Submitted By:
Guided By:
Akash Suresh K 4VP14CV402 8th Sem Civil Engg. VCET Puttur.
Prof. Divya Swaroopa Asst Professor Dept. of Civil Engg. VCET Puttur. 1
CONTENTS
Introduction Uses of Mivan Formwork Advantages and limitations of Mivan formwork Comparison of Mivan formwork with Conventional formwork Working cycle of Mivan formwork Case study Summary Reference
2
INTRODUCTION Mivan technology is a fast-paced construction
technique by using aluminium formworks. Mivan is an aluminum formwork system developed by a European construction company.
In 1990, the Mivan Company Ltd. from Malaysia started manufacturing these formwork systems.
To facilitate fast construction, early removal of forms. Mivan Formwork 3
USES OF MIVAN FORMWORK 3S – System of Construction – Speed, Strength, Safety. Column and beam construction are eliminated. Walls and slabs are cast in one operation. Specially designed, easy to handle light weight pre-engineered aluminium forms. Fitting and erecting the portion of shuttering. Carrying out concreting of the walls and slabs together.
4
ADVANTAGES OF MIVAN FORMWORK Fast construction is assured and is particularly suitable for large magnitude construction of respective nature at one project site. Construction carried out by this system has exceptionally good quality with accurate dimensions for all openings i.e., doors & windows. .Concrete surface finishes are good to receive painting directly without plaster.
System components are durable and can be used several times without sacrificing the quality or correctness of dimensions and surface. As all the walls are cast monolithic and simultaneously with floor slabs requiring no
further plasters finish. Therefore the time required in the conventional method for construction of walls and plastering is saved.
5
LIMITATIONS OF MIVAN FORMWORK It requires uniform planning as well as uniform elevations to be cost effective. Due to box-type construction, contraction cracks are likely to appear. Heat of hydration is high due to shear walls. It is rigid in design once placed, as any alteration becomes tough later. The formwork requires number of spacer, wall ties etc. which are placed @ 2ft c/c; these produce problems such as seepage, leakages during monsoon. Services after completing become slightly difficult.
6
COMPARSION OF MIVAN FORMWORK WITH CONVENTIONAL FORMWORK SL NO 1.
CHARACTERISTICS
2.
Quality of surface finish
3.
Pre-planning of formwork system
4.
Wastage of formwork material
5.
Accuracy in construction
6.
Resistance to earthquake
Speed of construction
MIVAN CONVENTIONAL FORMWORK FORMWORK Four days cycle per Ten days cycle per floor floor Excellent plastering is Plastering is required not required Required Not required Very less
In great amount
Accurate construction Less than Aluminium formwork Good resistance Less than Aluminium formwork
7
WORKING CYCLE OF MIVAN FORMWORK Setting up the wall reinforcement Positioning of brackets & platforms
Lifting & fixing of panels Fixing kicker & external shutters Erection of wall Pouring concrete Dismantling 8
CASE STUDY 1 COST COMPARISON OF MIVAN TECHOLOGY WITH COVENTIONAL CONSTRUCTION TECHNOLOGY Study site: Blue Ridge Tower HA-1, Pune. It is a part of Paranjpe scheme’s “Blue Ridge” a 138 acre integrated township Hinjewadi , Pune. They had acquired the data of Tower HA-1 (25 Floors).
“Blue Ridge” Tower HA-1 Hinjewadi, Pune. 9
DETAILS ABOUT THE STRUCTURE: 1. Grade of concrete 2. Slump 3. Wall thickness 4.
Steel
5.
Slab thickness
6.
Finishing
7.
Number of floors
8.
Area
M 35 180 -200mm External wall : 200mm Internal wall : 100 mm Partition wall : 10mm dia Structural : 12mm dia Shear wall : 16mm dia Hall : 175mm Bed room : 150mm Kitchen : 125mm External : Textural paint Internal : Paint over gypsum 25 floors 10
3 BHK : 184 Sq.m 2 BHK : 125.4 Sq.m
COST COMPARSION: Sl no
Parameter
Cost by conventional technology Wooden materials = Rs.88.50/sq.m M.S. materials=Rs.100/sq.m
Cost by Mivan technology
Rs.83.8/sq.m
Rs.104.63/sq.m
Cost saving
1.
Shuttering after repitation
2.
Concreting
Rs.1400/sq.m
Rs.1505/sq.m
Rs.105/sq.m
3.
Reinforcement
1,480.00
2,115.20
Rs.635.2/sq.m
4.
Brickwork
484.00
0.00
Rs.480/sq.m
5.
Plaster
700.00
0.00
Rs.700/sq.m
Total cost saving = RS.548.43/sq.m 11
CONCULSION OF CASESTUDY It’s well known that the Mivan Technology reduces the cost of construction from above analysis, hence the technology is useful to the construction company and builder. MIVAN formwork played a vital role in the construction of the project. The project
was completed not only on stipulated period of time but also paid off with its attributes. Speedy & quality dwelling units were provided to the people of low income groups at very reasonable costs. MIVAN is a definitely future of this ever
growing construction industry with lots of project still awaiting its touch of excellence. 12
SUMMARY Civil engineers not only build but also enhance the quality of life. Their creativity and technical skill help to plan, design, construct and operate the facilities essential to life. It is important for civil engineers to gain and harness the potent and versatile construction tools. MIVAN serves as a cost effective and efficient tool to solve the problems of the mega housing project all over the world. MIVAN aims to maximize the use of modern construction techniques and equipments on its entire project. Thus it can be concluded that quality and speed must be given due consideration with regards to economy. Good quality construction will never deter to projects speed nor will it be uneconomical. 13
REFERENCES Ketan Shah., (2005),“Modular formwork
for faster, economical and quality
Construction”, Indian Concrete Journal, Vol-79, pg. 6-23. Kushal Patil., Ajitkumar Jadhav., Nikhil Shingat.,(2015),“Mivan Technology”, International Journal of Engineering and Technical Research (IJETR) ISSN: 2321-0869, Volume-3, Issue-6. Mr. Shankar Bimal Banerjee., Mr. Pawan Dilip Barhate., Mr. Vipul Pradip Jaiswal., (2015),“Mivan Technology”, Novateu Publications International Journals Of Innovation In Engineering Research And Technology [IJIERT], Volume 2, Issue 3. Patil R.S., Pawale D.B., Tambe H. D. and Pawar P.D., Wakchuare A.V., (2016),“Mivan Technology
Using
Aluminium Formwork”, International Journals Of Engineering
Sciences & Management, ISSN 2277 – 5528,14 Impact Factor- 3.145.