Project Calculation-ashraf Hussein

  • December 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Project Calculation-ashraf Hussein as PDF for free.

More details

  • Words: 1,675
  • Pages: 27
Tel: +202 24099539 Mobile phone # 0106697767 Mobile Phone # 0166302632

E-Mail : [email protected]

CONTINGENCY AND RISK ANALYSIS CONTINGENCIES (provisions for own cost overrun) ESTIMATED COST 1) 2) 3) 4) 5) 6)

Material and equipment Manufacturing Engineering Outside erection, comm. and start-up Project management Other special direct costs

Contingency value % 0.00% 0.00% 0.00% 0.00% 0.00%

Contingency value (to be included in the full cost calculation) Contingency value (%)

RISKS (provisions for other identified risks, e.g. political etc.) Risk factor

EXPOSURE

1) 2) 3) 4) 5) 6) Total risk provision (to be included in the full cost calculation) Total risk provision (%)

Risk provision %

tingency value Amount 0 0 0 0 0 0 0 #DIV/0!

isk provision Amount 0 0 0 0 0 0 0 #DIV/0!

The purpose of the Scenario analysis is to illustrate the "what if" effects. The bid case shall show what is included in the bid, e.g the amounts in A2, B2 and C2 shall in the bid case column be the amounts included in the full cost estimate. The best and worst case shall show the upside and downside of the project. Both best and worst case shall be realistic. Please note that for the worst case situation it is expected that all consequenses shall be incorporated. I.e. if the project is 30 days delayed, it is not likely that the only costs incurred are the delay penalties.

SCENARIO ANALYSIS

BID CASE

BEST CASE

WORST CASE

I. ASSUMPTIONS A1) Cost over- / underrun (in % of cost) 1) Material and Equipment 2) Manufacturing 3) Engineering 4) Outside erection, comm. and start-up 5) Project management 6) Other special direct costs B1) Other identified costs (in % or amount) 1) 2) 3) C1) Guarantee/ rework cost assumption 1) 2) 3) D1) Schedule - Delay (number of days) E1) Process guarantees (in % or other) II. SCENARIO NET RESULTS based on above assumptions (All amounts in tender currency) NET RESULT BID CASE

#REF!

A2) Cost over- / underrun -> consequences of A1 1) Material and Equipment 2) Manufacturing 3) Engineering 4) Outside erection, comm. and start-up 5) Project management 6) Other special direct costs B2) Other identified costs -> consequences of B1 1) 2) 3) C2) Guarantee / rework costs -> consequences of C1 1) 2) 3) D2) Delay penalties (Liquidated damages) -> consequences of D1 E2) Process guarantees -> consequences of E1 COST COVERAGE AND NET RESULT EFFECT Reversal of the Contingency, Risk and Warranty provisions included in Full Cost Calculation NET RESULT OF SCENARIOS

#REF!

#REF!

#REF!

Material Cash Flow Table Prepare by :

PERIOD

Item Description

Grand Total

1

-----------------

Sales price

Cost price

0

IN

0

2 OUT

0

IN

0

OUT

0

0

3 IN

4 OUT

0

IN

0

5 OUT

0

IN

0

6 OUT

0

IN

0

7 OUT

0

IN

0

OUT

0

0

8 IN

9 OUT

0

IN

0

10 OUT

0

IN

11 OUT

IN

12 OUT

IN

OUT

0

0

0

0

0

0

0

1,424,441

766,973

969,920

1,142,879

1,265,820

1,900,015

2,422,282

13 IN

14 OUT

IN

15 OUT

IN

OUT

0

0

0

0

0

0

2,567,890

5,144,028

4,331,738

3,899,442

4,166,585

3,232,164

16 IN

17 OUT

IN

18 OUT

IN

19 OUT

IN

OUT

0

0

0

0

0

0

0

0

3,275,705

3,379,860

3,238,917

3,338,540

5,020,512

8,178,599

7,880,383

7,147,180

20 IN

21 OUT

IN

22 OUT

IN

0

0

0

0

7,005,697

6,222,383

7,393,147

4,119,341

23 OUT

0

IN

0

24 OUT

0

IN

0

OUT

0

0

Accumulated Gross Paid Result 1 0.95 0.9 0.85 0.8 0.75 0.7 0.65 0.6 0.55 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 Row 1

CASH-FLOW Project name:

North Helwan 4 Stations

Country:

Egypt

Currency:

EGP

Responsible:

Mohamed Moneim

Date:

6/3/2000

Period

->

1

2

3

Milestones ->

A . "CASH FLOW" Cash In Openning Balance

0

Payments received (incl. calc. interest on advances)

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Other Cash In

Total Cash IN Cash Out - Material - Enineering (Manpower) - Erection - Commissioning - Training - Special Selling Cost - Finance Cost - Paid Sales & Admin Cost - Others = Direct Cost Paid - Project costs incurred, but not paid = Exposure A B. OTHER EXPOSURE DURING DELIVERY PERIOD - Committed project costs + Covered by cancellation = Cancellation costs + Residual Value + Insurance Coverage (incl. Export Guarantee Institute) - Rest exposure on On-demand guarantees = Exposure B C. RESIDUAL RISK ON FINANCING - Net Present Value of Residual Risk on Financing = Exposure C

0

0

0

= Total Project Exposure (PE) (A+B+C)

0

0

0

0

0

0

0

0

0

Total Cash Out

0

0

0

Cash Balance

0

0

0

CALCULATION OF POLITICAL RISK PROVISION FOR FINANCING Net Present Value of Residual Risk on Financing Net Present Value of Retention Money Total NPV Political Risk Provision for Financing/Retention Money

Summary Of Cashflow Opening Balance 0 0 0 Cash In 0 0 0 Cash Out 0 0 0 --------------------------------------------------------------------------------------------------- ---------------------- ---------------------- ---------------------Balance 0 0 0 Max Project Exposure (A+B+C)

0

In Period MAPE for this country

#VALUE!

4

0

0 0

0 0

0

0

0 0 0 0

0 0

0 0 0 ---------------------0

5

6

7

8

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0 0 0 0 ---------------------- ---------------------- ---------------------- ---------------------0 0 0 0

9

10

11

12

13

14

15

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ---------------------- ---------------------- ---------------------- ---------------------- ---------------------- ---------------------- ---------------------0 0 0 0 0 0 0

16

17

18

19

20

21

22

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ---------------------- ---------------------- ---------------------- ---------------------- ---------------------- ---------------------- ---------------------0 0 0 0 0 0 0

23

24

0

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0 0 0 0 0 0 ---------------------- ---------------------0 0

0

### -284000 -565000 -104000 -208000 -1280 -347000

Total Project Exposure 1 1 1 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu Colu mn mn mn mn mn mn I mn J mn mn mn mn mn mn mn mn mn mn mn mn mn mn mn mn mn D E F G H K L M N O P Q R S T U V W X Y Z AA

Risk Analysis Checklist (Optional. All boxes are extendible. Add rows if necessary.)

Project: Date: App. 2

1/23/2009 RISK FACTOR

2.0

SCOPE OF WORK 1 2 3 4

3.0

CUSTOMER AND CUSTOMER COUNTRY 1 2 3 4

4.0

CONSORTIUM/JOINT VENTURE 1 2 3 4

5.0

BASIS FOR EXECUTION 1 2 3 4

6.0

CONTRACTUAL ISSUES 1 2 3 4

7.0 1 2 3 4 8.0

PRICE

CASH FLOW/PAYMENT 1 2 3 4

9.0 1 2 3 4

OTHER IMPORTANT ISSUES

REMARKS

Risk Provision

Contingency

RISK MITIGATION Contract

Insurance

Co-suppliers

EXAMPLE

Risk Analysis Checklist (Optional. All boxes are extendible. Add rows if necessary.)

Project: Date: 1/23/2009 App. 2 RISK FACTOR 2.0 1 2 3

SCOPE OF WORK Scope of Work definition Engineering Procurement

4

Construction

3.0

REMARKS

Risk Provision

Contingency

Good condition. Minor risks, typical work. Worldwide procurement. Client purchased equipment. By consortium partner.

X X

Working with consortium partner.

X

RISK MITIGATION Contract

Insurance

Co-suppliers X

X X

X

CUSTOMER AND CUSTOMER COUNTRY 1 2 3 4

4.0 1 2 3 4 5.0

CONSORTIUM/JOINT VENTURE JV organisation risks

1 2

BASIS FOR EXECUTION Site conditions Project logistics

1 2 3 4 5 6 7 8 9 10

CONTRACTUAL ISSUES Defects in warranty period Reperformance of engineering Reperformance of construction Consequential losses Damage to client property liabilities Damage to contract works liabilities Third party liabilities Technology ownership and use Liability for pollution Overall limit of liability

6.0

7.0 1 2 3 4 8.0

PRICE Completeness of data for equipment, engineering and commissioning Labour costs Freight costs Currency exposure CASH FLOW/PAYMENT

1 2 3 4 9.0 1 2 3 4

OTHER IMPORTANT ISSUES

X X X X X

X

Waived. Proposed reciprocal indemnities.

X X X X

Qualified. Proposed.

X

Well known. By consortium partner. To be hedged.

X X X X

X

Related Documents

Imam Hussein
November 2019 26
Saddam Hussein
October 2019 28
Tun Hussein Onn.docx
December 2019 18
Saddam Hussein Biography
November 2019 21