2018 GIS INSTALLATION REPORT
Prepared by: Eng. Mohamed Mustafa Elgweiny followed by: Eng. Ali Abo ashour (site manager) Checked by: Eng. Tawfik Elsaid (project manager)
محمد مصطفى الجوينى.م
Uptown Cairo Project Mokattam, Cairo – Egypt Zahraa El Mokattam 220/22 KV GIS Substation (2*75 MVA) Power Transformers
Client
: Emaar Misr for Development S.A.E.
Supervision : Shaker Consultancy Group
Contractor
: Consortium: (KN / HHI)
Page 1
محمد مصطفى الجوينى.م
Table of contents Table of contents ............................................................................................................................................. 2 General information and specifications for GIS................................................................................................ 3
General specifications.......................................................................................................................... 3
GIS main components information ....................................................................................................... 4
GIS sub components information. ...................................................................................................... 21
2. General requirements for GIS installation. ................................................................................................ 30
Preparation of Site Condition ............................................................................................................. 30
Preparation for Installation ................................................................................................................. 31
Ground marking and Transportation sequence. ................................................................................ 33
Transportation process ...................................................................................................................... 35
3. Installation process. .................................................................................................................................. 36
Initial assembly process ..................................................................................................................... 36
Docking process ................................................................................................................................ 39
Vacuum and SF6 gas works .............................................................................................................. 43
4. Accessories installation .............................................................................................................................. 46
Earthing shield ................................................................................................................................... 46
Linkage bars ...................................................................................................................................... 47
Platforms ............................................................................................................................................ 47
Supports............................................................................................................................................. 48
Cables work ....................................................................................................................................... 49
5. Schematic diagram for OHTL Bay. ............................................................................................................ 50
List of contents ................................................................................................................................... 50
External wire specification ................................................................................................................. 50
SLD, layout, interlock, internal arrangement and sf6 system ............................................................. 50
DC and AC systems........................................................................................................................... 50
Closing and tripping circuits for C.B ................................................................................................... 50
Closing and opining circuits for D.S and E.S ..................................................................................... 50
Alarms, indicators, monitoring and control circuits ............................................................................. 50
C.Ts and V.Ts wiring.......................................................................................................................... 50
Page 2
محمد مصطفى الجوينى.م
General information and specifications for GIS
General specifications
maximum voltage / Nominal voltage
245kv rms / 220kv rms
Entrance and out let
Through GIB
Rated current for bus bar
2000 A
Rated short time withstand current
50KA / 1sec
Maximum ambient temperature
50 ºC C.B
7 bar
Others
5 bar
C.B
6.5 bar
others
4.5 bar
Rated gas pressure
Minimum gas pressure
2 OHTL 2 Transformers No. of bays
5 bays+3 future
1 Bus coupler 2 future underground cable bays 1 transformer future bay
Page 3
محمد مصطفى الجوينى.م
GIS main components information
Bays single line diagram (SLD).
Double bus bar single breaker system.
7 LCCs panels.
4 voltage transformers for each bus bar.
Page 4
م .محمد مصطفى الجوينى
Page 5
محمد مصطفى الجوينى.م
1.
Circuit breaker (C.B).
Circuit breaker is designed to protect the circuit from damage caused by excess current from an overload or short circuit. Its basic function is to interrupt current flow after a fault is detected.
Rated voltage 245KV. Rated current 1600A except bus coupler 2000A. Short circuit 50KA /1s Rated gas pressure 7 bars. First stage leak alarm 6.7 bar. Second stage leak alarm 6.5 bar. Bursting pressure of relief 15 bars.
Circuit breaker components. 1. Close coil 2. Two trip coils 3. Mechanism box per phase. 4. Position indicator (open or close) 5. Operation Counter 6. Spring indicator (Charged or Discharged) 7. Charging Hand (crank) 8. Charging motor 9. Spring for close coil 10. Spring for trip coils 11. Terminal blocks 12. Connection socket 13. Close push Button 14. Open push Button 15. Movable and fixed contacts. Page 6
م .محمد مصطفى الجوينى
Page 7
محمد مصطفى الجوينى.م
Mechanical operation for CB per phase. 1. 2. 3. 4. 5. 6.
Charge the spring. Press at close push button (close order). Press at trip push button (open order). Close time around 65ms. Trip time around 25ms. The charged spring is enough to operate both close and open orders.
CB SITE TEST. Contact resistance (mΩ).
1.
By inject 100A DC and measuring the voltage, and then get the resistance.
Micro-ohm meter
Resistance must be less than 20 MΩ.
Page 8
محمد مصطفى الجوينى.م
2.
Timing test
This test to be done to determine the close and open time for circuit breaker
This test is done for all electrical D.S / E.S.
Page 9
محمد مصطفى الجوينى.م
2.
Disconnector switches (D.S) and Earthing switch (E.S).
Used to isolate or connect circuits for maintenance, test, and load transfer and operation reliability.
Each phase in separate compartment with or without E.S. In each bay there are one or more D.S depend on its function.
Operation of D.S / E.S done off load.
D.S (Q1)
E.S (Q51)
D.S (Q2) E.S (Q52)
Rated voltage 245KV. Rated current 1600A except bus coupler 2000A. Short circuit 50KA /1s Rated gas pressure 5 bars. First stage leak alarm 4.7 bar. Second stage leak alarm 4.5 bar. Bursting pressure of relief 10 bars.
Page 10
D.S (Q9) E.S (Q8)
محمد مصطفى الجوينى.م
Disconnector and Earth switch components. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
Main box for 3phases Dc motor Moving Mechanism Open limit switch Close limit switch Door limit switch Selector switch (operate and lock) Terminal block Socket Mechanism per phase Link rods between 3 phases the Mechanism
Page 11
محمد مصطفى الجوينى.م
Mechanical operation for (DS/E.S). 1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
Open the door. Put selector on operate position. Check lock pin appear or No. When Appears, you must release interlock. Insert manual handle. Check position (open or close). Follow operation direction mark. Remove handling. Close the door. Close operation time around 2.5: 3 s the three phase mechanisms operate simultaneously at same time by Linked operation rods.
Difference between (E.S) and (DS). 1. 2. 3.
Isolate the mechanism by plastic material. Isolate the bolts by plastic material. Copper plate to connect mechanism to body (enclosure).
Page 12
محمد مصطفى الجوينى.م
4. E.S rod is conductor (metallic) opposite to D.S which is insulator.
D.S isolator rod
E.S Metallic rod
3.
High speed earthing switches
(HSES).
Same components as E.S but include hydraulic piston (damper).
Mechanical operation for (HSES).
The motor charges piston and the piston suddenly perform the operation of main.
contacts at smaller time than normal ES (very short time) Used at overhead transmission line or long underground cable for fast discharge
Page 13
محمد مصطفى الجوينى.م
Mechanical interlock between DS (Q9) with ES (Q8).
Used allow for one equipment only closing D.S or E.S.
Mechanical inter lock
4.
Local control cubical (LCC).
The local control of GIS equipment through LCC panel.
All signals of V.Ts, C.Ts, and position indicators of (C.B, D.S, E.S...) transferred to LCC panel by L.V cables.
These signals transferred to control and protection panels from LCC panels by L.V cables.
Page 14
محمد مصطفى الجوينى.م
LCC components: 1.
Mimic diagram.
2.
Annunciator.
3.
Ammeters, voltmeters, multi meters.
4.
Terminal blocks, Wiring.
5.
Push buttons / selector switches.
6.
Test switch.
7.
Heaters.
8.
MCB (AC/DC/VT).
9.
Contactors, Auxiliary relay
10.
Timer
11.
Ventilation fans.
12.
Semaphore
13.
Lamps
14.
Thermostat
Annunciator, push bottoms, selectors
Ammeters, voltmeters, test switch
Operation Procedures from LCC: 1. 2. 3. 4. 5. 6.
All MCB close All signal DC and AC ok Interlock ok Block operation ok Indication ok Put selector switch at local
7.
Put selector switch at emergency
8.
Operation DS , ES and CB at test position
Operation CB at normal operation
Push the push button for operate
Page 15
Mimic diagram, semaphore, selectors
محمد مصطفى الجوينى.م
Relationship between LCC with other panels.
Page 16
محمد مصطفى الجوينى.م
5.
Current transformer (C.T).
Measurement of current in small values available through secondary windings to connected to measuring and protection devices.
CT Components:
1. 2. 3. 4. 5.
Primary winding (main conductor) Secondary winding (coils) Pushing for secondary Terminal Terminal block with sliding links Test switch for core measurement at LCC.
Types:
According to class:
1. 2.
Class (5P20, 5P10) for protection. Class (0.5CL) for Measurement. According to secondary ratio:
1. 2. 3.
1A for numerical relays 5A for mechanical and static relays 2A for special use (winding temperature indicator) According to location:
1. 2. 3.
Around bushing BCT Switch gear CT Outdoor CT
CT connection
Facility for shorting CT Facility for use any ratio Facility for reverse polarity Facility for Earthing CT
Page 17
محمد مصطفى الجوينى.م
Terminal block connection.
C.T site tests:
1. 2. 3. 4.
Polarity test Ratio test Exciting current characteristic test Megger test
Technical data:
Page 18
محمد مصطفى الجوينى.م
6.
Voltage transformer (V.T, P.T).
Measurement of voltage in small values available through secondary windings connected to measuring and protection devices.
VT Components:
1. 2. 3. 4. 5. 6.
Primary winding. Secondary winding. MCB with auxiliary contact on secondary side. Terminal block. Hand Earthing for primary winding at CCVT. Manual Isolating DS for underground Bays.
Types:
1. 2.
GIS type(Inductive) VT Outdoor type (coupling capacitive voltage transformer) CCVT
Technical data:
Terminal block connection
C.T site tests: 1. 2.
Ratio test Megger test
Page 19
محمد مصطفى الجوينى.م
7.
Gas isolated bus (GIB).
There are two methods to Connect between OHTL and transformer bays inside GIS room with outdoor gantry and transformer respectively. 1. 2.
Gas isolated bus (GIB) Underground cable
In our case:
GIB for the current OHTL, transformer bays. Underground Cables for future bays.
GIB or cables connect with gantry or transformer bushing through SF6/air bushing.
GIB divided to two parts inside and outside GIS room.
8.
Inside part connect to GIS equipment. Outside part connect to SF6/air bushing.
Air / SF6 bushing.
SF6/air bushing to be installed after installation the gantry to avoid any damage due to gantry installation process. There are 12 bushings for 4 circuits.
Page 20
محمد مصطفى الجوينى.م
GIS sub components information. Bays gas sections schemes.
Page 21
محمد مصطفى الجوينى.م
Normal pressure for C.B = 7 bar Normal pressure for other compartment =5 bar Minimum pressure for C.B = 6.5 bar Minimum pressure for other compartment =4.5 bar
Page 22
محمد مصطفى الجوينى.م
1.
Pressure disc.
2.
This device used to release SF6 gas when its pressure increases inside the compartment. It is fabricated from aluminum and must be replaced after damage.
Absorbent zeoram.
This material used to absorb humidity from SF6; it must be used for each compartment. It’s attached to pressure disc flange or man holes covers which used for cleaning. This material must change directly before vacuum process or after open its flange.
Page 23
محمد مصطفى الجوينى.م
3.
Pressure gauges.
Used to monitor the pressure of SF6 gas inside the gas section. Have two contacts: 1- alarm contact when the pressure reaches to first stage. 2- Trip contact when the pressure reaches to second stage.
4.
Insulation spacer (gas tight).
Used to isolate gas between two sections supporting the conductors centralized. Marked by yellow color from outside.
Page 24
محمد مصطفى الجوينى.م
5.
Insulation spacer (gas through).
6.
Used to supporting the conductors centralized. Marked by silver color from outside.
Ultra high frequency partial discharge sensor (UHF PD).
Used to measure the partial discharge for check wave around conductor symmetrical without distortion. The PD test is applied at 1.2 design voltage per phase. Acceptance criteria: less than 5pC.
Page 25
محمد مصطفى الجوينى.م
7.
Non return valve (normally open).
8.
Used to connect between SF6 gas inside the enclosure and gas gauge and to link between multi compartments to become one gas section.
Non return valve (normally closed).
Used to vacuum process, gas filling and test point (dew point).
Page 26
محمد مصطفى الجوينى.م
9.
Inspection windows.
Used for inspection of moving mechanism and inside area of each compartment. Do not look inside which mechanism is operating.
Page 27
محمد مصطفى الجوينى.م
10.
SF6 GAS. (SULFUR HEXAFLORIDE)
Advantages:
SF6 is non-flammable Electrical insulating capability is much than air SF6-Gas is a cooling gas New and clean SF6 is NOT poisonous SF6 is chemically stable SF6 has approx. 5,7x higher density than air
This cylinder is ≈ 600 KG and ≈ 23 bar
Page 28
higher
محمد مصطفى الجوينى.م
11.
Supporting insulators
12.
Supporting conductors fixed in the center of the enclosure
Conductor.
Conductor s fabricated from pure aluminum in tubular shape Enclosure outer bay 322mm Enclosure thickness 8mm Conductor 93mm Enclosure thickness 10mm
Page 29
محمد مصطفى الجوينى.م
2. General requirements for GIS installation.
Preparation of Site Condition Access road should be backfilled, compacted and settled for safely received package boxes before transportation and slope road ground near the main entrance before transportation. Lighting fixtures should be installed before GIS installation.
Painted the Epoxy paint on the floor Installing and loading test for over-head crane for GIS equipment transportation inside GIS room.
Page 30
محمد مصطفى الجوينى.م
Closed all opening holes by wooden plate and Fabricated of temporary door or the perpetually door (roll up door) must be installed; that should be done before transportation for keeping to clean room condition & safety. Check and prepare tools for installation completely.
Tools for tightening and assembly, lifting and erection and for unpacking Vacuum cleaner for installation.
Arrangement of transportation equipment
Hi‐dro crane hand‐lift Fork‐lift Steel pipes Hydraulic jack
: for lifting GIS equipment. : in order to easy for transportation of GIS equipment into GIS room. : in order to easy and fast for transportation of GIS equipment. : for carrying of GIS main‐body equipment. : for adjust the height and level of equipment.
Preparation for Installation Checking boxes
Before start the installation process we should check the equipment boxes if there are any damage or loose.
Man power.
The requested man power depends on bays number and time available for mission, in normal conditions 4Technicians, 4 helpers, 1 erection engineer and 1project engineer.
Page 31
محمد مصطفى الجوينى.م
Transportation and equipment arrangement plan.
In the beginning erection engineer should study the packing list and its drawings to can put suitable transportation plan and arrangement for equipment in GIS room, erection schedule is depend on this study. All required documents like inspection and test plan (ITP), method of statements and tools certificates…etc.). Should be prepared.
Preparation of vacuum pump at the least two sets and prepares the vacuum hose and torr gauge.
Fabricated of shelf should be installed before starting the erection to arrange and keeps installation materials, prepare fabricated of shim plates for adjusted of alignment each of thickness like (1mm, 2mm, 3mm), Preparing the wooden plates for protecting the GIS equipment.
Page 32
محمد مصطفى الجوينى.م
Ground marking and Transportation sequence.
Check the finishing condition and embedded plate position according to the foundation plan and measure height on each of embedded plate surface.
Marking center line on the embedded plate surface floor for positioning of main-body equipment and draw the main bus and datum line of each bay Ground marking executed according to layout drawing and civil drawings that contain all dimensions of equipment and distance between them. The basic lines in ground marking are X-axis and Y-axis which representative of C.Bs centers and transformer GIB holes centers respectively. 1.Surveyor takes several points on X-axis and Y-axis lines, and then start connects between these points making these 2 lines. 2.Draw parallel and vertically lines according to drawings. 3.These lines representative of bus bar line, center of bus coupler C.B, all C.Bs positions points and M/B supports which hold the V.Ts.
4.Then take height and level of plates take in consideration that, bus coupler plate is the reference level. 5.Using shim plates with different thickness we can adjust the level between plates.
Page 33
م .محمد مصطفى الجوينى
Page 34
محمد مصطفى الجوينى.م
Transportation process After revise and compare the packing list drawings with packing list and boxes, start transport the boxes and unpacking the equipment then arrange this equipment inside GIS room according to the installation process. The amount of equipment to be transported inside GIS room is determined on the basis of the area of GIS room, so the transportation process may divide to more than one stage. In general the transportation and arrangement process is executed as follow:
Each C.B to be moved near to its final position Each D.S, E.S, C.Ts and V.Ts moved near to its breaker (bay) Each bus bar and support moved near to its final position.
Plate form and all accessories after installation of main equipment
Page 35
محمد مصطفى الجوينى.م
3. Installation process.
Initial assembly process After arrange the equipment and completely close all doors, windows and holes, start the installation process as follow:
Install of each C.B equipment without any docking between bays or any ground welding Install of C.T, D.S, E.S, supports and bus bars for each C.B.
Installing of C.Ts with C.B
Installing of D.S/E.S with C.B
Notes: C.T and D.S compartment may be in one compartment or separate depend on them size.
One compartment
Separate compartment Page 36
محمد مصطفى الجوينى.م
Some compartment needs to assembly its conductor before installing.
Installation starts by remove the transportation cover then replace gasket by a new one, and cleaning the spacer, flange, gasket and conductor by alcohol and wipes.
Page 37
محمد مصطفى الجوينى.م
Replace the old grease of flange (yellow grease) and conductor contact positions (white grease) with new grease.
After preparing the flange of equipment for assembling cover it till assembling it. .
Page 38
محمد مصطفى الجوينى.م
After assembling the C.B equipment, it become ready to install and temporary welding in ground.
Docking process There are two methods two to docking the bays together as follow: 1.
Install all C.Bs in it positions and temporary welding, then start assembling the equipment of (bay1) in direction to the extension for future bays, then bus bars and GIB reach to AIR/SF6 bushing.
2.
Just install bus coupler C.B and temporary welded then start assembling the equipment and docking it to this C.B from it both sides to the final sides of GIS (used method).
Sequence of docking regarding to method (no.2)
After assembling the equipment of each C.B and welded the bus coupler C.B start docking the bays together. Note that: the amount of assembling equipment with C.B depends on the capacity of overhead crane and Available empty space.
Page 39
محمد مصطفى الجوينى.م
In our case:
Capacity of overhead crane = 6.3 tons No empty space
So C.B assembled with:
C.Ts. D.S/E.S. Supports for D.S/E.S. Bus bar in one side.
After welded bus coupler C.B by temporary welding: 1. 2. 3.
Assembling the tie bus bar with bus coupler Install the D.S/E.S for sections in the both sides B.C Install the D.S/E.S for V.Ts in the both sides of B.C
1
2
Page 40
3
محمد مصطفى الجوينى.م
4.
Docking transformer bays with V.Ts sections in the both sides
4
5.
Docking the OHTL bays with transformer bays in the both sides
5
6.
Installing of V.Ts in the both sides
In our case V.Ts installation postponed after H.V test.
6
Page 41
محمد مصطفى الجوينى.م
7.
Gas isolated bus (GIB)
7
8.
SF6 / AIR bushing
8
Page 42
محمد مصطفى الجوينى.م
Vacuum and SF6 gas works Vacuum work
After welding a bay start opening the flange of absorbent zeoram and add new silica gel for all separate champers.
All tools and equipment are already prepared (DILO MACHINE, ADAPTER and HOSES).
Then connect the hose of (DILO MACHINE) to non-return valve (normally closed) and running the machine.
Vacuum continue at least 1 hour at 1torr (1mmHg), but the actual process reach to 3 hours at (0.45 torr).
Notes: Vacuum process can do to each phase separately but to save time we use adapter to execute the process for the three phases one time. (One hose from machine to adapter and three from adapter to phases). For C.B compartment the vacuum period from 20 to 24 hours to can reach to (0.6mm bar/0.45torr) but other compartment as same as mentioned above. The vacuum period and value depend on the machine capacity and age, so period and value of vacuum process are inverse related depend on one another as follow:
If the vacuum value can increase more the period is decrease also.
In the begging of vacuum process the value of vacuum is out of range, wait just few minutes then the value appear of machine in range of 100 m bar then start gradually decrease till machine capacity (0.6m bar). In case of opening any compartment for any reason it should be replace the silica gel and take vacuum again. We use Green Sticker to sign the vacuumed compartment from other.
Page 43
محمد مصطفى الجوينى.م
Gas filling
After vacuum process of each compartment start the gas filling process directly.
The same tools as vacuum in addition to gas filling device and SF6 gas cylinder.
Connect the gas filling device to cylinder and other side to adapter or to DILO machine and then to adapter select gas filling function from multi functions selector in DILO machine.
Open valve cylinder and gas filling device then control the gas pressure by gas regulator. As a first stage of gas filling continue filling to 1bar. The second stage continues to final value 7 bar for C.B, 5 bar for others.
Page 44
محمد مصطفى الجوينى.م
Notes: As the vacuum process the gas filling process can do to each phase separately but to save time we use adapter to execute the process for the three phases one time. (One hose from machine to adapter and three from adapter to phases). We use red sticker to sign the vacuumed compartment from other. When the pressure inside the cylinder decrease, gas temperature decrease and gas freezes, so we use the compressor in DILO machine. Gas filling process carried out to all compartment in stages of different pressures not one time to save the barrier spacer condition although it bear the pressure difference but for more confirmation.
Gas test
Gas leakage test
Dew point test
Used to check tightness for pipes and enclosure Device mane :Portable Gas leak detector Continuous sound alarm meaning gas leakages
Used to check humidity for gas to clarify Insulating gas efficiency Device mane :Portable dew point meter
Acceptance criteria
C.B parts: Dew point less than150 PPM Volume Others: Dew point less than 300 PPM Volume below.
Page 45
محمد مصطفى الجوينى.م
4. Accessories installation
Earthing shield
There are already installed earhing shields with equipment like E.S bars and its shields, but the main earthing bars needs to be assembled in site and installed.
There are several types of earthings connection bars shapes depend on its position.
These shapes are assembled from earthing accessories.
Page 46
محمد مصطفى الجوينى.م
Linkage bars
Linkage bars between the mechanism and phase’s movable part are assembled and installed in site. There are two types of length and two types contact point. These linkages contain flexible joint to adjust the required space.
Platforms
Firstly unpacking the platform box then start arranges and numbering its parts regarding to drawings. Start assembling these parts according to drawings.
Page 47
محمد مصطفى الجوينى.م
Supports As plat form;
Firstly unpacking the platform box then start arranges and numbering its parts regarding to drawings.
Start assembling these parts according to drawings.
Page 48
محمد مصطفى الجوينى.م
Cables work Cable tray
As plat form;
Firstly unpacking the trays box then start arranges its parts regarding to drawings. There are several lengths and dimensions of trays, we use the suitable part according to its function and position regarding to drawings.
Cable termination
After installed the cable trays, start the cable termination process according to cable list schedule.
Page 49
محمد مصطفى الجوينى.م
5. Schematic diagram for OHTL Bay.
Including:
List of contents
External wire specification
SLD, layout, interlock, internal arrangement and sf6 system
DC and AC systems
Closing and tripping circuits for C.B
Closing and opining circuits for D.S and E.S
Alarms, indicators, monitoring and control circuits
C.Ts and V.Ts wiring
Page 50
A3_B_COVER
S SPECIFICATION
CHEMATIC DIAGRAM FOR GIS LCC
245kV 50kA GIS
PROJECT NAME
OHTL 1 D01
GIS BAY REFERENCE NO.
CONTRACT NUMBER HHI REFERENCE NO.
GIS BAY NAME
16316
REVISION NO.
04
ZAHRAA EL-MOKATTAM 220/22kV GIS SUBSTATION
HEAVY INDUSTRIES CO.,LTD.
A3(420mm * 297mm)
1
2
3
4
5
6
7
8
Project
A
A
DRAWING LIST SHEET NO
B
C
D
REVISION
DESCRIPTION REV.0
REV.1
REV.2
REV.3
REV.4
1
COVER
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
2
LIST OF CONTENTS
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
3
LIST OF CONTENTS
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
4
LIST OF CONTENTS
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
5
LIST OF CONTENTS
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
6
INTERNAL WIRE SPECIFICATION
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
7
EXTERNAL WIRE SPECIFICATION
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
8
FERRULING SYSTEM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
9
SYMBOL LEGEND
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
10
SF6 GAS SCHEME DIAGRAM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
11
220kV GIS SINGLE LINE DIAGRAM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
12
INTERLOCK DIAGRAM FOR T/L
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
13
LCC LAYOUT FOR T/L
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
14
LCC MIMIC DIAGRAM FOR T/L
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
15
LCC ANNUNCIATOR LIST
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
16
INTERNAL ARRANGEMENT OF T/L (1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
17
INTERNAL ARRANGEMENT OF T/L (2)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
18
DC POWER SUPPLY
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
19
DC POWER SUPPLY
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
20
AC POWER SUPPLY
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
21
CB CLOSE CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
22
CB TRIP 1 CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
23
CB TRIP 2 CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
24
CB MOTOR CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
25
CB MOTOR POWER
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
26
CB MECHANISM 1
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
27
CB MECHANISM 2
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
28
BUS DS(-Q1) CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
29
BUS DS(-Q1) MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
30
BUS DS(-Q2) CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
LIST OF CONTENTS Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EA
SHEET NO.
2
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
DRAWING LIST SHEET NO
B
C
D
REVISION
DESCRIPTION REV.0
REV.1
REV.2
REV.3
REV.4
31
BUS DS(-Q2) MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
32
LINE DS(-Q9) CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
33
LINE DS(-Q9) MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
34
WORK ES(-Q51) CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
35
WORK ES(-Q51) MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
36
WORK ES(-Q52) CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
37
WORK ES(-Q52) MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
38
LINE ES(-Q8) CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
39
LINE ES(-Q8) MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
40
MULTIPLY CONTACT
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
41
MULTIPLY CONTACT
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
42
MULTIPLY CONTACT
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
43
OPERATING CONDITION
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
44
DS/ES INCOMPLETE CONDITION
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
45
INTERLOCK (CB)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
46
INTERLOCK (BUS DS)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
47
INTERLOCK (LINE DS/ES)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
48
GAS MONITORING
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
49
GAS MONITORING
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
50
GAS MONITORING
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
51
GAS MONITORING
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
52
GAS MONITORING
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
53
GAS MONITORING
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
54
POSITION INDICATOR
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
55
POSITION INDICATOR
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
56
HEATER CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
57
HEATER CONTROL
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
58
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
59
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
60
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
LIST OF CONTENTS Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EA
SHEET NO.
3
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
DRAWING LIST SHEET NO
B
C
D
REVISION
DESCRIPTION REV.0
REV.1
REV.2
REV.3
REV.4
61
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
62
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
63
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
64
ANNUNCIATOR (H1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
65
METERING (1)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
66
METERING (2)
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
67
REMOTE
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
68
REMOTE
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
69
REMOTE
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
70
CURRENT TRANSFORMER
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
71
CURRENT TRANSFORMER
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
72
CURRENT TRANSFORMER
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
73
SWITCH
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
74
SWITCH
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
75
SWITCH
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
76
SWITCH
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
77
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
78
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
79
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
80
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
81
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
82
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
83
PARTS LIST FOR LCC
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
84
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
85
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
86
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
87
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
88
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
89
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
90
PARTS LIST FOR MECHANISM
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
LIST OF CONTENTS Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EA
SHEET NO.
4
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
DRAWING LIST SHEET NO
B
REVISION
DESCRIPTION REV.0
REV.1
REV.2
REV.3
REV.4
91
PARTS LIST FOR TERMINAL BLOCK
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
92
PARTS LIST FOR TERMINAL BLOCK
01.SEP.2016
19.JUN.2017
09.AUG.2017
10.AUG.2017
24.JAN.2018
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
LIST OF CONTENTS Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EA
SHEET NO.
5
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
WIRE SPECIFICATION WIRE
WIRE NO. MARK
KINDS OF WIRE
ADDITIONAL MARK TERMINAL LUG
INSULATION
COLOR
SIZE
SLEEVE COLOR
INSULATION CAP
MARKING
SLEEVE COLOR
LETTER COLOR
MARKING
AC
XHHW/SIS
BLACK
2.5mm²
WHITE
BLUE
WIRE NO.
N/A
N/A
N/A
DC
XHHW/SIS
GRAY
2.5mm²
WHITE
BLUE
WIRE NO.
N/A
N/A
N/A
TRIP
XHHW/SIS
GRAY
2.5mm²
WHITE
RED
WIRE NO.
RED
N/A
N/A
ALARM
XHHW/SIS
GRAY
2.5mm²
WHITE
BLUE
WIRE NO.
N/A
N/A
N/A
DC(+)
XHHW/SIS
GRAY
2.5mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
+
DC(-)
XHHW/SIS
GRAY
2.5mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
-
AC(A)
XHHW/SIS
RED
2.5mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
A
AC(B)
XHHW/SIS
YELLOW
2.5mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
B
WIRE NO.
WHITE
BLACK
C
REMARK
Reference DWG
B
CIRCUIT CONTROL
POWER SUPPLY C
REV.
B
BLADE TYPE
EMPLOYER / DEVELOPER
AC(C)
XHHW/SIS
BLUE
2.5mm²
WHITE
BLUE
AC(N)
XHHW/SIS
GREEN
2.5mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
N
A
XHHW/SIS
RED
6.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
A
B
XHHW/SIS
YELLOW
6.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
B
C
XHHW/SIS
BLUE
6.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
C
N
XHHW/SIS
GREEN
6.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
N
A
XHHW/SIS
RED
4.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
A
B
XHHW/SIS
YELLOW
4.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
B
C
XHHW/SIS
BLUE
4.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
C
N
XHHW/SIS
GREEN
4.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
N
CT SECONDARY CIRCUIT
DATE
NO. DWG
C BLADE TYPE
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
VT SECONDARY CIRCUIT
RING TYPE
D
04 03 02 01 00
REV.
BLADE TYPE
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
GROUND
XHHW/SIS
GREEN
4.0mm²
WHITE
BLUE
WIRE NO.
WHITE
BLACK
EARTH
XHHW ( Cross-linked Polyethylene High Heat-resistant Water-resistant )
E
- Rated Voltage : 600/1000V
E
- Heat resistant temperature : 90℃ (By Standard of UL) - Conductor : Plain or Tinned annealed copper wire Power supply circuit is defined as circuit from power supply to MCB. N/A : Not applicable 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
INTERNAL WIRE SPECIFICATION Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
6
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
MUTI-CABLE SPECIFICATION NO
A
KINDS OF WIRING DC CONTROL CIRCUIT
SPEC.
INSULATION
FR-CCV-SB
XLPE
NO. OF CORES
CROSSSECTIONAL AREA
COLOR OF SHEATH
SHIELD
24 CORES
2.5SQMM
BLACK
COPPER BRAID
REMARK
Reference DWG
DATE
NO. DWG
REV.
B
B B
GAS CONTROL CIRCUIT
FR-CCV-SB
XLPE
6 CORES
2.5SQMM
BLACK
COPPER BRAID
C
CT CONTROL CIRCUIT
FR-CCV-SB
XLPE
6 CORES
6.0SQMM
BLACK
COPPER BRAID
VT CONTROL CIRCUIT
FR-CCV-SB
XLPE
6 CORES
4.0SQMM
BLACK
COPPER BRAID
D
EMPLOYER / DEVELOPER
C E
HEATER CONTROL
FR-CCV-SB
XLPE
2 CORES
4.0SQMM
BLACK
C
COPPER BRAID
FR-CCV-SB : Flame retardant control cross linked polyethylene sheathed cable
PROJECT MANAGER.
- Rated Voltage : 0.6/1KV - Heat resistant temperature : 90 degrees ( By Standard of UL) - Conductor : Plain or Tinned annealed copper wire SUPERVISION CONSULTANT
GAS MONITORING BOX
D
B
A B
SECONDARY BOX OF CT
C
LOCAL CONTROL CUBICLE
E
D
CUBICLE
04 03 02 01 00
REV.
A SECONDARY BOX OF VT
D
LOCAL CONTROL
E
MECHANISM OF DISCONNECTOR & EARTHING SWITCH
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
EXTERNAL WIRE SPECIFICATION Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
7
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
DETAILS OF FERRULING
DETAILS OF CABLE CONNECTION Reference DWG
DATE
NO. DWG
REV.
B
B
DETAILS TERMINAL TYPE
3
6
4
5
K201-14 / X1-79 1
RING TYPE
BLADE TYPE
K201-13 / X1-71
K201-13 / X1-71
C
2
1
WIRE FERRULING A. WHITE SLEEVE WITH BLACK LETTERS
2
ADDITIONAL MARKING
3
LETTERS DIRECTION
4
INSULATED CAP A. TRIP : RED B. OTHERS : BLUE
5
TERMINAL
6
WIRE
INTERNAL WIRING
TERMINAL BLOCK
X21 1
1
2
2
3
3
4
4
DETAIL "A" TERMINAL BLOCK
PVC DUCT
EMPLOYER / DEVELOPER
C
EXTERNAL WIRING PVC DUCT
DETAIL "A" X1-71 / K201-13
-K201 X1-71 / K201-13
PROJECT MANAGER.
-X1 71 72 73
13
21
31 43
MULTI CORE CABLE
74
GROUND WIRE
75
BOTTOM PLATE (FOR GLAND)
SUPERVISION CONSULTANT
CABLE GLAND
-K201
DETAIL "B"
76
D
14
22
33 44
D
77 78 79
X1-79 / K201-14
80
X1-79 / K201-14
CABLE ENTRY HOLE
GROUND BUS-BAR
BOTTOM PLATE
REV.
K201-14 / X1-79
K201-14 / X1-79
DETAIL "B"
04 03 02 01 00
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
FERRULING SYSTEM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
8
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
SYMBOLS
DESCRIPTION
SYMBOLS
DESCRIPTION
CIRCUIT BREAKER
LIMIT SWITCH
OPERATED BY HYDRAULIC
MECHANICALLY OPERATED
DISCONNECTOR OPERATED
LIMIT SWITCH
BY MOTOR SPRING
MECHANICALLY OPERATED
SYMBOLS
DESCRIPTION
SYMBOLS
DESCRIPTION
RELAY COIL
INDICATOR
DIODE
HORN
Reference DWG
DATE
NO. DWG
REV.
B
B
DISCONNECTOR OPERATED BY MOTOR
MAKE CONTACT
THERMAL RELAY
HEATER
EARTHING SWITCH OPERATED BY MOTOR SPRING
BREAK CONTACT
TIMER
RESISTOR
CURRENT TRANSFORMER
EARLY MAKE CONTACT MECHANICALLY OPERATED
COUNTER
ILLUMICATION EMPLOYER / DEVELOPER
C
C
LATE BREAK CONTACT VOLTAGE TRANSFORMER
MECHANICALLY OPERATED
SURGE ARRESTER
DELAYED MAKE CONTACT
CABLE HEAD
DELAYED BREAK CONTACT
ANNUNCIATOR
OUTLET
A
AMMETER
PLUG & SOCKET
V
VOLTMETER
CONDUCTOR
PROJECT MANAGER.
SUPERVISION CONSULTANT
SF6/AIR BUSHING
P
D
EARTH
P
MINIATURE CIRCUIT BREAKER
MAKE CONTACT DENSITY METER
M
BREAK CONTACT DENSITY METER
M
THERMOSTAT
DIRECT CURRENT MOTOR
CONNECTION D
INDUCTION MOTOR 3 PHASE
EXTERNAL EQUIPMENT BOUNDARY 04 03 02 01 00
GIS EQUIPMENT BOUNDARY
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
OPERATED BY KEY
OPERATING MECHANIAM
E
E
EXTERNAL EQUIPMENT
OTHER LCC 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
SYMBOL LEGEND Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
9
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
OHTL1
A
A
(=D01)
NOTE
G/A BUSHING
1. RATED GAS PRESSURE CB : 7 Bar MAIN BUS : 5 Bar OTHERS : 5 Bar
AØ
G01-07A
-Z1
BØ
G01-07B CØ
G01-07C AØ
G01-06A
B
BØ
G01-06B CØ
G01-06C
M HS
HSES
AØ
G01-05A
(-Q8)
BØ
G01-05B CØ
G01-05C
DS
M
(-Q9) AØ
G01-04A
2. SETTING PRESSURE(at 20°C) OF DENSITY MONITOR IS AS FOLLOWS SF6 GAS PRESSURE EQUIPMENT DESCRIPTION (20°C) FIRST STAGE LEAK ALARM 6.7 Bar (RE-FILLING STAGE) CB SECOND STAGE LEAK ALARM 6.5 Bar (PRESSURE FAILURE) FIRST STAGE LEAK ALARM OTHERS 4.7 Bar (RE-FILLING STAGE) (DS,ES,CT) SECOND STAGE LEAK ALARM 4.5 Bar (VT, BUS,etc) (PRESSURE FAILURE)
Reference DWG
DATE
NO. DWG
REV.
B
ES
BØ
G01-04B
(-Q52)
M
CØ
* ACCURACY RANGE : ±1% (at 20°C), ±2.5% (at -20°C ~ 60°C)
G01-04C C5
3. GAS SECTION NUMBER OF GAS MONITORING IS AS FOLLOWS DESCRIPTION
C4
C
C3
CT (-T1)
EMPLOYER / DEVELOPER
C
C2 C1
G X X -
X X A PHASE MARKING GAS COMPARTMENT NO. GIS BAY NO.
AØ
G01-00A BØ
CB (-Q0)
G01-00B
PROJECT MANAGER.
CØ
G01-00C
4. BURSTING PRESSURE OF PRESSURE RELIEF DEVICE CB : 15 Bar OTHERS : 10 Bar
AØ
G01-03A BØ
G01-03B
ES CØ
G01-03C
(-Q51)
M
SUPERVISION CONSULTANT
LEGEND SYMBOL
D
DESCRIPTION
D
NON-RETURN VALVE (NORMALLY OPEN) NON-RETURN VALVE (NORMALLY CLOSED)
M
M DS
DS
(-Q2)
(-Q1)
04 03 02 01 00
GAS PRESSURE MONITOR INSULATION SPACER (GAS TIGHT)
REV.
INSULATION SPACER (GAS THROUGH)
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
245kV, 2000A, 50kA, 1s, 50Hz, BB-I ABSORBENT ZEORAM RUPTURE DISC (PRESSURE RELIEF DEVICE) AØ
BØ
CØ
AØ
BØ
CØ
UHF PD SENSOR
E G01-01B
G01-01C
G01-01A
G07-08A
G07-08B
G07-08C
E
245kV, 2000A, 50kA, 1s, 50Hz, BB-II
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE: AØ
BØ
CØ
AØ
BØ
CØ
G01-02C
G01-02B
G01-02A
G01-09C
F
G01-09B
G01-09A
SF6 GAS SCHEME DIAGRAM Drawing Number : ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
10
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
OHTL 1
BUS COUPLER
MBP-1
(=D01)
(=D03)
(=DMP1)
-Z1
OHTL 2
MBP-2
(=D05)
(=DMP2)
FUTURE (=D07)
-Z1 -Q8 50kA/1s
M HS
-Q9 1600A 50kA/1s
-Q9 1600A 50kA/1s
-Q52 50kA/1s M
P2
P2
C5
B
M
M
M
M
M
M
-Q52 50kA/1s M
Reference DWG
DATE
NO. DWG
REV.
B
C3
-T1
C2
C2
C1
P1
P1 -T3
245kV 1600A 50kA/1s
-T15
M
-Q3 2000A 50kA/1s
M
-Q51 50kA/1s
-Q25 50kA/1s
M
C2
-Q11 2000A 50kA/1s
-Q15 50kA/1s
M
C2
M
M
M
-Q52 50kA/1s
M
245kV 1600A 50kA/1s -Q51 50kA/1s
M
-Q21 2000A 50kA/1s
M
-Q1 2000A 50kA/1s
-Q0
-T16
P2
-Q35 50kA/1s
M
-Q2 1600A 50kA/1s
P1
C1 -T4
P2
-Q51 50kA/1s
M
C1
P1 C1
-Q1 1600A 50kA/1s
M
C4
245kV 2000A 50kA/1s
-Q0
C3
-Q0
-Q8 50kA/1s
-Z2
C5
C4 -T1
(=D08)
-Z2
M HS
M
FUTURE
-Q2 2000A 50kA/1s
M HS
-Q5 2000A 50kA/1s
M
M
-Q1 1600A 50kA/1s
-Q45 50kA/1s
M
M
-Q65 50kA/1s
M
M
M
-Q55 50kA/1s M
-Q2 1600A 50kA/1s
-Q31 2000A 50kA/1s
M
M
M
M
M HS
M
245kV, 2000A, 50kA, 1s, 50Hz, BB-I M
M
M
EMPLOYER / DEVELOPER 245kV, 2000A, 50kA, 1s, 50Hz, BB-II
C
-Q1 M 1600A 50kA/1s
M
-Q2 1600A 50kA/1s
-Q51 50kA/1s 245kV 1600A 50kA/1s
M HS
-Q4 2000A 50kA/1s
M
-Q0
-Q16 50kA/1s
M
M
-Q12 2000A 50kA/1s
M
-Q22 2000A 50kA/1s
-Q36 50kA/1s
-Q32 2000A 50kA/1s
-Q46 50kA/1s
M
-Q1 M 1600A 50kA/1s
-Q6 2000A 50kA/1s
M
-Q26 50kA/1s
M
C1
C2
C2
C3
C3
-T2
C4
C4
C5
C5
P2
M
P2 M
M
-Q52 50kA/1s
-Z1
TR 2
FUTURE
(=D02)
(=D04)
(=D06)
2. TECHNICAL DATA FOR CT
HS
MOTOR SPRING MECHANISM
DISCONNECTING SWITCH
MOTOR MECHANISM
EARTHING SWITCH
MOTOR MECHANISM
E
HIGH SPEED EARTHING SWITCH
3. TECHNICAL DATA FOR VT
REMARK
EQUIPMENT NAME CIRCUIT BREAKER
M
M
-Z1
TR 1
1. LEGEND FOR EACH EQUIPMENT
M
SUPERVISION CONSULTANT
-Q52 50kA/1s
-Z1
SYMBOL
PROJECT MANAGER.
P1 C1
D
M
245kV 1600A 50kA/1s
-T26
P1
-T2
C
M
-Q51 50kA/1s -Q0
-T25
M
-Q66 50kA/1s
M
-Q56 50kA/1s
M
-Q2 1600A 50kA/1s
M HS
MOTOR SPRING MECHANISM
SPECIFICATION LOCATION
OHTL FEEDER (D01, D05)
CT No.
-T1
CLASS
Vk
Rct @75°C
Im
BURDEN
C1
1600-800/1A
5P30
-
≤ 5.0-2.5 Ω
-
60-30 VA
C2
1600-800/1A
5P30
-
≤ 5.0-2.5 Ω
-
60-30 VA
C3
1600-800/1A
0.2FS5
-
REV.
2'nd
220/ √3kV : 100/ √3V
3P
200 VA
3. RATED CURRENT
: 2000 / 1600 A
3'rd
220/ √3kV : 100/ √3V
3P
200 VA
4. RATED POWER FREQUENCY WITHSTAND VOLTAGE
: 460 / 530 kV : 1050 / 1200 kV
60-30 VA
6. RATED SHORT-TIME WITHSTAND CURRENT
: 50 kA
-
60-30 VA
7. RATED DURATION
:1s
≥ 1200 V
≤ 2.0 Ω
≤ 60.0 mA
8. RATED PEAK WITHSTAND CURRENT
: 125 kA
9. RATED SF6 GAS PRESSURE at 20℃(CB / Others)
: 7.0 / 5.0 bar.G
10. RATED CONTROL VOLTAGE (DC / AC)
: 220 Vdc / 220 Vac
5P30
800-400/1A
5P30
CABLE HEAD BOX (FOR FUTURE BAY)
Z2
PX
≥ 600 V -
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-
1600-800/1A
C1
BUS COUPLER (D03)
: 50 Hz
≤ 5.0-2.5 Ω
C5
Z1
5P30
: 245 kV
2. RATED FREQUENCY
≤ 2.5-1.25 Ω
CURRENT TRANSFORMER GAS TO AIR BUSHING (CONDENSER TYPE)
400/1A
100 VA
1. RATED VOLTAGE
-
-
800-400/1A
0.2
BURDEN
-
5P30
C3
220/ √3kV : 100/ √3V
CLASS
60-30 VA
1600-800/1A
C2
30-15 VA
1'st 1PH, INDUCTIVE
VOLTAGE RATIO
-
C4
RING AND BUSHING TYPE CT
-T2
-
WIND NO.
≤ 5.0-2.5 Ω
INDUCTIVE TYPE
800/1A
≤ 6.2-3.1 Ω
-T15 -T16 -T25 -T26
TYPE
04 03 02 01 00
4. SUMMARIZED SPECIFICATION
5. RATED LIGHTNING IMPULSE WITHSTAND VOLTAGE
VOLTAGE TRANSFORMER (1PH)
TR FEEDER (D02, D04)
PT NO.
RATIO
D
E
≤ 1.0 Ω ≤ 120.0 mA ≤ 2.5-1.25 Ω
-
60-30 VA
C4
800-400/1A
0.2FS5
-
≤ 1.8-0.9 Ω
-
30-15 VA
C5
800-400/1A
5P30
-
≤ 2.5-1.25 Ω
-
60-30 VA
11. FIRST POLE TO CLEAR FACTOR
: 1.3
C1
2000-1000/1A
5P30
-
≤ 11.2-5.6 Ω
-
60-30 VA
12. PAINTING COLOR
: RAL 7032
C2
2000-1000/1A
5P30
-
≤ 11.2-5.6 Ω
-
60-30 VA
C1
2000-1000/1A
0.2FS5
-
≤ 6.3-3.3 Ω
-
30-15 VA
C2
2000-1000/1A
5P30
-
≤ 11.2-5.6 Ω
-
60-30 VA
-T3
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
-T4
DRAWING TITLE:
220kV GIS SINGLE LINE DIAGRAM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
11
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
OHTL 1 (=D01)
A
A
-Z1 EQUIPMENT REF.
-Q8 50kA/1s
M HS B
-Q9 1600A 50kA/1s
DS -Q1
STATUS OF THE RELATED EQUIPMENT CONTROL
-
-
-
C
C
C
C
-
-
-
-
-
O
-
-
-
-
-
-
-
C
C
C
C
C
-
-
-
-
-
-
-
-
O
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
C
-
-
-
-
-
-
-
-
-
-
-
C
-
-
-
-
-
-
-
-
-
-
-
-
C
-
-
-
-
-
-
-
-
-
C
-
-
-
C
-
-
-
-
-
-
-
-
-
-
C
-
C
-
-
-
-
-
-
-
-
-
TEST
-
-
-
-
-
-
-
-
-
-
-
-
-
-
INTERLOCK BYPASS
LOCAL CLOSE &REMOTE /OPEN LOCAL
O
O
-
-
-
O
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
LOCAL CLOSE &REMOTE /OPEN LOCAL
-
-
O
O
O
-
O
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
INTERLOCK BYPASS
LOCAL CLOSE &REMOTE /OPEN LOCAL
-
-
-
-
-
O
-
-
-
-
-
-
-
-
LINE DEAD
-
-
-
-
-
-
-
-
-
-
-
-
-
-
INTERLOCK BYPASS
LOCAL
DS -Q2
LOCAL CLOSE /REMOTE /OPEN
M
LOCAL
P2 C5
ES -Q51
C4
LOCAL CLOSE &REMOTE /OPEN LOCAL
C
REMOTE
C3
-T1
C2
CB -Q0
C1
CLOSE LOCAL
P1 245kV 1600A 50kA/1s
-Q0
ES -Q52
D
-Q51 50kA/1s
M
DS -Q9
ES -Q8
DS -Q1
DS -Q2
ES DS -Q52 -Q9
ES -Q8
-
O
O
O
O
-
-
O
-
-
-
-
C
-
-
-
-
-
-
-
C
-
-
-
-
-
-
-
-
-
O
-
O
O
O
-
-
-
C
-
-
-
-
-
-
-
-
-
-
-
-
O
O
-
-
-
-
-
-
-
C
-
-
-
C
C
REMARK DS -Q2
LOCAL CLOSE /REMOTE /OPEN
ES CB -Q51 -Q0
B/C =D03 CB -Q0
M
-Q52 50kA/1s
T/L =D01
ES ES DS DS DS -Q15 -Q16 -Q11 -Q12 -Q1
Reference DWG
DATE
NO. DWG
REV.
BUS TRANSFER
B
INTERLOCK BYPASS
BUS TRANSFER INTERLOCK BYPASS
INTERLOCK BYPASS
EMPLOYER / DEVELOPER
C
EMERGENCY LOCAL CLOSE
PROJECT MANAGER.
SUPERVISION CONSULTANT
INTERLOCK BYPASS D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
M
M
-Q1 1600A 50kA/1s
E
-Q2 1600A 50kA/1s
BB-I
* REMARK O : OPEN STATE C : CLOSED STATE - : NO RELATION
E
* FOLLOWING CONDITIONS SHALL BE SATISFIED ALSO. 1. DISCONNECTING SWICHES ARE NOT INTERMEDIATE POSITION. 2. MECH. DOOR FOR MANUAL OPERATION IS NOT OPENED.
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
BB-II
DRAWING TITLE:
INTERLOCK DIAGRAM FOR T/L Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
12
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
220kV GIS LCC (=D01) OHTL 1
FILTER &MESH
VENTILATION COVER
H1 ANNUNCIATOR
UC625 CH40
Reference DWG
DATE
NO. DWG
REV.
S11 CONTROL LOCATION SELECTION
B AM1
AM2
AM3
AMMETER 1
AMMETER 2
AMMETER 3
G01-08
S1
S2
S3
CB MOTOR LOCK - USE
CB MOTOR LONG RUN RESET
INTERLOCK BYPASS INTERLOCK - RELEASE
S12
ER O
T
BUS BAR - II
BUS DS Q2 BUS DS Q1
DE R E VO
R
B
BUS DS Q2
P O R W ME
SE
G01-02
BUS DS Q1
VM1
SF6 GAS COMPARTMENT N/P
S5 HEATER TEST
BUS BAR - I
G01-01
G01-09
GIS N/P
S4 LAMP TEST
WORK ES Q51 WORK ES Q51
G01-03
STOPPER
S2C-H6R
S2C-H6R S2C-H11L
CIRCUIT BREAKER Q0
G01-00
F8A2
STOPPER S2C-H11L
2250 mm
F8A1
CIRCUIT BREAKER Q0
WORK ES Q52 WORK ES Q52
G01-04
LINE DS Q9
S2C-H6R STOPPER
F8D4
S2C-H6R S2C-H11L
F8D3
S2C-H6R S2C-H11L
S2C-A2
S2C-H6R S2C-H11L
STOPPER S2C-H11L
F8D2
F8D1
LINE DS Q9
G01-05
LINE ES Q8 LINE ES Q8
GIS N/P
G01-06
EMPLOYER / DEVELOPER
S2C-H6R STOPPER
S2C-H6R S2C-H11L
F8D7
S2C-H6R S2C-H11L
STOPPER S2C-H11L
F8D6
C
F8D5
G01-07
C
GAS TO AIR BUSHING
STORAGE BOX FOR PLUG
SOCKET OUTLET AC 380V (3-PH)
SOCKET OUTLET AC 220V (1-PH)
PROJECT MANAGER.
850 mm
1600 mm
FRONT VIEW
D
SUPERVISION CONSULTANT
SIDE VIEW
INTERNAL DOOR
INTERNAL DOOR
( LEFT SIDE)
( RIGHT SIDE)
D
04 03 02 01 00
PANEL SPEICIFICATION
REV.
1. PROTECTION DEGREE 2. PAINT COLOR 3. MIMIC COLOR
E
4. 5. 6. 7.
850 mm
MATERIAL THICKNESS EARTHING BUS BAR MATERIAL EARTHING BUS BAR SIZE
IP 54
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
RAL 7032 220kV: RAL 1016 (YELLOW) EARTHING: RAL 9005 (BLACK) COLD ROLLED STEEL SHEET PANEL - 2.3mm BOTTOM & INDOOR PLATE - 3.2mm
E
CU 30mm X 5T
HEATER
8. OUT DOOR OPENING ANGLE INNER DOOR OPENING ANGLE
170˚ 90˚
1600 mm 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
BOTTOM VIEW
DRAWING TITLE:
LCC LAYOUT FOR T/L Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
13
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
-M4
1. MIMIC BUS (220kV: RAL 1016 (YELLOW)) (EARTHING: RAL 9005 (BLACK)) 2. CONTROL SWITCH (OPEN - CLOSE) 3. POSITOIN INDICATOR (LED TYPE) 4. S11: CONTROL SWITCH WITH KEY (LOCAL - REMOTE)
H1 ANNUNCIATOR
10
UC625 CH40 B
8
5 S11 CONTROL LOCATION SELECTION
S1
S2
S3
CB MOTOR LOCK - USE
CB MOTOR LONG RUN RESET
INTERLOCK BYPASS INTERLOCK - RELEASE
S4
S5
LAMP TEST
HEATER TEST
4 6
G01-08
9
7. S3 : SELECTOR SWITCH WITH KEY (INTERLOCK - RELEASE)
7
8. S4 : PUSH BUTTON SWITCH (LAMP TEST)
1
9. S5 : PUSH BUTTON SWITCH (HEATER TEST) 10. ANNUNCIATOR
BUS BAR - I
G01-01
G01-09
G01-02
BUS DS Q1
BUS BAR - II
BUS DS Q2 BUS DS Q1
5. S1 : SELECTOR SWITCH (CB MOTOR OPERATION) 6. S2 : PUSH BUTTON SWITCH (CB MOTOR LONG RUN RESET)
BUS DS Q2
2
C 3
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
11. OUTLET SOCKET (AC 220V)
C
12. OUTLET SOCKET (AC 380V) WORK ES Q51 WORK ES Q51
PROJECT MANAGER.
G01-03
CIRCUIT BREAKER Q0
CIRCUIT BREAKER Q0
G01-00
WORK ES Q52 WORK ES Q52
SUPERVISION CONSULTANT
G01-04
LINE DS Q9 LINE DS Q9
D
D
G01-05
WORK ES Q53 WORK ES Q53
G01-06
04 03 02 01 00
G01-07
REV. GAS TO AIR BUSHING
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E STORAGE BOX FOR PLUG
SOCKET OUTLET AC 380V (3-PH)
SOCKET OUTLET AC 220V (1-PH)
11
12
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
LCC MIMIC DIAGRAM FOR T/L
MOUNTING PLATE
F
(FRONT SIDE OF RIGHT DOOR)
MANUFACTURER/VENDER NAME
Drawing Number : ACTION A B C
DRAWING NUMBER
16316 01 EB
SHEET NO.
14
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
40CHANNEL SPEC. : UC625-40YW-HH-024D-R-M3 MANUFACTURER : RTK MAKER :
8
Project
REMARKS
A
A
RTK
INSTRUMENTS
1
9
5
13
DS/ES MOTOR RUNNING TIME EXCEEDED
CB MOTOR LONG RUN AND STOP
17 G01-00 GAS LOW 1 (ALARM)
DC SUPPLY MCB TRIP/OFF
21 G01-04 GAS LOW 1 (ALARM)
25 G01-08 GAS LOW 1 (ALARM)
33
29
G01-02 GAS LOW 2
G01-06 GAS LOW 2
37
SPARE
MAIN DC SUPPLY FAIL
SPARE
Reference DWG
DATE
NO. DWG
REV.
B
B 2
6 CB MOTOR OVER LOAD AND STOP
3
10 DS/ES SWITCHING INCOMPLETE
7
14 G01-01 GAS LOW 1 (ALARM)
AC SUPPLY FAIL
11
18
22 G01-05 GAS LOW 1 (ALARM)
15
19
26 G01-09 GAS LOW 1 (ALARM)
23
30
G01-03 GAS LOW 2
27
34
G01-07 GAS LOW 2
31
38
SPARE
AUX. AC SUPPLY FAIL
SPARE
39
35
SUPPLY 1 CB MOTOR SPRING UNCHARGED/LOCK
INTERLOCK BY-PASS ON
G01-02 GAS LOW 1 (ALARM)
220VDC SUPPLY 1 FAIL
G01-06 GAS LOW 1 (ALARM)
G01-00 GAS LOW 2 (LOCKOUT)
G01-04 GAS LOW 2
G01-08 GAS LOW 2
SUPPLY 2
SPARE
SPARE
EMPLOYER / DEVELOPER
C
C 4
8
POLE DISCREPANCY
12
AC SUPPLY MCB TRIP/OFF
16
220VDC SUPPLY 2 FAIL
20 G01-03 GAS LOW 1 (ALARM)
24
28
32
40
36
TEST ACK
G01-07 GAS LOW 1 (ALARM)
G01-01 GAS LOW 2
G01-05 GAS LOW 2
G01-09 GAS LOW 2
SPARE
SPARE
PROJECT MANAGER.
MUTE RESET
UC625
SUPERVISION CONSULTANT
D
D INPUT OUTPUT
CH.
COLOR
1
(YELLOW)
NO
NO
2
(YELLOW)
NO
3
(YELLOW)
NO
REMARKS
INPUT OUTPUT
CH.
COLOR
RESPONSE TIME : 5ms
16
(YELLOW)
NO
NO
NO
RESPONSE TIME : 5ms
17
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
18
(YELLOW)
NO
CONTACT CONTACT
REMARKS
INPUT OUTPUT
REMARKS
CH.
COLOR
RESPONSE TIME : 5sec
31
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
NO
RESPONSE TIME : 5sec
32
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
NO
RESPONSE TIME : 5sec
33
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
CONTACT CONTACT
CONTACT CONTACT
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
DATE
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
4
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
19
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
34
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
5
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
20
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
35
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
6
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
21
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
36
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
7
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
22
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
37
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
8
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
23
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
38
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
9
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
24
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
39
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
10
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
25
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
40
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
11
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
26
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
12
(YELLOW)
NO
NO
RESPONSE TIME : 5ms
27
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
13
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
28
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
14
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
29
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
15
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
30
(YELLOW)
NO
NO
RESPONSE TIME : 5sec
E
04 03 02 01 00
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
F
LCC ANNUNCIATOR LIST Drawing Number : ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
15
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
DRAWING NUMBER
16316 01 EB 16 OF
60
E 2
SHEET NO.
92 REV NO.
04 19
1 20
X0C(A) PHOENIX
PHOENIX
X0C(B) 2
XA 4
5
6 4
5
6
7
8
1
PHOENIX PHOENIX
1
7
8
PHOENIX
4
5
6
1
7
8
PHOENIX
4
5
6
7
8
1
PHOENIX
3
4
5
6
1
01~80
7
PHOENIX PHOENIX PHOENIX PHOENIX PHOENIX PHOENIX
X1C X2C X8C X9C X51C 8
X52C
3
4
5
6
01~65
PHOENIX PHOENIX PHOENIX PHOENIX PHOENIX PHOENIX PHOENIX
X1 X2 X8 X9 X51 X52 XS
3
DUCT 100x100
2
16 1 1 1 1 1 1 1
2 2 2 2 2 2 2
PHOENIX
4
5
6
AT8N PG-08
AT8N PG-08
AT8N PG-08
AT8N PG-08
AT8N PG-08
AT8N PG-08
NF40E-13
NF22E-13 CA4-22N
NF40E-13
NF22E-13 CA4-22N
MT-32/2H5
MT-32/2H5
PHOENIX
PHOENIX
K204T
T88
T48B
T47A
CR-M230AC4
3
7
8
01~90
NF40E-13
NF40E-13 CA4-40N
HRN-37
HRN-37
HRN-37
CR-M230AC4
CR-M230AC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
CR-M220DC4
K203T
K102T
K104
K103
K49
K102
F49C
F49B
01~60
DUCT 100x100 = L880
PHOENIX
K11.1
K11
KG0.2B
KG0.2A
KG0.2
KG0.1
KLR
KL8
KL51
KL9
KL2
KL1
K204
K205
K203
K201
K202
F49A
K88MC
K88MB
K88MA
K47B
KQ0T2
K47A
KQ0T1
K101C
K101B
1 1
2 2
4 4
5 5
6 6
3
4 1
5 2
6
4
5
3
PHOENIX
9 6
10 7
11 8
12 9
PHOENIX
13
1
8
2
F MANUFACTURER/VENDER NAME
ACTION A
B
C
D
DUCT 80x100
01~130
NF40E-13 CA4-40N
NF40E-13 CA4-40N
NF22E-13 CA4-13N
NF22E-13 CA4-13N
NF22E-13 CA4-13N
NF22E-13 CA4-22N
NF40E-13 CA4-40N
NF40E-13
NF40E-13
NF40E-13
NF40E-13
KQ8C
XA1
CR-M220DC4
PHOENIX
XA2
K101A
PHOENIX
X0 CR-M230AC4
PHOENIX
KQ0C
PHOENIX
PHOENIX
PHOENIX
PHOENIX
PHOENIX
PHOENIX
PHOENIX
KHTS1
KHTS
K501 K502 K503
KA4
KA3
KA2
KG9.2
KG9.1
KG8.2
KG8.1
KG7.2
KG7.1
KG6.2
KG6.1
KG5.2
KG5.1
KG4.2
KG4.1
KG3.2
KG3.1
KG2.2
KG2.1
KG1.2
KG1.1
KD7
KD6
KD5
KD4
KD3
KD2
KD1
KA1
-M1
01~100
PHOENIX
KQ8
AF09-30-10-13
KQ52T
MT-32/2H5
AF09-30-10-13
KQ8T
AF09-30-10-13
NF40E-13 CA4-40N
KQ51T KQ52C
AF09-30-10-13
NF40E-13 CA4-40N
KQ9T KQ51C
AF09-30-10-13
KQ9C
KQ2T
NF22E-13
NF22E-13
NF22E-13
PHOENIX
5
DUCT 80x100
KDN-220DC
PHOENIX
NF40E-13
AF09-22-00-13 CA4-22E
AF09-22-00-13
NF40E-13
AF09-22-00-13 CA4-22E
NF22E-13
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
PHOENIX
DUCT 80x100
PHOENIX
KQ52
KQ51
KQ9
KQ2
KQ1
XAD
DUCT 80x100
3
01~80
11
80x100
KDN-220DC
2
DUCT 80x100
01~80
3
DUCT 80x100
DUCT 80x100
3
KDN-220DC
KDN-220DC
KDN-220DC
KDN-220DC
AF09-30-10-13 CA4-22M
AF09-30-10-13 CA4-22M
KQ2C
KQ1T
AF09-30-10-13
4
01~40
D 3
DUCT 80x100
01~15
18
3
01~15
17
DUCT 80x100
DUCT 80x100
3
DUCT 80x100
PHOENIX
01~80
15
DUCT 80x100
PHOENIX
01~15
2 14
01~80
9
KQ0.1
8
AF09-30-10-13 CA4-22M
6
KQ1C
2
01~15
XD 3
AF09-30-10-13 CA4-22M
7 PHOENIX
2
01~15
10
KQ0
1
AF09-30-10-13 CA4-22M
1
KDN-220DC
PHOENIX
01~200
DUCT 80x100
DUCT 80x100
12
KDN-220DC
5
DUCT 100x100
4
01~80
1 13
DUCT 80x100
01~30
-M2
DUCT 80x100
XH
DUCT 80x100
PHOENIX
01~20
01~30
B
01~15
01~20
01~25
C
01~20
01~20
DUCT 80x100
1 6 7
XR1
7
1
1 1 2
04 03 02 01 00
REV.
8
Project
A A
DUCT 80x100 -M3
DUCT 80x100
Reference DWG
A3
NO. DWG
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
Drawing Number :
PK55-SD-EL-GS-14
Project No.:
008006400
Sheet Size : Rev. :
04 01.SEP.2016
DATE
PREPARED : K.H.SONG
Scale : CHECKED :
Plot Date: APPROVED :
S.Y.JANG
C.Y.HONG
REV.
3
B
XG
PHOENIX
1 7
2 8
PHOENIX
9
EMPLOYER / DEVELOPER
C
3
PROJECT MANAGER.
SUPERVISION CONSULTANT
XR2
PHOENIX
10
D
PHOENIX
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
ISSUED TO / FOR :
X0C(C) PHOENIX
1 3
1
PHOENIX
2 PHOENIX
4
PHOENIX
PHOENIX
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
INTERNAL ARRANGEMENT OF T/L (1) F
1
2
3
4
5
6
7
8
Project
A
A
PHOENIX
XC1
Reference DWG
DATE
NO. DWG
REV.
1 2
B
B
3 4 5 6 7 8 9
PHOENIX
PHOENIX
10 11 12 13 14 15 16 17 18
PHOENIX
PHOENIX
19
EMPLOYER / DEVELOPER
20 21 22
C
C
23 24 25 26 27
PHOENIX
545
PHOENIX
28 29
PROJECT MANAGER.
30 31
-M4
32
DUCT 60X80
33 34 35 36
PHOENIX
PHOENIX
37 38 39
SUPERVISION CONSULTANT
40 41
DUCT 60X80
42 43 44 45
D
D
DUCT 60X80
DUCT 60X80
922
DUCT 60X80
PHOENIX
PHOENIX
04 03 02 01 00
XM 1 2 3 4
REV.
PHOENIX
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI ) PHOENIX
XC2
HTS
TH
DUCT 60X80
PHOENIX
PHOENIX
PHOENIX
E
1 PHOENIX
E DUCT 40X80
MOUNTING PLATE (REAR SIDE OF LEFT DOOR)
MOUNTING PLATE (INSIDE OF LEFT)
MOUNTING PLATE (INSIDE OF RIGHT)
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
INTERNAL ARRANGEMENT OF T/L (2) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EB
SHEET NO.
17
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
=DC DIST
=DC DIST
=DC DIST
DC 220V
DC 220V
DC 220V
+
-
+
-
+
-
Reference DWG
DATE
NO. DWG
REV.
B
B
-XD
2
-XD
11
3
1
4
2
-F8D1
C
-XD
1
-XD
-XD
10
-XD
3
12
3
1
4
2
-XD
7
-XD
-F8D2
S202M-K6UC S2C-H11L
-XD
16
4
-XD
-XD
13
3
1
4
2
-F8D3
S202M-K6UC S2C-A2
5
-XD
14
3
1
4
2
EMPLOYER / DEVELOPER
-F8D4
S202M-K16UC S2C-H11L
S202M-K16UC S2C-H11L
C
C1 PROJECT MANAGER.
-F8D2 C2 23
-K203 /43.E6
24 SUPERVISION CONSULTANT
D
D 21
-K202 /43.E2
22
/75.B2
REV.
12
(-)220V_F4
10/75.B2
(+)220V_F4
21.E1
LOCAL
11
REMOTE_F4
21.B1
-S11
REMOTE
LOCAL_F4
/75.B2
8
(-)220V_F3
6/75.B2
9
(+)220V_F3
28.E1
LOCAL
7
REMOTE_F3
28.B1
-S11
REMOTE
LOCAL_F3
/75.B2
4
(-)220V_F2
2/75.B2
5
(+)220V_F2
48.E1
LOCAL
REMOTE_F2
(-)220V_F1
48.B1
3
-S11
LOCAL_F2
(+)220V_F1
1 REMOTE
04 03 02 01 00
22.B1
22.E1
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E 28.B1
SIGNAL LAMP & ALARM DC SUPPLY 13 21 34 32
14 22 /68.D3 31 /64.B4
28.A1
E 21.B1
DS/ES MOTOR & INTERLOCK DC SUPPLY C1
C2 /18.C3
13 21 34 32
14 22 /68.D4 31 /64.B4
21.A1
22.B1
CB CLOSE DC SUPPLY
13 21 34 32
14 22 /68.D4 31 /64.B5
22.A1
CB TRIP1 DC SUPPLY
13 21 34 32
14 22 /68.D4 31 /64.B5
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
DC POWER SUPPLY Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
18
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
=DC DIST
=DC DIST
+
-XD
6
-
-XD
+
15
-XD
21
-XD
-
22 Reference DWG
DATE
NO. DWG
REV.
B
B
-XD
3
1
-XD
3
-F8D5
C
8
1
-F8D6
S202M-K16UC S2C-H11L
4
9
-XD
18
3
1
4
2
EMPLOYER / DEVELOPER
-F8D7
S202M-K16UC S2C-H11L
2
-XD
17
4
2
S202M-K16UC S2C-H11L
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
21
23
(-)220V_F6
(+)220V_F7
(-)220V_F7
LOCAL_F5
REV.
24
(+)220V_F6
22 REMOTE /75.B3
(-)220V_F5
LOCAL
(+)220V_F5
-S11 REMOTE_F5
-S11 /75.B3
04 03 02 01 00
24.B1
24.E1
25.A1
25.E1
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E 23.B1
23.A1
CB TRIP 2 DC SUPPLY
13 21 34 32
14 22 /68.D4 31 /64.B6
23.A1 23.E1
CB MOTOR CONTROL DC SUPPLY
13 21 34 32
14 22 /68.D5 31 /64.B6
E
CB MOTOR POWER DC SUPPLY
13 21 34 32
14 22 /68.D5 31 /64.B6
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
DC POWER SUPPLY Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
19
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
A
-XA
1
N
-XA
3
-XA
2
-XA
-XA
4
A
B
C
N
5-XA
7-XA
9-XA
11
-XA
6-XA
8-XA
10-XA
12
Reference DWG
DATE
NO. DWG
REV.
B
B
3
1
-F8A1
1
3
5
7N
2
4
6
8N
-F8A2
S202M-K6UC S2C-H11L
4
2
S203M-K32NA S2C-H11L
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
(772 13)
D
-SOCKET(1-PH)
(5 552 89) -SOCKET(3-PH)
1 1
A220V_F1
N220V_F1
A1
56.A1
E
SOCKET OUTLET CONTROL SUPPLY
(16A)
A2
u=220V AC 1-phase
14 22 /68.D1 31 /64.B2
3
u=380V AC 3-phase
(32A)
A1
A1
-KA3 SOCKET OUTLET CONTROL SUPPLY
-KA4 SOCKET OUTLET CONTROL SUPPLY
A2
04 03 02 01 00
A2
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
56.E1
HEATING & ANNUNCIATOR AC SUPPLY
13 21 34 32
4
2
-KA2
D
2
SOCKET OUTLET AC (3Φ 380V & 1Φ 220V) SUPPLY
14 12 24 22 34 32 44 42
11 /64.C2 21 /68.D2 31 41
7N 13 21 34 32
8N /20.C4 14 22 /68.D2 31 /64.B2
E
14 12 24 22 34 32 44 42
11 /64.C2 21 /68.D2 31 41
14 12 24 22 34 32 44 42
11 /64.C3 21 /68.D3
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
31
DRAWING TITLE:
41
AC POWER SUPPLY Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
20
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
CB CLOSE A
CLOSE CIRCUIT (A)
+Remote Control Panel
REMOTE_F3
/ 18.E5
-XR1
1
CLOSE CIRCUIT (B)
CLOSE CIRCUIT (C) A
+Protection Panel
-XR1
2
-XR1
86
87
-XR1
88
-XR1
14
-XR1
15
16
(+)220V_F3
/ 18.E5
LOCAL_F3
/ 18.E4
1L1
3L2
-KQ0C
5L3
-KQ0C
/21.E1
-KQ0C
/21.E1
2T1
Reference DWG
/21.E1
4T2
DATE
NO. DWG
REV.
6T3
B
B 3
-SQ0 CLOSE
4
-X0C(A)
3
-J1
3
-Q0(A)
/73.B3
1
-J1
B4 / 45.A1 / 45.E1
CB INT.1
CB INT(CRP).1
CB INT.2
CB INT(CRP).2
/ 45.A5 / 45.E5
-XR1 =CRP C
3
-J1
3
-Q0(B)
1 LA1
B04
-X1
-X1
2
-J1
4 4
-J1
2
-X0C(B)
2 14
6
/21.E3
22
D
-XR1
7
13
/48.E4
-XR1
R3
1
B4
LA1
B04
LA01
1 1 EMPLOYER / DEVELOPER
-X1
2
-J1
4 4
-J1
2
-X0C(C)
2
21 /21.E5
/24.E3
14 /21.E5
22
/48.E4
C
2
-J1
4 4
13
2 2 PROJECT MANAGER.
21
14
-K101C
-K101B
/21.E6
-K101C /21.E6
22
13
62
-K102 /24.E3
31 31
-KG0.2
22
-J1
2
-K102 21 21
-KG0.2 8
-X1
32
-K102 /24.E3
-XR1
LA01
1 1
-K101B
-K101A
1
-52C
22
-XR1
3
2
-K101A /21.E3
-J1
-Q0(C)
1
-52C
-X0C(A)
3
LA1
B04
-X1
-52C
-X0C(C)
-S1
LA01
1 1
21 5
-J1
-S1
-X1
4
1
B4
-S1
-J1
-XR1
3
2
86 RY
-XR1
-X0C(B)
61 61
SUPERVISION CONSULTANT
-KG0.2 /48.E4
32
D
62
9
-K201 /43.E5
R4
-XR1
10
-XR1
11
-XR1
12
04 03 02 01 00
R4
-K205 /44.E2
R3
REV.
CLOSE
E
A1
-K101A ANTI-PUMPING
A2
-XR1
(-)220V_F3
/ 18.E5
1L1 3L2 5L3 13
2T1 /21.B3 4T2 /21.B4 6T3 /21.B5 14
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
-KQ0C
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
A1
-K101B A2
ANTI-PUMPING
A1
A1
-K101C A2
ANTI-PUMPING
-KD3 CB CLOSE POWER SUPPLY
A2
A2
E
13
14 21 31 43
13 /21.C4 22 /21.C3 32 44
14 21 31 43
13 /21.C5 22 /21.C4 32 44
14 21 31 43
14 12 24 22 34 32 44 42
13 /21.C6 22 /21.C5 32 44
11 /64.C4 21
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea 31 /68.D6 DRAWING TITLE:
41
CB CLOSE CONTROL Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
21
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
PHASE-A TRIP 1
CB OPEN A
+Remote Control Panel
-XR2 REMOTE_F4
/ 18.E6
1
2
PHASE-B TRIP 1
PHASE-C TRIP 1
POLE DISCREPANCY 1 A
+Protection Panel
23
24
-XR2
25
3
4
-XR2
5
6
7
-XR2
8
9
10
11
(+)220V_F4
/ 18.E6
LOCAL_F4
/ 18.E6
1L1
-KQ0T1
1
4T2
/22.E1
13
-SQ0
-K47A
OPEN
/22.E6
2
Reference DWG
-KQ0T1
/22.E1
2T1
1
5L3
-KQ0T1
/22.E1
B
-XS
3L2
B
33
-K47A
-X0
-K47A
/22.E6
14
/22.E6
24
34
-Q0(A) -J2
1
-X0
1
-Q0(B)-J2
A4
-J2 -Q0(A)
-J1
5
-X0C(A)
5
-J1
* A2
C
-S1
* A02 -X1 -52T1
*
-X1 -J1* -X0C(A)
3 1
6 6
* B2
-X0C(B) -Q0(B)
-J1
7 7
/48.E4
D
5
-J1
* A2
B02
* A02 -X1
*
-X1 -J1* -X0C(B)
21
-KG0.2A
-X0C(B)
-S1
-52T1 2 4
5
3 1
-XR1
17
-XR1
18
-XR1
19
6
* B2
-X0C(C)
5
-X0C(C)
6
-J1
5
-J1
6
-Q0(C)
* A2
-S1
B02
* A02 -X1 -52T1
2 4 7 7
*
-X1 -J1* -X0C(C)
31
-KG0.2A 22
6
/48.E4
3 1
-X0
3
-X0
1
-Q0(C) -J2
5 1
A4
-S1 -X0C(A)
REV.
6T3
23
/73.B3
DATE
NO. DWG
A4
-S1 A04 2
-J2 -X0
2
-S1 A04 2
-J2 -X0
4
A04 2 6 EMPLOYER / DEVELOPER
* B2
C
B02
-X0
35
-X0
37
-X0
-Q0(A) -J2
13
-Q0(B)-J2
13
-Q0(C) -J2
B5
-J2 -X0
7
-S1 B05
-J2
14
-X0
36
PROJECT MANAGER.
B5
-S1 B05
7
13
B5
-S1
2 4
39
B05
-J2
14
-X0
38
14 40 SUPERVISION CONSULTANT
61
-KG0.2A 32
/48.E4
62
D
4
3
04 03 02 01 00
-T47A /22.E6
1
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
A1
-XR1
-KQ0T1 OPEN
E
-XR1
1L1 3L2 5L3 13
2T1 /22.B3 4T2 /22.B4 6T3 /22.B5 14
F
7
-K47A POLE DISCREPANCY
A2
(-)220V_F4
/ 18.E6
20
A1
-KD4
-T47A A2
POLE DESCREPANCY (SET:100mSEC)
CB TRIP1 POWER SUPPLY
2
[NOTE] PLEASE REFER TO CLOUDED PART. TRIP CIRCUIT SUPERVISION RELAYS WILL BE CONNECTED TO THIS PART.
13 23 33 43 53 63 73 83
14 24 34 44 54 64 74 84
/22.B3 /22.B4 /22.B5 /59.B3 /68.B3
3 4 6 5
1 /22.D5 8
ACTION A B C
16316 01 EC
SHEET NO.
22
OF
92
REV NO.
04
E
21
MANUFACTURER/VENDER NAME
DRAWING NUMBER
A2
D
14 12 24 22 34 32 44 42
11 /64.C4 21
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
CB TRIP 1 CONTROL
31 /68.D6 41
Drawing Number :
PREPARED :
PK55-SD-EL-GS-14 Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
PHASE-A TRIP 2
CB OPEN +Remote Control Panel
5
PHASE-B TRIP 2
6
7
8
Project
PHASE-C TRIP 2
POLE DISCREPANCY 2
+Protection Panel
A
A
-XR2 12 -XR2 REMOTE_F5
/ 19.E2
13
26
27
-XR2
28
14
15
16
-XR2
17
18
-XR2
19
20
21
22
(+)220V_F5
/ 19.E2
LOCAL_F5
/ 19.E2
1L1
3L2
-KQ0T2 /23.E1
B
5L3
-KQ0T2 /23.E1
2T1
-XS
-KQ0T2 4T2
/23.E1
6T3
Reference DWG
-X0 -Q0(A) -J2
-SQ0 6 13
/73.B3
23
-K47B /23.E5
33
-K47B /23.E5
14
/23.E5
24
-X0C(A)
8
-X0C(A)
9
-J1
8
-J1
9
*
B3
-Q0(A)
*
C
A3
-S1
* -X1 -52T2
*
-X1
*
-J1 -X0C(A)
A03 5 1
-X0C(B)
8
-X0C(B)
9
-J1
8
-J1
9
*
B3
-Q0(B)
*
-S1
*
B03
-X1 -52T2
2 6
*
-X1
*
10
-J1
10
-X0C(B)
21
D
34
-KG0.2B
/48.E5
/48.E5
-XR1
A03 5 1
-X0C(C)
9
-J1
8
-J1
9
*
B3
*
-S1
*
B03
-X1 -52T2
2 6
A3
*
-X1
*
10
-J1
10
-X0C(C)
A03
-X0 -J2 -Q0(C)
9 3 A5
8
3
-S1 A05
-J2 -X0
4
11
A05
-J2 -X0
4 10
4 12
EMPLOYER / DEVELOPER
-X0 -Q0(A) -J2
-X0 -Q0(B)-J2
41 15 B6
B03
2 6
16 42
C
15
-S1 B06
-J2 -X0
45
B6
-S1 B06
-J2 -X0
15 B6
-S1
5 1
-X0 -J2 -Q0(C)
43
B06
-J2 -X0
16 44
PROJECT MANAGER.
16 46
10 10
SUPERVISION CONSULTANT
61
-KG0.2B 32
/48.E5
D
62
22 4
3 04 03 02 01 00
-T48B /23.E6
-XR1
1
REV.
23
A1
-XR1
A2
-XR1
(-)220V_F5
/ 19.E3
1L1 3L2 5L3 13
2T1 /23.B3 4T2 /23.B4 6T3 /23.B5 14
F
24
7
-K47B POLE DISCREPANCY
-T48B A2
POLE DESCREPANCY (SET:100mSEC)
CB TRIP2 POWER SUPPLY
2
[NOTE] PLEASE REFER TO CLOUDED PART. TRIP CIRCUIT SUPERVISION RELAYS WILL BE CONNECTED TO THIS PART.
13 23 33 43 53 63 73 83
14 24 34 44 54 64 74 84
/23.B3 /23.B4 /23.B5 /59.B3 /68.B3
3 4
1 /23.D5
6 5
8
14 12 24 22 34 32 44 42
ACTION
C
16316 01 EC
23
92
REV NO.
04
A2
E
25
B
OF
ISSUED TO / FOR :
A1
A
SHEET NO.
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
-KD5
MANUFACTURER/VENDER NAME
DRAWING NUMBER
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
-KQ0T2 E
REV.
A5
-S1 A05
8
31
-KG0.2B 22
A3
3
-S1
-X0C(C) -Q0(C)
-X0 -Q0(B)-J2
7
A5
-K47B
-J2 -X0
OPEN
DATE
NO. DWG
B
5 OPEN
2
D
11 /64.C6 21
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
CB TRIP 2 CONTROL
31 /68.D6 41
Drawing Number :
PREPARED :
PK55-SD-EL-GS-14 Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
/ 19.E4
(+)220V_F6
1
97
-S1
B
USE
-F49A
2
3
-F49C
/25.B2
/75.C5
Reference DWG
97 /25.B5
98
/75.D5
13 13
15
-J1
15
-X0C(B) -Q0(B) -J1
13 13
15
-J1
15
-X0C(C) -Q0(C) -J1
13 13
-F49B
15
-J1
4
/25.B3
/24.E6
-K88MA 14
1
15
c
-LS1
c d
-LS2
c
-LS3
C
c
-J1 -X0C(A)
-J1
14
16 16
-J1 -X0C(B)
/24.E4
14
1
13
-K88MC 14
/24.E3
14
-K103 13
-LS2
c
d
EMPLOYER / DEVELOPER
d
-LS3 d
14
B
c d
-LS3 d
-LS1
-LS2
c
d
REV.
c
-LS1 d
/24.E1
DATE
NO. DWG
3
-K102T
13
/24.E5 c
/24.E2
4
3
-T88 98
4
-K88MB
-S2
98
97
-X0C(A) -Q0(A) -J1
13
C d
-J1
14 14
16 16
-J1 -X0C(C)
-J1
14 14
16 PROJECT MANAGER.
16
SUPERVISION CONSULTANT
D
D 95
95
-F49A /25.B2
/25.B3
96 22
/25.B5
96
/24.E5
21 A1
-K103 /24.E5
31 A1
-K88MA
CB MOTOR OPERATION
A2
REV.
61
-K88MC CB MOTOR OPERATION
A2
A1
-K102 A2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
-K88MB
CB MOTOR OPERATION
04 03 02 01 00
96 62
-K103
/24.E5
/ 19.E4
-F49C
32
-K103
E
95
-F49B
CB MOTOR SPRING UNCHARGED
A2
7
A1
A1
-K102T
-K49
-K103
SPRING UNCHARGED SET:30sec
2 CB MOTOR OVER LOAD
A2 CB MOTOR LONG RUN
7
A1
-T88 MOTOR LONG RUN SET:1Min
A2
A1
-KD6
-K104 2
CB MOTOR SPRING CHARGING FAULTY
CB MOTOR CONTROL SUPPLY
A2
A2
E
(-)220V_F6 1L1 3L2 5L3 13
2T1 /25.B2 4T2 6T3 /25.E2 14 /24.B5
F
1L1 3L2 5L3 13
2T1 /25.B3 4T2 6T3 /25.E3 14 /24.B5
1L1 3L2 5L3 13
2T1 /25.B5 4T2 6T3 /25.E5 14 /24.B6
13 22 32 43 53 62 71 83
14 21 /21.D3 31 /21.D4 44 54 61 /21.D5 72 84
3 4 6 5
1 /24.B6 13 23 8 33 43
14 /59.B2 14 24 /68.B2 22 32 34 43 44 53 62 71 83
13 21 31 44 54 61 72 84
/24.B5 /24.E1 /24.E2 /59.B1 /68.B2 /24.E3
3 4
1 /24.B5
6 5
8
13 23 33 43
14 /59.B3 24 /68.B3 34 44
ACTION A B C
16316 01 EC
SHEET NO.
24
OF
92
REV NO.
04
11 /64.C5 21
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
31 /68.D6
CB MOTOR CONTROL
41 Drawing Number :
PREPARED :
PK55-SD-EL-GS-14
MANUFACTURER/VENDER NAME
DRAWING NUMBER
14 12 24 22 34 32 44 42
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
CB MOTOR OPERATION (A PHASE) / 19.E5
CB MOTOR OPERATION (B PHASE)
(+)220V_F7 1L1
1L1
-K88MA
-K88MC
/24.E2
2T1
-X0C(A)
11
-J1
11
-X1
7
/26.A5 u=220V AC
1
2
11
-J1
11
-X1
7
(16A)
3
-X1
DC
4
/26.B4
C
9 1
-S13
-S13
AC
2 AC /26.B5
/26.B4
10 5
M
/26.C4 6
8
-X1 -J1
D
-X0C(A)
8
M
-M1
/25.B2
/24.E1
DC
/26.C4
8
-X1 -J1
-X0C(B)
/ 19.E5
8
7
-S13
AC
2 AC /26.C5
10 5
-OUTLET_C /26.E5 u=220V AC
-X1
-S13 DC
4
/26.E4 6
1 9 1
-S13
-S13
AC
2 AC /26.E5
/26.E4
2
(16A) 10 5 EMPLOYER / DEVELOPER
6
C
M1
M
-M1
PROJECT MANAGER.
M01 7 DC
/26.E4
12
-X1 -J1
-X0C(C)
5 /25.B3
8
D
12 12
-F49C 6
04 03 02 01 00
5 /25.B5
5L3 /24.E2
SUPERVISION CONSULTANT
8
12
-K88MB 6T3
-X1
(16A)
-S13
5L3
-K88MA
2
7
-F49B 6
11
M01
5
-F49A
-J1
M1
12 12
9
-S13 /26.C4
-S13
DC
1
1
4
7
/26.B4
11
3
-X1
DC
M01
-S13
/26.C5 u=220V AC
-S13
M1
-M1
-X0C(C) -Q0(C)
-OUTLET_B
2
3
-S13
A1
6
5L3
REV.
-KD7 CB MOTOR POWER SUPPLY
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A2
-K88MC 6T3
/24.E3
6T3
(-)220V_F7
E
14 12 24 22 34 32 44 42
F
11 /64.C5 21
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
31 /68.D7
CB MOTOR POWER
41 Drawing Number :
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
REV.
B
/25.D5 SET: 5A
2
-X0C(B) -Q0(B)
-OUTLET_A
DATE
NO. DWG
-F49C
/25.D3 SET: 5A
2
Reference DWG
1
-F49B
/25.D2 SET: 5A
2T1
1
-F49A
-Q0(A)
/24.E3
2T1
1
B
1L1
-K88MB
/24.E1
E
A
CB MOTOR OPERATION (C PHASE)
SHEET NO.
25
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
-W1
/56.D5
/56.B5
/24.B1
/24.B1
/25.B2
7
/24.C1
6 /24.C1
5 /25.D2
4 /23.D3
/23.C3
/23.C3
/22.D3
/22.C3
/22.C3
/21.B3
/21.B3
-X0C(A)
3
/21.C3
2 /21.C3
1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
6
4
5
7
8
9
10
11
12
13
14
15
16
-XH -W4
8
Project
9
12
1
2
A
A -Q0(A)
-J1 1
2
3
LA1
4
*
B4
5 A2
6
* B2 *
7
*
8 A3
9
* B3 *
10
11
-X1
-S1 LA01
B04
-X1
A02
1
2
* *
-X1
B02
A03
3
4
* *
12
7
8
/25.B2 u=220V AC
-X1
B03 3
5
6
-S13 DC
DC
4
/25.C2
8
/25.D2
1
-S13
AC
2 AC /25.C3
/25.C2
-LS1
15
16
1
2
c d c
5
-S13
14
c 10
1
-JA 13
(16A)
2
9
7
-S13
-J1
-OUTLET_A
-LS2
6
1 d
-LS3
-HT
d
2 Reference DWG
M1
-W2
2
B
/56.D5
/56.B5
/24.C2
/24.B2
/24.C2
/24.B2
/25.B3
/23.D4
M01
/23.C4
/21.B4
DC 220V, 60 Ohm
2
/21.C4
2
REV.
M
-M1
-52T2
/23.C4
DC 220V, 60 Ohm
1
/22.D4
-52T1
DC 220V, 60 Ohm
/22.C4
-52C
/21.C5
/21.B5
-X0C(B)
1
/25.D3
1
/22.C4
B
DATE
NO. DWG
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
6
4
5
7
8
9
10
11
12
13
14
15
16
-XH -W5
10
13
1
2
EMPLOYER / DEVELOPER
C
-Q0(B)
-J1 1
2
3
LA1
*5 *6 *7
4
A2
B4
* 8 * 9 * 10 A3
B2
11
12
7
8
B3
-X1
-S1 LA01
B04
-X1
1
*
2
A02
-X1
B02
*
3
*
4
A03
-X1
5
*
/25.B4 u=220V AC
B03 3 6
-S13
DC
4
/25.C3
8
/25.D3
1
-S13
AC
2 AC /25.C4
/25.C4
-LS1
15
C
16
1
2
c d c
5
-S13
14
c 10
1
-JA 13
(16A)
2
9
7
-S13
DC
-J1
-OUTLET_B
1 d
-LS3
6
PROJECT MANAGER.
-LS2 -HT
d
2
M1
-W3
-Q0(C)
D
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
1
2
3
6
4
5
7
8
9
10
11
12
13
14
15
16
10
11
12
13
14
15
16
-J1 2
3
LA1
B4
LA01
B04
4
*
5 A2
6
* B2 *
A02
B02
7
*
8 A3
9
* B3 *
A03
B03
-S1
-X1 -X1
1
2
*
-X1
3
4
*
5
6
7
7
-S13 DC
4
/25.C5
1
(16A)
2
/25.D5
8
9 1
-S13
-S13
AC
2 AC /25.C6
/25.C6
-XH -W6
11
14
1
2
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-JA 1
2
c
8
3 DC
/25.B6 u=220V AC
-X1
-S13
-J1
-OUTLET_C
/56.D6
/56.B6
/24.C3
/24.B3
/25.B5
/23.D5
M01
/23.C5
/22.D5
/22.C5
/22.C5
2
SUPERVISION CONSULTANT
/24.C3
DC 220V, 60 Ohm
2
/23.C5
DC 220V, 60 Ohm
M
-M1
1
1
E
/21.B5
/21.C6
/21.B6
-X0C(C)
2
/21.C5
DC 220V, 60 Ohm
D
1
-52T2
/24.B3
1
-52T1
/25.D5
1
-52C
10
-LS1 d c
5
-LS2
1 d
-LS3 6
E
c
-HT
d
2
M1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea 1
-52C DC 220V, 60 Ohm
F
-52T1 2
DC 220V, 60 Ohm
*
1
-52T2 2
DC 220V, 60 Ohm
*
1
2
-M1
M
DRAWING TITLE:
CB MECHANISM 1 M01 Drawing Number :
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
26
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
-Q0(A)
7
13
19
25
31
35
41
47
53
59
65
1
3
5
7
9
11
13
15
17
21
19
23
-J2
1
3
5
7
9
11
13
15
17
19
21
23-J3
A4
A5
A6
A7
A8
LB1
B5
B6
B7
B8
B9
INTERLOCK WITH Q9
INTERLOCK WITH Q1
INTERLOCK WITH Q2
/46.C2
/46.C5
LATCHED RELAY FOR MULTIPLY
/40.B4
/47.B2
OPEN/CLOSE INDICATION
LATCHED RELAY FOR MULTIPLY
/40.B3
1
-W7
/54.B3
OPEN/CLOSE INDICATION
-X0
69
73
77
81
85
89
93
97
101
105
109
113
1
3
5
7
9
11
13
15
17
21
19
23
1
3
5
7
9
11
13
15
17
19
21
23-J4
LA1
A2
A3
A4
A5
A6
A7
A8
LB1
B2
B3
B4
LA01
A02
A03
A04
A05
A06
A07
A08
LB01
B02
B03
B04
-W10
A
117
121
125
129
1
3
5
7
1
3
5
7
B5
B6
B7
B8
B9
B05
B06
B07
B08
B09
-W13
-S2 LB01
B05
B06
B07
B08
B09
-J2
2
4
6
8
10
12
14
16
18
20
22
24-J3
2
4
6
8
10
12
14
16
18
20
22
24-J4
2
4
6
8
-W7
2
4
6
8
10
12
14
16
18
22
20
24-W10
2
4
6
8
10
12
14
16
18
22
20
24
2
4
6
8
-X0
2
8
14
20
26
32
36
42
48
54
60
66
70
74
78
82
86
90
94
98
102
106
110
114
118
122
126
130
CB TRIP1 CICUIT
CB TRIP2 CIRCUIT
/23.B6
1
3
5
7
9
11
13
15
17
21
19
23
1
3
5
7
-X0
3
9
15
21
27
-W8
1
3
5
7
9
11
-W13
Reference DWG
DATE
NO. DWG
REV.
B
/67.B3 REMOTE
CB TRIP2 CIRCUIT
A08
/23.C6
A07
CB TRIP1 CICUIT
A06
/22.C6
A05
/67.B2 REMOTE
A04
/22.B6
-S1 B
/54.B3
CB TRIP2 CIRCUIT
/23.C5
/67.B2 REMOTE
CB TRIP1 CICUIT
/22.C6
CB TRIP2 CIRCUIT
/23.B5
/67.B1 REMOTE
CB TRIP1 CICUIT
A
/22.B6
Project
37
43
49
55
61
13
15
17
21
19
23
-W11
-W14
EMPLOYER / DEVELOPER
C
C -Q0(B)
-J2
1
3
5
7
9
11
A4
A5
A6
A7
A8
LB1
B5
13
B6
15
B7
17
B8
19
B9
A04
A05
A06
A07
A08
LB01
B05
B06
B07
B08
B09
-J2
2
4
6
8
10
12
14
16
18
20
22
-W8
2
4
6
8
10
12
14
16
18
22
-X0
4
10
16
22
28
33
38
44
50
56
-Q0(C)
3
5
7
9
11
13
15
1
3
5
7
A2
A3
A4
A5
A6
A7
A8
LB1
B2
B3
B4
B5
B6
B7
B8
B9
19
21
LA01
A02
A03
A04
A05
A06
A07
A08
LB01
B02
B03
B04
B05
B06
B07
B08
B09
24-J3
2
4
6
8
10
12
14
16
18
20
22
24-J4
2
4
6
8
20
24-W11
2
4
6
8
10
12
14
16
18
22
20
24
2
4
6
8
62
67
71
75
79
83
87
91
95
99
103
107
111
115
119
123
127
131
-S2
CB TRIP2 CIRCUIT
/23.C6
/67.B4 REMOTE
CB TRIP1 CICUIT
/22.C6
CB TRIP2 CIRCUIT
/23.B6
/67.B3 REMOTE
CB TRIP1 CICUIT
/22.B6
D
-X0
5
11
17
23
29
39
45
51
57
63
-W9
1
3
5
7
9
11
13
15
17
21
19
23
-J2
1
3
5
7
9
11
13
15
17
19
21
23-J3
A4
A5
A6
A7
A8
LB1
B5
-W14
PROJECT MANAGER.
SUPERVISION CONSULTANT
B6
B7
B8
B9
1
3
5
7
9
11
13
15
17
21
19
23
1
3
5
7
9
11
13
15
17
19
21
23-J4
LA1
A2
A3
A4
A5
A6
A7
A8
LB1
B2
B3
B4
LA01
A02
A03
A04
A05
A06
A07
A08
LB01
B02
B03
B04
-W12
1
3
5
7
1
3
5
7
B5
B6
B7
B8
B9
B05
B06
B07
B08
B09
-W15
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-S2
-S1
E
17
23-J4
1
LA1
-S1
D
23-J3
21
A04
A05
A06
A07
A08
LB01
B05
B06
B07
B08
B09
-J2
2
4
6
8
10
12
14
16
18
20
22
24-J3
2
4
6
8
10
12
14
16
18
20
22
24-J4
2
4
6
8
-W9
2
4
6
8
10
12
14
16
18
22
20
24-W12
2
4
6
8
10
12
14
16
18
22
20
24
2
4
6
8
-X0
6
12
18
24
30
34
40
46
52
58
64
68
72
76
80
84
88
92
96
100
104
108
112
116
120
124
128
132
133
135
151
153
E
-X0
137
139
141
143
145
147
-X0
149
155
157
159
161
-W15
163
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea L13 L11
L14 L12
L9 L7
L10 L8
L5
L6
R8 R10 R7 R9
R12 R14 R11 R13
-KQ0 /40.E3
L13 L11
L14 L12
L9 L7
L10 L8
L5
L6
R8 R10 R7 R9
R12 R14 R11 R13
DRAWING TITLE:
-KQ0.1 L3
L4
R6
R5
R4
R3
/40.E4
CB MECHANISM 2 L3
L4
R6
R5
R4
R3 Drawing Number :
F
-X0
134
136
138
140
142
144
146
148
-X0
150
152
154
156
158
160
162
164
ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
27
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
BUS DS (BB-1) CLOSE A
BUS DS (BB-1) OPEN
MANUAL OPERATION
BUS DS (BB-1) MOTOR OPERATION A
+CRP
-XR1 REMOTE_F2
/ 18.E3 / 18.E3 / 18.E3
-XR1
26
-XR1
27
28
REMOTE_F2
(+)220V_F2
(+)220V_F2
LOCAL_F2
LOCAL_F2
/ 30.A1 / 30.B1 / 30.B1 Reference DWG
B
2T1 1
3 CLOSE
/28.C2
OPEN
4
REV.
B
2T1
-KQ1T
-SQ1
-SQ1
DATE
NO. DWG
-KQ1C /28.C2
1L1
1L1
2
/73.C3
/73.C3
3L2
3L2
-KQ1T 14
/28.C2
14
-KQ1C
-KQ1C /28.C2
4T2
4T2
-KQ1T
/28.C2
/28.C2
13
13 EMPLOYER / DEVELOPER
C
C 21 A1
A1
-KQ1C CLOSE
-KQ1C
-KQ1T OPEN
A2
/28.C2 A2
22 22
PROJECT MANAGER.
-KQ1T /28.C2
-Q1
-X1C
1
-X1C
2
-X1C
3
-J1
1
-J1
2
-J1
3
1 c
c
-LSA D
2
-LSA b
5
-J1
21 7 7 SUPERVISION CONSULTANT
M1 a
d
a
-DS1
-J1
-Q1
-DS2
d a
5
c
-ILM
-LSB d
-X1C
-M
a b
-DS2
D b
-LSB b
M M01
OPERATION
2
1
04 03 02 01 00
-PS -J1 -X1C
44
-KL1
E
/46.E3
43
/28.C2
4
-X1C
44
-KQ1T 43
-J1
/28.C2
6
/28.C2
2T1 4T2 6T3 14 21 31 44 53
F
1L1 3L2 5L3 13 22 32 43 54
/28.B5 /28.B5 /28.E5 /28.C1 /28.C5 /28.E3 /43.B2
2T1 4T2 6T3 14 22 31 44 53
1L1 3L2 5L3 13 21 32 43 54
5L3
/28.C2
E
5L3
/28.B4 /28.B4 /28.E6 /28.C3 /28.C5
DRAWING TITLE:
BUS DS(-Q1) CONTROL
/28.E4 /43.B2
Drawing Number :
C
16316 01 EC
28
92
04
PREPARED :
PK55-SD-EL-GS-14 B
REV NO.
/ 30.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
A
OF
ISSUED TO / FOR :
6T3
ACTION
SHEET NO.
DATE
-KQ1T
MANUFACTURER/VENDER NAME
DRAWING NUMBER
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
6T3
-KQ1C 43
REV.
6
(-)220V_F2
(-)220V_F2
/ 18.E4
44
-KQ1C
4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
A
/57.D1
/57.B1
/28.D5
/28.E5
/28.D5
/28.E4
/28.D4
/28.D2
/28.D2
Project
-X1C
1
2
3
4
5
6
7
8
9
-W2
1
2
3
4
5
6
7
8
9
-J1
1
2
3
4
5
6
7
8
9
-XH
21
15
-W4
1
2
-JA
1
2
A
-Q1
-J1
c c
-DS2
c
-LSA
a d
-LSB d
-DS2
OPERATION
1
d
1
B
2
-M
a
a
-DS1
Reference DWG
DC220V, 350W
a
DATE
NO. DWG
REV.
d
B
M1
2
DC220V, 6.2W, 9200 Ohm
-DS1 b
-PS
-ILM
c
1
M
-HT 2
M01
-LSA -LSB b
b
b
EMPLOYER / DEVELOPER
-W1
D
-Q1
-J2
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
B6
A01
A02
A03
A04
A05
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
-X1 -W3
INTERLOCK WITH Q11
INTERLOCK WITH Q51, Q52
/47.B3
PROJECT MANAGER.
=D03/67.B3
INTERLOCK WITH Q2
/46.B4
/45.B3
INTERLOCK WITH Q0 CLOSE (LOCAL)
COUPLING INTERLOCK
=D03/70.B1
/44.B1
1
25
27
29
31
33
35
37
39
41
43
45
47
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
A6
A01
A02
A03
A04
A05
A06
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
24
SUPERVISION CONSULTANT
D
-Q1
-J3
Wc1
-S1 -J2
INTERLOCK WITH /46.B6 Q2
DS/ES INCOMPLETE CONDITION
INTERLOCK WITH Q15
=D03/66.C4
LATCHED RELAY FOR MULTIPLY
/41.B2
/67.E2 REMOTE
/54.B4
/67.B5 REMOTE
OPEN/CLOSE INDICATION
LATCHED RELAY FOR MULTIPLY
/41.B2
/67.E1 REMOTE
OPEN/CLOSE INDICATION
/54.B3
-X1
/67.B4 REMOTE
INTERLOCK WITH Q0 CLOSE (REMOTE)
C
/45.B5
C
B1
B2
B3
B4
B5
B6
-S2 Wc01 24
-J3
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI ) -W1
-X1
E
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
-W3
-X1
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
E
-X1
49
51
L13 L11
L14 L12
53
55
L9 L7
L10 L8
L5
L6
57
59
61
R8 R10 R7 R9
63
R12 R14 R11 R13
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
-KQ1 /41.E2
L3
L4
R6
R5
R4
R3
DRAWING TITLE:
BUS DS(-Q1) MECHANISM -X1
50
52
54
56
58
60
62
64 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
29
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
BUS DS (BB-2) CLOSE A
BUS DS (BB-2) OPEN
MANUAL OPERATION
BUS DS (BB-2) MOTOR OPERATION A
+CRP
-XR1 REMOTE_F2
/ 28.A6 / 28.B6 / 28.B6
-XR1
29
-XR1
30
31
REMOTE_F2
(+)220V_F2
(+)220V_F2
LOCAL_F2
LOCAL_F2
/ 32.A1 / 32.B1 / 32.B1 Reference DWG
2T1
B 3
-KQ2T
1
-SQ2
/30.C2
-SQ2
CLOSE
OPEN
4
/73.D3
2
/30.C2
1L1
14
B
1L1 3L2
-KQ2T /30.C2
REV.
-KQ2C
3L2
/73.D3
DATE
NO. DWG
2T1
-KQ2C /30.C2
4T2
4T2
14
-KQ2C
-KQ2T
/30.C2
/30.C2
13
13 EMPLOYER / DEVELOPER
C
C 21 A1
A1
-KQ2C CLOSE
-KQ2C
-KQ2T OPEN
A2
/30.C2 A2
22 22
PROJECT MANAGER.
-KQ2T /30.C2
-Q2
-X2C
1
-X2C
2
-X2C
3
-J1
1
-J1
2
-J1
3
1 c
c
-LSA D
-J1
5
-Q2
2 a
-LSA
7
M1 a
d
a
b
-J1
21 7
SUPERVISION CONSULTANT
-DS2
d
-DS1
5
c
-ILM
-LSB d
-X2C
-M
a b
-DS2
D b
-LSB b
M M01
OPERATION
2
1
04 03 02 01 00
-PS -J1 -X2C
44
-KL2
E
/46.E6
43
/30.C2
4
-X2C
44
-KQ2T 43
-J1
/30.C2
6
/30.C2
2T1 4T2 5L3 14 21 31 44 53 6L3
F
1L1 3L2 6T3 13 22 32 43 54 5T3
/30.B5 /30.B5 /30.C1 /30.C5 /30.E3 /43.B3 /30.E5
2T1 4T2 6T3 14 22 31 44 53
1L1 3L2 5L3 13 21 32 43 54
5T3
/30.C2
E
5L3
/ 32.E1
/30.B4 /30.B4 /30.E6 /30.C3 /30.C5
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
BUS DS(-Q2) CONTROL
/30.E4 /43.B3
Drawing Number :
B C
16316 01 EC
30
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 A
OF
ISSUED TO / FOR :
6T3
ACTION
SHEET NO.
DATE
-KQ2T
MANUFACTURER/VENDER NAME
DRAWING NUMBER
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
6L3
-KQ2C 43
REV.
6
(-)220V_F2
(-)220V_F2
/ 28.E6
44
-KQ2C
4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
A
/57.D2
/57.B2
/30.D5
/30.E5
/30.D5
/30.E4
/30.D4
/30.D2
/30.D2
Project
-X2C
1
2
3
4
5
6
7
8
9
-W2
1
2
3
4
5
6
7
8
9
-J1
1
2
3
4
5
6
7
8
9
-XH
22
16
-W4
1
2
-JA
1
2
A
-Q2
-J1
c c
c
-LSA
a
-DS2
-LSB
-DS2
OPERATION
d
d
1
d
B
2
a
-M
a
-DS1
d
Reference DWG
M1
2
-ILM DC220V, 6.2W, 9200 Ohm
-DS1 b
-PS
1
c
DC220V, 350W
a
DATE
NO. DWG
REV.
B
1
M
-HT 2
M01
-LSA -LSB
b
b
b
EMPLOYER / DEVELOPER
-W1
D
-Q2
-J2
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
B6
A01
A02
A03
A04
A05
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
-X2 -W3
INTERLOCK WITH Q12
INTERLOCK WITH Q51, Q52
/47.B3
PROJECT MANAGER.
=D03/67.B5
INTERLOCK WITH Q1
/46.B1
/45.B3
INTERLOCK WITH Q0 CLOSE (LOCAL)
COUPLING INTERLOCK
=D03/70.C1
/46.B3
1
25
27
29
31
33
35
37
39
41
43
45
47
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
A6
A01
A02
A03
A04
A05
A06
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
24
SUPERVISION CONSULTANT
D
-Q2
-J3
Wc1
-S1 -J2
INTERLOCK WITH Q1
DS/ES INCOMPLETE CONDITION
/44.B2
=D03/68.C2
INTERLOCK WITH Q16
LATCHED RELAY FOR MULTIPLY
/41.B4
/67.E3 REMOTE
/54.B4
/67.B6 REMOTE
OPEN/CLOSE INDICATION
LATCHED RELAY FOR MULTIPLY
/41.B3
/67.E2 REMOTE
OPEN/CLOSE INDICATION
/54.B4
-X2
/67.B5 REMOTE
INTERLOCK WITH Q0 CLOSE (REMOTE)
C
/45.B6
C
B1
B2
B3
B4
B5
B6
-S2 Wc01 24
-J3
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI ) -W1
-X2
E
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
-W3
-X2
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
E
-X2
49
51
L13 L11
L14 L12
53
55
L9 L7
L10 L8
L5
L6
57
59
61
R8 R10 R7 R9
63
R12 R14 R11 R13
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
-KQ2 /41.E3
L3
L4
R6
R5
R4
R3
DRAWING TITLE:
BUS DS(-Q2) MECHANISM -X2
50
52
54
56
58
60
62
64 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
31
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
LINE DS CLOSE A
LINE DS OPEN
MANUAL OPERATION
LINE DS MOTOR OPERATION A
+CRP
-XR1 REMOTE_F2
/ 30.A6 / 30.B6 / 30.B6
-XR1
32
-XR1
33
34
REMOTE_F2
(+)220V_F2
(+)220V_F2
LOCAL_F2
LOCAL_F2
/ 34.A1 / 34.B1 / 34.B1 Reference DWG
2T1
B
-KQ9T /32.C2
1
3
-SQ9
-SQ9 CLOSE
OPEN
4
/32.C2
1L1
14
B
1L1 3L2
-KQ9T /32.C2
REV.
-KQ9C
3L2
2
/73.E3
/73.E3
DATE
NO. DWG
2T1
-KQ9C /32.C2
4T2
4T2
14
-KQ9C
-KQ9T
/32.C2
/32.C2
13
13 EMPLOYER / DEVELOPER
C
C 21 A1
A1
-KQ9C CLOSE
-KQ9C
-KQ9T OPEN
A2
/32.C2 A2
22 22
PROJECT MANAGER.
-KQ9T /32.C2
-Q9
-X9C
1
-X9C
2
-X9C
3
-J1
1
-J1
2
-J1
3
1 c
c
-LSA D
2
-LSA b
5
-J1
21 7 7 SUPERVISION CONSULTANT
M1 a
d
a
-DS1
-J1
-Q9
-DS2
d a
5
c
-ILM
-LSB d
-X9C
-M
a b
-DS2
D b
-LSB b
M M01
OPERATION
2
1
04 03 02 01 00
-PS -J1 -X9C
44
-KL9
E
/47.E2
43
/32.C2
4
-X9C
44
-KQ9T 43
-J1
/32.C2
6
/32.C2
2T1 4T2 6T3 14 21 31 44 53
F
1L1 3L2 5L3 13 22 32 43 54
/32.B5 /32.B5 /32.E5 /32.C1 /32.C5 /32.E3 /43.B4
2T1 4T2 6T3 14 22 31 44 53
1L1 3L2 5L3 13 21 32 43 54
5L3
/32.C2
E
5L3
/ 34.E1
/32.B4 /32.B4 /32.E6 /32.C3 /32.C5
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
LINE DS(-Q9) CONTROL
/32.E4 /43.B4
Drawing Number :
B C
16316 01 EC
32
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 A
OF
ISSUED TO / FOR :
6T3
ACTION
SHEET NO.
DATE
-KQ9T
MANUFACTURER/VENDER NAME
DRAWING NUMBER
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
6T3
-KQ9C 43
REV.
6
(-)220V_F2
(-)220V_F2
/ 30.E6
44
-KQ9C
4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
-X9C
A
1
2
3
4
5
6
/57.D2
/57.B2
/32.D5
/32.E5
/32.D5
/32.E4
/32.D4
/32.D2
/32.D2
Project
7
8
9
8
9
8
9
-W2
1
2
3
4
5
6
7
-J1
1
2
3
4
5
6
7
-XH
23
17
-W4
1
2
-JA
1
2
A
-Q9
-J1
c c
-DS2
c
-LSA
a
-LSB d
d
OPERATION
1
d
B
DC220V, 6.2W, 9200 Ohm
2
a
-M
a
-DS1
d
Reference DWG
M1
2
-ILM
-DS1 b
-PS
1
c
-DS2
DC220V, 350W
a
DATE
NO. DWG
REV.
B
1
M
-HT 2
M01
-LSA -LSB
b
b
b
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
-X9 -W3
INTERLOCK WITH Q8
INTERLOCK WITH Q51, Q52
/47.B4
/47.C3
/45.C3
INTERLOCK WITH Q0 CLOSE (LOCAL)
DS/ES INCOMPLETE CONDITION
/44.B2
LATCHED RELAY FOR MULTIPLY
/41.B5
/54.B5
/67.D2 REMOTE
OPEN/CLOSE INDICATION
LATCHED RELAY FOR MULTIPLY
/41.B5
OPEN/CLOSE INDICATION
/54.B5
-X9 -W1
/67.D1 REMOTE
INTERLOCK WITH Q0 CLOSE (REMOTE)
C
/45.B5
EMPLOYER / DEVELOPER
C
PROJECT MANAGER.
25
27
29
31
33
35
37
39
41
43
45
47
1
3
5
7
9
11
13
15
17
19
21
23
SUPERVISION CONSULTANT -Q9
-J2
D
1
3
5
7
9
11
17
13
15
19
21
23
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
B6
Wc1
A01
A02
A03
A04
A05
B01
B02
B03
B04
B05
B06
Wc01
2
4
6
8
10
12
18
14
16
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
-S1
-Q9
-J3
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
A6
B1
B2
B3
B4
B5
B6
A01
A02
A03
A04
A05
A06
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
D
-S2
-J2 -W1
-J3 -W3
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-X9
2
4
6
8
10
12
14
16
18
20
22
24
-X9
26
28
30
32
34
36
38
40
42
44
46
48
E
E
-X9
49
51
L13 L11
L14 L12
53
55
L9 L7
L10 L8
L5
L6
57
59
61
R8 R10 R7 R9
63
R12 R14 R11 R13
-KQ9 /41.E5
L3
L4
R6
R5
R4
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
R3
DRAWING TITLE:
-X9
50
52
54
56
58
60
62
LINE DS(-Q9) MECHANISM
64
Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
33
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
WORK ES CLOSE A
WORK ES OPEN
MANUAL OPERATION
WORK ES MOTOR OPERATION A
+CRP
-XR1 REMOTE_F2
/ 32.A6 / 32.B6 / 32.B6
-XR1
35
-XR1
36
37
REMOTE_F2
(+)220V_F2
(+)220V_F2
LOCAL_F2
LOCAL_F2
/ 36.A1 / 36.B1 / 36.B1 Reference DWG
2T1
B
-KQ51T /34.C2
1
3
-SQ51
-SQ51 CLOSE
OPEN
4
/34.C2
1L1
-KQ51T /34.C2
14
REV.
B
-KQ51C 1L1
3L2
2
/74.B3
/74.B3
DATE
NO. DWG
2T1
3L2
-KQ51C /34.C2
4T2
4T2
14
-KQ51C
-KQ51T
/34.C2
/34.C2
13
13 EMPLOYER / DEVELOPER
C
C 21 A1
A1
-KQ51C CLOSE
-KQ51C
-KQ51T OPEN
A2
/34.C2 A2
22 22
PROJECT MANAGER.
-KQ51T /34.C2
-X51C
1
-X51C
2
-J1
1
-J1
2
-Q51
c
-LSB d
D
3
1
-J1
3
2
-DS2
-ILM
c
-LSA
-X51C
-X51C
5
-J1
5
-Q51
7
c
SUPERVISION CONSULTANT
M1 a
d
d a
a
-DS1
-J1
21 7
-LSA b
-M
a b
-DS2
D b
-LSB b
M M01
OPERATION
2
1
04 03 02 01 00
-PS -J1 -X51C
44
-KL51
E
/47.E3
43
/34.C2
4
-X51C
44
-KQ51T 43
-J1
/34.C2
6
/34.C2
2T1 4T2 6T3 14 21 31 44 53
F
1L1 3L2 5L3 13 22 32 43 54
/34.B5 /34.B5 /34.E5 /34.C1 /34.C5 /34.E3 /43.B4
2T1 4T2 6T3 14 22 31 44 53
1L1 3L2 5L3 13 21 32 43 54
6T3
5L3
/34.C2
E
5L3
/34.B4 /34.B4 /34.E6 /34.C3 /34.C5
DRAWING TITLE:
WORK ES(-Q51) CONTROL
/34.E4 /43.B5
Drawing Number :
B C
16316 01 EC
34
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 A
OF
/ 36.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
ACTION
SHEET NO.
ISSUED TO / FOR :
-KQ51T
MANUFACTURER/VENDER NAME
DRAWING NUMBER
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
6T3
-KQ51C 43
REV.
6
(-)220V_F2
(-)220V_F2
/ 32.E6
44
-KQ51C
4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
-X51C
1
2
3
4
5
6
7
8
9
-W2
1
2
3
4
5
6
7
8
9
-J1
1
2
3
4
5
6
7
8
9
-Q51
-J1
-XH
A
/57.D3
/57.B3
/34.D5
/34.E5
/34.D5
/34.E4
/34.D4
/34.D2
A
/34.D2
Project
24
18
-W4
1
2
-JA
1
2
c Reference DWG
-DS2 c
B
c
-LSA
a
d
-LSB
-DS2
OPERATION
d
1
-ILM 2
-M
a
a
B
d
M1
2
DC220V, 6.2W, 9200 Ohm
-DS1
b
-PS
DC220V, 350W
a
REV.
-DS1
1
d
DATE
NO. DWG
c
1
M
-HT 2
M01
-LSA -LSB
b
b
b EMPLOYER / DEVELOPER
-W1
D
-Q51
-J2
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
B2
B3
B4
B5
B6
-X51 -W3
-Q51
-J3
Wc1
-S1
INTERLOCK WITH Q1
INTERLOCK WITH Q2
INTERLOCK WITH Q9
/46.D1
/46.D4
/47.B2
/45.C4
1
B1
INTERLOCK WITH Q0 CLOSE (LOCAL)
DS/ES INCOMPLETE CONDITION
/44.B3
LATCHED RELAY FOR MULTIPLY
/42.B2
/67.D3 REMOTE
OPEN/CLOSE INDICATION
/54.B6
/42.B2
/67.D2 REMOTE
/54.B6
-X51
LATCHED RELAY FOR MULTIPLY
C
OPEN/CLOSE INDICATION
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
25
27
29
31
33
35
37
39
41
43
45
47
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
A6
B1
B2
B3
B4
B5
B6
A01
A02
A03
A04
A05
A06
B01
B02
B03
B04
B05
B06
D
04 03 02 01 00
-S2 A01
-J2 -W1
A02
A03
A04
A05
B01
B02
B03
B04
B05
B06
Wc01
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
-J3 -W3
REV.
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
-X51
-X51
49
51
L13 L11
L14 L12
53
L9 L7
55
L10 L8
57
59
61
R8 R10 R7 R9
-X51
E
63
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
R12 R14 R11 R13
DRAWING TITLE:
-KQ51 /42.E2
L3
L4
L5
L6
R6
R5
R4
WORK ES(-Q51) MECHANISM
R3
Drawing Number :
F
-X51
50
52
54
56
58
60
62
ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
35
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
64
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
WORK ES CLOSE A
WORK ES OPEN
MANUAL OPERATION
WORK ES MOTOR OPERATION A
+CRP
-XR1 REMOTE_F2
/ 34.A6 / 34.B6 / 34.B6
-XR1
38
-XR1
39
40
REMOTE_F2
(+)220V_F2
(+)220V_F2
LOCAL_F2
LOCAL_F2
/ 38.A1 / 38.B1 / 38.B1 Reference DWG
2T1
B
-KQ52T /36.C2
1
3
-SQ52
-SQ52 CLOSE
OPEN
4
/36.C2
1L1
-KQ52T /36.C2
14
REV.
B
-KQ52C 1L1
3L2
2
/74.C3
/74.C3
DATE
NO. DWG
2T1
3L2
-KQ52C /36.C2
4T2
4T2
14
-KQ52C
-KQ52T
/36.C2
/36.C2
13
13 EMPLOYER / DEVELOPER
C
C 21 A1
A1
-KQ52C CLOSE
-KQ52C
-KQ52T OPEN
A2
/36.C2 A2
22 22
PROJECT MANAGER.
-KQ52T /36.C2
-X52C
1
-X52C
2
-X52C
3
-J1
1
-J1
2
-J1
3
-Q52
c
-LSA
a
-LSA b
5
-J1
21 7 7 SUPERVISION CONSULTANT
M1 a
d
a
-DS1
-J1
-Q52
-DS2 2
d
5
c
-ILM
-LSB d
D
1
c
-X52C
-M
a
-DS2
D b
-LSB b
M M01
OPERATION
b
2
1
04 03 02 01 00
-PS -J1 -X52C
34
-KL51
E
/47.E3
34
/36.C2
4
-X52C
44
-KQ52T 43
-J1
/36.C2
6
/36.C2
2T1 4T2 6T3 14 21 31 44 53
F
1L1 3L2 5L3 13 22 32 43 54
/36.B5 /36.B5 /36.E5 /36.C1 /36.C5 /36.E3 /43.B5
2T1 4T2 6T3 14 22 31 44 53
1L1 3L2 5L3 13 21 32 43 54
6T3
5L3
/36.C2
E
5L3
/36.B4 /36.B4 /36.E6 /36.C3 /36.C5
DRAWING TITLE:
WORK ES(-Q52) CONTROL
/36.E4 /43.B5
Drawing Number :
B C
16316 01 EC
36
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 A
OF
/ 38.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
ACTION
SHEET NO.
ISSUED TO / FOR :
-KQ52T
MANUFACTURER/VENDER NAME
DRAWING NUMBER
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
6T3
-KQ52C 43
REV.
6
(-)220V_F2
(-)220V_F2
/ 34.E6
44
-KQ52C
4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
A
-X52C
1
2
3
4
5
6
7
8
9
-W2
1
2
3
4
5
6
7
8
9
-J1
1
2
3
4
5
6
7
8
9
-Q52
/57.D3
/57.B3
/36.D5
/36.E5
/36.D5
/36.E4
/36.D4
/36.D2
/36.D2
Project
-J1
-XH -W4
-JA
25
19
1
2
1
2
A
c
-DS2 c
c
-LSA
a
d
-LSB d
1
d
1
B
-M a
-DS1
DATE
NO. DWG
REV.
B
2
a
Reference DWG
d
M1
2
DC220V, 6.2W, 9200 Ohm
-DS1 b
-PS
-ILM
c
-DS2
OPERATION
DC220V, 350W
a
1
M
-HT 2
M01
-LSA -LSB
b
b
b
EMPLOYER / DEVELOPER
-W1
D
-Q52
-J2
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
B2
B3
B4
B5
B6
-X52 -W3
-Q52
-J3
Wc1
-S1
INTERLOCK WITH Q1
INTERLOCK WITH Q2
INTERLOCK WITH Q9
/46.D1
/46.D4
/47.B2
/45.C4
1
B1
INTERLOCK WITH Q0 CLOSE (LOCAL)
DS/ES INCOMPLETE CONDITION
/44.B3
LATCHED RELAY FOR MULTIPLY
/42.B4
/67.D4 REMOTE
OPEN/CLOSE INDICATION
/55.B2
/42.B3
/67.D3 REMOTE
/55.B2
-X52
LATCHED RELAY FOR MULTIPLY
C
OPEN/CLOSE INDICATION
C
PROJECT MANAGER.
25
27
29
31
33
35
37
39
41
43
45
47
1
3
5
7
9
11
13
15
17
19
21
23
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
A6
B1
B2
B3
B4
B5
B6
A01
A02
A03
A04
A05
A06
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
SUPERVISION CONSULTANT
D
-S2
-J2
A01
A02
A03
A04
A05
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
2
4
6
8
10
12
14
16
18
20
22
24
Wc01
-J3
04 03 02 01 00
REV. -W1
-X52
-W3
-X52
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
-X52
49
51
L13 L11
L14 L12
53
55
L9 L7
L10 L8
L5
L6
57
59
61
R8 R10 R7 R9
63
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
R12 R14 R11 R13
-KQ52 /42.E3
-X52
F
DRAWING TITLE:
L3
L4
50
52
54
56
R6
58
R5
60
R4
62
R3
WORK ES(-Q52) MECHANISM Drawing Number :
64 ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
37
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
LINE ES CLOSE
LINE ES OPEN
MANUAL OPERATION
LINE ES MOTOR OPERATION
+CRP
A
A
-XR1
-XR1
41
-XR1
42
43
REMOTE_F2
/ 36.A6
(+)220V_F2
(+)220V_F2
/ 36.B6
/ 40.A1
LOCAL_F2
/ 36.B6
Reference DWG
DATE
NO. DWG
REV.
B
B 1
3
-SQ8
-SQ8 CLOSE
2T1
OPEN
4
-KQ8C
2
/74.D3
/74.D3
/38.C2
6T3
2T1
-KQ8T 1L1
/38.C2
1L1
6T3
-KQ8C
-KQ8T
/38.C2
/38.C2
5L3
5L3 EMPLOYER / DEVELOPER
C
C A1
A1
-KQ8C CLOSE
-X8C
-KQ8T OPEN
A2
-X8C
1
A2
PROJECT MANAGER.
-X8C
2
-X8C
3
-J1
-Q8
-J1 1 B1
2 A5
3 c
5 SUPERVISION CONSULTANT
-DS2
-S1 B01
D
M1
A05
d
a
1
-DS1
2
44
-KL8 /47.E4
-J1
4
-X8C
4
14 /38.C2
04 03 02 01 00
1
-KQ8C 43
D
M M01
OPERATION
2
E
-M
-PS
-ILM b
6
-X8C
6
14
-KQ8T 13
-J1
/38.C2
REV.
4T2
-KQ8C 13
/38.C2
2T1 4T2 6T3 14 21 31 43 53
F
1L1 3L2 5L3 13 22 32 44 54
/38.B5 /38.E5 /38.C1 /38.E4
/43.B3
2T1 4T2 6T3 14 21 31 43 53
1L1 3L2 5L3 13 22 32 44 54
3L2
/38.C2
E
/38.B5 /38.E5 /38.C3 /38.E4
DRAWING TITLE:
LINE ES(-Q8) CONTROL Drawing Number :
/43.B3
38
92
04
PREPARED :
PK55-SD-EL-GS-14
C
16316 01 EC
/ 40.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
B REV NO.
ISSUED TO / FOR :
3L2
A
OF
DATE
4T2
ACTION
SHEET NO.
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
-KQ8T
MANUFACTURER/VENDER NAME
DRAWING NUMBER
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
CONTRACTOR: CONSORTIUM( KN / HHI )
(-)220V_F2
(-)220V_F2
/ 36.E6
5
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
-X8C
1
2
3
4
5
6
7
8
-W1
1
2
3
4
5
6
23
24
-J1
1
2
3
4
5
6
23
24
B1
A5
-Q8
B
B01
-J1
c 1
d
-W3
1
2
-JA
1
2
OPERATION
DATE
NO. DWG
REV.
B 1
2
M
-M DC220V, 210W
1
Reference DWG
d
M1
-PS
a
20
-DS1
OPERATION
A05
-XH
A
26
c
-DS2
-S1
/57.D4
/57.B4
/38.E5
/38.C5
/38.E4
/38.C3
A
/38.C2
/38.C2
Project
-HT 2
M01
-ILM
-DS1 b
DC220V, 5.94W, 9200 Ohm
2
EMPLOYER / DEVELOPER
INTERLOCK WITH Q9
PROJECT MANAGER.
/47.C2
LATCHED RELAY FOR MULTIPLY
/42.B5
OPEN/CLOSE INDICATION
/55.B3
/67.D5 REMOTE
LATCHED RELAY FOR MULTIPLY
/67.D4 REMOTE
/55.B3
/42.B5
C
OPEN/CLOSE INDICATION
C
-X8
1
3
5
7
9
11
13
15
-X8
17
19
21
23
25
27
29
31
33
35
37
39
-W1
7
9
11
13
15
17
19
21
-W2
1
3
5
7
9
11
13
15
17
19
21
23
SUPERVISION CONSULTANT
D
D -Q8
-J1
7
9
11
13
15
17
19
21
A1
A2
A3
A4
B2
B3
B4
B5
A01
A02
A03
A04
B02
B03
B04
B05
8
10
12
14
16
18
20
22
-W1
8
10
12
14
16
18
20
22
-X8
2
4
6
8
10
12
14
16
-S1
-Q8
-J2
1
3
5
7
9
11
13
15
17
19
21
23
A1
A2
A3
A4
A5
A6
B1
B2
B3
B4
B5
B6
A01
A02
A03
A04
A05
A06
B01
B02
B03
B04
B05
B06
2
4
6
8
10
12
14
16
18
20
22
24
-W2
2
4
6
8
10
12
14
16
18
20
22
24
-X8
18
20
22
24
26
28
30
32
34
36
38
40
04 03 02 01 00
-S2
REV.
-J1
-J2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
-X8
41
43
L13 L11
L14 L12
45
47
L9 L7
L10 L8
L5
L6
49
51
53
R8 R10 R7 R9
E
55
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
R12 R14 R11 R13
-KQ8
DRAWING TITLE:
/42.E5
L3
-X8
F
42
L4
44
46
48
R6
50
R5
52
R4
54
R3
LINE ES(-Q8) MECHANISM Drawing Number :
56 ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
39
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
/ 38.B6
(+)220V_F2
(+)220V_F2
/ 41.A1
Reference DWG
-X0 -Q0(A)-J3
B
73 3
DATE
NO. DWG
REV.
105
-J3
A3
B
19 B3
-S2 A03
-J3 -X0 -Q0(B)-J3
4
B03
-J3
74 3
20 106
-J3
A3
19 B3
-S2 A03
-J3 -X0 -Q0(C)-J3
C
4
B03
-J3
75 3
EMPLOYER / DEVELOPER
20
C
107
-J3
A3
19 B3
-S2 A03
-J3 -X0
4 76
B03
-J3
PROJECT MANAGER.
20 108
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
L1
R1
L2
R2
-KQ0
L1
R1
L2
R2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-KQ0.1
CB -Q0 MULTIPLY
CB -Q0 MULTIPLY
E
E / 38.E6
(-)220V_F2
(-)220V_F2 L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
F MANUFACTURER/VENDER NAME
DRAWING NUMBER
16316 01 EC
SHEET NO.
40
OF
92
REV NO.
04
L3 /27.F2 L4 /27.F2 L5 /27.F2 L6 /27.F3 R6 /27.F3 R5 /27.F3 R4 /27.F3 R3 /27.F3
L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
/ 41.E1
L3 /27.F4 L4 /27.F4 L5 /27.F4
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
L6 /27.F5
MULTIPLY CONTACT
R6 /27.F5 R5 /27.F5 R4 /27.F5 R3 /27.F5
Drawing Number :
PREPARED :
PK55-SD-EL-GS-14 ACTION A B C D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
/ 40.A6
(+)220V_F2
(+)220V_F2
-X1
9
-X2
19
9
19
-X9
7
-J2
7
/ 42.A1
17 Reference DWG
9
-Q1
B
-J2
19
A5
B5
A05
19
A5
B5
B05
A05
B05
20
10
-S1
-Q9
-S1
10
-X1
-J2
9
-Q2
-J2
10
-X2
20
-J2
DATE
NO. DWG
REV.
15
A4
B4
A04
B04
B
-S1 -J2
10
-J2
20
-X9
20
8
-J2
8
16 18
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
L1
R1
-KQ1
/ 40.E6
R1
-KQ2
BUS DS -Q1 MULTIPLY
E
L1
L2
R2
L1
REV.
R1
L2
R2
LINE DS -Q9 MULTIPLY
L2
(-)220V_F2
F MANUFACTURER/VENDER NAME
L3 /29.F1 L4 /29.F1 L5 /29.F2 L6 /29.F2 R6 /29.F2 R5 /29.F2 R4 /29.F2 R3 /29.F3
L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
L3 /31.F1 L4 /31.F1 L5 /31.F2 L6 /31.F2 R6 /31.F2 R5 /31.F2 R4 /31.F2 R3 /31.F3
L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
L4 /33.F1 L5 /33.F2
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
L6 /33.F2
DRAWING TITLE:
R6 /33.F2
MULTIPLY CONTACT
R5 /33.F2 Drawing Number :
R4 /33.F2 R3 /33.F3
16316 01 EC
41
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 ACTION A
C SHEET NO.
E / 42.E1
L3 /33.F1
B DRAWING NUMBER
ISSUED TO / FOR :
R2
(-)220V_F2 L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
-KQ9
BUS DS -Q2 MULTIPLY
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
/ 41.A6
(+)220V_F2
(+)220V_F2
B
-X51
7
-X51
17
-X52
7
-X52
17
-X8
7
-X8
13
-Q51-J2
7
-J2
17
-Q52-J2
7
-J2
17
-J1
13
-J1
19
A4
B4
A04
B04
-S1 -J2 -X51
A4
B4
A04
B04
-Q8
-S1
8 8
-J2 -X51
-J2
18
-X52
18
A4
B4
A04
B04
/ 43.B1
Reference DWG
DATE
NO. DWG
REV.
B
-S1
8 8
-J2 -X52
-J1
18
-X8
18
14 8
-J1 -X8
20 14
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
L1
R1
-KQ51
/ 41.E6
R1
-KQ52
WORK ES -Q51 MULTIPLY
E
L1
L2
R2
L1
04 03 02 01 00
R1
REV.
-KQ8
WORK ES -Q52 MULTIPLY
L2
R2
LINE ES -Q8 MULTIPLY
L2
F MANUFACTURER/VENDER NAME
L4 /35.F1 L5 /35.F2 L6 /35.F2 R6 /35.F2 R5 /35.F2 R4 /35.F3 R3 /35.F3
L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
L3 /37.F1 L4 /37.F1 L5 /37.F2 L6 /37.F2 R6 /37.F2 R5 /37.F2 R4 /37.F2 R3 /37.F3
L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
L4 /39.F2 L5 /39.F2
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
L6 /39.F2
DRAWING TITLE:
R6 /39.F2
MULTIPLY CONTACT
R5 /39.F2 Drawing Number :
R4 /39.F3 R3 /39.F3
16316 01 EC
42
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 ACTION A
C SHEET NO.
E / 43.E1
L3 /39.F1
B DRAWING NUMBER
ISSUED TO / FOR :
R2
(-)220V_F2 L3 /35.F1
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
(-)220V_F2 L11 L13 L12 L14 L7 L9 L8 L10 R10 R8 R9 R7 R14 R12 R13 R11
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
DOUBLE INTERLOCKING / 42.A6
(+)220V_F2
(+)220V_F2
-XS
3
Reference DWG
=DMP1
B
-XS
3
-K201 /43.E5
-K213
53
53
-KQ1C -KQ1T 14
DATE
NO. DWG
REV.
B
13 13
=DMP1/47.E6
/ 44.B1
/28.C2
53
-KQ2C -KQ2T
54/28.C2
54 /30.C2
54/30.C2
53
53
53
-KQ8C -KQ8T -KQ9C 54 /38.C2
54/38.C2
54/32.C2
53
53
53
53
53
-KQ9T -KQ51C -KQ51T -KQ52C 54 /32.C2
54 /34.C2
54/34.C2
54 /36.C2
53
-KQ52T 54 /36.C2
4
3
-K203T /43.E2
54
1
14
-XS
4
-XS
4 EMPLOYER / DEVELOPER
C
C
43
PROJECT MANAGER.
-K201 /43.E5
44 13
-K202 /43.E2
SUPERVISION CONSULTANT
14
D
=DMP1/47.B1
D
-XS A1
-K202 DOUBLE INTERLOCKING
E
/ 42.E6
(-)220V_F2 13 21 31 43
F
7 DS/ES MOTOR RUNNING TIME EXCEEDED SET:5SEC
14 /43.D2 22 /18.D3 32 44
REV.
5
-K201 /43.E5
2
-XS
8 6
A1
1 /43.B6
6 5
8
DS/ES MOTOR OPERATING
DS/ES MOTOR RUNNING EXCEEDED
A2
E
1 R3 R5 7 13 21 31 43
2 R4 R6 8 14 22 32 44
/21.D1 /43.E5 /43.B2
13 23 33 43
14 /59.B4 24 /18.D3 34 /68.B4 44
DRAWING TITLE:
OPERATING CONDITION Drawing Number :
/43.C2
C
16316 01 EC
43
92
04
PREPARED :
PK55-SD-EL-GS-14 B
REV NO.
/ 44.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
A
OF
ISSUED TO / FOR :
A2
ACTION
SHEET NO.
DATE
-K203
MANUFACTURER/VENDER NAME
DRAWING NUMBER
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
A1
-K201
(-)220V_F2 3 4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
CONTRACTOR: CONSORTIUM( KN / HHI )
7
-K203T A2
04 03 02 01 00
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
(+)220V_F2
/ 43.B6
B
(+)220V_F2
-X1
23
-J2
23
-Q1
-Q2
-X2
23
-J2
23
Wc1
-S1 /29.D3
-J2 -X1
-Q9
/31.D3
-J2
24 24
23
-J2
23
Wc1
-X2
-X51
23
-J2
23
-Q51
Wc1
-S1 Wc01
-X9
-S1 -J2
24
-X9
24
/35.D3
Wc01
-J2
24
23
-J2
23
-Q52
Wc1
-S1 /33.D3
Wc01
-X52
-X51
24
24 24
Reference DWG
4
Wc1 /37.D3
-J2 -X52
DATE
NO. DWG
REV.
B 3
-K204T
-S1 Wc01
/ 46.A1
Wc01
/44.E1
1
24 24
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
-XS
7 1
04 03 02 01 00
9
REV.
R5
/44.E2 A1
-K204T DS/ES SWITCH INCOMPLTE SET : 5sec
E
/ 43.E6
-XS
-K205 DS/ES SWITCH INCOMPLETE
2
2 8
10
A1
-K204 A2
E
(-)220V_F2
(-)220V_F2
3 4
1 /44.B4
6 5
8
F
1 R4 R5 7
2 R3 R6 8
/44.E2 /21.E1 /44.E3 /68.B5
1 R3 R5 7 13 21 31 43
2 /59.B5 R4 R6 8 /68.B6 14 22 32 44
DRAWING TITLE:
DS/ES INCOMPLETE CONDITION Drawing Number :
A B C
16316 01 EC
44
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14 ACTION
SHEET NO.
/ 46.F1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
MANUFACTURER/VENDER NAME
DRAWING NUMBER
ISSUED TO / FOR :
R6
DS/ES SWITCH INCOMPLETE FAIL
A2
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
-K205 7
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
CB CLOSE (LOCAL)
A
/ 21.C1
CB CLOSE (REMOTE)
CB INT.1
/ 21.C2
-XS
A
CB INT(CRP).1
11 -Q1
-XS
12
-X1 -J2
1 1
-Q2
-X2 -J2
A1
-S1
13
-KLR /47.E5
-X1 -Q1 -J3
14
29 5
-Q2
-X2 -J3
A3
-S2
-X9 -Q9 -J3
6 30
-S1
A03
-J3 -X2
5
6
6 30
2
-X9 -J2
1
2
DATE
NO. DWG
REV.
-J2 -X2
B
2 2
1
30
-S1 -X51 -Q51-J3
A01 25
-J2 -X9
1 A1
2 2
-S2 -J3
A03
-J2 -X1
Reference DWG
A01
A1
29
-S2 -J3 -X9
-Q9
-S2
A3
C
5 A3
A03
-J3 -X1
29
1 A1
A01
B
1
-X51 -X52 -Q52-J3
EMPLOYER / DEVELOPER
A01 2
C
26 25 1
PROJECT MANAGER.
A1
-S2 -J3 -X52
A01 2 26 SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
-XS
/ 21.C1
CB INT.2
E
50
/ 21.C2
CB INT(CRP).2
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
INTERLOCK (CB) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
45
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
BUS DS(-Q1) INTERLOCK / 44.B6
BUS DS(-Q2) INTERLOCK (+)220V_F2
(+)220V_F2
-Q2
-XS
13
-X2 -J3
37 13
-Q2
-X2 -J3
B1
B
-J3
A01 2
-X2
38
-X2
26
-XS
14
/47.E5
24
45 21 B5
-S2
C
=D03/44.E6
-J3 -X15
-X0 -Q0(A)-J4
121
22 46
-X0
-X51
37
-Q51-J3
13
122 3
B07
B1
-S2
-X0 -Q0(C)-J4
B01
-J3 -X51
14
-X52 -Q52-J3
37
D
25
-XS
16
4 123
-X11
-XS1
1
=D03/69.E2
-XS1
-J4 -X0
4 124
A01 2 26
-XS
-KLR /47.E5
A01 2
-X1
38
-X1
26
-XS
23
=D03 -X16 -Q16-J3
21
-X0 -J4 -Q0(A)
125
20
=D03 -X12 -Q12-J3
1
-S2 =D03/54.D4
-J3 -X12
A01 2 26
27
=D03 -X11 -Q11-J3
27 3
-S2
B8
-J4
-XS
=D03/52.D4
-XS
6
-J3 25
EMPLOYER / DEVELOPER
A02 4
-X11
28
-XS
28
-XS
29
=D03 -X12 -Q12-J3
27
C
22 46
-XS
24
-X51
39
-Q51-J3
15
-X0
126 5
-S2 B08
B2
-S2 B02
-J3 -X51
16
-X52 -Q52-J3
39
B1
=D03 -XS1
40
15 B2
-J4 -X0 -Q0(C) -J4
6 127
3 23
-KBL =D03/69.E2
-XS1
24 4
5
-XS B08
-J4 -X0
6 128
SUPERVISION CONSULTANT
3 A2
B8
-S2
PROJECT MANAGER.
26
-S2
D
=D03/54.D4
-J3
A02 4
-X12
28
-XS
30
04 03 02 01 00
-S2 B01
-XS
21
B02
-J3 -X52
14 38
REV.
A2
-S2
-Q0(B) -J4
25
DATE
NO. DWG
B
5
B08 B05
19
14
17
45
-S2 =D03/48.E6
Reference DWG
1
-S2
B5 34
25 A1
B8
-XS 2
-X1 -J3
-J3
-J3 -X16
-S2 -J3 -X52
-Q1
14
A1
-XS B07
33
13
-KBL
3
-S2
1
=D03
B7
38
13
=D03 -X11 -Q11-J3
-J3
4
-S2 -J4
18
-S2
B7 15
-XS
=D03/52.D4
-S2 -J4
13
B01
-J3
A1
B7
-Q0(B)-J4
-XS
37 B1
3
B07 B05
-X1 -J3
-S2
14
=D03 -X15 -Q15-J3
-Q1
-S2 B01
-J3
-KLR
1
22
A1
-S2
23
25
-XS
/ 47.A1
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
16 40
E
E
A1
-KL1
/ 44.E6
INTERLOCK (-Q1)
(-)220V_F2
A1
-KL2 A2
INTERLOCK (-Q2)
A2
(-)220V_F2
/ 47.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
13 23 33 44
F
14 24 34 43 /28.E3
13 23 33 44
14 24 34 43 /30.E3 ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
46
OF
92
REV NO.
04
D
INTERLOCK (BUS DS) Drawing Number :
PREPARED :
PK55-SD-EL-GS-14 Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
LINE DS(-Q9) INTERLOCK
WORK ES(-Q51, -Q52) INTERLOCK
LINE ES(-Q8) INTERLOCK
INTERLOCK RELEASE
(+)220V_F2
/ 46.A7
-XS
31
-X52
41
-X0
-Q52-J3
17
-J4 -Q0(A)
B3
-S2
B
-KLR /47.E5
44
-J3
18
-X52 -X51 -Q51-J3
42 41 17
18
-X51 -X8 -Q8 -J2
42 29 13
-X0 -J4 -Q0(B)
-X0 -J4 -Q0(C)
2 118
-X8
30
-XS
32
-XS
33
-KLR /47.E5
1
54
-X0
37
2 119 1
40 39 16
15 40 39
63
-J3 -X9
-KLR /47.E5
REV.
B
-S3 2
/75.C2
-K501 15 16 18
-K502 /66.E4
15
EMPLOYER / DEVELOPER
16 18
C
-K503 /66.E4
15
B02
-J3 -X9
15
-XS
38
-XS
39
-XS
40
PROJECT MANAGER.
40
+REMOTE VOLTAGE DEAD D
DATE
NO. DWG
1
38
RELEASE
64
Reference DWG
18
/75.B3
14
16 18
16
-S2
120
LOCAL
/66.E4
B2
2
-S11
B01
B02
-J3 -X2 -X9 -Q9 -J2
17
13 B1
15
B2
B06
-J4
-X9 -J3
-S2
-S2
-S2 14
53
-J3 -X1 -X2 -Q2 -J3
B6
B01
-Q9
37
B02
B06
-J4
16
-S2
B6
B1
-S2
39
-XS
B2
-S2
-J3
-X1 -J3
B06
-J4
B03
-J2
-Q1
34
B6
B3
-S2
C
1
-S2 B03
43
117
-XS
-XS
35
-XS
36
SUPERVISION CONSULTANT
-XS
41
-XS
42
-XS
43
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
DATE
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
E
A1
-KL9 INTERLOCK (-Q9)
(-)220V_F2
/ 46.F7
13 23 33 44
F
-KL51 INTERLOCK (-Q51,-Q52)
A2
14 24 34 43 /32.E3
13 23 33 44 34
A1
-KL8 A2
14 24 34 43 /34.E3 34 /36.E3
INTERLOCK (-Q8)
13 23 33 44
A1
A1
A2
14 24 34 43 /38.E3
INTERLOCK RELEASE
13 23 33 43 53 63 73 83
DS/ES MOTOR & INTERLOCK SUPPLY
A2
14 24 34 44 54 64 74 84
/45.B2 /46.C1 /46.C4 /47.B1 /47.B3 /47.B4 /59.B5 /68.B5
A2
14 12 24 22 34 32 44 42
11 /64.C4 21 31 /68.D5
B C
16316 01 EC
47
92
REV NO.
04
INTERLOCK (LINE DS/ES) PREPARED :
PK55-SD-EL-GS-14 A
OF
DRAWING TITLE:
Drawing Number : ACTION
SHEET NO.
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
41
MANUFACTURER/VENDER NAME
DRAWING NUMBER
E
-KD2
-KLR
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
- LOW STAGE 1 : UNDER 6.7 Bar - LOW STAGE 2 : UNDER 6.5 Bar A
A
SF6 GAS PRESSURE SF6 GAS PRESSURE SF6 GAS PRESSURE LOW STAGE 1 LOW STAGE 1 LOW STAGE 1 (G01-00A) (G01-00B) (G01-00C) SF6 GAS PRESSURE SF6 GAS PRESSURE SF6 GAS PRESSURE LOW STAGE 2 LOW STAGE 2 LOW STAGE 2 (G01-00A) (G01-00B) (G01-00C) (+)220V_F1
/ 18.E2
(+)220V_F1
/ 49.B1
Reference DWG
B
-XG
1
2
-XG
3
4
-XG
5
6
-W1
1
3
-W2
1
3
-W3
1
3
-G01_00A
-G01_00B 1
P
3 P
(6.7Bar) GAUGE -W1
-XG
2
(6.5Bar) GAUGE
2
4
61
64
3
1
P
(6.7Bar) GAUGE -W2
-XG
REV.
B
-G01_00C 1
P
4
DATE
NO. DWG
2
(6.5Bar) GAUGE
3
P
P
(6.7Bar) GAUGE
4
2
4
62
65
-W3
-XG
(6.5Bar) GAUGE
2
4
2
4
63
66 EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
-KG0.1 CB GAS PRESSURE STAGE 1
E
A2
A1
A1
A1
-KG0.2
-KG0.2A
-KG0.2B
CB GAS PRESSURE STAGE 2
A2 CB GAS LEAK STAGE2
A2 CB GAS LEAK STAGE2
A2
E
(-)220V_F1
/ 18.E2
(-)220V_F1 13 21 31 43 53 61 71 83
F
14 /60.B4 22 32 44 /69.B2 54 62 72 84
13 21 31 43 53 61 71 81
14 22 32 44 54 62 72 82
/61.B5 /21.D3 /21.D4 /69.E2 /21.D5
13 21 31 43 53 61 71 81
14 22 /22.D3 32 /22.D4 44 54 62 /22.D5 72 82
13 21 31 43 53 61 71 81
14 22 /23.D3 32 /23.D4 44 54 62 /23.D5 72 82
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
GAS MONITORING Drawing Number : ACTION A B C
16316 01 EC
SHEET NO.
48
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
MANUFACTURER/VENDER NAME
DRAWING NUMBER
/ 49.E1
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
- LOW STAGE 1 : UNDER 4.7 Bar - LOW STAGE 2 : UNDER 4.5 Bar A
A
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-01A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-01B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-01C)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-02A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-02B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-02C)
(+)220V_F1
/ 48.B6
(+)220V_F1 -XG
7
8
-W4
1
3
9
10
1
3
11
12
1
3
13
14
1
3
15
16
1
3
17
18
1
3
/ 50.B1
Reference DWG
-W5
-W6
-W7
-W8
-W9
DATE
NO. DWG
REV.
B
B
-G01_01A
-G01_01B 1
P
3 P
(4.7Bar) GAUGE -W4
-XG
2
(4.5Bar) GAUGE
-G01_01C 1
P
4
2
4
67
70
3 P
(4.7Bar) GAUGE -W5
2
-G01_02A 1
3
P
(4.5Bar) GAUGE
2
4
68
71
P
(4.7Bar) GAUGE
4
-W6
(4.5Bar) GAUGE
2
-G01_02B 1
P
P
(4.7Bar) GAUGE
4
2
4
69
72
3
-W7
2
(4.5Bar) GAUGE
-G01_02C 1
P
4
2
4
73
76
3
1
P
(4.7Bar) GAUGE -W8
2
3
P
(4.5Bar) GAUGE
(4.7Bar) GAUGE
4
2
4
74
77
P
-W9
(4.5Bar) GAUGE
2
4
2
4
75
78
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
A1
-KG1.1 01 GAS PRESSURE STAGE 1
E
A1
-KG1.2 01 GAS PRESSURE STAGE 2
A2
A1
-KG2.1 02 GAS PRESSURE STAGE 1
A2
-KG2.2 02 GAS PRESSURE STAGE 2
A2
A2
E
(-)220V_F1
/ 48.E6
(-)220V_F1 14 12 24 22 34 32 44 42
11 /60.B5 21 /69.B2 31 41
14 12 24 22 34 32 44 42
11 /61.B6 21 /69.E2 31 41
14 12 24 22 34 32 44 42
11 /60.B5 21 /69.B3 31 41
14 12 24 22 34 32 44 42
/ 50.E1
11 /62.B1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
21 /69.E3
DRAWING TITLE:
31
GAS MONITORING
41 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
49
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
- LOW STAGE 1 : UNDER 4.7 Bar - LOW STAGE 2 : UNDER 4.5 Bar A
A
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-03A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-03B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-03C)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-04A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-04B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-04C)
(+)220V_F1
/ 49.B6
(+)220V_F1 -XG
19
20
1
3
21
22
1
3
23
24
1
3
25
26
1
3
27
28
1
3
29
30
1
3
/ 51.B1
Reference DWG
-W10
-W11
-W12
-W13
-W14
-W15
DATE
NO. DWG
REV.
B
B
-G01_03A
-G01_03B 1
P
(4.7Bar) GAUGE -W10
-XG
3 P
2
(4.5Bar) GAUGE
-G01_03C 1
P
4
2
4
79
82
(4.7Bar) GAUGE -W11
3 P
2
-G01_04A 1
3
P
(4.5Bar) GAUGE
(4.7Bar) GAUGE
4
2
4
80
83
-W12
P
(4.5Bar) GAUGE
2
-G01_04B 1
P
(4.7Bar) GAUGE
4
2
4
81
84
-W13
3 P
2
(4.5Bar) GAUGE
-G01_04C 1
P
4
2
4
85
88
(4.7Bar) GAUGE -W14
3
1
P
2
3
P
(4.5Bar) GAUGE
(4.7Bar) GAUGE
4
2
4
86
89
-W15
P
(4.5Bar) GAUGE
2
4
2
4
87
90
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
A1
-KG3.1 03 GAS PRESSURE STAGE 1
E
A1
-KG3.2 03 GAS PRESSURE STAGE 2
A2
A1
-KG4.1 04 GAS PRESSURE STAGE 1
A2
-KG4.2 04 GAS PRESSURE STAGE 2
A2
A2
E
(-)220V_F1
/ 49.E6
(-)220V_F1 14 12 24 22 34 32 44 42
11 /60.B6 21 /69.B3 31 41
14 12 24 22 34 32 44 42
11 /62.B2 21 /69.E3 31 41
14 12 24 22 34 32 44 42
11 /61.B1 21 /69.B4 31 41
14 12 24 22 34 32 44 42
/ 51.E1
11 /62.B3
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
21 /69.E4
DRAWING TITLE:
31
GAS MONITORING
41 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
50
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
- LOW STAGE 1 : UNDER 4.7 Bar - LOW STAGE 2 : UNDER 4.5 Bar A
A
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-05A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-05B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-05C)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-06A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-06B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-06C)
(+)220V_F1
/ 50.B6
(+)220V_F1 -XG
31
32
1
3
33
34
1
3
35
36
1
3
37
38
1
3
39
40
1
3
41
42
1
3
/ 52.B1
Reference DWG
-W16
-W17
-W18
-W19
-W20
-W21
DATE
NO. DWG
REV.
B
B
-G01_05A
-G01_05B 1
P
(4.7Bar) GAUGE -W16
-XG
3 P
2
(4.5Bar) GAUGE
-G01_05C 1
P
4
2
4
91
94
(4.7Bar) GAUGE -W17
3 P
2
-G01_06A 1
3
P
(4.5Bar) GAUGE
(4.7Bar) GAUGE
4
2
4
92
95
-W18
P
(4.5Bar) GAUGE
2
-G01_06B 1
P
(4.7Bar) GAUGE
4
2
4
93
96
-W19
3 P
2
(4.5Bar) GAUGE
-G01_06C 1
P
4
2
4
97
100
(4.7Bar) GAUGE -W20
3
1
P
2
3
P
(4.5Bar) GAUGE
(4.7Bar) GAUGE
4
2
4
98
101
-W21
P
(4.5Bar) GAUGE
2
4
2
4
99
102
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
A1
-KG5.1 05 GAS PRESSURE STAGE 1
E
A1
-KG5.2 05 GAS PRESSURE STAGE 2
A2
A1
-KG6.1 06 GAS PRESSURE STAGE 1
A2
-KG6.2 06 GAS PRESSURE STAGE 2
A2
A2
E
(-)220V_F1
/ 50.E6
(-)220V_F1 14 12 24 22 34 32 44 42
11 /61.B2 21 /69.B4 31 41
14 12 24 22 34 32 44 42
11 /62.B3 21 /69.E4 31 41
14 12 24 22 34 32 44 42
11 /61.B3 21 /69.B4 31 41
14 12 24 22 34 32 44 42
/ 52.E1
11 /62.B4
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
21 /69.E4
DRAWING TITLE:
31
GAS MONITORING
41 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
51
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
- LOW STAGE 1 : UNDER 4.7 Bar - LOW STAGE 2 : UNDER 4.5 Bar A
A
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-07A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-07B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-07C)
SF6 GAS PRESSURE LOW STAGE 1,2 (G07-08A)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-08B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-08C)
(+)220V_F1
/ 51.B6
-XG
(+)220V_F1 43
44
1
3
45
46
1
3
47
48
1
3
49
50
1
3
51
52
1
3
53
54
1
3
/ 53.B1
Reference DWG
-W22
-W23
-W24
-W25
-W26
-W27
DATE
NO. DWG
REV.
B
B
-G01_07A
-G01_07B 1
3
P
(4.7Bar) GAUGE -W22
-XG
P
(4.5Bar) GAUGE
2
-G01_07C 1
3
P
4
2
4
103
106
(4.7Bar) GAUGE -W23
P
2
(4.5Bar) GAUGE
-G01_08A 1
3
P
(4.7Bar) GAUGE
4
2
4
104
107
-W24
P
(4.5Bar) GAUGE
2
-G01_08B 1
3
P
(4.7Bar) GAUGE
4
2
4
105
108
-W25
P
2
(4.5Bar) GAUGE
-G01_08C 1
3
P
4
2
4
109
112
(4.7Bar) GAUGE -W26
1
P
2
3
P
(4.5Bar) GAUGE
(4.7Bar) GAUGE
4
2
4
110
113
-W27
P
(4.5Bar) GAUGE
2
4
2
4
111
114
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
A1
-KG7.1 07 GAS PRESSURE STAGE 1
E
A1
-KG7.2 07 GAS PRESSURE STAGE 2
A2
A1
-KG8.1 08 GAS PRESSURE STAGE 1
A2
-KG8.2 08 GAS PRESSURE STAGE 2
A2
(-)220V_F1
/ 51.E6
A2
E
(-)220V_F1 14 12 24 22 34 32 44 42
11 /61.B3 21 /69.B5 31 41
14 12 24 22 34 32 44 42
11 /62.B5 21 /69.E5 31 41
14 12 24 22 34 32 44 42
11 /61.B4 21 /69.B5 31 41
14 12 24 22 34 32 44 42
/ 53.E1
11 /62.B5 21 /69.E5
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
31
GAS MONITORING
41 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
52
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
- LOW STAGE 1 : UNDER 4.7 Bar - LOW STAGE 2 : UNDER 4.5 Bar
A
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-09A) / 52.B6
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-09B)
SF6 GAS PRESSURE LOW STAGE 1,2 (G01-09C)
(+)220V_F1
(+)220V_F1 -XG -W28
B
55
56
1
3
-G01_09A 3
P
-W28
-XG
58
1
3
-W30
-G01_09B 1
(4.7Bar) GAUGE
-W29
57
P
2
(4.5Bar) GAUGE
2
4
115
118
(4.7Bar) GAUGE -W29
59
60
1
3
/ 54.B1
Reference DWG
DATE
NO. DWG
REV.
B
-G01_09C 1
3
P
4
A
1
P
2
(4.5Bar) GAUGE
3
P
(4.7Bar) GAUGE
4
2
4
116
119
-W30
P
(4.5Bar) GAUGE
2
4
2
4
117
120 EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
A1
-KG9.1 E
09 GAS PRESSURE STAGE 1
/ 52.E6
-KG9.2 09 GAS PRESSURE STAGE 2
A2
A2
E
(-)220V_F1
(-)220V_F1 14 12 24 22 34 32 44 42
11 /61.B5 21 /69.B6 31 41
14 12 24 22 34 32 44 42
/ 54.E1
11 /62.B6
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
21 /69.E6
DRAWING TITLE:
31
GAS MONITORING
41 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
53
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
CB(-Q0)
BUS DS(-Q2)
LINE DS(-Q9)
WORK ES(-Q51)
(+)220V_F1
/ 53.B6
(+)220V_F1 -X0 -Q0(A)-J3
1
B
BUS DS(-Q1)
69 1
101
-J3
A2
17
-Q1
B2
A02
-J3 -XS
-X0 -Q0(B)-J3
51
3
-X1 -J2
13 13
-Q2
2 70 1
A02
-J2
18 102
-J3
A2
3 3
-X2 -J2
A2
13 13
-Q9
-X1
4 4
-X1
A02
-J2
14
-X2
14
3 3
-J2
A2
13
-X51
17
-Q51-J2
B2
4 4
-X2
A02
-J2
14
-X9
14
3
-J2
13 13
Reference DWG
DATE
NO. DWG
REV.
B2
B
-S1
B02
-J2
3 -X51 A2
-S1
B02
-J2
-X9 -J2
B2
-S1
B02
-J3
-X2 -J2
B2
-S1
2
/75.D2
3 A2
-S2
-S4 CLOSE
-X1 -J2
/ 55.B1
4
B02
-J2
4
A02
-J2
18
-X51
14
4
B02
-J2
4 -X51
14 14
17 B2
-S2 A02
-J3 -X0 -Q0(C)-J3
2
B02
-J3
71 1
103
-J3
A2
C
18 EMPLOYER / DEVELOPER
17 B2
C
-S2 A02
-J3 -X0
2
B02
-J3
72
18 PROJECT MANAGER.
104
SUPERVISION CONSULTANT
D
D
(+)220V_F1_1/ 55.D1 -XS
52 13
23
33
43
53
63
73
83
-K11 /54.E1
13
23
14
24
04 03 02 01 00
-K11.1 14
24
34
44
54
64
84 /54.E2
74
A1
A1
-K11 LAMP TEST
E
-LQ0
-K11.1 LAMP TEST
A2
HK-DSPI-GR-220V/S
A2
X2
X1 X0
-LQ1 HK-DSPI-GR-220V/R
X2
X1 X0
-LQ2 HK-DSPI-GR-220V/R
X2
X1 X0
-LQ9 HK-DSPI-GR-220V/R
X2
X1 X0
-LQ51 HK-DSPI-GR-220V/R
X2
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
GREEN
RED
GREEN
RED
GREEN
RED
GREEN
RED
RED
GREEN
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
X1 X0
E
/ 53.E6
(-)220V_F1 13 23 33 43 53 63 73 83
F
14 24 34 44 54 64 74 84
/54.D2 /54.D3 /54.D3 /54.D4 /54.D4 /54.D5 /54.D5 /54.D5
-XS 13 23 33 43 53 63 73 83
14 24 34 44 54 64 74 84
53
(-)220V_F1
/54.D6 /54.D6 /55.D2 /55.D2 /55.D3 /55.D3 /56.D2
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
POSITION INDICATOR Drawing Number : ACTION A B C
16316 01 EC
SHEET NO.
54
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
MANUFACTURER/VENDER NAME
DRAWING NUMBER
/ 55.E1
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
WORK ES(-Q52) / 54.B7
LINE ES(-Q8)
(+)220V_F1
(+)220V_F1 -X52 -Q52-J2
3 -X52
13
-J2
13
3 A2
B
-Q8
-X8 -J1
B2
3 9
-X8 -J1
A2
-S1
/ 58.B1
9 15
Reference DWG
DATE
NO. DWG
REV.
B2
B
-S1 A02
-J2 -X52
4
B02
-J2
4 -X52
A02
-J1
14
-X8
14
10 4
B02
-J1 -X8
16 10
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D / 54.D7
D
(+)220V_F1_1 33
43
53
63 04 03 02 01 00
-K11.1 /54.E2
34
44
54
64
-LQ52 HK-DSPI-GR-220V/R
E
X2
X1 X0
-LQ8 HK-DSPI-GR-220V/R
X2
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
GREEN
RED
RED
GREEN
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
X1 X0
E
/ 54.E7
(-)220V_F1
(-)220V_F1
/ 58.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
POSITION INDICATOR Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
55
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
LIGHTING DOOR RIGHT DOOR LEFT
HEATER CONTROL
CB(-Q0)
A220V_F1
/ 20.E1
-XH
A220V_F1
-XH
1
2 13
33
-KHTS
-KHTS
/56.D3
/56.D3
/56.D3
14
24
Reference DWG
DATE
NO. DWG
REV.
B
34
NC NO COM
NC NO
23
-KHTS B
-DS1
/ 57.A1
-DS2 COM
X1
-S5
OFF MANUAL
AUTO
COM
-TH
Θ
SET : 5°C
COM
10
-Q0(B)
-JA
NC
-XH
9
-Q0(A)
Θ
-HTS SET : 80%
ON
X2
-XH
1
-XH
11
-JA
1
-Q0(C)
-JA
1
EMPLOYER / DEVELOPER
C
1
-HT -XH
-XH
3
-S5
1
3
/75.E5
2
4 /75.E5
/26.B6 AC220V HEATER MECHANISM
4
-S5
-JA -XH
73
1
-HT 2
2
12
/26.C6 AC220V HEATER MECHANISM
-JA -XH
C
1
-HT 2
2
13
/26.E6 AC220V HEATER MECHANISM
-JA -XH
2 PROJECT MANAGER.
2
14
SUPERVISION CONSULTANT
-K11.1 /54.E2
D
1
74
-XH
5
D
1 1
-IL1
-IL2
10W
10W 2
-HT AC220V, 100W 2
2
A1
A1
-KHTS
-KHTS1
HEATER OPERATING
HEATER A2 OPERATING
04 03 02 01 00
A2
REV.
-XH
8
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
N220V_F1
/ 20.E2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
N220V_F1
/ 57.E1
E
E
13 23 33 43 53 63 73 83
F
14 24 34 44 54 64 74 84
/56.B5 /56.B5 /56.B6 /57.B1 /57.B2 /57.B2 /57.B3 /57.B3
13 23 33 43
14 /57.B4 24 34 44
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
HEATER CONTROL Drawing Number : ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
56
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
BUS DS -Q1
BUS DS -Q2
LINE DS -Q9
WORK ES -Q51
WORK ES -Q52
LINE ES -Q8
A220V_F1
/ 56.A6
A220V_F1
43
53
-KHTS
B
/56.D3
/56.D3
44
-XH
-XH
21
-Q1
-KHTS
-XH
22
1
73
-KHTS 64
/56.D3
-XH
23
-Q9
-JA
1
/56.D3
54
-Q2
-JA
63
-KHTS
74
1
/56.D3
-XH
24
-Q51
-JA
83
-KHTS
1
13
Reference DWG
DATE
NO. DWG
REV.
-KHTS1 84
/56.D4
25
-Q52
-JA
/ 58.B1
B
14
-XH
26
-JA
1
-Q8
-JA
1
EMPLOYER / DEVELOPER
C
1
1
-HT
-HT
-HT
/29.B5 AC220V MECHANISM /29.B5
/31.B6 AC220V HEATER MECHANISM /31.B6
/33.B5 AC220V MECHANISM /33.B5
2
-JA
-JA
2
-XH
-XH
15
2
2
16
1
1
-JA -XH
-HT 2
2
17
/35.B5 AC220V HEATER MECHANISM /35.B5
-JA -XH
1
-HT 2
2
18
/37.B6 AC220V HEATER MECHANISM /37.B6
-JA -XH
1
C
-HT 2
2
19
/39.B5 AC220V HEATER MECHANISM /39.B5
-JA -XH
2 PROJECT MANAGER.
2
20
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
N220V_F1
/ 56.E6
N220V_F1
/ 58.E1
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
HEATER CONTROL Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
57
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
(+)220V_F1
/ 55.B6
(+)220V_F1
/ 65.A3
A220V_F1
/ 57.A6
Reference DWG
DATE
NO. DWG
REV.
B
B
-XD
19
-XA
13
-H1 1+
2L EMPLOYER / DEVELOPER
SUPPLY 2 INPUT FAILURE ALARM
SIGNAL SUPPLY FAILURE
R1
R2
FC
2N
D
20
-XA
14
ANN1.1
-XS
-XD
COMMON ALARM
PROJECT MANAGER.
ALARM HORN A
ALARM HORN B
N
S1R
S1RC
44
45
64.C5 64.D5
-XS
S2R
S2RC
46
47
ANN1.2
1-
SUPPLY 1 INPUT FAILURE ALARM
ANN1.2
N
L
ANN1.1
L
SUPPLY 2 INPUT
C
SUPPLY 1 INPUT
C
-XS
A
B
48
49
GP
HNA
HNB SUPERVISION CONSULTANT
FG
D
1
-PE 04 03 02 01 00
64.C2 64.D2
REV.
A1
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-KA1 HEATER & ANN.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
A2
E
(-)220V_F1
/ 55.E6
E
(-)220V_F1
/ 65.B3
N220V_F1
/ 57.E6
14 12 24 22 34 32 44 42
11 /64.C1 21 /68.D2
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
31
ANNUNCIATOR (H1)
41 Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
58
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
CB MOTOR LONG RUN AND STOP
CB MOTOR OVER LOAD AND STOP
CB MOTOR SPRING UNCHARGED/LOCK
DS/ES MOTOR RUNNING TIME EXCEEDED
POLE DISCREPANCY
DS/ES SWITCHING INCOMPLETE
INTERLOCK BY-PASS ON
AC SUPPLY MCB TRIP/OFF
-XA1
Reference DWG
52
DATE
NO. DWG
REV.
B
B 43
13
-K103 /24.E5
-K49 /24.E4
44
43
13
-K47A
-K104 /24.E6
14
/22.E6
14
43
-K47B 44
/23.E5
1
13 /43.E6
-KLR
-K204
-K203 44
73
/44.E4
14
/47.E5
2
AC_MCB
74
64.B2
AC_MCB 64.B2
EMPLOYER / DEVELOPER
C
-XA1 -H1
-XA1
1
1C
-XA1
2
11
-XA1
3
22
-XA1
4
51
-XA1
33
5
-XA1
44
6
-XA1
5C
-XA1
7
51
-XA1
8
62
-XA1
9
73
10
C
84 PROJECT MANAGER.
-CH1
-CH2
(YELLOW) RESPONSE TIME : 5ms
-CH3
(YELLOW) RESPONSE TIME : 5ms
-CH4
(YELLOW) RESPONSE TIME : 5ms
-CH5
(YELLOW) RESPONSE TIME : 5ms
-CH6
(YELLOW) RESPONSE TIME : 5ms
-CH7
(YELLOW) RESPONSE TIME : 5ms
-CH8
(YELLOW) RESPONSE TIME : 5ms
(YELLOW) RESPONSE TIME : 5ms
SUPERVISION CONSULTANT
D
D
1R1
1RC
2R2
2RC
3R3
3RC
4R4
4RC
5R1
5RC
6R2
6RC
7R3
7RC
8R4
8RC
04 03 02 01 00
REV.
-XA2
1
2
-XA2
3
-XA2
4
-XA2
5
-XA2
6
-XA2
7
-XA2
8
-XA2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
9
E
E
+SPARE
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
ANNUNCIATOR (H1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
59
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
DC SUPPLY MCB TRIP/OFF
-XA1
AC SUPPLY FAIL
-XA1
53
220VDC SUPPLY 1 FAIL
-XA1
54
220VDC SUPPLY 2 FAIL
-XA1
55
G01-00 GAS LOW 1 (ALARM)
G01-01 GAS LOW 1 (ALARM)
G01-02 GAS LOW 1 (ALARM)
G01-03 GAS LOW 1 (ALARM)
56 Reference DWG
B
DC_MCB
AC
DC_1
DC_2
64.B4
64.E1
64.E3
64.E6
13 /48.E3
-XA1
AC
DC_1
DC_2
64.B4
64.E2
64.E4
64.E6
-XA1
11
-XA1
12
-XA1
13
-XA1
14
15
REV.
B 12 14
-KG0.1
DC_MCB
DATE
NO. DWG
-XA1
16
-XA1
12 14
-KG1.1 /49.E3
14
-XA1
17
12 14
-KG2.1 /49.E5
11
-XA1
18
-KG3.1 /50.E3
11
-XA1
19
11
20
EMPLOYER / DEVELOPER
C
C -H1
9C
91
102
113
124
13C
131
142
153
164 PROJECT MANAGER.
-CH9
-CH10
(YELLOW) RESPONSE TIME : 5ms
-CH11
(YELLOW) RESPONSE TIME : 5ms
-CH12
(YELLOW) RESPONSE TIME : 5ms
-CH13
(YELLOW) RESPONSE TIME : 5ms
-CH14
(YELLOW) RESPONSE TIME : 5sec
-CH15
(YELLOW) RESPONSE TIME : 5sec
-CH16
(YELLOW) RESPONSE TIME : 5sec
(YELLOW) RESPONSE TIME : 5sec
SUPERVISION CONSULTANT
D
D
9R1
9RC
10R2 10RC
11R3 11RC
12R4 12RC
13R1 13RC
14R2 14RC
15R3 15RC
16R4 16RC
04 03 02 01 00
REV.
-XA2
10
11
-XA2
12
-XA2
13
-XA2
14
-XA2
15
-XA2
16
-XA2
17
-XA2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
18
E
E
+SPARE
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
ANNUNCIATOR (H1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
60
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
G01-04 GAS LOW 1 (ALARM)
G01-05 GAS LOW 1 (ALARM)
G01-06 GAS LOW 1 (ALARM)
G01-07 GAS LOW 1 (ALARM)
G01-08 GAS LOW 1 (ALARM)
G01-09 GAS LOW 1 (ALARM)
G01-00 GAS LOW 2 (LOCKOUT)
G01-01 GAS LOW 2
Reference DWG
DATE
NO. DWG
REV.
B
B 12 14
12 14
-KG4.1 /50.E5
12 14
-KG5.1 /51.E3
11
12 14
-KG6.1 /51.E5
11
12 14
-KG7.1 /52.E3
11
-KG8.1 /52.E6
11
13
12 14 /53.E4
11
12 14
-KG0.2
-KG9.1
/48.E4
11
-KG1.2 /49.E3
14
11
EMPLOYER / DEVELOPER
C
-XA1
-XA1
21
-H1
17C
-XA1
22
171
-XA1
23
182
-XA1
24
193
25
-XA1
204
26
-XA1
21C
-XA1
27
211
-XA1
28
222
-XA1
29
233
30
C
244 PROJECT MANAGER.
-CH17
-CH18
(YELLOW) RESPONSE TIME : 5sec
-CH19
(YELLOW) RESPONSE TIME : 5sec
-CH20
(YELLOW) RESPONSE TIME : 5sec
-CH21
(YELLOW) RESPONSE TIME : 5sec
-CH22
(YELLOW) RESPONSE TIME : 5sec
-CH23
(YELLOW) RESPONSE TIME : 5sec
-CH24
(YELLOW) RESPONSE TIME : 5sec
(YELLOW) RESPONSE TIME : 5sec
SUPERVISION CONSULTANT
D
D
17R1 17RC
18R2 18RC
19R3 19RC
20R4 20RC
21R1 21RC
22R2 22RC
23R3 23RC
24R4 24RC
04 03 02 01 00
REV.
-XA2
19
20
-XA2
21
-XA2
22
-XA2
23
-XA2
24
-XA2
25
-XA2
26
-XA2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
27
E
E
+SPARE
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
ANNUNCIATOR (H1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
61
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
G01-02 GAS LOW 2
G01-03 GAS LOW 2
G01-04 GAS LOW 2
G01-05 GAS LOW 2
G01-06 GAS LOW 2
G01-07 GAS LOW 2
G01-08 GAS LOW 2
G01-09 GAS LOW 2
Reference DWG
DATE
NO. DWG
REV.
B
B 12 14
12 14
-KG2.2 /49.E6
-XA1
-XA1
31
12 14
-KG3.2 /50.E3
11
-XA1
32
12 14
-KG4.2 /50.E6
11
-XA1
33
12 14
-KG5.2 /51.E3
11
-XA1
34
12 14
-KG6.2 /51.E6
11
35
-XA1
36
-XA1
12 14
-KG7.2 /52.E4
11
-XA1
37
12 14
-KG8.2 /52.E6
11
-XA1
38
-KG9.2 /53.E5
11
-XA1
39
11
EMPLOYER / DEVELOPER
40
C
C -H1
25C
251
262
273
284
29C
291
302
313
324 PROJECT MANAGER.
-CH25
-CH26
(YELLOW) RESPONSE TIME : 5sec
-CH27
(YELLOW) RESPONSE TIME : 5sec
-CH28
(YELLOW) RESPONSE TIME : 5sec
-CH29
(YELLOW) RESPONSE TIME : 5sec
-CH30
(YELLOW) RESPONSE TIME : 5sec
-CH31
(YELLOW) RESPONSE TIME : 5sec
-CH32
(YELLOW) RESPONSE TIME : 5sec
(YELLOW) RESPONSE TIME : 5sec
SUPERVISION CONSULTANT
D
D
25R1 25RC
26R2 26RC
27R3 27RC
28R4 28RC
29R1 29RC
30R2 30RC
31R3 31RC
32R4 32RC
04 03 02 01 00
REV.
-XA2
28
29
-XA2
30
-XA2
31
-XA2
32
-XA2
33
-XA2
34
-XA2
35
-XA2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
36
E
E
+SPARE
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
ANNUNCIATOR (H1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
62
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
SPARE
-XA1
SPARE
-XA1
58
SPARE
-XA1
59
SPARE
-XA1
60
SPARE
-XA1
61
SPARE
-XA1
62
SPARE
-XA1
63
SPARE
-XA1
64
Reference DWG
65
DATE
NO. DWG
REV.
B
B
EMPLOYER / DEVELOPER
-XA1
C -H1
-XA1
41
33C
-XA1
42
331
-XA1
43
342
-XA1
44
353
45
-XA1
364
46
-XA1
37C
-XA1
47
371
-XA1
48
382
-XA1
49
393
C
50
404 PROJECT MANAGER.
-CH33
-CH34
(YELLOW) RESPONSE TIME : 5ms
-CH35
(YELLOW) RESPONSE TIME : 5ms
-CH36
(YELLOW) RESPONSE TIME : 5ms
-CH37
(YELLOW) RESPONSE TIME : 5ms
-CH38
(YELLOW) RESPONSE TIME : 5ms
-CH39
(YELLOW) RESPONSE TIME : 5ms
-CH40
(YELLOW) RESPONSE TIME : 5ms
SUPERVISION CONSULTANT
(YELLOW) RESPONSE TIME : 5ms
D
D
33R1 33RC
34R2 34RC
35R3 35RC
36R4 36RC
37R1 37RC
38R2 38RC
39R3 39RC
40R4 40RC
04 03 02 01 00
REV.
-XA2
37
38
-XA2
39
-XA2
40
-XA2
41
-XA2
42
-XA2
43
-XA2
44
-XA2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
45
E
E
+SPARE
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
ANNUNCIATOR (H1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
63
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
AC SUPPLY MCB TRIP/OFF
59.B6 /
60.B1 /
AC_MCB
32 34
-F8A1 /20.C1
B 59.C6 /
DC SUPPLY MCB TRIP/OFF DC_MCB
32 34
32 34
-F8A2 /20.C4
31
-F8D1 /18.C2
31
32 34
-F8D2 31
32 34
-F8D3
/18.C3
31
32 34
-F8D4
/18.C4
31
/18.C6
32 34
-F8D5 /19.C2
31
32 34
-F8D6 31
/19.C4
32 34
-F8D7 31
Reference DWG
/19.C5
DATE
NO. DWG
REV.
31
B
AC_MCB 60.C1 /
DC_MCB
AC SUPPLY FAIL
220VDC SUPPLY 1 FAIL
220VDC SUPPLY 2 FAIL
EMPLOYER / DEVELOPER
C
C
ANN1.2
PROJECT MANAGER.
58.D3 12 14
-KA1 /58.E6
11
12 14
12 14
12 14
12 14
12 14
12 14
58.D3
-KA2
-KA3
-KA4
-KD1
-KD2
-KD3
ANN1.2
/20.D3
11 /20.D5
11 /20.D6
/66.B6
11 /47.E6
11 /21.E7
11
12 14
12 14
12 14
-KD4
-KD6
-KD7
/22.E7
11 /24.E7
11 /25.E7
11
11
12 14
ANN1.1
-KD5
58.D3
/23.E7
11
58.D3
ANN1.1 -XA1
D
66 -XA1
67
-XA1
76
-XA1
77
-XA1
-XA1
78
68
-XA1
69
-XA1
70
-XA1
71
-XA1
72
-XA1
73
-XA1
SUPERVISION CONSULTANT
-XA1
74
75
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
AC
AC
DC_1
DC_1
DC_2
DC_2
60.B2
60.C2
60.B3
60.C3
60.B3
60.C3
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
ANNUNCIATOR (H1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
64
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
/ 58.E6
/ 58.B6
(+)220V_F1 (-)220V_F1 (+)220V_F1
66.A2 /
Reference DWG
B
(-)220V_F1
-AM1
7
-AM2
8
16
C
7
DATE
NO. DWG
REV.
66.A2 /
B
-AM3
8
16
7
8
16
15
1
15
1
15
1
14
2
14
2
14
2
13
3
13
3
13
3
12
4
12
4
12
4
11
5
11
5
11
5
EMPLOYER / DEVELOPER
C
PROJECT MANAGER.
-TT1
D
IA_M
/ 71.E1
D
IB_M
/ 71.E2
8
9
12 F
11
14
13
16
15
18
17
G
IC_M
9
10 E
H
/ 71.E3
7
I
10
9
9
10
10
SUPERVISION CONSULTANT
D
04 03 02 01 00
6
6
REV.
6
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
IN_M
/ 71.E2
E
-XM
E 1
2
3
4
=CONTROL PNL
BKR. FAIL
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
METERING (1) Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
65
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
/ 65.B6
/ 65.B6
(+)220V_F1 (-)220V_F1
A1
-KD1 SIGNAL LAMP & ALARM SUPPLY
A2 Reference DWG
DATE
NO. DWG
REV.
=OUTDOOR CVT(AT OHTL)
B
B
-VM1 7
8
16 1
-XS
15
-XS
54
55
-XS
56
-XS
57
14 12 24 22 34 32 44 42
11 /64.C3 21 31 /68.D5 41
2 14 3 13
EMPLOYER / DEVELOPER
4
C
C
/76.B2
12
-S12
5
-TT1
11 2
9
/76.B3
5
/76.B3
10
9
/76.B3
3 6
14
13
18
17
/76.B3
D
1
2
A
PROJECT MANAGER.
/76.B3
10
1
B
SUPERVISION CONSULTANT
5
6
C
D
19 22
4
20
04 03 02 01 00
J
21
REV.
6
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
A1
~
-K501
A2
A1
~ UMAX : 150V UMIN : 30% A2 -K502 TIME : 1 Sec UMAX : 150V UMIN : 30% TIME : 1 Sec
E
E A1
~
-K503 A2
UMAX : 150V UMIN : 30% TIME : 1 Sec
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea 18 16
DRAWING TITLE:
15 /47.B4 18 16
18 16
F
METERING (2)
15 /47.C4 15 /47.C4
Drawing Number : ACTION
MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
66
OF
92
REV NO.
04
PREPARED :
PK55-SD-EL-GS-14
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
CB(-Q0.A)
CB(-Q0.B)
CB(-Q0.C)
BUS DS(-Q1)
BUS DS(-Q2)
A
A
-J2
-Q0(A)
-J2
5 A6
17 B7
13
-J2
17
B07
-J2
6
B7
14
47
-J2
48
-X0
15
5
-J2
17
A6
B7
B07
A06
B07
-J2
6
16
49
-J2
18
50
-X0
17
-J2
-Q1
5
-J2
15
A3
B3
A03
B03
-J2
-Q2
-S1
-S1 A06
18
-J2
-Q0(C)
-S1 A06
-X0
5 A6
-S1 -J2
-J2
-Q0(B)
-J2
6
18
51
-J2
18
52
-X1
5
-J2
5
15
A3
B3
A03
B03
-S1 -J2
6
6
15
-J2
16
16
-X2
5
-J2
6
6
15
16
16 Reference DWG
DATE
NO. DWG
REV.
B
B
=CRP
LINE ES(-Q9)
WORK ES(-Q51)
WORK ES(-Q52)
LINE ES(-Q8)
LOCAL
SELECTOR SWITCH REMOTE EMPLOYER / DEVELOPER
C
C
-J2
-Q9
5
-J2
A3
13 B3
5
-J2
15
B03
-J2
6
B3
6
15
-J2
16
-X51
5
5
-J2
A3
15
B03
-J2
6
6
15
-J2
16
-X52
5
11
-S1 -J2
6
15
-J1
16
16
-X8
5
17 B3
-S1 A03
B03
6
-J1
A3
B3
A03
16
-J1
-Q8
-S1 A03
14
-J2
-Q52
-S1 A03
-X9
5 A3
-S1 -J2
-J2
-Q51
B03
-J1
12
6
11
18
12
13
15
-S11
REMOTE
LOCAL
14/75.B3
PROJECT MANAGER.
16
/75.B3
-XR1
44
-XR1
45
-XR1
46
SUPERVISION CONSULTANT
D
D
=CRP 04 03 02 01 00
BUS DS(-Q1)
REV.
BUS DS(-Q2)
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-J2
-Q1
7
-J2
E
7
-J2
8
8
17
7
-J2 -X2
7
E B04
A04
18
17 B4
-S1
-S1
18
-J2
A4
B04
A04
-X1
-J2
-Q2
-S1
-S1 -J2
17 B4
A4
-J2
8
8
17
18
18
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
REMOTE =REMOTE
Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
67
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
CB MOTOR CB MOTOR CB MOTOR SPRING POLE LONG RUN & STOP OVER LOAD CHARGING DESCRIPANCY FAULTY
53
23
-K103 /24.E5
B
-XR1
47
-K49 /24.E4
54
48
23
-K104 24
/24.E6
49
24
DS/ES MOTOR RUNNING TIME EXCEEDED
53
-K47B
/22.E6
54 /23.E5
50
33
53
-K47A
DS/ES SWITCH INCOMPLTE
-XR1
51
/44.E2
34
52
-XR1
53
54
7
83
-K205
/43.E6
54
INTERLOCK RELEASE
7
-K203
-K204
-KLR 8
/47.E5
-XR1
55
56
A
DS/ES SWITCH INCOMPLETE FAIL
/44.E4
84
57
-XR1
-XR1
58
Reference DWG
DATE
NO. DWG
REV.
8
B
59
EMPLOYER / DEVELOPER
=CRP
C
C
PROJECT MANAGER.
AC SUPPLY FAIL
DC SUPPLY FAIL
SUPERVISION CONSULTANT
21
D
21
-F8A1
-F8A2
/20.C1
/20.C4
22
22 24
-KA1
22 /58.E6
22 24
22 24
-KA2
-KA3
-KA4
21/20.D3
21/20.D5
21/20.D6
21
22 24
21
21
21
21
21
21
-F8D1
-F8D2
-F8D3
-F8D4
-F8D5
-F8D6
-F8D7
/18.C2
/18.C3
/18.C4
/18.C6
/19.C2
/19.C4
/19.C5
21
22
22
22
22
22
22
-KD1
22/66.B6
32 34
32 34
32 34
32 34
32 34
32 34
32 34
-KD2
-KD3
-KD4
-KD5
-KD6
-KD7
/47.E6 31
/21.E7 31
/22.E7 31
/23.E7 31
31/24.E7
31 /25.E7
D 31
04 03 02 01 00
-XR1
60
-XR1
61
-XR1
62
-XR1
REV.
63
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
REMOTE E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
REMOTE Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
68
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
GAS6 GAS PRESSURE LOW STAGE 1
43
-KG0.1
B
/48.E3
-XR1
64
22 24
-KG1.1 44
/49.E3
65
22 24
-KG2.1 21
/49.E5
66
22 24
-KG3.1 21
/50.E3
67
22 24
-KG4.1 21
/50.E5
68
22 24
-KG5.1 21
/51.E3
69
22 24
-KG6.1 21
/51.E5
70
22 24
-KG7.1 21
/52.E3
71
22 24
-KG8.1 21
/52.E6
72
Reference DWG
22 24
DATE
NO. DWG
REV.
-KG9.1 21
/53.E4
73
B 21
74
EMPLOYER / DEVELOPER
C
=CRP
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
GAS6 GAS PRESSURE LOW STAGE 2 D
D
04 03 02 01 00
43
-KG0.2 /48.E4
22 24
-KG1.2 44
/49.E3
22 24
-KG2.2 21
/49.E6
22 24
-KG3.2 21
/50.E3
22 24
-KG4.2 21
/50.E6
22 24
-KG5.2 21
/51.E3
22 24
-KG6.2 21
/51.E6
22 24
-KG7.2 21
/52.E4
22 24
-KG8.2 21
/52.E6
22 24
REV.
-KG9.2 21
/53.E5
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
21
E
-XR1
E 75
76
77
78
79
80
81
82
83
84
85
=CRP
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
REMOTE Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
69
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
T1-C1
T1-C2
CLASS : 5P30, 60-30VA
CLASS : 5P30, 60-30VA
TAP S1-S3 S1-S2
RATIO 1600A/1A 800A/1A
TAP S1-S3 S1-S2
-T1(C1)
RATIO 1600A/1A 800A/1A
-T1(C2) Reference DWG
P1 B
P1
P2
A
AΦ S1
CB SIDE
S2
S3
S1
P1
S2
S3
P1
P2
P2
B
BΦ S1
CB SIDE
S2
S3
S1
P1
S2
S3
P1
P2
P2
C
CΦ S1
CB SIDE
S2
DATE
NO. DWG
REV.
P2
S3
S1
S2
S3
B / 71.B1
/ 71.B1
/ 71.C1
EMPLOYER / DEVELOPER
C
-CTB1(A)
-CTB1(B)
1
-W1
-XC1
2
3
1
1
2
3
1
2
3
-W2
-XC1
-CTB1(C) 2
3
1
1
2
3
4
5
6
-W3
-XC1
-CTB1(A) 2
3
4
1
2
3
7
8
9
-W1
-XC1
-CTB1(B) 5
6
4
4
5
6
10
11
12
-W2
-XC1
C
-CTB1(C) 5
6
4
4
5
6
13
14
15
-W3
-XC1
5
6
4
5
6
16
17
18
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D 1
2
-XC2
-XC2
-E
-E
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
=BUSBAR PROT.PANEL MAIN ZONE1
DRAWING TITLE:
=BUSBAR PROT.PANEL MAIN ZONE2
CURRENT TRANSFORMER Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
70
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
T1-C3
T1-C4
CLASS : 0.2FS5, 30-15VA
CLASS : 5P30, 60-30VA
TAP S1-S3 S1-S2
RATIO 1600A/1A 800A/1A
TAP S1-S3 S1-S2
-T1(C3)
RATIO 1600A/1A 800A/1A
-T1(C4) Reference DWG
P1 B / 70.B6
/ 70.B6
/ 70.C6
P1
P2
A
A S1
S2
S3
S1
P1
B
S2
S3
P1
P2
S1
S2
S3
S1
P1
C
P2 S2
B
S3
P1
P2
S1
S2
DATE
NO. DWG
REV.
P2
S3
P2
S1
S2
C
S3
B / 72.B2
/ 72.B2
/ 72.C2
EMPLOYER / DEVELOPER
C
-CTB1(A) 7
-W4
-XC1
-CTB1(B) 8
9
7
1
2
3
19
20
21
-W5
-XC1
-CTB1(C) 8
9
7
1
2
3
22
23
24
-W6
-XC1
-CTB1(A) 8
9
10
1
2
3
25
26
27
-W4
-XC1
D
11
-CTB1(B) 12
10
4
5
6
28
29
30
-W5
-XC1
C
-CTB1(C) 11
12
10
4
5
6
31
32
33
-W6
-XC1
11
12
4
5
6
PROJECT MANAGER.
34
35
36
SUPERVISION CONSULTANT
3
D
4
-XC2
-XC2
-E
-E
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
IA_M IN_M
IB_M
IC_M
65.D1
65.D1
65.E1
65.E1
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
CURRENT TRANSFORMER
METERING
Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
71
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
T1-C5
A
A
CLASS : 5P30, 60-30VA TAP S1-S3 S1-S2
RATIO 1600A/1A 800A/1A
-T1(C5) P1 B
/ 71.B6
/ 71.B6
/ 71.C6
Reference DWG
P2
DATE
NO. DWG
REV.
AΦ
A S1
S2
S3
B
LINE SIDE P1
B
S1
P2 S2
BΦ
S3
LINE SIDE P1
C
P2
S1
S2
CΦ
S3
LINE SIDE EMPLOYER / DEVELOPER
-CTB1(A)
C
13
-W7
-XC1
14
-CTB1(B) 15
13
1
2
3
37
38
39
-W8
-XC1
-CTB1(C) 14
15
13
1
2
3
40
41
42
-W9
-XC1
C 14
15
1
2
3
43
44
45
PROJECT MANAGER.
SUPERVISION CONSULTANT
5
D
D
-XC2 -E
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
=RCP
DRAWING TITLE:
CURRENT TRANSFORMER Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
72
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
CLOSE
OPEN
CLOSE
OPEN
1
3
5
7
9
2
4
6
8
10 12
/23.B1
CB -Q0 OPEN/CLOSE
CLOSE
YSDNC3305-64RP20R
OPEN
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-PISTOL, COLOR-RED
/21.B1
A
/22.B1
A
OPEN
CLOSE
1 3 5 7
9 11
OPEN
11
-SQ0
CLOSE 2 4 6 8 10 12 Reference DWG
DATE
NO. DWG
REV.
CLOSE
3
5
7
OPEN
CLOSE
BUS DS -Q1 OPEN/CLOSE
2
4
6
1 3 5 7 OPEN
EMPLOYER / DEVELOPER
-SQ1 /28.B2
C
1
/28.B2
YSDNC3205-64RE20B
OPEN
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
CLOSE
B
OPEN
B
CLOSE
8
C
2 4 6 8
CLOSE
OPEN
CLOSE
YSDNC3205-64RE20B
1
3
5
7
2
4
6
8
/30.B2
D
OPEN
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
/30.B2
PROJECT MANAGER.
SUPERVISION CONSULTANT OPEN
CLOSE
-SQ2
BUS DS -Q2 OPEN/CLOSE
1 3 5 7
D
OPEN CLOSE 2 4 6 8 04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CLOSE
OPEN
CLOSE
LINE DS -Q9 OPEN/CLOSE
1
3
5
7
2
4
6
8
/32.B2
YSDNC3205-64RE20B
OPEN
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
E
/32.B2
CONTRACTOR: CONSORTIUM( KN / HHI )
-SQ9
E
OPEN
CLOSE
1 3 5 7 OPEN CLOSE 2 4 6 8
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
SWITCH Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
73
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
CLOSE
OPEN
CLOSE
/34.B2
CLOSE
OPEN
CLOSE
8
1
3
5
7
2
4
6
8
/36.B2
6
/34.B2
4
1 3 5 7 OPEN
Reference DWG
DATE
NO. DWG
REV.
CLOSE
B
2 4 6 8
EMPLOYER / DEVELOPER OPEN
CLOSE
1 3 5 7
C
OPEN
-SQ52
WORK ES -Q52 OPEN/CLOSE
CLOSE 2 4 6 8
PROJECT MANAGER.
CLOSE
OPEN
CLOSE
1
3
5
7
2
4
6
8
/38.B2
SUPERVISION CONSULTANT
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
LINE ES -Q8 OPEN/CLOSE
2
OPEN
C
YSDNC3205-64RE20B
7
/36.B2
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
D
5
-SQ51
WORK ES -Q51 OPEN/CLOSE
YSDNC3205-64RE20B
3
OPEN
B
1
/38.B2
YSDNC3205-64RE20B
OPEN
SELECTOR SWITCH PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
CLOSE
A
OPEN
A
-SQ8
D OPEN
CLOSE
1 3 5 7 OPEN 04 03 02 01 00
CLOSE 2 4 6 8
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
SWITCH Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
74
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
7
9
REMOTE
LOCAL
REMOTE
LOCAL
REMOTE
LOCAL
REMOTE
LOCAL
REMOTE
LOCAL
REMOTE (Key removable position)
11 13 15 17 19 21 23 25 27 29 31
LOCAL
DATE
NO. DWG
REV.
B
(Key removable position)
LOCK
RELEASE
1
2
3
4
CB MOTOR OPERATION
1
3
LOCK
LOCK
RELEASE
USE
INTERLOCK
KGS-C2M2
5
7
-S1 2
4
6
8
LOCK LOCK
USE
USE
1
2
3
4
5
6
7
8
EMPLOYER / DEVELOPER
C
/24.B1
4
/47.B5
2
SELECTOR SWITCH
MANUAL RETURN, 2NO 2NC
USE
/18.E5
-S3
/19.D2
/18.E4
3
/19.D2
/18.E3
INTERLOCK
1
10 12 14 16 18 20 22 24 26 28 30 32 /47.B5
8
/67.C6
6
/67.C5
4
/18.E3 KGK-J2R1A
Reference DWG
REMOTE 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32
RELEASE
KEY SWITCH
AUTO-RETURN, 1NO 1NC
INTERLOCK RELEASE
5
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 LOCAL
-S11 2
C
3
/18.E6
B
1
/18.E6
LOCAL - REMOTE SELECTOR
REMOTE
YSKDNC2801-79M20L
LOCAL
REMOTE
SELECTOR SWITCH WITH KEY MANUAL RETURN WITH KEY
REMOTE
A
LOCAL
A
LAMP TEST
-S4
CLOSE OPEN 1 3
/54.B1
2
4
KGF-CM2R 2 4
CB MOTOR LONG RUN RESET
RESET
3
SET
D
1
1
3
5
7
-S2 2
4
6
8
SET
RESET
SUPERVISION CONSULTANT
1
2
3
4
5
6
7
8
/24.B5
KGF-CM1B
RESET
SELF-RETURN, 2NO 2NC, COLOR-RED
OPEN
PUSH BUTTON SWITCH
SELF-RETURN, 1NO 1NC, COLOR-BLACK
CLOSE
PUSH BUTTON SWITCH
SET
PROJECT MANAGER.
D
04 03 02 01 00
REV.
OPEN
1
3
ISSUED TO / FOR :
CLOSE OPEN
X1
4
1
2
3
4
X1
X2
E
X2 /56.C3
2
/56.C3
-S5 /56.C3
HEATER TEST
CLOSE
MANUAL-RETURN, 1NO 1NC, YELLOW LED KGX-CMV21Y
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
CONTRACTOR: CONSORTIUM( KN / HHI )
PUSH BUTTON SWITCH WITH LED LAMP
E
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
SWITCH Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
75
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
9
SPARE
7
N
5
SPARE
B
3
C
SPARE
1
SPARE
B
B
SPARE
YSDNC7602-64MR20B OFF-AB-BC-CA-AN-BN-CN SELECTOR
A
SELECTOR SWITCH MANUAL RETURN, HANDLE-CHRYSANTHEMUM, COLOR-BLACK
C
A
SPARE
A
1 3 5 7 9 11 13 15 17 19 21 23 OFF
CA BC
11 13 15 17 19 21 23
Reference DWG
DATE
NO. DWG
REV.
AB
AN
B
BC
-S12 /66.D3
10 12 14 16 18 20 22 24 /66.D3
8
/66.D3
6
/66.D3
4
/66.D3
/66.C3
2
AB
BN
CA AN
OFF
CN
BN CN 2 4 6 8 10 12 14 16 18 20 22 24
EMPLOYER / DEVELOPER
C
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
SWITCH Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EC
SHEET NO.
76
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL
DIGITAL AC AMMETER
-AM1 B
DIGITAL AC AMMETER
-AM2
DIGITAL AC AMMETER
-AM3
-DS1
-DS2
MINIATURE CIRCUIT BREAKER
-F8D1
INDICATOR & ALARM
MINIATURE CIRCUIT BREAKER
-F8D2
DS/ES MOTOR & INTERLOCK
MINIATURE CIRCUIT BREAKER
-F8D3
CB CLOSE
MINIATURE CIRCUIT BREAKER
-F8D4
CB TRIP1
MINIATURE CIRCUIT BREAKER
-F8D5
CB TRIP2
MINIATURE CIRCUIT BREAKER
-F8D6
INDICATOR & ALARM
MINIATURE CIRCUIT BREAKER
-F8D7
INDICATOR & ALARM
THERMAL RELAY
-F49A
CB MOTOR OVERLOAD
THERMAL RELAY
-F49B
CB MOTOR OVERLOAD
E
THERMAL RELAY
-F49C
CB MOTOR OVERLOAD
ANNUNCIATOR
-H1
ANNUNCIATOR (1)
SPACER HEATER
-HT
LCC
HUMIDISTAT
-HTS
HUMIDITISTATE
SHEET NO
KYONGBO
KOREA
/65.B3
KYONGBO
KOREA
/65.B4
KYONGBO
KOREA
/65.B5
YONGSUNG
KOREA
/56.B1
YONGSUNG
KOREA
/56.B1
ABB
GERMANY
/20.C1
ABB
GERMANY
/20.C4
ABB
GERMANY
/18.C2
Reference DWG
DATE
NO. DWG
REV.
B
DM1T-AA21 SINGLE PHASE 1A, POWER 100-240VAC/DC, CLASS 0.2, OUTPUT 4-20MA, RS485
YSR1215GW-B
3-PH & 1-PH SOCKET OUTLET
ORIGIN
DM1T-AA21 SINGLE PHASE 1A, POWER 100-240VAC/DC, CLASS 0.2, OUTPUT 4-20MA, RS485
LIMIT SWITCH
MINIATURE CIRCUIT BREAKER
-F8A2
MANUFACTURER
DM1T-AA21 SINGLE PHASE 1A, POWER 100-240VAC/DC, CLASS 0.2, OUTPUT 4-20MA, RS485
YSR1215GW-B
HEATING & ANNUNCIATOR
C
MODEL NUMBER
LIMIT SWITCH
MINIATURE CIRCUIT BREAKER
-F8A1
D
DESCRIPTION
S202M-K6UC / S2C-H11L / S2C-H6R 2P, 6A, 10KA / 1NO 1NC / 1C
EMPLOYER / DEVELOPER
C
S203M-K32NA / S2C-H11L / S2C-H6R 3P+1N, 32A, 10KA / 1NO 1NC / 1C
S202M-K6UC / S2C-H11L / S2C-H6R 2P, 6A, 10KA / 1NO 1NC / 1C
PROJECT MANAGER.
S202M-K6UC / S2C-A2 / S2C-H11L / S2C-H6R 2P, 6A, 10KA / 1NO 1NC / 1C
ABB
GERMANY
/18.C3
ABB
GERMANY
/18.C4
ABB
GERMANY
/18.C6
ABB
GERMANY
/19.C2
ABB
GERMANY
/19.C4
ABB
GERMANY
/19.C5
S202M-K16UC / S2C-H11L / S2C-H6R 2P, 16A, 10KA / 1NO 1NC / 1C
S202M-K16UC / S2C-H11L / S2C-H6R 2P, 16A, 10KA / 1NO 1NC / 1C
SUPERVISION CONSULTANT
S202M-K16UC / S2C-H11L / S2C-H6R 2P, 16A, 10KA / 1NO 1NC / 1C
D
S202M-K16UC / S2C-H11L / S2C-H6R 2P, 16A, 10KA / 1NO 1NC / 1C
04 03 02 01 00
S202M-K16UC / S2C-H11L / S2C-H6R 2P, 16A, 10KA / 1NO 1NC / 1C
REV.
MT-32/2H5 4~6
LS
KOREA
/25.B2
LS
KOREA
/25.B3
LS
KOREA
/25.B5
RTK
United Kingdom
/58.C1
RARA
KOREA
/56.D3
RUN ELEC
KOREA
/56.C3
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
MT-32/2H5 4~6
MT-32/2H5 4~6
E
UC625-40YW-HH-024D-R-M3 40CHANNEL
RSHT 200 100W, 500Ω
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
RHC-80 HUMIDITY RANGE 20~80%
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
77
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL LED LAMP
-IL1
LCC
B
LED LAMP
-IL2
LCC
AUXILIARY RELAY
-K11
LAMP TEST
AUXILIARY RELAY
-K11.1
LAMP TEST
AUXILIARY RELAY
-K47A
POLE DISCREPANCY
AUXILIARY RELAY
-K47B
POLE DISCREPANCY
C
AUXILIARY RELAY
-K49
CB MOTOR OVER LOAD
MAGNETIC CONTACTOR
-K88MA
CB MOTOR OPERATION
MAGNETIC CONTACTOR
-K88MB
CB MOTOR OPERATION
MAGNETIC CONTACTOR
-K88MC
CB MOTOR OPERATION
AUXILIARY RELAY
-K101A D
DESCRIPTION
ANTI-PUMPING
AUXILIARY RELAY
-K101B
ANTI-PUMPING
AUXILIARY RELAY
-K101C
ANTI-PUMPING
AUXILIARY RELAY
-K102
CB MOTOR SPRING UNCHARGED
ON DELAY TIMER (A MODE)
-K102T
SPRING UNCHARGED
AUXILIARY RELAY
-K103
CB MOTOR LONG RUN
E
AUXILIARY RELAY
-K104
CB MOTOR SPRING CHARGING FAULTY
MAGNETIC CONTACTOR
-K201
DS/ES MOTOR OPERATING
AUXILIARY RELAY
-K202
DOUBLE INTERLOCKING
AUXILIARY RELAY
-K203
DS/ES MOTOR RUNNING EXCEEDED
MODEL NUMBER
MANUFACTURER
ORIGIN
SHEET NO
RUN ELEC
KOREA
/56.D1
RUN ELEC
KOREA
/56.D2
ABB
FRANCE
/54.E1
ABB
FRANCE
/54.E2
ABB
FRANCE
/22.E6
ABB
FRANCE
/23.E5
ABB
FRANCE
/24.E4
ABB
FRANCE
/24.E1
RLB-10WH AC220~240V, 50/60HZ
Reference DWG
DATE
NO. DWG
REV.
RLB-10WH AC220~240V, 50/60HZ
B
NF40E-13 / CA4-40N AC/DC 100~250V, 50/60HZ, 4NO / 4NO
NF40E-13 / CA4-40N AC/DC 100~250V, 50/60HZ, 4NO / 4NO
NF40E-13 / CA4-40N AC/DC 100~250V, 50/60HZ, 4NO / 4NO
NF40E-13 / CA4-40N AC/DC 100~250V, 50/60HZ, 4NO / 4NO
EMPLOYER / DEVELOPER
C
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
AF09-30-10-13 AC/DC 100~250V, 50/60HZ, 3NO 1NO
PROJECT MANAGER.
AF09-30-10-13 AC/DC 100~250V, 50/60HZ, 3NO 1NO
ABB
FRANCE
/24.E2
ABB
FRANCE
/24.E3
ABB
FRANCE
/21.E3
ABB
FRANCE
/21.E5
ABB
FRANCE
/21.E6
ABB
FRANCE
/24.E3
AF09-30-10-13 AC/DC 100~250V, 50/60HZ, 3NO 1NO
NF22E-13 AC/DC 100~250V, 50/60HZ, 2NO 2NC
SUPERVISION CONSULTANT
NF22E-13 AC/DC 100~250V, 50/60HZ, 2NO 2NC
D
NF22E-13 AC/DC 100~250V, 50/60HZ, 2NO 2NC
04 03 02 01 00
NF22E-13 / CA4-22N AC/DC 100~250V, 50/60HZ, 2NO 2NC / 2NO 2NC
REV.
AT8N / PG-08 AC 100-240V / DC 24-240V, 2 CHANGE OVER CONTACT
AUTONICS
KOREA
/24.E4
ABB
FRANCE
/24.E5
ABB
FRANCE
/24.E6
ABB
FRANCE
/43.E5
ABB
FRANCE
/43.E2
ABB
FRANCE
/43.E6
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
NF22E-13 / CA4-22N AC/DC 100~250V, 50/60HZ, 2NO 2NC / 2NO 2NC
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
E
AF09-22-00-13 / CA4-22E AC/DC 100~250V, 50/60HZ, 2NO 2NC / 2NO 2NC
NF22E-13 AC/DC 100~250V, 50/60HZ, 2NO 2NC
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
78
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL
ON DELAY TIMER (A MODE)
-K203T
DS/ES MOTOR RUNNING TIME EXCEEDED
B
MAGNETIC CONTACTOR
-K204
DS/ES SWITCH INCOMPLETE FAIL
ON DELAY TIMER (A MODE)
-K204T
DS/ES SWITCH INCOMPLTE
MAGNETIC CONTACTOR
-K205
DS/ES SWITCH INCOMPLETE
VOLTAGE CHECK RELAY
-K501
LINE VT (R PHASE) LIVE CONDITION
VOLTAGE CHECK RELAY
-K502
LINE VT (Y PHASE) LIVE CONDITION
C
VOLTAGE CHECK RELAY
-K503
LINE VT (B PHASE) LIVE CONDITION
CONTROL RELAY
-KA1
HEATER & ANN.
CONTROL RELAY
-KA2
SOCKET OUTLET CONTROL SUPPLY ALARM
CONTROL RELAY
-KA3
SOCKET OUTLET CONTROL SUPPLY ALARM
CONTROL RELAY
-KA4 D
DESCRIPTION
SOCKET OUTLET CONTROL SUPPLY ALARM
CONTROL RELAY
-KD1
SIGNAL LAMP & ALARM SUPPLY ALARM
CONTROL RELAY
-KD2
DS/ES MOTOR & INTERLOCK SUPPLY
CONTROL RELAY
-KD3
CB CLOSE POWER SUPPLY ALARM
CONTROL RELAY
-KD4
CB TRIP1 POWER SUPPLY ALARM
CONTROL RELAY
-KD5
CB TRIP2 POWER SUPPLY ALARM
E
CONTROL RELAY
-KD6
CB MOTOR CONTROL SUPPLY ALARM
CONTROL RELAY
-KD7
CB MOTOR POWER SUPPLY ALARM
AUXILIARY RELAY
-KG0.1
CB GAS PRESSURE STAGE 1
AUXILIARY RELAY
-KG0.2
CB GAS PRESSURE STAGE 2
MODEL NUMBER
MANUFACTURER
ORIGIN
SHEET NO
AT8N / PG-08 AC 100-240V / DC 24-240V, 2 CHANGE OVER CONTACT
AUTONICS
KOREA
/43.E2
ABB
FRANCE
/44.E4
AUTONICS
KOREA
/44.E1
ABB
FRANCE
/44.E2
ELKO
CZECH
/66.E4
ELKO
CZECH
/66.E4
ELKO
CZECH
/66.E4
ABB
POLAND
/58.E6
Reference DWG
DATE
NO. DWG
REV.
AF09-22-00-13 / CA4-22E AC/DC 100~250V, 50/60HZ, 2NO 2NC / 2NO 2NC
B
AT8N / PG-08 AC 100-240V / DC 24-240V, 2 CHANGE OVER CONTACT
AF09-22-00-13 AC/DC 100~250V, 50/60HZ, 2NO 2NC
HRN-37 AC24~150V, 1CHANGE OVER CONTACT
HRN-37 AC24~150V, 1CHANGE OVER CONTACT
EMPLOYER / DEVELOPER
C
HRN-37 AC24~150V, 1CHANGE OVER CONTACT
CR-M230AC4 AC 230V, 4 CHANGEOVER CONTACT
PROJECT MANAGER.
CR-M230AC4 AC 230V, 4 CHANGEOVER CONTACT
ABB
POLAND
/20.D3
ABB
POLAND
/20.D5
ABB
POLAND
/20.D6
ABB
POLAND
/66.B6
ABB
POLAND
/47.E6
ABB
POLAND
/21.E7
CR-M230AC4 AC 230V, 4 CHANGEOVER CONTACT
CR-M230AC4 AC 230V, 4 CHANGEOVER CONTACT
SUPERVISION CONSULTANT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
D
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
04 03 02 01 00
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
REV.
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
ABB
POLAND
/22.E7
ABB
POLAND
/23.E7
ABB
POLAND
/24.E7
ABB
POLAND
/25.E7
ABB
FRANCE
/48.E3
ABB
FRANCE
/48.E4
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
E
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
NF22E-13 / CA4-22N AC/DC 100~250V, 50/60HZ, 2NO 2NC / 2NO 2NC
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
NF22E-13 / CA4-13N AC/DC 100~250V, 50/60HZ, 2NO 2NC / 1NO 3NC
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
79
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL
AUXILIARY RELAY
-KG0.2A
CB GAS LEAK STAGE2
B
AUXILIARY RELAY
-KG0.2B
CB GAS LEAK STAGE2
CONTROL RELAY
-KG1.1
01 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG1.2
01 GAS PRESSURE STAGE 2
CONTROL RELAY
-KG2.1
02 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG2.2
02 GAS PRESSURE STAGE 2
C
CONTROL RELAY
-KG3.1
03 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG3.2
03 GAS PRESSURE STAGE 2
CONTROL RELAY
-KG4.1
04 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG4.2
04 GAS PRESSURE STAGE 2
CONTROL RELAY
-KG5.1 D
DESCRIPTION
05 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG5.2
05 GAS PRESSURE STAGE 2
CONTROL RELAY
-KG6.1
06 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG6.2
06 GAS PRESSURE STAGE 2
CONTROL RELAY
-KG7.1
07 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG7.2
07 GAS PRESSURE STAGE 2
E
CONTROL RELAY
-KG8.1
08 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG8.2
08 GAS PRESSURE STAGE 2
CONTROL RELAY
-KG9.1
09 GAS PRESSURE STAGE 1
CONTROL RELAY
-KG9.2
09 GAS PRESSURE STAGE 2
MODEL NUMBER
MANUFACTURER
ORIGIN
SHEET NO
NF22E-13 / CA4-13N AC/DC 100~250V, 50/60HZ, 2NO 2NC / 1NO 3NC
ABB
FRANCE
/48.E4
ABB
FRANCE
/48.E5
ABB
POLAND
/49.E3
ABB
POLAND
/49.E3
ABB
POLAND
/49.E5
ABB
POLAND
/49.E6
ABB
POLAND
/50.E3
ABB
POLAND
/50.E3
Reference DWG
DATE
NO. DWG
REV.
NF22E-13 / CA4-13N AC/DC 100~250V, 50/60HZ, 2NO 2NC / 1NO 3NC
B
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
EMPLOYER / DEVELOPER
C
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
PROJECT MANAGER.
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
ABB
POLAND
/50.E5
ABB
POLAND
/50.E6
ABB
POLAND
/51.E3
ABB
POLAND
/51.E3
ABB
POLAND
/51.E5
ABB
POLAND
/51.E6
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
SUPERVISION CONSULTANT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
D
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
04 03 02 01 00
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
REV.
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
ABB
POLAND
/52.E3
ABB
POLAND
/52.E4
ABB
POLAND
/52.E6
ABB
POLAND
/52.E6
ABB
POLAND
/53.E4
ABB
POLAND
/53.E5
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
E
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
CR-M220DC4 DC 220V, 4 CHANGEOVER CONTACT
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
80
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL
AUXILIARY RELAY
-KHTS
HEATER OPERATING
B
AUXILIARY RELAY
-KHTS1
HEATER OPERATING
AUXILIARY RELAY
-KL1
INTERLOCK (-Q1)
AUXILIARY RELAY
-KL2
INTERLOCK (-Q2)
AUXILIARY RELAY
-KL8
INTERLOCK (-Q8)
AUXILIARY RELAY
-KL9
INTERLOCK (-Q9)
C
AUXILIARY RELAY
-KL51
INTERLOCK (-Q51,-Q52)
AUXILIARY RELAY
-KLR
INTERLOCK RELEASE
LATCHED RELAY
-KQ0
CBMULTIPLY
LATCHED RELAY
-KQ0.1
CBMULTIPLY
MAGNETIC CONTACTOR
-KQ0C D
DESCRIPTION
CBCLOSE
MAGNETIC CONTACTOR
-KQ0T1
CBOPEN
MAGNETIC CONTACTOR
-KQ0T2
CBOPEN
LATCHED RELAY
-KQ1
BUS DSMULTIPLY
MAGNETIC CONTACTOR
-KQ1C
BUS DSCLOSE
MAGNETIC CONTACTOR
-KQ1T
BUS DSOPEN
E
LATCHED RELAY
-KQ2
BUS DSMULTIPLY
MAGNETIC CONTACTOR
-KQ2C
BUS DSCLOSE
MAGNETIC CONTACTOR
-KQ2T
BUS DSOPEN
LATCHED RELAY
-KQ8
LINE ESMULTIPLY
MODEL NUMBER
MANUFACTURER
ORIGIN
SHEET NO
NF40E-13 / CA4-40N AC/DC 100~250V, 50/60HZ, 4NO / 4NO
ABB
FRANCE
/56.D3
ABB
FRANCE
/56.D4
ABB
FRANCE
/46.E3
ABB
FRANCE
/46.E6
ABB
FRANCE
/47.E4
ABB
FRANCE
/47.E2
ABB
FRANCE
/47.E3
ABB
FRANCE
/47.E5
Reference DWG
DATE
NO. DWG
REV.
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
B
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
EMPLOYER / DEVELOPER
C
NF40E-13 AC/DC 100~250V, 50/60HZ, 4NO
NF40E-13 / CA4-40N AC/DC 100~250V, 50/60HZ, 4NO / 4NO
PROJECT MANAGER.
KDN-220DC 8 CHANGE OVER CONTACTS
NIEAF-SMITT
NETHERLANDS
/40.E3
NIEAF-SMITT
NETHERLANDS
/40.E4
ABB
FRANCE
/21.E1
ABB
FRANCE
/22.E1
ABB
FRANCE
/23.E1
NIEAF-SMITT
NETHERLANDS
/41.E2
KDN-220DC 8 CHANGE OVER CONTACTS
AF09-30-10-13 AC/DC 100~250V, 50/60HZ, 3NO 1NO
SUPERVISION CONSULTANT
AF09-30-10-13 AC/DC 100~250V, 50/60HZ, 3NO 1NO
D
AF09-30-10-13 AC/DC 100~250V, 50/60HZ, 3NO 1NO
04 03 02 01 00
KDN-220DC 8 CHANGE OVER CONTACTS
REV.
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
ABB
FRANCE
/28.C2
ABB
FRANCE
/28.C2
NIEAF-SMITT
NETHERLANDS
/41.E3
ABB
FRANCE
/30.C2
ABB
FRANCE
/30.C2
NIEAF-SMITT
NETHERLANDS
/42.E5
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
KDN-220DC 8 CHANGE OVER CONTACTS
E
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
KDN-220DC 8 CHANGE OVER CONTACTS
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
81
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL
MAGNETIC CONTACTOR
-KQ8C
LINE ESCLOSE
B
MAGNETIC CONTACTOR
-KQ8T
LINE ESOPEN
LATCHED RELAY
-KQ9
LINE DSMULTIPLY
MAGNETIC CONTACTOR
-KQ9C
LINE DSCLOSE
MAGNETIC CONTACTOR
-KQ9T
LINE DSOPEN
LATCHED RELAY
-KQ51
WORK ESMULTIPLY
C
MAGNETIC CONTACTOR
-KQ51C
WORK ESCLOSE
MAGNETIC CONTACTOR
-KQ51T
WORK ESOPEN
LATCHED RELAY
-KQ52
WORK ESMULTIPLY
MAGNETIC CONTACTOR
-KQ52C
WORK ESCLOSE
MAGNETIC CONTACTOR
-KQ52T D
DESCRIPTION
WORK ESOPEN
SEMAPHORE INDICATOR
-LQ0
MODEL NUMBER
SEMAPHORE INDICATOR
SEMAPHORE INDICATOR
SEMAPHORE INDICATOR
SEMAPHORE INDICATOR
SEMAPHORE INDICATOR
-LQ51
SEMAPHORE INDICATOR
SELECTOR SWITCH CB MOTOR OPERATION
PUSH BUTTON SWITCH
-S2
CB MOTOR LONG RUN RESET
FRANCE
/38.C2
NIEAF-SMITT
NETHERLANDS
/41.E5
ABB
FRANCE
/32.C2
ABB
FRANCE
/32.C2
NIEAF-SMITT
NETHERLANDS
/42.E2
ABB
FRANCE
/34.C2
ABB
FRANCE
/34.C2
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
C
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
PROJECT MANAGER.
KDN-220DC 8 CHANGE OVER CONTACTS
NIEAF-SMITT
NETHERLANDS
/42.E3
ABB
FRANCE
/36.C2
ABB
FRANCE
/36.C2
HANKUK INSTRUMENT
KOREA
/54.E3
HANKUK INSTRUMENT
KOREA
/54.E4
HANKUK INSTRUMENT
KOREA
/54.E4
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
SUPERVISION CONSULTANT
HK-DSPI-GR-220V/S
D
HK-DSPI-GR-220V/R 04 03 02 01 00
HK-DSPI-GR-220V/R
REV.
HK-DSPI-GR-220V/R HANKUK INSTRUMENT
KOREA
/55.E3
HANKUK INSTRUMENT
KOREA
/54.E5
HANKUK INSTRUMENT
KOREA
/54.E6
HANKUK INSTRUMENT
KOREA
/55.E2
KG AUTO
KOREA
/75.C5
KG AUTO
KOREA
/75.D5
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
HK-DSPI-GR-220V/R
HK-DSPI-GR-220V/R
E
HK-DSPI-GR-220V/R LED TYPE WITH 2 COLOR-RED/GREEN, ROUND
-S1
ABB
Reference DWG
KDN-220DC 8 CHANGE OVER CONTACTS
LED TYPE WITH 2 COLOR-RED/GREEN, ROUND
-LQ52
/38.C2
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
LED TYPE WITH 2 COLOR-RED/GREEN, ROUND
E
FRANCE
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
LED TYPE WITH 2 COLOR-RED/GREEN, ROUND
-LQ9
ABB
KDN-220DC 8 CHANGE OVER CONTACTS
LED TYPE WITH 2 COLOR-RED/GREEN, ROUND
-LQ8
SHEET NO
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
LED TYPE WITH 2 COLOR-RED/GREEN, ROUND
-LQ2
ORIGIN
AF09-30-10-13 / CA4-22M AC/DC 100~250V, 50/60HZ, 3NO 1NO / 2NO 2NC
LED TYPE WITH 2 COLOR-RED/GREEN, SQURE
-LQ1
MANUFACTURER
KGS-C2M2 MANUAL RETURN, 2NO 2NC
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
KGF-CM2R SELF-RETURN, 2NO 2NC, COLOR-RED
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
82
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST DEVICE NAME
SYMBOL KEY SWITCH
-S3
INTERLOCK RELEASE
B
PUSH BUTTON SWITCH
-S4
LAMP TEST
PUSH BUTTON SWITCH WITH LED LAMP
-S5
HEATER TEST
SELECTOR SWITCH WITH KEY
-S11
LOCAL - REMOTE SELECTOR
SELECTOR SWITCH
-S12
OFF-AB-BC-CA-AN-BN-CN SELECTOR
OUTLET
-SOCKET(1-PH)
MODEL NUMBER
OUTLET
-SOCKET(3-PH)
SELECTOR SWITCH
-SQ1
LINE ESOPEN/CLOSE
SELECTOR SWITCH
-SQ9
LINE DSOPEN/CLOSE
SELECTOR SWITCH
-SQ51
WORK ESOPEN/CLOSE
SELECTOR SWITCH
-SQ52
WORK ESOPEN/CLOSE
ON DELAY TIMER (A MODE)
-T47A
POLE DESCREPANCY
ON DELAY TIMER (A MODE)
-T48B
POLE DESCREPANCY
E
ON DELAY TIMER (A MODE)
-T88
MOTOR LONG RUN
THERMALSTAT
-TH
THERMAL STATE
TEST SWITCH
-TT1
TEST SWITCH
DIGITAL AC VOLTMETER
-VM1
MULTI FUNCTION METER
/75.C2
KG AUTO
KOREA
/75.D2
KG AUTO
KOREA
/75.E5
YONGSUNG
KOREA
/75.B2
YONG SUNG
KOREA
/76.B2
LEGRAND
FRANCE
/20.D4
LEGRAND
FRANCE
/20.D5
YONGSUNG
KOREA
/73.B3
Reference DWG
DATE
NO. DWG
REV.
B
AC_OUTLET(1Ph) EMPLOYER / DEVELOPER
C
AC_OUTLET(3Ph)
YSDNC3305-64RP20R
YSDNC3205-64RE20B
SELECTOR SWITCH
-SQ8
KOREA
YSDNC7602-64MR20B MANUAL RETURN, HANDLE-CHRYSANTHEMUM, COLOR-BLACK
SELECTOR SWITCH
BUS DSOPEN/CLOSE
KG AUTO
YSKDNC2801-79M20L MANUAL RETURN WITH KEY
CBOPEN/CLOSE / CBOPEN / CLOSE
SELECTOR SWITCH
-SQ2
SHEET NO
KGX-CMV21Y MANUAL-RETURN, 1NO 1NC, YELLOW LED
PULLING TURN & AUTOMATIC RETURN, HANDLE-PISTOL, COLOR-RED
BUS DSOPEN/CLOSE
ORIGIN
KGF-CM1B SELF-RETURN, 1NO 1NC, COLOR-BLACK
OUTLET (380Vac, 32A, - 5 552 89)
-SQ0
MANUFACTURER
KGK-J2R1A AUTO-RETURN, 1NO 1NC
OUTLET (220Vac, 16A, - 772 13)
C
D
DESCRIPTION
PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
PROJECT MANAGER.
YONGSUNG
KOREA
/73.C3
YONGSUNG
KOREA
/73.D3
YONGSUNG
KOREA
/74.D3
YONGSUNG
KOREA
/73.E3
YONGSUNG
KOREA
/74.B3
YONGSUNG
KOREA
/74.C3
YSDNC3205-64RE20B PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
YSDNC3205-64RE20B PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
SUPERVISION CONSULTANT
YSDNC3205-64RE20B PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
D
YSDNC3205-64RE20B PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
04 03 02 01 00
YSDNC3205-64RE20B PULLING TURN & AUTOMATIC RETURN, HANDLE-EGG
REV.
AT8N / PG-08 AC 100-240V / DC 24-240V, 2 CHANGE OVER CONTACT
AUTONICS
KOREA
/22.E6
AUTONICS
KOREA
/23.E6
AUTONICS
KOREA
/24.E6
RUN ELEC
KOREA
/56.B3
ABB
USA
/65.C2
KYONGBO
KOREA
/66.B2
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
AT8N / PG-08 AC 100-240V / DC 24-240V, 2 CHANGE OVER CONTACT
AT8N / PG-08 AC 100-240V / DC 24-240V, 2 CHANGE OVER CONTACT
E
RT-50HT -10~50°C 1NO+1NC
FT-1 10POLE 10 POLE, P-P-P-C-C-C-C-C-C-P
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea
DM1T-AV22 SINGLE PHASE AC150V, POWER 100-240VAC/DC, CLASS 0.2, OUTPUT 4-20MA, RS485
DRAWING TITLE:
PARTS LIST FOR LCC Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
83
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM
A3-S-PART-MECH-005
DEVICE NAME
-Q0(A)
DESIGNATION
-52C
-HT B -J1
-J2
-J3
-J4
-JA
C
-LS1
-LS2
-LS3
-M1
-OUTLET_A
SOLENOID COIL CB -Q0(A) CLOSING COIL
HEATER CB -Q0(A)
CONNECTOR CB -Q0(A)
CONNECTOR CB -Q0(A)
CONNECTOR CB -Q0(A)
CONNECTOR -Q0(A)
CONNECTOR CB -Q0(A)
LIMIT SWITCH
LIMIT SWITCH
LIMIT SWITCH
UNIVERSAL MOTOR CB -Q0(A)
OUTLET
SPECIFICATION
MANUFACTURER
ORIGIN
4CG4382-D
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
DC 220V, 60 Ohm
MODEL NUMBER
Reference DWG
60W 2KΩ
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
3CG4457-002
DMK
KOREA
DC220V, 800W
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
OUTLET (220Vac, 16A, - 772 13)
AC_OUTLET(1Ph)
LEGRAND
FRANCE
D
D -S1
-S2
-S13
-52T1
-52T2
E
-Q0(B)
-52C
-HT
AUXILIARY SWITCH CB -Q0(A)
AUXILIARY SWITCH CB -Q0(A)
SELECTOR SWITCH AC-DC SELECTOR FOR CB MOTOR OPERATION
SOLENOID COIL CB -Q0(A) TRIP COIL 1
SOLENOID COIL CB -Q0(A) TRIP COIL 2
SOLENOID COIL CB -Q0(B) CLOSING COIL
HEATER CB -Q0(B)
AUXILIARY SWITCH 8NO 9NC
2CG1180-010
YONG SUNG
KOREA
AUXILIARY SWITCH 8NO 9NC
2CG1180-010
YONG SUNG
KOREA
YSDNC2201-69MO20B
YONGSUNG
KOREA
MANUAL RETURN, HANDLE-COMPASS, COLOR-BLACK
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
DC 220V, 60 Ohm
4CG4382-D
HYUNDAI
KOREA
DC 220V, 60 Ohm
4CG4382-D
HYUNDAI
KOREA E
DC 220V, 60 Ohm
60W 2KΩ
4CG4382-D
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
84
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM
A3-S-PART-MECH-005
DEVICE NAME
-Q0(B)
DESIGNATION
-J1
-J2 B -J3
-J4
-JA
-LS1
-LS2
C
-LS3
-M1
-OUTLET_B
-S1
-S2 D -S13
-52T1
-52T2
-Q0(C)
-52C
-HT
E
-J1
-J2
CONNECTOR CB -Q0(B)
CONNECTOR CB -Q0(B)
CONNECTOR CB -Q0(B)
CONNECTOR -Q0(B)
CONNECTOR CB -Q0(B)
LIMIT SWITCH
LIMIT SWITCH
LIMIT SWITCH
UNIVERSAL MOTOR CB -Q0(B)
OUTLET
AUXILIARY SWITCH CB -Q0(B)
AUXILIARY SWITCH CB -Q0(B)
SELECTOR SWITCH AC-DC SELECTOR FOR CB MOTOR OPERATION
SOLENOID COIL CB -Q0(B) TRIP COIL 1
SOLENOID COIL CB -Q0(B) TRIP COIL 2
SOLENOID COIL CB -Q0(C) CLOSING COIL
HEATER CB -Q0(C)
CONNECTOR CB -Q0(C)
CONNECTOR CB -Q0(C)
SPECIFICATION
MODEL NUMBER
MANUFACTURER
ORIGIN
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
3CG4457-002
DMK
KOREA
AC_OUTLET(1Ph)
LEGRAND
FRANCE
2CG1180-010
YONG SUNG
KOREA
DC220V, 800W
OUTLET (220Vac, 16A, - 772 13)
AUXILIARY SWITCH 8NO 9NC
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
AUXILIARY SWITCH 8NO 9NC
2CG1180-010
YONG SUNG
KOREA D
MANUAL RETURN, HANDLE-COMPASS, COLOR-BLACK
YSDNC2201-69MO20B
YONGSUNG
KOREA
DC 220V, 60 Ohm
4CG4382-D
HYUNDAI
KOREA
DC 220V, 60 Ohm
4CG4382-D
HYUNDAI
KOREA
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
DC 220V, 60 Ohm
60W 2KΩ
4CG4382-D
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA E
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
85
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM
A3-S-PART-MECH-005
DEVICE NAME
-Q0(C)
DESIGNATION
-J3
-J4 B -JA
-LS1
-LS2
-LS3
-M1
C
-OUTLET_C
-S1
-S2
-S13
-52T1 D -52T2
-Q1
-DS1
-DS2
-HT
-ILM
E
-J1
-J2
CONNECTOR CB -Q0(C)
CONNECTOR -Q0(C)
CONNECTOR CB -Q0(C)
LIMIT SWITCH
LIMIT SWITCH
LIMIT SWITCH
UNIVERSAL MOTOR CB -Q0(C)
OUTLET
AUXILIARY SWITCH CB -Q0(C)
AUXILIARY SWITCH CB -Q0(C)
SELECTOR SWITCH AC-DC SELECTOR FOR CB MOTOR OPERATION
SOLENOID COIL CB -Q0(C) TRIP COIL 1
SOLENOID COIL CB -Q0(C) TRIP COIL 2
LIMIT SWITCH BUS DS -Q1 DOOR OPEN
LIMIT SWITCH BUS DS -Q1 DOOR OPEN
HEATER BUS DS -Q1
SOLENOID COIL BUS DS -Q1 SOLENODE
CONNECTOR BUS DS -Q1
CONNECTOR BUS DS -Q1
SPECIFICATION
MODEL NUMBER
MANUFACTURER
ORIGIN
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
Reference DWG
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
3CG4457-002
DMK
KOREA
AC_OUTLET(1Ph)
LEGRAND
FRANCE
AUXILIARY SWITCH 8NO 9NC
2CG1180-010
YONG SUNG
KOREA
AUXILIARY SWITCH 8NO 9NC
2CG1180-010
YONG SUNG
KOREA
YSDNC2201-69MO20B
YONGSUNG
KOREA
DC220V, 800W
OUTLET (220Vac, 16A, - 772 13)
MANUAL RETURN, HANDLE-COMPASS, COLOR-BLACK DC 220V, 60 Ohm
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
4CG4382-D
HYUNDAI
KOREA D
4CG4382-D
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
DC 220V, 60 Ohm
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
60W 2KΩ
DC220V, 6.2W, 9200 Ohm
SPR 319-1
RARA
KOREA
4CS1161-002
HYUNDAI
KOREA E
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
86
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM DEVICE NAME
-Q1
DESIGNATION
-JA
-LSA B -LSB
-M
-PS
-S1
-S2
C
-Q2
-DS1
-DS2
-HT
-ILM
-J1 D -J2
-JA
-LSA
-LSB
-M
E
A3-S-PART-MECH-005
-PS
-S1
CONNECTOR BUS DS -Q1
LIMIT SWITCH BUS DS -Q1
LIMIT SWITCH BUS DS -Q1
DC MOTOR BUS DS -Q1
KEY SWITCH BUS DS -Q1
AUXILIARY SWITCH BUS DS -Q1
AUXILIARY SWITCH BUS DS -Q1
LIMIT SWITCH BUS DS -Q2 DOOR SWITCH
LIMIT SWITCH BUS DS -Q2 DOOR SWITCH
HEATER BUS DS -Q2
SOLENOID COIL BUS DS -Q2
CONNECTOR BUS DS -Q2
CONNECTOR BUS DS -Q2
CONNECTOR BUS DS -Q2
LIMIT SWITCH BUS DS -Q1
LIMIT SWITCH BUS DS -Q1
DC MOTOR BUS DS -Q2
KEY SWITCH BUS DS -Q1
AUXILIARY SWITCH BUS DS -Q2
SPECIFICATION
MODEL NUMBER
MANUFACTURER
ORIGIN
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
HSK-10
HYUNDAI
KOREA
3CS9676-002
DMK
KOREA
KH-302K-2105
KUN HEUNG
KOREA
3CS3686-401
HYUNDAI
KOREA
Reference DWG
10A
DC220V, 350W
MANUAL RETURN, 1NO 1NC
AUXILIARY SWITCH 5NO 6NC 1WC
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
3CS3686-601
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA
4CS1161-002
HYUNDAI
KOREA
AUXILIARY SWITCH 6NO 6NC
60W 2KΩ
DC220V, 6.2W, 9200 Ohm
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
M40
WIELAND-24P-M40
WIELAND
GERMANY D
M40
WIELAND-24P-M40
WIELAND
GERMANY
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
10A
DC220V, 350W
HSK-10
HYUNDAI
KOREA
3CS9676-002
DMK
KOREA E
MANUAL RETURN, 1NO 1NC
AUXILIARY SWITCH 5NO 6NC 1WC
KH-302K-2105
KUN HEUNG
KOREA
3CS3686-401
HYUNDAI
KOREA 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
87
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM DEVICE NAME
B
DESIGNATION
-Q2
-S2
-Q8
-DS1
-HT
-ILM
-J1
-J2
-JA
C
-M
-PS
-S1
-S2
-Q9
-DS1
D -DS2
-HT
-ILM
-J1
-J2
E
A3-S-PART-MECH-005
AUXILIARY SWITCH BUS DS -Q2
LIMIT SWITCH LINE ES -Q8
HEATER LINE ES -Q8
SOLENOID COIL LINE ES -Q8
CONNECTOR LINE ES -Q8
CONNECTOR LINE ES -Q8
CONNECTOR LINE ES -Q8
DC MOTOR LINE ES -Q8
KEY SWITCH LINE ES -Q8
AUXILIARY SWITCH LINE ES -Q8
AUXILIARY SWITCH LINE ES -Q8
LIMIT SWITCH LINE DS -Q9
LIMIT SWITCH LINE DS -Q9
HEATER LINE DS -Q9
SOLENOID COIL LINE DS -Q9
CONNECTOR LINE DS -Q9
CONNECTOR
SPECIFICATION
MODEL NUMBER
MANUFACTURER
ORIGIN
AUXILIARY SWITCH 6NO 6NC
3CS3686-601
HYUNDAI
KOREA
HSK-10
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA
3CS1860-005
HYUNDAI
KOREA
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
Reference DWG
10A
60W 2KΩ
DC220V, 5.94W, 9200 Ohm
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
WIELAND-5P-M20
WIELAND
GERMANY
4CS1267-003
DMK
KOREA
MANUAL RETURN, 1NO 1NC
KH-302K-2105
KUN HEUNG
KOREA
AUXILIARY SWITCH 5NO 5NC
3CS3686-301
HYUNDAI
KOREA
AUXILIARY SWITCH 6NO 6NC
3CS3686-501
HYUNDAI
KOREA
M20
DC220V, 210W
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
10A
HSK-10
HYUNDAI
KOREA D
10A
60W 2KΩ
DC220V, 6.2W, 9200 Ohm
HSK-10
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA
4CS1161-002
HYUNDAI
KOREA
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY E
-J3
-JA
CONNECTOR LINE DS -Q9
CONNECTOR LINE DS -Q9
M40
WIELAND-24P-M40
WIELAND
GERMANY
M20
WIELAND-5P-M20
WIELAND
GERMANY 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
88
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM DEVICE NAME
-Q9
DESIGNATION
-LSA
-LSB B -M
-PS
-S1
-S2
-Q51
C
-DS1
-DS2
-HT
-ILM
-J1
-J2 D -J3
-JA
-LSA
-LSB
-M
E
A3-S-PART-MECH-005
-PS
-S1
LIMIT SWITCH BUS DS -Q1
LIMIT SWITCH BUS DS -Q1
DC MOTOR LINE DS -Q9
KEY SWITCH BUS DS -Q1
AUXILIARY SWITCH LINE DS -Q9
AUXILIARY SWITCH LINE DS -Q9
LIMIT SWITCH WORK ES -Q51
LIMIT SWITCH WORK ES -Q51
HEATER WORK ES -Q51
SOLENOID COIL WORK ES -Q51
CONNECTOR WORK ES -Q51
CONNECTOR WORK ES -Q51
CONNECTOR WORK ES -Q51
CONNECTOR WORK ES -Q51
LIMIT SWITCH BUS DS -Q1
LIMIT SWITCH BUS DS -Q1
DC MOTOR WORK ES -Q51
KEY SWITCH BUS DS -Q1
AUXILIARY SWITCH WORK ES -Q51
SPECIFICATION
MODEL NUMBER
MANUFACTURER
ORIGIN
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
3CS9676-002
DMK
KOREA
KH-302K-2105
KUN HEUNG
KOREA
AUXILIARY SWITCH 5NO 6NC 1WC
3CS3686-401
HYUNDAI
KOREA
AUXILIARY SWITCH 6NO 6NC
3CS3686-402
HYUNDAI
KOREA
Reference DWG
DC220V, 350W
MANUAL RETURN, 1NO 1NC
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA
4CS1161-002
HYUNDAI
KOREA
WIELAND-24P-M40
WIELAND
GERMANY
60W 2KΩ
DC220V, 6.2W, 9200 Ohm
M40
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
M40
WIELAND-24P-M40
WIELAND
GERMANY D
M40
WIELAND-24P-M40
WIELAND
GERMANY
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
10A
DC220V, 350W
HSK-10
HYUNDAI
KOREA
3CS9676-002
DMK
KOREA E
MANUAL RETURN, 1NO 1NC
AUXILIARY SWITCH 5NO 6NC 1WC
KH-302K-2105
KUN HEUNG
KOREA
3CS3686-401
HYUNDAI
KOREA 1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
89
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST MECHANISM DEVICE NAME
B
DESIGNATION
-Q51
-S2
-Q52
-DS1
-DS2
-HT
-ILM
-J1
-J2
C
A3-S-PART-MECH-005
-J3
-JA
-LSA
-LSB
-M D -PS
-S1
-S2
AUXILIARY SWITCH WORK ES -Q51
LIMIT SWITCH WORK ES -Q52
LIMIT SWITCH WORK ES -Q52
HEATER WORK ES -Q52
SOLENOID COIL WORK ES -Q52
CONNECTOR WORK ES -Q52
CONNECTOR WORK ES -Q52
CONNECTOR WORK ES -Q52
CONNECTOR WORK ES -Q52
LIMIT SWITCH BUS DS -Q1
LIMIT SWITCH BUS DS -Q1
DC MOTOR WORK ES -Q52
KEY SWITCH BUS DS -Q1
AUXILIARY SWITCH WORK ES -Q52
AUXILIARY SWITCH WORK ES -Q52
SPECIFICATION
MODEL NUMBER
MANUFACTURER
ORIGIN
AUXILIARY SWITCH 6NO 6NC
3CS3686-402
HYUNDAI
KOREA
HSK-10
HYUNDAI
KOREA
HSK-10
HYUNDAI
KOREA
SPR 319-1
RARA
KOREA
4CS1161-002
HYUNDAI
KOREA
WIELAND-24P-M40
WIELAND
GERMANY
Reference DWG
10A
10A
60W 2KΩ
DC220V, 6.2W, 9200 Ohm
M40
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
M40
WIELAND-24P-M40
WIELAND
GERMANY
M40
WIELAND-24P-M40
WIELAND
GERMANY
M20
WIELAND-5P-M20
WIELAND
GERMANY
10A
HSK-10
HYUNDAI
KOREA
10A
HSK-10
HYUNDAI
KOREA
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
DC220V, 350W
3CS9676-002
DMK
KOREA D
KH-302K-2105
KUN HEUNG
KOREA
AUXILIARY SWITCH 5NO 6NC 1WC
3CS3686-401
HYUNDAI
KOREA
AUXILIARY SWITCH 6NO 6NC
3CS3686-402
HYUNDAI
KOREA
MANUAL RETURN, 1NO 1NC
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR MECHANISM Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
90
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST FOR TERMINAL BLOCK DEVICE NAME
MODEL NUMBER
Manufacturer
ORIGIN
TERMINAL BLOCK FOR CB (-Q0)
UK 5 N
PHOENIX
GERMANY
-X0C(A)
TERMINAL BLOCK FOR CB (-Q0) A-PHASE CONTROL
UK 5 N
PHOENIX
GERMANY
-X0C(B)
TERMINAL BLOCK FOR CB (-Q0) B-PHASE CONTROL
UK 5 N
PHOENIX
GERMANY
-X0C(C)
TERMINAL BLOCK FOR CB (-Q0) C-PHASE CONTROL
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR BUS DS(-Q1)
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR BUS DS(-Q1) CONTROL
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR BUS DS(-Q2)
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR BUS DS(-Q2) CONTROL
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR LINE ES(-Q8)
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR LINE ES(-Q8) CONTROL
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR LINE DS(-Q9)
UK 5 N
PHOENIX
GERMANY
-X0
DESCRIPTION
Remarks
Reference DWG
B
-X1 -X1C
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
-X2
C
-X2C -X8 -X8C -X9
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
-X9C
TERMINAL BLOCK FOR LINE DS(-Q9) CONTROL
UK 5 N
PHOENIX
GERMANY
D
D
-X51 -X51C -X52
TERMINAL BLOCK FOR WORK ES(-Q51)
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR WORK ES(-Q51) CONTROL
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR WORK ES(-Q52)
UK 5 N
PHOENIX
GERMANY
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
-X52C -XA
E
TERMINAL BLOCK FOR WORK ES(-Q52) CONTROL
UK 5 N
PHOENIX
GERMANY
TERMINAL BLOCK FOR AC MAIN INPUT
UK 16 N
PHOENIX
CHINA E
-XA1
TERMINAL BLOCK FOR ANNUNCIATOR
UT 4-MT
PHOENIX
GERMANY
-XA2
TERMINAL BLOCK FOR ANNUNCIATOR
UT 4-MT
PHOENIX
GERMANY
-XAD
TERMINAL BLOCK FOR
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR TERMINAL BLOCK Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
91
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F
1
2
3
4
5
6
7
8
Project
A
A
PARTS LIST FOR TERMINAL BLOCK DEVICE NAME
DESCRIPTION
MODEL NUMBER
Manufacturer
ORIGIN
-XC1
TERMINAL BLOCK FOR CT
YSCT-03ACS
YONGSUNG
KOREA
-XC2
TERMINAL BLOCK FOR CT
USST 6-T
PHOENIX
POLAND
-XD
TERMINAL BLOCK FOR DC MAIN INPUT
UK 16 N
PHOENIX
CHINA
-XG
TERMINAL BLOCK FOR GAS GAUGE
UK 5 N
PHOENIX
GERMANY
-XH
TERMINAL BLOCK FOR HEATER CONTROL
UK 5 N
PHOENIX
GERMANY
-XM
TERMINAL BLOCK FOR CT
YSCT-04ACS
YONGSUNG
KOREA
-XR1
TERMINAL BLOCK FOR REMOTE
UK 5 N
PHOENIX
GERMANY
-XR2
TERMINAL BLOCK FOR PROTECTION TRIP
USST 10
PHOENIX
POLAND
TERMINAL BLOCK FOR INTERLOCK AND GENERAL
UK 5 N
PHOENIX
GERMANY
Remarks
Reference DWG
B
DATE
NO. DWG
REV.
B
EMPLOYER / DEVELOPER
C
-XS
C
PROJECT MANAGER.
SUPERVISION CONSULTANT
D
D
04 03 02 01 00
REV.
24.JAN.2018 10.AUG.2017 09.AUG.2017 19.JUN.2017 01.SEP.2016
DATE
REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT REVISED AS PER COMMENT FOR APPROVAL
ISSUED TO / FOR :
CONTRACTOR: CONSORTIUM( KN / HHI )
E
E
1000, Bangeojinsinhawn-doro, Dong-gu, Ulsan, Korea DRAWING TITLE:
PARTS LIST FOR TERMINAL BLOCK Drawing Number :
F
PREPARED :
PK55-SD-EL-GS-14 ACTION MANUFACTURER/VENDER NAME
A B C DRAWING NUMBER
16316 01 EE
SHEET NO.
92
OF
92
REV NO.
04
D
Project No.:
Scale :
CHECKED :
Plot Date:
APPROVED :
008006400 Sheet Size : Rev. :
A3
04
K.H.SONG
S.Y.JANG
01.SEP.2016
C.Y.HONG
F