Pipeline Repair Project Feed 1

  • Uploaded by: Nurcahyo Djati W
  • 0
  • 0
  • April 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Pipeline Repair Project Feed 1 as PDF for free.

More details

  • Words: 1,405
  • Pages: 46
PIPELINE REPAIR AT KP 110 – KP 133 KUALA TUNGKAL TO PANARAN TGI OFFSHORE PIPELINE 18th-June-08

FEED Handover Meeting Agenda 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13.

Project Introduction Problem Definition Design Basis Pipeline Mechanical Design Pipeline Outline Installation Analysis Repair Methodology Cost Estimate and Schedule Valve Skid Design EIA Review HAZID & HAZOP Action Items Prof. Andrew Palmer’s Review Closeout Report Discussion and Close Out

Project Introduction

KP 133.5

KP 110.5

FEED OBJECTIVES 

Engineer a feasible repair method that can be executed by available installation contractors in the region



Develop a method based on use of industry proven equipment and procedures



Review the method with potential EPCC contractors to get feedback on their construction risks.



Develop a method which offers no or minimum stoppage of Gas to the consumers



Develop a method which enables restoring the gas flow to the full design pressure as early as possible



Conduct risk work shop and identify risks that should be managed by PMT



Identify long lead items for procurement so that repair work can be executed as early as practically possible

Project Introduction 

Details of Damaged Section (KP110.5 to KP133.5) • Total of 19 buckles along the damaged section • Maximum deformation of buckle – 7.59% of OD • Water depth at damaged section – 35m

Project Introduction

Design Basis of Replacement Pipeline DESCRIPTION

UNIT

PARAMETERS

Approximate Length

km

Approximately 23.0

Pipeline OD

mm

711.2 (28”)

Material

-

Carbon Steel

Line Pipe Specification

-

API 5L X65, manufactured to DNV OS-F101

Pipeline Wall Thickness

mm

15.9 (.625”)

Service

-

Dry Sales Gas

Pipeline Corrosion Allowance

mm

0.0

Internal Coating

-

80 micron DFT Epoxy Coating

External Corrosion Coating

-

3 Layer PE

External Corrosion Coating Thickness

mm

2.1

Concrete Weight Coating Thickness

mm

94

Design Pressure

Barg

113.8 (1650 psig)

Operating Temperature

°C

40.6

Hydrotest Pressure

Barg

136.7 (1983 psig)

Maximum Operating Pressure

Barg

103.4 (1500 psig)

Product Density

Kg/m3

63.0

Pressure Rating of Pipeline Components

-

ANSI Class 900

Design Basis of Replacement Pipeline

Pipeline Mechanical Design

Pipeline Mechanical Design

Pipeline Mechanical Design

Pipeline Mechanical Design

Pipeline Mechanical Design

Pipeline Mechanical Design

Pipeline Mechanical Design

Pipeline Installation Analysis

Pipeline Installation Analysis

Final Repair Method 

Repair Method • Zero Downtime Method

Micros oft PowerPoint Presentation

Schematic Diagram

Comparison Between Both Methods

Cost Flange Connections/ KaMos Gaskets

Hot Taps

STOPPLE

Barred Tees

5D Bend

Gate Valve

Shut-down Time

CM – Reduced Downtime

Nil

6 (4 in-place)

4

Nil

Nil

Nil

Zero Downtime Method

6

8 (6 in-place)

4

2

4

2 x 28” 2 x 16”

Note: 2.

CM – Conventional Method

3.

The hardware cost stated above includes 10% for transportation cost.

Hardware Cost

Construction Cost

Total Cost

4 – 6 Wks

US$3.3

US$30M

US$33.3

Nil

US$9.6M

US$40M

US$49.6

Comparison Between Both Methods Reduced Downtime Method Advantages

Disadvantages



No flange connections along the pipeline



Involves less construction and diving work

• •

Stoppage of gas supply to consumers for 4 to 6 weeks Delay in construction work will result in more stoppage of gas supply to consumers



After commissioning sales gas will have some water till complete dryness is achieved



Equipment procured does not offer flexibility to switch to zero down time method



4 In-place hot-tap clamps

Zero Downtime Method •

Zero Shut-down time and any delay in construction will not disrupt flow to the consumers



Restoration of full design pressure before completion of repair



Equipment procured offers flexibility to switch to reduced down time method



6 flange connections



Involves more construction / diving work



6 In-place hot-tap clamps

Material Cost

US$3.3M

US$9.6M

Construction Cost

US$30.0M

US$40.0M

Comparisons of Risks Reduced Downtime Method

Zero Downtime Method

1.

Emergency Response Plan required

1.

Emergency Response Plan required

1.

Gas Freeing the abandoned pipeline

1.

Gas Freeing the abandoned pipeline

1.

Potential of buckling the pipeline during above water tie-in

1.

KaMOS gasket failure

1.

Presences of large amount of water and air pockets in the pipeline while restoring the flow

1.

Experienced Hot-tap contractor should be engaged

1.

Gas supply shut down time can increase due to construction delays

1.

Experienced Hot-tap contractor should be engaged

Shut-Down Time for Reduce Downtime Method

Overall Schedule for Zero Downtime Method – Best Scenario

Overall Schedule for Zero Downtime Method - Realistic

Potential EPCC Contractors Pipelay

Subsea

Cal Dive





Saipem





Global





Acergy





Technip Subsea 7





Valve Skid Design

Valve Skid Design

Valve Skid Design

Valve Skid Design

EIA Action Plan

EIA Action Plan

EIA Action Plan

HAZID & HAZOP Action Items 

HAZID Action Items –



HAZOP Action Items –

Adobe Acrobat 7.0 Document

Adobe Acrobat 7.0 Document

Dr Andrew Palmer’s Review and Actions Required

Dr Andrew Palmer’s Review and Actions Required

Dr Andrew Palmer’s Review and Actions Required

Project Status – Engineering  S/N

Pipeline Mechanical Design Activities

Status

Further Actions

1.

28” Pipe WT and Concrete Thickness

Done

-

2.

16” Pipe WT and Stability

Done

EPC Contractor to check suitability of the available 16” pipe from Stockist. For a !6” dia 11.1 mm thick a 40mm concrete is required. EPC Contractor to proposed method to ensure stability of pipeline if 16” pipe is not concrete coated.

3.

Small Diameter Pipings, WT and Stability

Done

EPC Contractor to check suitability of the available 6” pipe from Stockist. EPC Contractor to ensure stability of piping during operation.

4.

Cathodic Protection Design

Done

No CP is proposed for the temporary piping as it is exposed to sea water for a short period only. There is enough margin on the anodes provided on the permanent facilities to take care of the temporary piping.

5.

Pipelay Analysis

Done

EPC Contractor to perform detailed dynamic lay analysis based on their proposed pipe laybarge

6.

Bottom Roughness

Done

EPC Contractor to perform pre-engineering survey and update the Bottom Roughness Analysis. Span rectification if required.

7.

Overall Schematic

Done

EPC Contractor to perform final HAZOP and HAZID and update overall schematic.

Project Status – Engineering  S/N

Installation Methodologies Activities

Status

Further Actions

1.

Zero Downtime Method

Done

EPC Contractor to develop a detailed execution plan and procedures for this method

2.

Reduced Downtime Method

Done

-

3.

Comparisons between Methods

Done

-

4.

HAZID and HAZOP

Done

EPC Contractor to perform HAZID and HAZOP based on the execution plan and procedures developed by EPC Contractor

Project Status – Engineering 

Valve Skid Design

S/N 1.

Activities

Statue

Piping Analysis - Caesar II Model

Done

2.

Structural Analysis - SACS Model

Done

3.

Drawings

Done

Further Actions EPC

Contractor to carry out detailed design of Valve Skids .

EPC

Contractor to re-check installation analysis and design installation aids based on the final skid design and equipment / vessel proposed for installation. EPC

Contractor to develop detailed fabrication drawings.

Project Status – Engineering  S/N

Material Specifications Activities

Status

Further Actions

1.

Flanges, Bolts, Nuts, Gaskets and Fittings

Done

-

2.

Subsea DBB Expandable Gate Valves / Gate Valves

Done

-

3.

5D Induction Bends

Done

4.

Subsea Mechanical Connectors & Hot Tap Assembly

Done

EPC

Contractor to attend all FAT testing for both mechanical connectors and hot tap assemblies EPC

Contractor to perform mock testing before the actual installation works 5.

Field Welding and NDT

Done

6.

Construction Materials

Not Done

EPC Contractor to prepare welding and NDT procedures All non-long lead and construction materials to be procured by EPC Contractor

Project Status – Engineering  S/N

Installation Specifications Activities

Status

Further Actions

1.

Pipeline Installation

Done

EPC Contractor to develop all necessary installation procedures

2.

Survey and Monitoring

Done

EPC Contractor to develop detail survey and monitoring procedures.

3.

Pipeline Cleaning, Gauging, Pigging and Hydrotest

Done

EPC Contractor develop detail pre-commissioning procedures. Final HAZOP and HAZID need to be performed

Project Status – Engineering  S/N

Drawings Activities

Status

Further Actions

1.

Pipeline Alignment

Done

EPC Contractor to update based on pre-engineering survey and identify locations where span rectification is required

2.

Tie-in Arrangements

Done



EPC Contractor to update based on final arrangement proposed and approved by PMT / TGI 

EPC Contractor to perform HAZOP and HAZID based on the final arrangement and make necessary adjustments 3.

Valve Skid Details

Done

EPC Contractor to include details of installation aids and prepare fabrication drawings.

Discussion and Close Out

Related Documents

Pipeline
May 2020 70
Repair
October 2019 50
Repair
October 2019 47
Repair
May 2020 27

More Documents from "bpt2"