Raipur – Bilaspur RFP floated for appointment of Technical Consultant for the conducting feasibility – cum – preliminary design for 4 – laning of Raipur – Bilaspur of NH-200 Salient Features
Project location: -
Raipur to Bilaspur, State of Chhatisgarh
Project offer: -
4 – laning of the existing road
Length of project: -
117.00 km
Type of Project: transfer)
DBFOT (Design, build, finance, operate,
EPC cost: –
Rs. 672 Cr.
Total cost: –
Rs. 840 Cr. Approx. (add 25% to the EPC cost, includes contingencies, IDC, financing costs, preconstruction expenses, etc.)
Schedule of selection process of the consultant: Event Description
Estimated Date
Last date for receiving queries/ clarifications
26.10.2009
Pre – proposal qualification
03.11.2009
Authority response to queries
09.11.2009
Proposal due date or PDD
17.11.2009 at 1100 hrs
Opening of proposals
17.11.2009
Letter of Award (LOA)
{within 15 days of PDD}
Signing of agreement
within 10 days of LOA
Validity of applications
90 days of proposal due date
Scope of services of consultant 1. 2. 3. 4.
Traffic surveys and demand assessment Engineering surveys and investigations Location and layout of toll plazas Location and layout of truck laybyes
5. Location and layout of bus bays and bus shelters 6. Social impact assessment 7. Environment impact assessment 8. Preliminary designs of road, bridges, structures, etc. 9. Preparation of Land Plan Schedules and Utility Relocation Plans 10.Preparation of indicative BOQ and rough Cost Estimates 11.Preparation of Schedules A, B, C, D and H of the Concession Agreement.
Traffic surveys and demand assessment Number of Survey Stations S.N Description of Activity o. 1.
Classified Traffic Volume Count
One station close to the proposed location of each Toll Plaza and one station for every 20 km of Project Highway.
2.
Intersection Volume Count
All major intersections (All locations where the Project Highway intersects or meets a NH/SH/MDR).
3.
Pedestrian/Cattle crossing traffic count
At all locations of settlements/habitations along the Project Highway
4.
Axle Load Spectrum
One station each close to the proposed location of each Toll Plaza
Time schedule for important deliverables Description of Deliverables
Week No
Payment
Inception Report
2
---
Report on Alignment (including proposed geometric improvements) and first traffic survey
8
15%
Report on Land Plan Schedules and Utility Relocation
12
10%
Report on Indicative GAD of structures (bridges, grade separators, ROB/RUBs)
13
10%
Report on Indicative GAD of structures (bridges, grade separators, ROB/RUBs)
14
10%
Draft Feasibility Report and Schedules to the Concession Agreement
16
25%
Final Feasibility Report
18
20%
Completion of Services including assistance during Bid Process
52
10%
Total
100%