C.D. :-CROSS DRAINAGE WORK SR.NO.& CODE No.
DESCRIPTION OF ITEMS
UNIT
RATES FOR 2006-2007 (in Rs.) Completed Labour
1 CD 1
Providing rubble filling of trap / granite / Cu.m. quartzite / gneiss stones in foundation including hand packing filling gravel / sand in the voids etc. complete. Spec.No.: CD.1/Page No.159
200.00
45.00
2 CD 3B
Providing and laying in situ cement concrete of Cu.m. 1:4:8 proportion with trap / granite / quartzite / gneiss metal in foundation including necessary compacting and curing complete. (Including plywood/ steel formwork) The C.M. 1:3 plaster is considered for rendering uneven and honeycombed surface only. Newly laid concrete shall be covered by gunny bag, plastic, tarpaulin etc. (Wooden centering/formwork will not be allowed).
1325.00
280.00
1900.00
290.00
Spec.No.: CD.3/Page No.160 3 CD 3A
Providing and laying in situ cement concrete of Cu.m. M-15 / 1:2:4 with trap / granite / quartzite / gneiss metal in face wall including plywood/ steel formwork and steel centering, compaction by vibrator, finishing uneven and honeycombed surface with C.M.1:3 of sufficient minimum thickness to give smooth and even surface, filling joints with bitumen, curing etc. complete. (Excluding cost of reinforcement.) The C.M. 1:3 plaster is considered for rendering uneven and honeycombed surface only. Newly laid concrete shall be covered by gunny bag, plastic, tarpaulin etc. (Wooden centering/formwork will not be allowed).
Spec.No.: CD.3/Page No.160/I.S.456 (2000)
214
SR.NO.& CODE No. 4 CD 4
DESCRIPTION OF ITEMS
UNIT
Providing trap / granite / quartzite / gneiss Sq.m. rubble stone paving of 23 cm thickness on a bed of 15 cm. thick cement concrete of 1:4:8 proportion and fixing stones in proper line and level and camber, filling joints by C.M.1:4 proportion, pointing, with C.M.1:3, curing etc. complete.
RATES FOR 2006-2007 (in Rs.) Completed Labour 420.00
110.00
460.00
140.00
Rmt. Rmt. Rmt. Rmt. Rmt. Rmt. Rmt.
510.00 830.00 1050.00 1250.00 1670.00 1990.00 2580.00
75.00 85.00 97.00 118.00 140.00 162.00 190.00
Rmt. Rmt. Rmt. Rmt. Rmt. Rmt. Rmt.
1070.00 1380.00 2000.00 2500.00 2630.00 3070.00 4300.00
96.00 106.00 118.00 140.00 167.00 190.00 220.00
Spec.No.: CD.4/Page No.160 5 CD 5
Providing trap / granite / quartzite / gneiss Sq.m. khandki paving of 23cm. thickness in 1:4 C.M. over bedding of 15cm thick cement concrete of 1:4:8 proportion with trap / granite / quartzite / gneiss metal including pointing with C.M. 1:3 and watering complete. Spec.No.: CD.5/Page No.161
6 CD 7AA
Providing and laying cement concrete pipe of I.S. N.P. class of required diameter in proper line, level and slope including providing, fixing collars or spigot and socket joint by rubber ring and in C.M.1:2 etc. complete. Diameter of pipe NP-2 Class 450 mm. 600 mm. 700 mm. 800 mm. 900 mm. 1000 mm. 1200 mm. NP- 3 Class 450 mm. 600 mm. 700 mm. 800 mm. 900 mm. 1000 mm. 1200 mm. Spec.No.: CD.7/Page No.162
215
SR.NO.& CODE No.
7 CD 8
DESCRIPTION OF ITEMS
UNIT
Providing cast in situ block of M-15 / Cu.m. 1:2:4cement concrete with circular or other shaped opening for waterway including necessary formwork, compaction, finishing and curing etc. complete.(for craddle)
RATES FOR 2006-2007 (in Rs.) Completed Labour
2000.00
300.00
3000.00
710.00
1550.00
290.00
110.00
28.00
2400.00
340.00
Spec.No.: CD.8/Page No.163/I.S.456 (2000) 8 CD 12
Providing PRECAST M-20 R.C.C. slabs over Cu.m. the spans of Cross Drainage work as per drawings including reinforcement, conveyance, fixing in C.M. 1:3 and curing, finishing complete. Spec.No.: CD.12/Page No.166/I.S.456 (2000)
9 CD 13
Providing and laying in situ 1:3:6 cement Cu.m. concrete of trap / granite quartzite / gneiss metal for haunch filling including forms, compacting, curing and scaffolding etc. complete. Spec.No.: CD.13/Page No.167
10 CD 14
Providing selected murum (having PI < 6 ) Cu.m. filling including laying in layers of 15 cm to 20 cm watering and compacting etc. complete. Spec.No.: CD.14/Page No.167
11 CD 15A
Providing and laying in situ M-20 cement Cu.m. concrete of trap / granite / quartzite / gneiss metal for wearing course 8 cm. thick including compacting, finishing, in C.M. 1:3 proportion curing and filling joints with bitumen complete. (Excluding reinforcement) Spec.No.: CD.15/Page No.168/I.S.456 (2000)
216
SR.NO.& CODE No.
DESCRIPTION OF ITEMS
UNIT
12 CD 27
Providing stream lined R.C.C. guard stone including M-20 Cement concrete and mild steel bar reinforcement.
No.
Spec.No.: CD.20/Page No.169/I.S.456 (2000)
217
RATES FOR 2006-2007 (in Rs.) Completed Labour 190.00
42.00