Improved Process chart --- Part A Quantity
Travel Feet
Symbol
Process
Remarks
Storage in tube cradle 55 tubes
0
Lifting using crane Loading on to trailer
1840 10 tubes
Trailer pulled by truck to Dept. 91 stores Loading onto trailer with crane
1000
Transported to Dept. 91 Loading onto wheeled rack
11 tubes
In wheeled rack 100
Transported to chamfering machine Chamfering Turning Cutting Unloading the stock Loading the cut piece Chamfering at cut off end
726 pieces
Cut pieces are loaded into the tub In tub 100
726 pieces
Transportation by gasoline lift truck to the inspection area Inspection for count and visual quality Pieces are loaded into tubs In tub
Use overhead crane Time in crane travel minimized Eliminate Dept. 97 and rack
Transported by Gasoline lift truck to Dept. 41 Loaded into washer Washing 726 pieces
Ejection into tub
Eliminate container
In tub 85
Transported to sand blast room Unloaded behind the sand blast machine Sand blasting
726 pieces
Loaded into the transportation tubs In transportation tub
1 tub
157
Transportation of tubs by electric lift truck to inspection area Counting of pieces
725 pieces
Retubbing In tub Lifting by gasoline lift truck 587
Transported to welding area
Eliminate ordinary tub
Improved Process chart --- Part B Quantity
Travel Feet
Symbol
Process Storage in Warehouse
58 strips
5 500
Loaded into a trailer Transported by trailer truck combo to Dept. 56 Loading on to piercing machine Piercing Blanking Unloading from machine Checking for size and no. of holes
500 pieces
Unloading to pan In pan 25
Transportation by lift truck to flattening machine Loading on machine Restriking Flattening
3000 pieces
Loading into tub In tub Checking for quality
1 tub
Lifting by electric hoist 12
Transported to washing machine Unloaded to washing machine Washing
3000 pieces
Unloading into tubs
Remarks
In tub
1265
Weighing for verification of count Transported by gasoline lift truck to Dept. 41 Unloading beside sand blasting machine Loading into sand blasting machine Sand blasting Extraction of grit
3000 pieces
Shoveling into tubs In tub
1 tub
Loading into electric lift truck 157
Transported to inspection area Verification of counts
1 tub
Loading onto gasoline lift truck
3000 pieces
Loading into bins by hand In bins
1 bin
Transportation to welding assembly fixtures in Dept. 42 Positioning on assembly fixtures
Instead of taking to dept. 43 for putting into boxes, just put into bin straightaway at dept.41
Process chart --- Assembly Quantity
Travel Feet
Symbol
Process Storage near welding machine
1 each
Clamping of parts A and B Gas welding Inspection Storage