NPI process flow chart
Customer
MPB PM receive NPI information
New product
Assign FPL
Set up NPI team
Need to update
MPB NPI plan
NPI build preparation
1.Resource plan 2.NPI Schedule 3.Sample plan 4.NPI risk Plan 5.NPI Training Plan 6.Ramp up plan
1.Engineering documents 2.Material preparation 3.Tool preparation 4.Equipment Function Check 5.Test SW Check 6.Training 7.Line Set up 8.Calibration 9.GR&R
Confir m
OK
Need another build
NPI Build
NPI build report
Confir m
OK
LV
Ramp up
※ ※
PROPRIETARY INFORMATION OF FOXCONN INTERATIONAL HOLDINGS LTD.
※ ※
Foxconn International Holdings Ltd
系統名稱
(SYSTEM):
產品開發作業系統 Product Development Procedure
主題 (SUBJECT):
文件編號
新產品導入作業辦法
(DOCUMENT NO)
CMOAG-00 PAGE
New Product Introduction Procedure
8 OF 11
SMT NPI build flow chart 客戶 Customer Customer production
市場 PM NPI
工程 ME
企劃 PMC
品管 QA
Receive NPI Get the related specification and documents of process
Get the related specification and documents of process
NG Make the first evaluation on the possibility(Evaluate Equipment/process capability)
OK
Kick-off meeting and make NPI schedule
Inventory
Approva l
Approval by Customer
Coresponding related departments principal and making up NPI team Making CQP and related engineering document
Material preparation Empty Buyer
IQC check Check Engineering documents SIP Preparation
Fixture Preparation
Training
ESD check NG SMD Process Check Program and parameter Check OK Product Introduction Meeting (review meeting)
NG LCR Meter OK
Confirm
NG
Notice custormer
Compare with golden sample OK OK
V/I NG
Review
NPI report
Delivery
※ ※ PROPRIETARY INFORMATION OF FOXCONN INTERATIONAL HOLDINGS LTD. ※ ※
編號
(DOCUMENT NO):
CMOAG-0015 8 OF 11
資訊 IT
REV
E
SMT 制造
t the related cification and ments of process
SMTprogram making
SFC ready
g)
Feeding
SMTprogram adjustment
Double sides board making
First production making
Discarding Unrepairabl e
V/I
Repairable
OK
OLDINGS LTD. ※ ※
Repair
Pilot Run
Foxconn International Holdings Ltd
系統 名稱 (SYSTEM):
產品開發作業系統 Product Development Procedure
主題 (SUBJECT):
文件 編號 (DOCUMENT NO):
新產品導入作業辦法
CMOAG-0015
New Product Introduction Procedure
PAGE
10 OF 11
REV
E
ENO NPI build flow chart Customer Custume r Product
PM
NPI
TE
ME
Get the related specification and documents of process
ENO Manufacture
Receive HWID,SWID, TEST Plan
evaluate testing /assembly equipment , fixture design capability and technical capability.
feasibility evaluation for new product OK
Approval NPI Planning by customer
Approva l
Kick-off meeting and make NPI planning
Approval by customer
Material preparatio n
download software to server
Coresponding related departments principal and making up NPI team
Approva l
PMC
Get the related specification and documents of process
Receive NPI
NG
QA
Inventory
Empty IQC check
Buyer
Check Engineering documents
Making CQP and related engineering document
SIP Preparation ESD check ENO process check
Fixture Preparation
check version of HWID/SWID/Test plan
Training
Product Introduction & review Meeting
get reference phone
Feeding
NG Approva l
Make 1st pcs
GR&R NG
OK
FLALI OK
NG
Failure analysis& adjust tester
FINUI OK NG
Bulk pack OK
Repairable
repair Unrepairable
Discarding Review
NPI report
Delivery Rump up
Rump up
※ ※
PROPRIETARY INFORMATION OF FOXCONN INTERATIONAL HOLDINGS LTD.
※ ※
Foxconn International Holdings Ltd
系統 名稱 (SYSTEM):
產品開發作業系統 Product Development Procedure
主題 (SUBJECT):
新產品導入作業辦法 New Product Introduction Procedure
文件 編號 (DOCUMENT NO): CMOAG-0015 PAGE
11 OF 11
REV
E
Ramp up flow chart Customer
Custume r Product
ME
SMT Manufacture
QA
Get the related specification and documents of process
TE
ENO Manufacture
Preparing for ramp up
IQC check Making CQP and related engineering document
PMC
Training by ME
ESD check
Prepare materials
Prepare Hardware&softwar e
Training by TE
Equipment function check
Fixture Preparation SIP Preparation
Produce PCBA
SMT process check
2+2 testersTrial Run
Line setup
NG
Gage R&R
Approva l
OK
Trial 100pcs
ESD& process check
Ramp up 40%
Ramp up 90%
Ramp up 100%
Mass production
※ ※
PROPRIETARY INFORMATION OF FOXCONN INTERATIONAL HOLDINGS LTD.
※ ※