PIPELINE REPAIR AT KP 110 – KP 133 KUALA TUNGKAL TO PANARAN TGI OFFSHORE PIPELINE 18th-June-08
FEED Handover Meeting Agenda 1.
Project Introduction
2.
Project Status
3.
MTO
4.
Procurement & Installation Specifications
5.
MR’s
6.
TBE/Table of Compliance
7.
Procurement Status
8.
Discussion and Close out
Project Introduction
KP 133.5
KP 110.5
Project Introduction
Details of Damaged Section (KP110.5 to KP133.5) • Total of 19 buckles along the damaged section • Maximum deformation of buckle – 7.59% of OD • Water depth at damaged section – 35m
Design Basis of Replacement Pipeline DESCRIPTION
UNIT
PARAMETERS
Approximate Length
km
Approximately 23.0
Pipeline OD
mm
711.2 (28”)
Material
-
Carbon Steel
Line Pipe Specification
-
API 5L X65, manufactured to DNV OS-F101
Pipeline Wall Thickness
mm
15.9 (.625”)
Service
-
Dry Sales Gas
Pipeline Corrosion Allowance
mm
0.0
Internal Coating
-
80 micron DFT Epoxy Coating
External Corrosion Coating
-
3 Layer PE
External Corrosion Coating Thickness
mm
2.1
Concrete Weight Coating Thickness
mm
94
Design Pressure
Barg
113.8 (1650 psig)
Operating Temperature
°C
40.6
Hydrotest Pressure
Barg
136.7 (1983 psig)
Maximum Operating Pressure
Barg
103.4 (1500 psig)
Product Density
Kg/m3
63.0
Pressure Rating of Pipeline Components
-
ANSI Class 900
FEED OBJECTIVES
Engineer a feasible repair method that can be executed by available installation contractors in the region
Develop a method based on use of industry proven equipment and procedures
Review the method with potential EPCC contractors to get feedback on their construction risks.
Develop a method which offers no or minimum stoppage of Gas to the consumers
Develop a method which enables restoring the gas flow to the full design pressure as early as possible
Conduct risk work shop and identify risks that should be managed by PMT
Identify long lead items for procurement so that repair work can be executed as early as practically possible
Schematic Diagram
MTO for Zero Downtime Method Hot Tap Tees Size
Material
Quantities
28 x 6”
ASTM A 694 F65
2
28 x 16”
ASTM A 694 F65
2
28 x 28”
ASTM A 694 F65
4
28” 28”, 90ºBends
5D Hot Induction Bends
API 5L X65
4+1spare
2 for Test bend and WPQT
Mechanical Connectors 28”
ASTM A 694 F65
2 Flanges
6” Pressurizing line
ASTM A 694 F65
4+1
Swivel type
16” Branch Line
ASTM A 694 F65
2+1
WN Flange
4+1
Swivel flange
8+1
Blind flange Misalignment flange
28” Pipeline
28” Pig Launcher/Receiver
ASTM A 694 F65
ASTM A 694 F65
4+1
WN Flange
6+1
Swivel flange
10+1
Blind flange
2+1
Misalignment flange
2
Swivel flange
MTO for Zero Downtime Method Testable Gaskets Size
Material
Quantities
28”
SS 316 Octagonal
4+1
Kamos Gasket
16”
SS 316 Octagonal
4+1
Kamos Gasket
Test Kit
SS316
2
Kamos
Weldolets 28 x 4 “
ASTM A 694 F65 / WPHY65
2+1
80XS
28 x 2”
ASTM A 694 F65 / WPHY65
2+1
80XS
16 x 4”
ASTM A 694 F65 / WPHY65
2+1
80XS
16 x 6”
ASTM A 694 F65 / WPHY65
2+1
80XS
2
Reducing Tee
4
90º
Barred Tee 28” x 16”
ASTM A 694 F65 / WPHY65 Elbow
16”
ASTM A 694 F65 / WPHY65 Subsea Ball Valves
2"
Body: A350-LF-2 / A352 LCC
2
Full Bore, RTJ x Welded End
4"
Ball & Seat: A182-F55 with WC coating
4
Full Bore, RTJ x Welded End
2
Full Bore, RTJ x Welded End
6”
Seat Spring: Inconel X750
MTO for Zero Downtime Method Expanding Gate Valves Size
Material
Quantities
16”
Body: A350-LF-2 / A352 LCC
2
Gate & Seat: A182-F55 with WC coating 28”
Seat Spring: Inconel X750
Reduced Bore, Welded end. Through conduit Double Block and Bleed
2
Full Bore, Piggable and welded end Through conduit Double Block and Bleed
Subsea Globe Valve 6”
Body: A350-LF-2 / A352 LCC Trim : A182-F55 with WC coating Stem packing : Flexible Graphite
2
RTJ X RTJ Welded bonnet
Material Specifications S/N
Activities TGI Specification
Status
Further Actions
Done
-
1.
Line Pipe
2.
Flanges, Bolts, Nuts, Gaskets and Fittings
29780-00-SU-SPC001
Done
-
3.
Subsea DBB Expandable Gate Valves / Gate Valves
29780-00-SU-SPC003
Done
-
4.
5D Induction Bends
Done
5.
Subsea Mechanical Connectors & Hot Tap Assembly
29780-00-SU-SPC004 29780-00-SU-SPC005
Done
EPC
Contractor to attend all FAT testing for both mechanical connectors and hot tap assemblies EPC
Contractor to perform mock testing at the works followed by full mock up before the actual installation works 6.
Field Welding and NDT
29780-00-SU-SPC002
Done
EPC Contractor to prepare welding and NDT procedures
7.
Installation
29780-00-SU-SPC007
Done
EPC Contractor to develop installation procedures.
8.
Survey and Monitoring
Done
-
9.
Hydrotest, Gauging and Pigging
29780-00-SU-SPC008 29780-00-SU-SPC009
Done
EPC to develop site procedures. Final HAZOP and HAZID need to be performed.
10.
Construction Materials
----
Not Done
All non-long lead and construction materials to be procured by EPC Contractor
Material Requisitions S/N
Activities
Status
Further Actions
1.
Line Pipe
TGI
Done
-
2.
Flanges, Bolts, Nuts, Gaskets and Fittings
29780-00-SU-RFQ-0003
Done
-
3.
Subsea DBB Expandable Gate Valves / Ball Valves
29780-00-SU-RFQ-0002
Done
-
4.
5D Induction Bends
29780-00-SU-RFQ-0001
Done
-
5.
Subsea Mechanical Connectors & Hot Tap Assembly
29780-00-SU-RFQ-0004
Done
-
TBE/Table of Complinace S/N
Activities
Status
Further Actions
1.
Line Pipe
TGI
--
-
2.
5D Induction Bends
TGI
--
-
3.
Flanges, Bolts, Nuts, Gaskets and Fittings
TGI
Done
-
4.
Subsea DBB Expandable Gate Valves / Ball Valves
TGI
Done
-
5.
Subsea Mechanical Connectors & Hot Tap Assembly
TGI
Done
-
Project Status – Procurement
Steel Plate and Line Pipe Manufacturing Inspection • AnYang Steel Plate Mill audit – Done • Line Pipe Manufacture Kick-off meeting and Mill audit – ????
All non-long lead items & consumables to be supplied by EPC Contractor and subjected to PMT’s approval – status ????
Specifications and MRs for Long Lead Items Preparation – Done • Long lead items are identified in the MTO Report
Project Status – Procurement S/N
Procurement Assistance Activities
Status
Further Actions
Float MR
TBE
1.
Flanges, Bolts, Nuts, Gaskets and Fittings
Done
Done
-
2.
Subsea Double Expandable Gate Valves / Gate Valves
Done
Done
-
3.
5D Induction Bends
-
-
Specifications and MRs issued to TGI. TGI to send out for quotations – Status unknown ???
4.
Subsea Mechanical Connectors & Hot Tap Assembly
Done
Done
PMT to ensure EPC Contractor attend all FAT testing and perform mock testing before actual repair works
Project Status – Procurement S/N 1.
Procurement Assistance Activities
Selected Vendor
Further Actions
PT Bakrie
28” Line Production status to be updated by TGI.
Line Pipe
Status of 16” pipe to be informed by TGI ???? 2.
5D Induction Bends
-
-
3.
Coating & Anodes
4.
Flanges, Bolts, Nuts, Gaskets and Fittings
Oceanering
TGI to update the staus
5.
Subsea Double Expandable Gate Valves / Globe/Ball Valves
BEL Valves
-
6.
Subsea Mechanical Connectors & Hot Tap Assembly
BrederoShaw -Batam
OCEANERING
Specifications and MRs issued to TGI. Awaiting TGI to send out for quotations. TGI to update the status ???? TGI to update the status ?????
PMT to ensure EPC Contractor attend all FAT testing and perform mock testing before actual repair works
Project Status – Procurement
Balance Procurement Items S/N
Activities
1.
Line Pipe
Small bore pipes like 6”,4”, 2” etc to be procured by EPC contractor
2.
Small Bore valves
¾” 2 “
3.
Flanges, Bolts, Nuts, Gaskets and Fittings
Small bore and miscellaneous items to be procured by EPC contractor
5.
Barred Tee
6.
Structurals for Skid assembly
To be confirmed by TGI ????? To be Procured by EPC contractor
Discussion and Close Out