customers to find what they want and consistent with other stores in the country. This will need to be approved by…? ● Have grand opening party with cooking demos ○ Customers will be expecting cooking demos of high quality by people who know what they are talking about. Is will be important to hire instructors with good experience and will be approved by the project manager as well as someone in the Marketing Department.
December 10, 2013
Scope Management Plan
Page 70
Scope and Requirements Integration As requirements are collected, they will be documented in a way that describes how the requirements meet the business need for the project. However, before being included into the scope, they must be unambiguous, traceable, complete, consistent, and acceptable to stakeholders. Components of requirements documentation may include: ● Business requirements (project objectives, business rules, and guidelines of the organization) ● Stakeholder requirements (impact to other entities or organization areas, stakeholder communication and reporting requirements) ● Solution requirements (functional/nonfunctional, technology and compliance, support and training, quality) ● Project requirements (performance, safety, compliance, levels of service, acceptance) ● Transition requirements ● Requirements assumptions, dependencies, and constraints. Requirements documentation may need to be updated to include any approved changes. Verification and integration of new or updated requirements into the WBS Dictionary must be accompanied with a signature from the project manager.
December 10, 2013
Scope Management Plan
Page 71
PROJECT SCOPE STATEMENT Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013
Product Scope Description The 50th Kitchen Heaven store, located in Colorado Springs, will open February 1 with a grandopening celebration. The project will involve: procuring the property, negot iating the lease, procuring the shelving and associated store furnishings, getting a contractor on the job, and preparing the 50th store festivities in collaboration with the marketing department.
Project Deliverables Storefront complete with shelving and other store furnishings, outfitted with retail product lines, with classrooms at back of store. Grand-opening celebration with Colorado Springs community, including cooking demos with local chefs.
Project Acceptance Criteria Storefront build out construction is complete and site passes independent, city and county inspections. Store furnishings are set up. > 90% of ordered retail products ordered are received and stocked on floor. > 90% of personnel needs are met and staff complete minimum two-week training. At least three local chefs are secured for cooking demonstrations for grand-opening celebration. Other catering for event is ordered.
Project Exclusion Site does not pass inspections. Store furnishings are poorly crafted/unavailable. < 90% of necessary retail products are not physically in store by project completion date. < 90% of personnel needs are not met at least two weeks before grand-opening. Local chefs are not located/booked for participation in grand-opening celebration. Catering is not secured for event.
Project Constraints Spend no more than $2 million on project. Complete project - have all deliverables completed by Feb. 1, 2014.
Project Assumptions ● ● ●
A store build-out usually takes 120 days Jill Overstreet will help with the initial store stocking Jake Peterson will provide supplies for the stores that aren’t retail products, such as store furnishings, shelving, and so on, and can help with the store build-out as well. The budget for the project will be between $1.5 and $2 million
December 10, 2013
Project Scope Statement
Page 72
STAKEHOLDER MANAGEMENT PLAN Project Title: New Kitchen Heaven Retail Store Stakeholder
Unaware
Resistant
Date Prepared: 12/10/2013 Neutral
Supportive
Dirk Perrier
Leading
C
Jill Overstreet
C/D
Jake Peterson
C/D
Ricardo
C/D C/D
Gomez Construction Crew
C/D
Arrow Consulting Team C
Marketing Team
D
C = Current level of engagement D = Desired level of engagement
December 10, 2013
Stakeholder Management Plan
Page 73
Stakeholder
Communication Needs
Method/Medium
Timing/Frequency
Dirk Perrier
Inform Project Sponsor of Face-to-face communication completion of milestones, give preferable, email or phone when updates on project progress, necessary. and consult for critical project decisions.
Weekly.
Jill Overstreet
Receive frequent check-ins Face-to-face primarily, email or about progress of retail item phone secondarily. acquisition and staffing, give updates on changes to project schedule/budget/scope in case they have residual effect.
At least every three days.
Jake Peterson
Receive frequent check-ins Face-to-face primarily, email or about progress of store phone secondarily. furnishings acquisition; give updates on changes to project schedule/budget/scope in case they have residual effect.
At least every three days.
Ricardo
Receive frequent check-ins Face-to-face primarily, email or about progress of IT-related phone secondarily. installations and testing, give updates on changes to project schedule/budget/scope in case they have residual effect.
At least every two days.
Gomez Construction Crew Because deadline constraint is Telephone primarily, face-to-face critical to success of project, secondarily. check in frequently about construction progress and issues that arise.
December 10, 2013
Stakeholder Management Plan
Daily.
Page 74
Arrow Consulting Team
Update on all developments of Face-to-face primarily, email or project as they occur. phone secondarily.
Daily.
Marketing Team
Communicate changes to Face-to-face primarily, email or schedule/budget/scope that phone secondarily. may impact grand-opening celebration, receive updates on celebration plans to ensure they meet stakeholder expectations.
Weekly.
Pending Stakeholder Changes Madelyn was let go due to improper use of internet resource during work hours - need to find replacement stakeholder, two internal candidates are currently under consideration.
Stakeholder Relationships There is a high level of trust and respect amongst the stakeholders involved in the new Kitchen Heaven retail store project, and thus communication is effective and team dynamics functional and positive.
December 10, 2013
Stakeholder Management Plan
Page 75
STAKEHOLDER MANAGEMENT PLAN Stakeholder Engagement Approach
Stakeholder
Approach
Local Colorado Springs chefs
Jill will reach out to local restaurants and cooking schools to inquire about chefs who are wellconnected in the Colorado Springs community, to measure interest in participating in grand-opening celebration.
Colorado Springs community
Marketing team will begin advertising grand-opening celebration and new retail store several months before Feb. 1 project completion date, to garner interest and excitement.
Grand-opening celebration vendors
Jill and her team, in conjunction with Arrow Consultants, will perform online search for caterers will positive online reviews. The top five candidates will be contacted by telephone and will be informed of Kitchen Heaven’s needs for the event, and if interested will receive an RFQ from Kitchen Heaven via email. The five vendors will submit seller proposals and the top three candidates will participate in a bidder conference with key project stakeholders who are invested in this area of the project.
Jill Overstreet’s team
Two months out of project completion date, Project Manager and Arrow Consulting Team will begin meeting with Jill’s team to discuss transition of project management after Feb. 1.
Kitchen Heaven employees
All employees will receive an email one month before project completion date from Project Sponsor announcing new store opening, including an invitation to grand-opening celebration.
December 10, 2013
Stakeholder Management Plan
Page 76
STAKEHOLDER ANALYSIS MATRIX Power/Interest Project Title: New Kitchen Heaven Retail Store
Date Prepared: 12/10/2013 Dirk Perrier
Colorado Springs community
Stakeholders at kick-off meeting
Power
Jill Overstreet Jake Peterson
General contractor Leasing agent
Local chefs Grand opening caterers Jill Overstreet’s group Garden and Home Show attendees and overseers
Marketing Department
Interest
December 10, 2013
Stakeholder Analysis Matrix
Page 77
STAKEHOLDER REGISTER Project Manager: Kirsten Rivera, Arrow Consulting
Name Dirk Perrier
Position VP of Marketing
Role
Date Prepared: 12/10/2013 Contact Information
Requirements
Expectations
Influence
Classification
Project Sponsor
(555) 456-7654
[email protected]
Sign off on major project decisions
Moderate project involvement
High
Important
Jake Peterson Facilities
In charge of store furnishings
(555) 324-5644
[email protected]
Ordering and High project installation of store involvement furnishings
High
Important
Jill Overstreet
Initial store stocking, ongoing operations postopening
(555) 385-4677
[email protected]
Ordering and set- High project up of retail involvement products, and hiring and training of store personnel
High
Important
Same as ab ove
Claim ongoing Moderate operations of new project retail store after involvement project completion date
Moderate
Semiimportant
Moderate
Semiimportant
High
Important
Moderate project involvement
Moderate
Semiimportant
Negotiate lease Moderate and secure leasing project agreement involvement
Moderate
Semiimportant
Director of Retail Products
Jill Overstreet’s Retail Products group
Will take over ongoing operations of store
Arrow Consulting Team
Project consultants
Assist project manager
Ricardo
IT Manager
Oversees tech needs for new store
Stakeholders in attendance at kick-off meeting
Kitchen Heaven employees
Influence decision making
Colorado Springs Elite Property Management
Leasing agent
In charge of leasing actions
December 10, 2013
[email protected] Project involvement over the life of the project (555) 385-4688
[email protected]
Ordering, High project installation, and involvement testing of tech equipment for store Approve project charter
(555) 853-4575
Stakeholder Register
Moderate project involvement
Page 78
Gomez Construction
General contractor
Responsible for build-out
(555) 883-2411
High project involvement
Important
Low/Moderate
Semiimportant
Marketing department Will be involved with planning grand opening celebration
Colorado Springs community
Citizens
New retail store customers
N/A
None
Low project involvement
Low
Lowimportance
Garden and Home Show conferences attendees
Consumers
Retail store target audience
N/A
None
Low project involvement
Low
Lowimportance
Grand opening Local caterers businesses/business owners
Provide food at event
N/A
Meet catering needs and expectations at grand-opening celebration
Low project involvement
Low
Lowimportance
Local chefs Community featured at members/new store grand opening target audience
Provide cooking demonstrations
N/A
Provide cooking demonstrations at grand-opening celebration
Low project involvement
Low
Lowimportance
Change Control Board
Responsible for approving changes to project management plan
Moderate
Semiimportant
December 10, 2013
Local email address book (Outlook)
Stakeholder Register
Planning and Moderate execution of grand- project opening involvement celebration
Moderate
Kitchen Heaven Marketing
Kitchen Heaven employees
Local email address book (Outlook)
Construction of store
Approve/deny Moderate changes to project project plan involvement
Page 79