Raipur – Bilaspur RFP floated for appointment of Technical Consultant for the conducting feasibility – cum – preliminary design for 4 – laning of Raipur – Bilaspur of NH-200 Salient Features

Project location: -

Raipur to Bilaspur, State of Chhatisgarh

Project offer: -

4 – laning of the existing road

Length of project: -

117.00 km

Type of Project: transfer)

DBFOT (Design, build, finance, operate,

EPC cost: –

Rs. 672 Cr.

Total cost: –

Rs. 840 Cr. Approx. (add 25% to the EPC cost, includes contingencies, IDC, financing costs, preconstruction expenses, etc.)

Schedule of selection process of the consultant: Event Description

Estimated Date

Last date for receiving queries/ clarifications

26.10.2009

Pre – proposal qualification

03.11.2009

Authority response to queries

09.11.2009

Proposal due date or PDD

17.11.2009 at 1100 hrs

Opening of proposals

17.11.2009

Letter of Award (LOA)

{within 15 days of PDD}

Signing of agreement

within 10 days of LOA

Validity of applications

90 days of proposal due date

Scope of services of consultant 1. 2. 3. 4.

Traffic surveys and demand assessment Engineering surveys and investigations Location and layout of toll plazas Location and layout of truck laybyes

5. Location and layout of bus bays and bus shelters 6. Social impact assessment 7. Environment impact assessment 8. Preliminary designs of road, bridges, structures, etc. 9. Preparation of Land Plan Schedules and Utility Relocation Plans 10.Preparation of indicative BOQ and rough Cost Estimates 11.Preparation of Schedules A, B, C, D and H of the Concession Agreement.

Traffic surveys and demand assessment Number of Survey Stations S.N Description of Activity o. 1.

Classified Traffic Volume Count

One station close to the proposed location of each Toll Plaza and one station for every 20 km of Project Highway.

2.

Intersection Volume Count

All major intersections (All locations where the Project Highway intersects or meets a NH/SH/MDR).

3.

Pedestrian/Cattle crossing traffic count

At all locations of settlements/habitations along the Project Highway

4.

Axle Load Spectrum

One station each close to the proposed location of each Toll Plaza

Time schedule for important deliverables Description of Deliverables

Week No

Payment

Inception Report

2

---

Report on Alignment (including proposed geometric improvements) and first traffic survey

8

15%

Report on Land Plan Schedules and Utility Relocation

12

10%

Report on Indicative GAD of structures (bridges, grade separators, ROB/RUBs)

13

10%

Report on Indicative GAD of structures (bridges, grade separators, ROB/RUBs)

14

10%

Draft Feasibility Report and Schedules to the Concession Agreement

16

25%

Final Feasibility Report

18

20%

Completion of Services including assistance during Bid Process

52

10%

Total

100%