ENGINEERING ,PROCUREMENT,CONSTRUCTION (EPC)PROJECT AT ONGC PLATFORM – STUDY
PRAVIN POHANE MMS (OPERATIONS) SEM III
Mumbai High Field located about 165 km from Mumbai base
ØNQD is well cum process platform.
ØTo increase the production from North field of Mumbai High, an additional well fluid handling facility to be created on NQD platform
UNMAN PLATFORM
OIL WELLS
RIG OVER
UNMAN PLATFORM
NQD ENHANCEMENT PROJECT •OWNER : OIL & NATURAL GAS CORPORATION LTD. •LOCATION : MUMBAI HIGH NORTH FIELD •PROJECT DESCRIPTION : 1) PRE-ENGINEERING SURVEY 2) DESIGN ENGINEERING 3) PROCUREMENT 4) FABRICATION 5) LOADOUT, SEA FASTENING 6) TRANSPORTATION 7) INSTALLATION, HOOK UPS 8) TESTING,COMMISSIONING •LUMPSUM COST : Rs. 178.38 Crores. •AWARD DATE : 05.09.2008
PROJECT OBJECTIVES • To study overall project. • To study different activities involved in it. • To study progress reports & analyze the performance of activities. • To find causes of delay in project activities. • To suggest possible solutions for better project management in future.
TEST SEPARA TOR
SURGE TANK
PROJECT MILESTONES & COSTWISE WEIGHTAGES
SURVEY 1. Pre Engineering Survey. 3. Pre Installation / Construction Survey. 5. Post Installation Survey.
STUDY & ANALYSIS OF DESIGN ENGINEERING Vendo r
DESIGN APPROVAL STATUS
DESIGN ENGINEERING ANALYSIS
OBSERVATION S • Inexperienced Design Engineering staff. • Lack of Co ordination. • Lack of monitoring.
OFFSHORE ACTIVITIES 2. Mobilization Activity. 4. Project Activity. 6. Demobilization Activity.
MARINE VESSELS INVOLVED SUPPLY BOAT
ACCOMODATION BARGE
TUG BOAT PULLING DUMB BARGE
ANALYSIS OF MOBILIZATION ACTIVITY Stand BY :6 Days Clearance /Approval: 3days
ANALYSIS OF PROJECT ACTIVITY
ANALYSIS OF DEMOBILIZATION ACTIVITY
PROJECT PERFORMANCE CURVE
Analysis of Project Performance Curve. 1) Delay in approval of final drawings, purchase specifications. 2) Late delivery of long lead items like separator, surge tank & other imported piping material. 3) Fabrication catch up plan for 24X7. 4) Offshore activity performance was
PROPOSED PROJECT PLAN ON MS PROJECT.
ACTUAL PROJECT PLAN ON MS PROJECT.
POSSIBLE SOLUTIONS FOR DESIGN ACTIVITY • Centralized Design Engineering Team. • Design Agency to deploy engineer to DOEIL base. • Formats of reports to review. FOR PROCUREMENT ACTIVITY • Approved Purchase Specifications given to vendors in time. • Vendor Development program.
POSSIBLE SOLUTIONS FOR MOBILIZATION ACTIVITY • Marine activity Planning well in advance. • Fully dedicated logistic Team. FOR OFFSHORE ACTIVITY • Planning for next day work. • Equipment Break down to minimize. • Estimation for effective man hours.
BIBLIOGRAPHY BOOKS • Operations Research – HIRA GUPTA • Fundamentals of Project management- LEWIS JAMES
PROJECT REPORTS STUDIED • Daily Progress Report (DPR) • Weekly Progress Report (WPR) • Monthly Progress Report (MPR) • Document Control Index (DCI) • Marine Log Book.
THANKYOU