INSPECTION REQUEST (IR) Inspection Request Number :
Date : Client :
PMC :
Contractor : Name of the work : Package No : Name of Work :
Area / Location of Inspection
Reference Dwg. No :
Date : Inspection required at: We request your attendence to inspect the following works : (Desrciption)
Requested by Project In-charge (Contractor) : Date : Works Ready for Inspection : Contractor Representative
Name
Time :
Date
Signature
Site/ Project Engineer MEP Engineer QA / QC Engineer EHS PMC Comments : Approved Approved with Corrective Actions Not Approved Name & Signature of PMC rep.
Name & Signature of CLIENT Rep.
Date :
Date :
Receieved by the contractor Signature
Date :
Check List for Concrete, Formwork & Reinforcement (POUR CARD) Pour Card Number :
Date :
Client :
PMC :
Contractor : Name of the work : Package No : Name of Work : Area / Location of Inspection Reference Drawing No and Rev No Start Date & Time Sl. No
Desrciption All Method statement & Risk Assessment approved by 1 Concerened Dept for location / level footing / column / beam / slab / 2 Check flooring completed as per relevant Dwgs for reinforcement work done as per approved Bar Bending 3 Check Schedule & structural drawing. for reinforcement work tied (with binding wire completed 4 Check as per drawing). for MEP Inserts / conduits / cut outs etc. laid as per 5 Check drawing and approved by the departments. for formwork laid to the correct dimensions including line, 6 Check level & plumb checked including form all for sufficient length and number of re-bars dowels, if any, 7 Check laid for future / further extension works as per drawing. 8 Check for staging including bracing work completed properly. reinforcement placed in correct position by placing cover 9 Check blocks / chairs / spacer bars etc.
10 Check for concrete top level marked at required places. for concrete area cleared off nails, binding wire, wooden 11 Check wastes & taped with haevy duty tapes etc. for sufficient number of vibrating & finishing items 12 Check available. for safety protection like barricades / scaffolding 13 Check platform / lighting arrangements completed. 14 Check for availability of curing arrangements. 15 Check for required grade of concrete M for concrete placed and compacted in layers and finished 16 Check as per the requirements. 17 Total Concrete Quantity 18 No. of Cubes taken & Identify No's
Remarks if any :
Completion Date & Time Signature Result Contractor's PMC/ CLIENT (OK/NA) Rep.
Name & Sign. Of Site Engg ( For Contractor)
Name & Sign. Of PMC eng / CLIENT Rep.
Date :
Date :
Remarks