Programme for casting of 1200 mm diameter RCC Hume pipes
Schedule based on two moulds
Date
Number of pipes Cummulative scheduled to Number of pipes cast
Monday, September 15, 2008
1
1
Tuesday, September 16, 2008
1
2
Wednesday, September 17, 2008
2
4
Thursday, September 18, 2008
2
6
Friday, September 19, 2008
0
6
Saturday, September 20, 2008
2
8
Sunday, September 21, 2008
2
10
Monday, September 22, 2008
2
12
Tuesday, September 23, 2008
2
14
Wednesday, September 24, 2008
2
16
Thursday, September 25, 2008
2
18
Friday, September 26, 2008
0
18
Saturday, September 27, 2008
2
20
Sunday, September 28, 2008
2
22
Monday, September 29, 2008
2
24
Tuesday, September 30, 2008
1
25
Schedule of delivery 1. On 27 th September 2008, 8 pipes ,which will be cast on or before 20 September 2008 shall be offered for testing. 2.First despatch of 8 pipes shall be on 28 September 2008. 3. Second lot of 10 pipes shall be despatced on 03.10.2008 after the pond curing of minimum 7 days and testing thereof. 4. Third lot of balance 7 pipes shall b e despatced on 08.10.2008 after the pond curing of minimum 7 days and testing thereof.
Observations
If PMC places / finalises for production of pi pes similar to specifications of the pipes for which the produ process the schedule of delivery can be squeezed by 6 days
m diameter RCC Hume pipes
Schedule based on three moulds
Number of pipes scheduled to cast
Cummulative Number of pipes
1
1
1
2
3
5
3
8
0
8
3
11
3
14
3
17
3
20
3
23
2
25
before 20 September 2008 shall be
er the pond curing of minimum 7
08 after the pond curing of minimum
Power cut
Power cut
ifications of the pipes for which the production is under
Programme for casting of 900 mm diameter RCC Hume pipes
Schedule based on two moulds
Date
Number of pipes Cummulative scheduled to Number of pipes cast
Monday, September 15, 2008
0
0
Tuesday, September 16, 2008
0
0
Wednesday, September 17, 2008
0
0
Thursday, September 18, 2008
2
2
Friday, September 19, 2008
0
2
Saturday, September 20, 2008
2
4
Sunday, September 21, 2008
2
6
Monday, September 22, 2008
2
8
Tuesday, September 23, 2008
2
10
Wednesday, September 24, 2008
2
12
Thursday, September 25, 2008
2
14
Friday, September 26, 2008
0
14
Saturday, September 27, 2008
2
16
Sunday, September 28, 2008
2
18
Monday, September 29, 2008
2
20
Tuesday, September 30, 2008
2
22
Wednesday, October 01, 2008
2
24
Thursday, October 02, 2008
2
26
Friday, October 03, 2008
0
26
Saturday, October 04, 2008
2
28
Sunday, October 05, 2008
2
30
Monday, October 06, 2008
2
32
Monday, October 06, 2008
2
34
Tuesday, October 07, 2008
2
36
Wednesday, October 08, 2008
2
38
Thursday, October 09, 2008
2
40
Friday, October 10, 2008
0
40
Saturday, October 11, 2008
2
42
Sunday, October 12, 2008
2
44
Monday, October 13, 2008
2
46
Tuesday, October 14, 2008
2
48
Wednesday, October 15, 2008
2
50
Thursday, October 16, 2008
2
52
Friday, October 17, 2008
0
52
Saturday, October 18, 2008
2
54
Sunday, October 19, 2008
2
56
Monday, October 20, 2008
2
58
Tuesday, October 21, 2008
2
60
Wednesday, October 22, 2008
2
62
Schedule of delivery
1. On 27 th September 2008, 6 pipes ,which will be cast on or before 20 September 2008 shall be offere 2.First despatch of 6 pipes shall be on 28 September 2008.
3. Second lot of 12 pipes shall be despatced on 03.10.2008 after the pond curing of minimum 7 days an thereof.
3. Third lot of 18 pipes shall be despatced on 08.10.2008 after the pond curing of minimum 7 days and t
4.Final lot of balance 26 pipes shall be despatced on 20.10.2008 after the pond curing of minimum 7 day thereof. 5.The period for the final quantity being despatched shall be squeezed by 11 days with three number of
m diameter RCC Hume pipes
Schedule based on three moulds
Number of pipes scheduled to cast
Cummulative Number of pipes
0
0
0
0
0
0
3
3
0
3
3
6
3
9
3
12
3
15
3
18
3
21 21
3
24
3
27
3
30
3
33
3
36
3
39
0
39
3
42
3
45
3
48
3
51
3
54
Power cut
Power cut
Power cut
3
57
3
60
0
60
2
62
before 20 September 2008 shall be offered for testing.
er the pond curing of minimum 7 days and testing
the pond curing of minimum 7 days and testing thereof.
08 after the pond curing of minimum 7 days and testing
queezed by 11 days with three number of moulds.
Power cut
Power cut
Date
Pipe, details, offered for testing Diameter
Numbers
1200 mm
8
900 mm
6
1200 mm
10
900 mm
12
1200 mm
7
900 mm
18
Saturday, September 27, 2008
Thursday, October 02, 2008
Tuesday, October 07, 2008
Sunday, October 19, 2008
Supply completed for 1200 mm diameter pipes 900 mm
Note:Number of pipes based on two moulds
26
Schedule of despatch Date
Diameter
Numbers
1200 mm
8
900 mm
6
1200 mm
10
900 mm
12
1200 mm
7
900 mm
18
Sunday, September 28, 2008
Friday, October 03, 2008
Wednesday, October 08, 2008
Monday, October 20, 2008
Supply completed for 1200 mm diameter pipes 900 mm
Note:Number of pipes based on two moulds
26