Obras urbanas de pavimentación. Bloque UCR nº

item

unid.

cant.

p.unit.

p.total

p.unit.

p.total

1 rotura y retiro de cordones cuneta existentes.

m.

220.00

40.70

8,954

33.60

7,392

2 excavación en suelo blando.



32,169.40

33.03

1,062,555

28.00

900,743

3 saneamiento de sub rasante



19,956.90

38.00

758,362

22.40

447,035

4 ejecución de base para pavimento de hormigón (esp.: 0,25m)



12,179.00

27.28

332,243

19.04

231,888

5 ejecución de base para pavimento asfáltico (esp.: 0,25m)



47,756.00

29.55

1,411,190

21.28

1,016,248

6 pavimento de hormigón (esp.: 0,15m)



11,500.00

197.00

2,265,500

156.80

1,803,200

7 cordón integral s/especificaciones

ml

1,200.00

31.50

37,800

22.40

26,880

8 ejecución de cordón cuneta (ancho: 0,70m)

ml

2,380.00

187.15

445,417

123.20

293,216

9 bordes de terminación (esp.: 0,15m)



211.00

197.00

41,567

156.80

33,085

10 badén de hormigón (esp.: 0,15m)



1,520.00

197.00

299,440

156.80

238,336

11 riego de imprimación



47,756.00

7.90

377,272

3.36

160,460

12 riego de liga



47,756.00

3.50

167,146

1.34

64,184

13 carpeta de concreto asfáltico (esp.: 0,05m)



47,756.00

56.04

2,676,246

33.60

1,604,602

14 remociones varias 1% suma A-1 a A-12

gl

1

98,837.65

98,838

68,272.68

68,273

total

9,982,531

Ppto.oficial

9,982,600

El presupuesto oficial tiene un pequeño error de $69,00.

6,895,541