TAKE OF SHEET PERHITUNGAN VOLUME PEKERJAAN DAN KEBUTUHAN BAHAN, UPAH DAN ALAT A. PEKERJAAN JALAN Panjang Jalan Rencana Lebar Jalan Luas Jalan

: : :

200 1 200

Meter Meter x 1

=

200

TOTAL LUAS PENGASPALAN =

200

m2

1. Pekerjaan Pengaspalan Jalan ----> Lapis Penetrasi (Lapen) ------->Kode Pekerjaan K.618 Volume Jalan

=

=

200

m2

Kebutuhan Bahan, Upah dan Alat : * Bahan

- Batu Pecah 3 - 5 cm - Batu Pecah 1 - 2 cm - Batu Pecah 0,5-1 / abu batu - Aspal - Kayu Bakar

= = = = =

0.051 0.016 0.009 4.08 0.007

x x x x x

200 200 200 200 200

* Upah

- Pekerja Aspal - Tukang Aspal

x x

200 200

= =

28.20 0.800

* Alat

- Stoom Walles = 0.004 x 200 = 0.80 ( Produktifitas/kemampuan alat unt pekj. jalan 1 hr = 250 m2 )

= 0.141 = 0.004

Total Kebutuhan Bahan, Upah dan Alat untuk Pekerjaan Jalan * BAHAN

- Batu Pecah 3 - 5 cm - Batu Pecah 1 - 2 cm - Batu Pecah 0,5-1 / abu batu - Aspal - Kayu Bakar

= = = = =

* UPAH

- Pekerja Aspal - Tukang Aspal

= =

28 1

hok hok

* ALAT

- - Stoom Walles

=

1

hari

10 3 2 816 1

m3 m3 m3 Kg m3

= = = = =

10.20 3.20 1.80 816.00 1.40

~ ~ ~ ~ ~

10 3 2 816 1

= =

28 1

~

1

E OF SHEET

AN DAN KEBUTUHAN BAHAN, UPAH DAN ALAT

m3 m3 kg m3 Hok Hok hari

RENCANA ANGGARAN BIAYA (RAB)

Bidang Kegiatan Lokasi Volume

: : : :

Pelaksanaan Pemb. Desa Pengaspalan Jalan (Lapis penetrasi) 200 m

No.

URAIAN

1 1 1 2 3 4 5 6 7 8 9

2 Belanja Barang dan Jasa Papan Proyek (cetak Banner Rangka Kayu) Pengki Ember Meteran Sekop Mobilisasi mesin Gilas Sewa Mesin Gilas Pekerja Aspal Tukang Aspal

a. b. c. d. e.

Belanja Modal Batu Pecah 3 - 5 cm Batu Pecah 1 - 2 cm Batu Pecah 0,5-1 / abu batu Aspal Kayu Bakar

2

Volume

Satuan

Harga Satuan

3

4

5

1.0 10.0 4.0 1.0 2.0 1.0 0.8 28.0 1.0

Bh Bh Bh Bh Bh Ls Hari Hok Hok

Rp 150,000 Rp 15,000 Rp 15,000 Rp 75,000 Rp 85,000 Rp 2,500,000 Rp 1,000,000 Rp 70,000 Rp 90,000 Sub Total (1)

10.00 3.00 2.00 832.00 1.00

M3 M3 M3 Kg M3

Rp Rp Rp Rp Rp

Rp

180,000 220,000 270,000 13,000 150,000

Sub Total (2 ) TOTAL RAB

Jumlah Total Rp 6=5x4 Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp Rp

150,000 150,000 60,000 75,000 170,000 2,500,000 800,000 1,960,000 90,000 5,955,000 1,800,000 660,000 540,000 10,816,000 150,000

Rp Rp

13,966,000 19,921,000

GAMBAR RENCANA Batu Pecah 0.5-1 cm Aspal Batu Pecah 1-2 cm Aspal Batu Pecah 3-5 cm Aspal

Jalan Eksisting 1.0

PROFIL MELINTANG JALAN

Related Documents

Rab
June 2020 33
Rab Mess.xlsx
November 2019 44
Rab Material.xlsx
October 2019 47
Contoh Rab
May 2020 30
Rab Gizi.doc
November 2019 30
Rab Gpura.docx
December 2019 24

More Documents from "Nanang Sulistiyanto"