Drainage works Section – 1 -
Survey layouts, excavation of trench, bed preparation, placing of precast RCBC and manhole, and pouring of sand cement from P07R - P10R. – In progress Rectification / reconstruction of street inlet bet. P12L – P13L. Survey layouts, excavation of trench, bed preparation, placing of RC pipes and concreting of manholes and sandfilling on top of RCPC from P20L – P22L. – In progress Survey layouts, excavation of trench, bed preparation and setting of rebars for cast-in-place RCBC at P36L – In progress Rebar works – fabrication of precast manholes at P54R. - In progress Hot works – fabrication of manhole frames at P81. - In progress Test pitting near P14C. Rectification of cement mortar joint collars for RCBC (bet. MH-3 and MH-3) from P08R-P10R. – Done
Section – 1A -
Excavation and removal of existing manholes from S1A-P07L to S1A-P09L. – In progress
Section – 2 -
No on-going activity.