Wind Farm Development Thursday 16th November 2006
Introduction to Mott MacDonald • Technical consultancy active in power, water,
transport, buildings, communication, education, health etc
• Leading capability in power covering renewables,
thermal and nuclear
• Approximately 800 staff active in
power…equivalent of 90 in renewables
• Mott MacDonald’s renewable energy capability
focussed in Glasgow with wind, biomass and marine technology skills
• Currently involved in 30+ wind projects across UK,
Europe and Asia
Introduction to SgurrEnergy • Leading independent multi-disciplinary consultancy
specialising in renewables
• Based in Glasgow and Beijing – Further international expansion planned • Over 40 experienced professionals • Accumulation of decades of experience • Experience in over 20 countries
Drivers and Regulatory Structures
UK Wind Project Development - Status
O&M
Handover
Construction
Procurement
Scheme Development
START OF COMMERCIAL OPERATIONS
Decommissioning
Onshore Offshore Operational No. & MW No. & MW England 49 210 3 153 N. Ireland 11 89 0 0 Scotland 31 568 0 0 Wales 23 254 1 60 Total 114 1124 4 213
Pre-Construction
Onshore No. Offshore Planning
& MW
No. & MW
England 43 N. Ireland 29
822 599
6 0
2718 0
Scotland 74 Wales 14 Total 160
5399 183 7006
0 0 6
0 0 2718
Construction
Under construction England N. Ireland
Onshore
Offshore
No. & MW
No. & MW
8 2
111 41
1 0
90 0
Scotland Wales Total
14
523 3 46 27 722
0 1 2
0 60 150
Revenues available to a UK wind generator
£ /M W h
100 90 80 70 60 50 40 30 20 10 0
LEC ROC Energy
•
A UK wind generator will be able to earn revenue from three sources; sales of energy and ROCs and LECs
•
ROCs and LECs are tradable green certificates issued for renewable generation – ROCs derive from the Renewable Obligation and LECs derive from the Climate Change Levy
ROCs – Renewable Obligation Certificates • Derive from the Renewable Energy Obligation
introduced in April 2002
• Obligation on retailers to buy a certain percentage
of their energy from accredited renewables generation – set at 3.2% in 2003, now 6.7%.
• If a retailer does not comply it pays a fine – buyout
penalty - now ~£33/MWh - on top of its energy cost
• Accredited renewables generators are issued ROCs
for energy produced - 1 ROC per 1 MWh
• Retailers buy ROCs to demonstrate compliance with
RO
ROC recycle • Buy-out payments are collected and are recycled to
holders of ROCs in proportion to their ROC holdings
• This means that a ROC has a value greater than the
buy-out price as holders of ROCs receive a share of buyout monies
• The recycle bonus rises as the level of shortfall
increases
• If the RO target were met the ROC price would drop
to zero!
ROC values versus RO shortfall in 2006 70
ROC value: £/MWh
60 50 40 30 20 10 0 0
10
20
30
% shortfall on RO Target
40
50
Drivers of ROC prices • Supply and demand • Supply will depend on amount of renewable capacity built and
its utilisation – rule changes
• Demand is set by the RO targets • Currently set to rise linearly to 10.4% in 2010 • View is that target will be raised after 2010 possibly to the 20% target aspired to. • Buy-out prices indexed to inflation • Banking of ROCs by suppliers/ traders may affect prices • Dominant suppliers (which are also the main owners of RE
plant) will ensure that RO target is not met to stop ROC values falling to zero
• Scheme is now being reviewed
RO Review - Issues • There are a number of concerns regarding the
RO
• Rewards to lower cost renewable generators are too
generous
• There is considerable uncertainty regarding ROC prices,
especially after 2015
• There is a cliff edge for ROC prices if full compliance of
the RO is achieved
• Rewards for high cost more innovative renewable
generation are too small to support deployment
RO Review Outcomes • Future ROC allocation may be banded. Mature
technologies likely to issued less ROCs per MWh than selected promising but high cost technologies (like PV).
• Scheme likely to be rolled out to 2020 • The recycle arrangements will be changed in order to
eliminate the possibility of ROC prices collapsing to zero
• EU Commission still favours that all Europe moved to
feed-in tariffs
Climate Change Levy (CCL) • Introduced in 2002, CCL is a tax on energy consumption by
large industrial and commercial users – not paid by generators
• Electricity is taxed at £4.3/MWh • Energy from certain renewable sources and from qualifying
cogeneration is exempted and is issued a Levy Exemption Certificate (LEC).
• Different set of renewables to RO – LECs include mini hydro
and municipal waste, while ROC don’t. ROCs include biomass co-firing, LECs don’t
• LECs are sold with energy to suppliers/customers who can then
offset their CCL obligation (£4.3/MWh) – Can be separated for output sold off-site
• Stand alone renewable generators can normally capture 85% of
LEC value
• Unclear how long tax will continue
Energy Review and Renewable Grid Issues •
One of the key issues that has delayed the introduction of renewables and limits the achievement of the 2010 target.
•
ER06 states there is the need to resolve a number of issues: – Final Sums Liability (paying up front for connection) – Connection queues as a result of increased interest in renewables [Clustering, i.e. group connections similar to NI, provide better network planning but can disadvantage some generators] – Renewables lower transmission use of system charges? – Need to change from ‘invest then connect’ to ‘connect and manage’ – Regulatory framework for offshore wind
•
All above issues were identified around time of ER03
Transmissionlevel issues Distribution and Transmissionlevel issues Distributionlevel issues
Stern Review of Economics of Climate Change • Sir Nicholas Stern’s review of the economics of
climate change has two key messages for renewables
• Renewables are central part of the carbon
mitigation strategy
• There should be a huge scale up in funding of R&D
and deployment of low carbon technologies, including renewables
Planning and Permitting Issues
Overview of Legislation Windfarm consent needs are driven by legislation • Planning permission/consent to build granted under –
Section 36 of Electricity Act for over 50MW
–
Town and Country Planning Act for under 50MW
• Environmental Impact Assessment (EIA) needed for planning
applications –
The Electricity Works (Environmental Impact Assessment) Regulations 2000
–
Town and Country Planning (Environmental Impact Assessment) Regulations 1999
If require consent for grid connection • Either Section 37 of Electricity Act or Town and Country Planning Act • Also need an EIA for grid connection consent
Planning Process – Initial Stage • Early consultation with key stakeholders – Initial approach to local authority – Seek initial views of key stakeholders
no surprises later
• Scoping of EIA – Focus on key issues through consultation and discussion with key
stakeholders – Time spent at scoping stage could save time later in process
• Identification of likely need for baseline studies – Identify available data / data gaps early
• Develop public consultation strategy • Landowner consultation
Interfaces Statutory Consultees (SEPA or EA, LPA, DTI or Scottish Exec, English Nature or SNH, MOD, CAA etc)
Client
Environmental Landscape and visual Ecology Ornithology Hydrology & hydrogeology Noise Communications Archaeology Traffic & transport
Public Consultees
Technical Transport/ Routes
Engineering Geology EIA preparation
Layout Optimisation Civil
Planning
Planning Process – EIA Stage • Ensure project assessed covers all potential technical options • EIA scope focussed on key issues in a robust manner e.g. – landscape and visual impact including cumulative impact – ornithology; presence of SPAs and SSSIs close to site ecology – radar interference
• Input from experts capable of taking to Public Inquiry • Supporting studies commissioned in timely manner and scope
agreed with key consultees
• Meeting project programme through management of large
environmental resource and sub-consultants
• Integration with the design process – Ensure mitigation measures consistent with project design
Planning Process – Application Stage • Maintain close interface with local planning
authority (LA) / Scottish Ministers (SM) after application
• Respond to queries/requests for more information
in timely manner
• Close integration with project design team to try
and mitigate issues to avoid Public Inquiry
• Agree planning conditions with LA and SM • Translate planning conditions into contractor
requirements
Public Consultation • On going throughout the planning stage • Manage flow of information / publicity to local
people and organisations – information voids can fill with bad news !
• Understand the local and regional politicians –
background to phase 1 essential
• Review comments from third parties of previous
EIA’s and identify potential supporters and risks
Project Evaluation
Site Identification & Provisional Layout • Wind resource and regime – NOABL – Reanalysis
• Grid connection • Access and buildability • Constraints
Technical & Environmental Constraints Houses (noise, Shadow-flicker)
Underground Cables / Pipelines
Areas with Historical Importance
Roads
Wildlife Areas
Overhead Lines
Landowner Boundary
Wind Regime Assessment • Undertake wind regime assessment campaign using: – Wind Monitoring Masts – SODAR – LIDAR
• Monitor for 12 months or more • Monitor at multiple locations
Measured Turbulence Intensity & Wind Shear Measured and Modeled Turbulence with Height
Ambient turbulence intensity and…
60
Height (m)
50 40
Modeled Fit
30 20
Measured Data
10
Measured and Modeled Wind Shear in Forestry
0 0%
20%
30%
40%
Tubulence (%)
80 Height Above Ground Level (m)
10%
70
Open Moorland Wind Shear Zo = 0.4
60 50
Forested Area Wind Shear
40 30 20
Theoretical Forest Wind Shear based on Zo = 0.8
10 0 0
1
2
3
4
5
6
Av e rage Wind Spe e d (m/s)
7
8
…wind shear must be accounted for in fatigue life calculations
Added Turbulence • Wake induced turbulence must also
be investigated.
• Modified Sten Frandsen model
combined with far wake modelling Plotting predicted CTI against IEC threshold
30%
Plotting predicted CTI against IEC threshold 25% 35% CTI (V90
20%
15%
10% 0
5
10
15
Wind Speed (m/s)
20
25
Characteristic Turbulence Intensity
Characteristic Turbulence Intensity
35%
2MW ) IEC 61400 threshold
30%
25%
CTI (Bonus 2.3) IEC 61400 threshold
20%
15%
10% 0
5
10
15
Wind Speed (m/s)
20
25
Impact of Complex Roughness Complex roughness, such as buildings and forestry has significant impact on wind turbine operation. These features produce higher than specified turbulence intensity & wind shear. Effects on: – Power Curve – Operational Loads – Fatigue Life
The effects of trees are further complicated by growth and felling
Extreme Wind Speed • Analysis typically
performed only at site mast
• Two methodologies for
Extreme Wind
• WAsP Engineering to
model gust values across the site
Components of a Wind Turbine (Model shown is Vestas V80) Nacelle
Oil cooler Rotor blades
Ultrasonic sensors
Hub controller
High voltage transformer
Main shaft
Electrical generator Gearbox
Yaw gears Tower
Hydraulic system
Technology Selection • IEC Classification – Mean & Extreme Wind Speed – Turbulence Intensity – Wind Shear
• Compliance – Noise Emission – Grid Code Compliance – Environmental Conditions
• Economic Viability – Production – Cost
Energy Yield Modelling • Final layout iteration – Compromise between
maximum production and constraints • Predict energy yield – Rigorous quality checks – Multiple MCP techniques – Model validation and tuning – Complex forestry modelling – Quantification of
uncertainty
Performance Testing • Power performance testing • Noise compliance • Planning & environmental compliance • Grid code compliance
Project Procurement and Financing
Overview of Contracting Strategies - Who and Why • EPC Contracts – Majority of risks on Contractor – One contract to deal with – Sometimes developers with little experience or as a pre-
requisite to Project Financing
• Multi-Contract – Lower overall costs – Increased competition; more choice of contractors – Usually developers with sufficient in house experience or
good OE support, using own funds – Prevalent for UK onshore projects
EPC Contracts • Single Contractor – Takes most of the risks, handles the interface workload and
risks, provides price certainty – More expensive than multi-contract; risk premium added in – Not always the WTG supplier who leads – Can be for multiple sites
• Owner still needs to do front-end development and
gain permits
• Owner may also need technical support
Multi-Contract • Multiple Contractors covering several scopes – Electrical, civil, WTG supply, grid connection – Lower overall cost – Owner takes interface risk and has much higher workload
• Owner still needs to do front-end development and
gain permits
• Several contracts to negotiate instead of one • Owner likely to need more technical or project
management support
Sources of Funding… Equity
Debt Project Finance
Investors i.e. VC
Shares
Standby Equity
Bonds
Subordinated Debt Mezzanine Finance
• Return on Investment
• Definite Term
• Payback period
• Financial Market Rates
• Initial commitment
• Fees
• Guarantees/Support
• Cover Ratios
Why Project Finance…Depends on who you are? PF for Sponsors • Insulation from Project Debt and Risks! •Spread of risks for large projects •Off balance sheet •Corporate borrowing restrictions •Tax advantages •Risk sharing
PF for Utilities/Govt •Access to foreign investment •Foreign skills and know how •Outside Public Sector Borrowing •Accelerates non-priority projects
Project Finance…why not! • Time…..
• Project scale…..
Project Structure Market Risks
Financial Risks
Suppliers
Banks Sponsors
Supply Agreements
Credit Agreements
Shareholder Agreements
Offtakers
Offtake Agreements
Project Company O&M Agreement
Consents/ Permits
Local Legislation Government
Legal & Regulatory Risks
Concession Agreement
Construction Agreement
Construction & Operation Risks
Operator Contractor
Implications of Gearing and Non/Limited Recourse Nature •Turbine Technology - turbine reliability issues ranging from minor to very major •EPC risk – Wrapped EPC no longer essential for banks but is risk pricing sufficiently clear? •Operations - Availability of third-party maintenance providers post warranty period •Offtake Risk – Firm Power Purchase Agreement (PPA) and confidence regarding Green Certificates •Wind Risk – Confidence needed in P50 or P90 value in FM
Summary •Drivers •Market drivers in the UK are sufficiently strong to ensure continued growth of RE projects. ROC improvements will reinforce this •Barriers •Availability of grid connection and planning consent are the major obstacles to the rate of deployment •Development Focus •An awareness of project financing and project risks is a requirement from the outset – all technical and environmental issues must ultimately relate to these
Summary •Contract Strategy •Need to adopt contract strategy based on resources and attitude to risk •Financing
•Financing options must be considered from the outset to ensure the project is developed appropriately •Need to understand how to match project structure and risk profile to financing options
www.mottmac.com