"'-r
..
I '
Professional Practices ENGINEERS
AT
THE
BAR
Ig,
gto goals
Shop Drawing Review: What does the Contract Say? Editor's Note: This is the first installment in a two-part series on shop drawings. The second part will appear next month (eSE, 01103). References to AlA Form A20I. General Conditions of the Contract for Construction, are to the 1997 'tration t mirror
edition, unless otherwise noted. For purposes of processing shop drawings, the architect's consulting engineers are its agents. Therefore, references in A20 1to the architect apply to the consulting engineers. By KENNETH M. ELOVITZ, P.E., Esq.
Energy Economics~ Inc. Foxboro, Moss.
Reviewing a contractor's shop drawings is one of my favorite parts of being a consulting engineer. Shop drawings often provide more information than manufacturers publish in their catalogs. Sometimes, they even explain how equipment works and identify installation considerations. But most important is that shop drawings tell engineers how well they communicated design intent to contractors. Keep in mind, however, that unresponsive shop drawings do not always mean the engineer did a lousy job conveying design intent. Contractors can be intractable. Sometimes a general contractor~and even the owner-see the
iation
Leom
plans and specifications as just a guide. But contractors should consider shop drawings as a primary way to demonstrate their understanding of the contract requirements-before lines on paper become systems in a building. In fact, AlA A20I. Section 3.12.4 explicitly states that the purpose of shop draw-
ing submittals is "to demonstrate '" the way by which the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents." Shop drawings also help engineers determine whether the contractor understands the requirements of the plans and specifications. One sees here the basic difference between how engineers look at shop drawings and the way contractors often view them. Engineers review shop drawings to increase the likelihood that defects or deficiencies in the contractor's submittals can be identified before offending equipment or systems are installed. But the only thing that contractors really want to know is that it is OK to proceed as indicated on the submittal. For this reason, engineers must be careful about how they word their approvals.
Weasel words By approving a submittal using "reviewed," "checked" or "returning without objection," an engineer is effectively saying that what has been submitted is "as acceptable to the engineer for the project's desired end result as if the engineer had included that particular item in the plans and specifications." (see John R. Clark, "Focus on Shop Drawings," Engineers' Joint Contract Documents CommitteeNo.1910-9-C,1985, p. 6.) However, approving shop drawings does not guarantee the systems will work, or that equipment will be free from defect or properly installed. Take a product substitution, for example. Approval simply means the submitted product is as good as the product the engineer used as the basis
of design for the purposes of implementing the design intent. '1\pproved as noted," "approved as corrected" and similar language are invitations to disagreement, even when only minor changes are required. Engineers who mark changes on a submittal and return it "approved as noted" never know whether the contractor and equipment supplier agree to make the requested changes. In fact, if the contractor releases the order for manufacture before receiving shop drawing approval, there's a good chance that the change will not be made. Contractors incur little additional trouble and expense to prepare corrected submittals, which become part of the permanent project documentation. Similarly, to simply "reject" a shop drawing is also unhelpful. If a contractor misunderstands some key aspect of the contract, rejection of the submittal does not solve the problem. "Revise and resubmit" accompanied by notes that explain the required changes is far more likely to produce a compliant resubmittal. A simple rejection might not communicate the need to make changes and try again.
Approved for what? When an engineer approves a shop drawing, the question is not whether it is approved, reviewed or processed. The real question is: Approved for what? The answer lies in another question: What does the contract say? Shop drawing review was never intended to make the engineer a guarantor that the contractor would perform in accordance with the contract requirements. AlA A201 Section 4.2.7 says shop drawing
CONSULTING-SPECIFYING
ENGINEER,
DECEMBER,
2002
13
Professional Practices
At Gamewell, as an independent manufacturer we know that you have choices in the selection of advanced Fire Alarm Systems. Let us simplify the process with our: • Dependable, full-featured family of fire alarm systems • Dedicated system engineering sales support team • Network of independent Engineered Systems Distributors. To select the right Gamewell system for your application, please contact us today.
Gamewell Worldwide 60 Pleasant Street, Ashland, Tel (888) FIREBOX·
MA 01721
(508) 231·1400
Fax (508) 231·0900
www.gamewell.com For more information
enter # 210
review is "only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents." Those words say more about what shop drawing review is not than what it is. The section also says a lot about "design concept" without really explaining it. And so, clients-and courts-can be understandably confused about the design professional's role in shop drawing review. A good guideline is that design concept means elements important to achieve the performance or end results that the specifications intend. This implies a duty to craft the specifications to focus on the essential equipment and system functions and not on unnecessary detail. It also implies that engineers who write specifications and review shop drawings understand the specified requirements and can discern how the submitted equipment meets or does not meet those requirements. One engineer learned this lesson the hard way. A specification for a steel stairway called for 10-ga. steel landing pads with angle supports, but the contractor's shop drawing listed 14-ga. steel instead. The architect stamped the submittal "Furnish as Submitted." The stairway collapsed. injuring two workers. The architect was sued and argued that its approval did not extend to every detail of the submittal. But the court found the designers liable. Uaeger v. Henningson, Durham & Richardson, Inc., 714 F.2d 773 (8th Cir.1983)] Since the Jaeger ruling, AIA A201 has been revised twice. Section 4.2.7 now contains language that submittal review is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities. or for substantiating instructions for installation or performance of equipment or systems-all of which remain the responsibility of the contractor as required by the contract documents. The revised language might have been an attempt to avoid the liability imposed in the Jaeger case. On the other hand, engineers ought to take shop
drawing review seriously and recognize that one important purpose of shop drawings is to check for errors that affect performance of the submitted item. For engineers-and their lawyerswho are concerned about the precise language used, "complies" might be a better choice than" approved." The engineer's review determines whether the shop drawing complies with the requirements stated in the contract documents. Clear contract language that defines the contractor's responsibilities to prepare shop drawings and circumscribes the engineer's responsibility for review helps everyone understand who is responsible for what. As always. behavior can expand responsibilities and alter the allocation of risks in a contract. For that reason, engineers need to know what the contract says and conform their behavior to it.
Substitutions:
design-build?
But what about substitutions? Plans and specifications show one way to carry out the design, but specifications often allow the contractor to supply "equal" equipment by another named manufacturer. In reality. no two products are exactly equal. There are always some variations among products. Manufacturers use those variations to distinguish their products from those of competitors. When a contractor selects a product other than the one that was the basis of design, does it introduce an element of design-build into the project? Some engineers say it does. The design responsibility associated with using different equipment can vary greatly. For example. a contractor's redesign of a fitting to accommodate a different size air-handling unit is trivial. However. the design responsibility is quite significant when the different dimensions of an AHU require rearranging piping or relocating fans to make everything fit. In public work, engineers might not be able to hold contractors responsible for coordinating equipment other than that which is used as the basis of design. For example. in one case the specifications for a fire station called for a particular system or approved equal. The
j
1 r
n
contractor
s :S IV
S r-
~r lr w
:n
submitted
a substitution.
'Revise and resubmit'
When the submittal was rejected. the contractor asked the architect to iden.tify two additional manufacturers whose products he would accept. The architect refused. saying it was the contractor's problem if he did not want to use the specified product. The contractor eventually furnished the specified product. sued for the extra cost and won. (E. Amanti & Sons. Inc. v.R. C. Griffin. Inc .. 53 Mass. App. Ct. 245. 2001.) The public bidding statute required specifications to contain the names of at least three eligible suppliers. The problem for engineers is the court's remark that the awarding authority must "demonstrate that there are at least three sources from which a bidder could obtain essential items for the project." The court also said the bidder is not responsible to identify "three sources for materials subject to a competitive bid." and that "providing the name of a single
with an explanation of changes is likely to produce compliant resubmittals vendor and placing the burden on the bidder to discover alternatives did not constitute competitive specifications." The case did not discuss who would be responsible if differences among three named products required design modifications. However. the decision seems to imply that contractors should not have to take any initiative to make a specified product work with the rest of the design. The Amanti case applies to conventional specifications. It does not discuss performance specifications. where different rules might apply.
Section 3.1.2 of AlA A20I requires the contractor to perform the work in accordance with the contract documents. If the specifications name more than one product as suitable for a particular application. those products. even if they are not the ones shown on the drawings as the basis of the design. are not substitutions. Substitutions are products not named in the specifications. Substitutions may be appropriate if the specified product is not available. On a plans-and-specification job. substitutions generally are not appropriate if their only reason is a lower cost to the contractor. Engineers and contractors both should be aware of section 3.4.2 of AlA A20I. Section 3.4.2 allows the contractor to make substitutions only with the consent of the owner. after evaluation by the architect. lesel In next month's Professional Practices. the author will discuss procedural questions. such as which shop drawings to review and who should conduct the review.
I1S
'---/ .re ne 11" lCt lsh ;ICof ry ,rs. .ICent lity Igi-
The Global Innovation Leaders. e technical insulation, #1 in quality and service.
'ac-
Inventors marine & offshore Arma"chek· insulation systems
Inventors Armaflex· flexible closed-cell elastomeric
Inventors
25/50
white elastomeric AP/Armaflex W
Inventors convenient continuouslength Armaflex
Continuing the legacy of Innovation Leadership."
Coil
late rial. uite ons gor not ;ible han
ARMACELL LLC MEBANE, NC 27302
1 800 86~5638
;igr
www.armacell.com
:ci,,-
Copyright 0 2002 AnTIaceU LLC
parThe For information
enter # 211 on the Reader Service Card CONSULTING-SPECIFYING
ENGINEER·
DECEMBER,
2002
15
r
Professional Practices ENGINEERS
AT
THE
BAR
A Guide to Shop Drawings: Who Should Review? Editor's Note:
This is the second
installment in a two-part series on reviewing and approving shop drawings. References to AlA Form A20 1, General Condi-
tions of the Contract for Construction,
>
are to the
1997 edition
unless otherwise
noted. For purposes of processing shop drawings, when a consulting engineer is the architect's agent, references in A20I to the architect apply to the consulting engineer. By KENNETH M. ELOVITZ, P.E., Esq.
'---' 2r )0 tar nher al n rch IC)st ~)f In lty
)f W
Energy Economics, Foxboro,
Inc.
Mass.
Many firms assign low-level staff to process shop drawings. But the practice-even if perceived as a menial duty-deprives a firm of a useful opportunity to make desired changes before the work is done. Consider this: hire an outside consultant to review the drawings and note suggested changes. Before dismissing the notion as too costly, consider the benefits. Sure, any changes this independent consultant might make could result in an extra cost to the contractor, but they'll certainly be nowhere near the cost of a problem that is not discovered until after the work is
•
I com~ ~862
completed. Moreover, if the change is something that would have been included in the bid documents had the engineer thought of it in time, the bids would have been correspondingly higher to reflect the additional work. Again, before rolling your eyes, keep in mind that the change order cost does not necessarily have to be passed on to the owner, nor should the client expect reimbursement for any claimed design
error-professional liability defense lawyers sometimes call this concept the principle of "betterment." Back to the subject of the independent reviewer. Depending on the job and the circumstances, an outside engineer can sometimes be more objective about whether a contractor's submittals comply with plans and specifications. Such a scenario might also provide a kind of internal peer review. For example, if the reviewing engineer finds a problem, or if the two differ, they can discuss it privately and professionally. Of course, being able to tell clients about design problems without losing their confidence is a skill that few have mastered. The key seems to be in providing solutions, not just identifying problems. A proposed contract change issued during shop drawing review, accompanied by an explanation, is bound to be less painful than blaming one another when the system does not work as intended.
Review only what's noted In examining the whole process, there are many steps that can be enacted to save headaches. First, specifications should call for only those shop drawings the engineer believes are needed. If a contractor submits a nonrequired shop drawing, and the engineer reviews it anyway. he or she will likely be held responsible for having approved it. Don't simply return these shop drawings marked "not reviewed." It leaves open the question of why it was not reviewed, and in the contractor's
lawyer's eyes, it means there was some need to have the engineer evaluate the drawing--otherwise, it would not have been submitted. Instead, return the drawing with a memo stating that the submittal is not required by the contract and has not been reviewed, and the engineer offers no comment on it. By taking precise action and clearly stating the basis for it, engineers can avoid confusion over whether they did review or should have reviewed the shop drawing. Remember that the engineer writes the specifications and the general conditions of the contract that define the engineer's obligations and scope of services-the contractor does not define the engineer's duties.
Do not do the contractor's job A second headache reliever involves insisting that contractors do their jobs. Under sections 3.12.6 and 3.12.7 of AlA A201, the contractor must review and approve shop drawings before sending them to the architect or engineer. Engineers should not accept submittals directly from a subcontractor or vendor. This bypasses the general contractor's opportunity to review drawings for coordination. If a submittal contains obvious errors, the engineer should return it immediately with an explanation and a requirement to resubmit once the contractor has corrected any errors. Likewise, if it looks like a contractor rubber stamped a submittal without reviewing it carefully, the engineer should .return it with instructions to resubmit after the contractor has completed its review. Keeping a record of the
CONSULTING-SPECIFYING
ENGINEER·
JANUARY.
2003
15
Professional Practices Further, the designer should insist that the contractor express the schedule in terms of milestones, not specific dates. For example, the engineer might agree to process all shop drawings within 10 business days of receipt. An engineer who agrees to process shop drawings by March 15 is asking for trouble, because the contractor might not make the submittal until March 14 or even March 16, The schedule should also address or provide the possibility that resubmittals will be required. Integrating shop drawing review-with adequate time allowed for review-into the construction schedule at the beginning of the job and adhering to schedule commitments can help engineers defend delay claims.
errors or discrepancies in the initial submittal might facilitate review of the resubmittal. Section 3.12.8 of ALA A20 1 requires the contractor to advise the architect specifically, in writing at the time of submittal, of any ways that submitted products deviate from the contract requirements. The contractor's approval stamp is the contractor's representation that he or she fulfilled this responsibility. By insisting on the contractor's approval stamp, engineers gain some insulation against claims that they implicitly waived a contract requirement by accepting non-conforming materials or equipment. Engineers can still get into trouble by approving shop drawings with deviations that the contractor identified, but at least it will not be due to unknowing approval. These precautions may impact the schedule, but remember it is not the only thing that is important. A job that finishes on time but does not meet the contract requirements breeds unhappiness. The contractor is in charge of schedule, and engineers must not let shop drawing review interfere with the contractor's schedule. Section 3.10.2 of ALA A20 1 calls for the contractor to prepare a schedule of submittals that allows the design team reasonable time for review. If the contractor is going to hold the designer to the review schedule, the designer should insist that the contractor prepare a schedule in advance.
I
Revoking shop drawing approval Shop drawings cannot change a contract. In other words, the engineer cannot use the review to impose new requirements. But it also means the contractor cannot use shop drawings to escape a contract's requirements. That is not to say the strategy has never been tried. For example, the specifications for steam piping at a certain university called for welded or threaded pipe. Nevertheless. the contractor submitted-and the engineer approved-grooved piping. Later, the engineer ordered the contractor to stop work and replace the grooved pipe with welded pipe. The contractor sued the owner and the engineer to recover the cost of the extra work. The contractor was not allowed to rely on the engineer's initial approval of a non-conforming submittal to change the contract requirements and leave the grooved piping in place. However, the court allowed the contractor to proceed with his action against the engineer for damages [Detweiler Bros., Inc. v. John Graham & Co., 412 F. Supp. 416 (B.D. Wash. 1976)]. In another case, a contract called for a fire-alarm system to be wired with solid copper No. 12 wire. The engineer approved the contractor's submittal "as noted" with a long list of required corrective actions. None of the comments addressed wire size, in part because the submittal did not say anything about wire size.
TM
ELECTRONIC FLOWHOOD DIRECT DIGITAL READOUT 0-2500 CFM
,"~
AUTOMATICALLY BACKPRESSURE
CORRECTS
FOR AIR DENSITY
&
CHOICE OF METERS· AIR FLOW ONLY, OR AIR FLOW, VELOCITY, PRESSURE & TEMPERATURE OPTIONS INCLUDE: MEMORY, AVERAGE & SUM TO 100 READINGS, SEQUENTIAL RECALL, AUTO·READ REPAIR POLICY·
ONE WEEK TURNAROUND
OR LESS
CUSTOM TOPS MADE TO ORDER
Shortridge Instruments, Inc. 7855 East Redfield Road • Scottsdale, Arizona 85260 (480) 991-6744 FAX (4811)44)-1267 For more info, enter # 211 on the Reader Service Card 11':
I
During construction, a consultant hired for construction observation reported that the fire-alarm system wire was stranded No. 14. The contractor had to replace it. The contractor then filed a claim for a change order. The contractor argued that neither it nor its supplier thought the No. 14 wire was a "substitution" or "deviation." For that reason, the contractor claimed it could not be faulted for failing to call the wire size to the engineer's attention during the submittal process. The court disagreed with the contractor, noting that. '1\nyone working in the electrical field ought to know that stranded conductor is not solid, and that 14 AWG wire has a smaller diameter than 12 AWG." The submittal approval could not alter the contract requirement. The approval was effectively revoked, and the contractor had to replace the work at its own cost [Twigg Corporation v. General Services Administration, GSBCA 14 387, cross-motions for
Professional Practices summary relief denied: June 4, 1998, GSB CA 14386,14387 denied: GSBCA14899 granted in part: February 11, 2000].
responsibilities on the part of the contractor that need to be specified in that contract.
Design delegation
Temporary vs. permanent
In the market today, there a number of specific shop drawing related issues engineers need to be aware of. The first involves the controversy over design delegation vs. abdication. For years, specialized systems have been specified on a performance basis. The architect specifies criteria, and the vendor provides the detailed design. In HVAC, for example, the design engineer specifies a sequence of operation for temperature controls and the specialty contractor selects the hardware to implement the specified sequence. Contractors sometimes claim the
Even people in the construction industry sometimes lose sight of the distinction between temporary and permanent work. The former falls within the contractor's exclusive realm. Shop drawings are permanent work to describe systems as they will be configured. As a general rule, engineers should not review submittals concerning the proposed implementation of means, methods, techniques, sequences or procedures of construction. Engineers also generally should not review shop drawings for temporary work. Reviewing them could subject the engineer to have accepted responsibility not normally undertaken by a design professional. There are exceptions: An engineer might want a contractor to submit
drawings for these systems contain too little information as to how to build something, forcing them to design the system themselves. Designers claim they are appropriately delegating details of design, like steel connections, to specially qualified professionals like steel fabricators. In such cases, the contractors' argument is not so far-fetched. Shop drawings are not a substitute for design documents and designers should not expect contractors to design the project or figure out how to make the building orthe system work. Section 3.12.10 of AlA A201 attempts to define the division of design responsibility between the architect-responsible for the design of the project-and the contractor, who the contract might require to design a portion of the work, but who is usually limited to a sub-system or ancillary work. When the contract delegates a portion of the design to the contractor, the architect must specify all performance and design criteria that the contractor's detailed design must satisfy. The architect is not responsible for checking that the contractor carried out the design properly, but the contractor is not responsible for the adequacy of the specified performance or design criteria. Design-build projects present more extensive design
a procedure for making a cut-over from old to new systems on critial operations. The engineer also might want a contractor to submit a written phasing plan that shows how the contractor plans to maintain continuity of service. In these examples, the purpose of the engineer's review is only to see whether the contractor has developed a reasonable plan, not evaluate details or provide an opinion on whether the plan is appropriate. To avoid interfering with the contractor's sole and exclusive right of control over means, methods, techniques, sequences or procedures of construction, the engineer's review or comment letter should state the scope and purpose of the review-that the engineer's review is intended to confirm that the contractor has developed a plan-and not to make an independent evaluation of the suitability of the plan. Continued on p. 49
'";';".
~Faii1rorcea;er8ctii~'heat~rsu~~,~elri" ~non~l1atMdolJ~ ~umid'el1Vironmm-:,' ,c',' ·t20.voltcontrors-'· . ;.-~ y ..
+jn~~:CK··· , .....,.
••• -
to • .....,
.
·rorlf~~·r,~~~';~:'~:#~~~'ted~~~~~ ;For more info, enter # 213 on the Reader Service Card CONSULTING·SPECIFYING
ENGINEER·
JANUARY,
2003
19
Professional Practices Continued from p. 19 One final thought on shop drawings: Engineers should not underestimate their value as a way to learn about products. Sometimes. contractors select products simply on price. Sometimes, it's based on incentives like expense-paid sales J;onferences at desirable vacation spots. But just as often, contractors select products based on reliability-no callbacks. technical support and service after the sale. Engineers rarely have the opportunity to experience first-hand how products perform over time. Contractors who service the equipment have that opportunity daily. A reliable contractor's choice of a particular product is one of the strongest recommendations a product can obtain. Engineers should make shop drawing review part of delivering a functional project, not a bureaucratic obstacle. Real power: Use it wisely Shop drawings really are a thing of beauty. How so? The engineer writes the contract-in the form of the specifications-and is then allowed to administer. enforce and interpret it. Perhaps the first answer to any question about managing shop drawings should be another question: "What does the contract say?" Maybe engineers should challenge every section in their specifications by asking. "Why do I need this?" or "What do I really want here?" Enforcing the contract specifications will be a lot easier under challenge if every requirement has a sound reason. But consistency is important. Engineers should be careful that their actions do not contradict either the words or intent of the contract. Engineers should check that their contract for professional services and their sections of the specifications are consistent with each other and with the other professional services agreements as well as the contract for construction. Finally, with specific regard to shop drawings. samples and other submittals. specify and review only those that are necessary-and have a reason why they lesel are needed.
"I Saved Our School District
$124 ooo':l~, ,
·."'M,
LastYear
",
with WORLD DRYER"
For more info. enter # 226 on the Reader Service Card
Water, St_m, Evaporator Condenser, and Booster Coils Custom Built and Made-to-Flt Field Measurement by Factory Trained Reps Computerized Coli Selections Quallty Construction ARI and ISO 9002 Cel'tlflcatlon 2 & 5 Days Explcllted Shipments Available
HEATCRAFTI. Ooutokumpu· heatctaft 1-aoo-225-4328
_h
••••crllftcp.~m
collsGheatc:I'lIft.~ •••
For more info. enter # 225 on the Reader Service Card CONSULTING-SPECIFYING
ENGINEER·
JANUARY.
2003
49