Costing Systems EMBA 5403 Fall 2008
Available costing systems
Absorption costing
Actual Costing Normal Costing Standard Costing
Variable costing
Actual Costing Normal Costing Standard Costing
Fall 2008-2009
Mugan
2/37
Costing systems Cost component
Actual
Normal
Standard
material
Actual
Actual
Standard
labor cost
Actual
Actual
Standard
Manufacturing Actual Overhead-Variable
Applied
Standard
Manufacturing Overhead-Fixed
Applied
Standard Applied
Fall 2008-2009
Actual
Mugan
3/37
Variance
Differences between the costs according to the costing system used and actual amounts Actual amounts are reflected in the financial statements
Fall 2008-2009
Mugan
4/37
Absorption Costing Cost of Goods Manufactured
Absorption costing allocates variable and fixed overhead costs to products. Cost of Goods Sold
Fall 2008-2009
Mugan
Finished Goods Inventory Valuation 5/37
Product Costing Procedures in Organizations
Process Costing
Job-order Costing
Distinct jobs or batches of units.
• Costs accumulated separately by job. •Typical job order cost applications: • Special-order printing • Building construction • Also used in service industry • Hospitals Fall 2008-2009 Mugan • Law firms
6/37
Product Costing Procedures in Organizations
Process Costing
Job-order Costing
Typical process cost applications:
Petrochemical refinery
Paint manufacturer
Paper mill
Fall 2008-2009
Mugan
7/37
Job-Order Costing
Manufacturing overhead (MOVH) Applied (added) to
Direct Direct Tra ced materials d ir e materials to e ctly ach jo b
Direct Direct labor labor Fall 2008-2009
y l t c ir e d ed c ob a j Tr h c a e to Mugan
each job using a predetermined rate
The The Job Job 8/37
Job-Order Costing Direct materials and labor
Raw materials could be used as direct or indirect product cost.
Part of the job cost
Materials Requisition and Time tickets
An employee’s time may be either direct or indirect. Fall 2008-2009
Indirect materials and labor Mugan
Manufacturing Overhead Control Account 9/37
Job-Order Costing wages
Other Actual OH Charges
Material usage Fall 2008-2009
Indirect Labor
Manufacturing Applied Overhead Overhead Control Account
Job-Order Cost Sheets
Indirect Materials Mugan
10/37
Job-Order Cost Sheet XYZ Job-Order Cost Sheet Job Number A - 143 Department A4 Item Steel water tank
Date Initiated 17 September 2008 Date Completed 17-Nov-08 Units Completed 2
Direct Materials Direct Labor Manufacturing Overhead Req. No. Amount Ticket Hours Amount Hours Rate Amount MR 1041 TL 1200 20 8 TL 160 8 TL 6 TL 48
Cost Summary Direct Materials Direct Labor Manufacturing Overhead Total Cost Unit Cost
Fall 2008-2009
Units Shipped Date Number Balance
TL 1200 TL 160 TL 48 1408 704 11/17/08
Mugan
1
1
11/37
Job-Order System Cost Flows Salaries and Wages Payable Direct Labor Indirect Labor
Mfg. Overhead Actual Applied Indirect Overhead Materials Applied to Indirect Work in Mugan Fall 2008-2009 Labor Process
Work-in-Process (Job Cost Sheet) Direct
Direct Materials Labor Overhead Applied
IfIfactual actualand andapplied applied manufacturing manufacturingoverhead overhead are arenot notequal, equal,aayear-end year-end adjustment adjustmentis isrequired. required. 12/37
Job-Order System Cost Flows Work-in-Process (Job Cost Sheet) Direct
Direct Materials Labor Overhead Applied
Cost of Goods Mfd.
Finished Goods Cost of Goods Mfd.
Cost of Goods Sold
Cost of Goods Sold Cost of Goods Sold Mugan
Fall 2008-2009
13/37
Allocation Process Define the cost objects. Accumulate indirect costs in cost pools. Choose an allocation base. Estimate an application rate. Allocate indirect costs based on use of the allocation base
Fall 2008-2009
Mugan
14/37
Over- and Underabsorbed Overhead Overabsorbed Overabsorbed overhead overhead
Underabsorbed Underabsorbed overhead overhead
Fall 2008-2009
Mugan
15/37
Over- and Underabsorbed Overhead XYZ’s actual overhead for the year was TL650,000 and a total of 100,000 direct labor hours were worked. Using XYZ’s predetermined overhead rate of TL 6.00 per direct labor hour, how much overhead was applied to XYZ’s jobs during the year?
SOLUTION SOLUTION Applied AppliedOverhead Overhead == POHR POHR××Actual ActualDirect DirectLabor LaborHours Hours Applied AppliedOverhead Overhead == TL TL6.00 6.00per perDLH DLH××100,000 100,000DLH DLH==TL TL600,000 600,000 Fall 2008-2009
Mugan
16/37
Accounting for Over- and Underabsorbed Overhead Three Three basic basic approaches approaches Prorate Prorate among among work-in-process, work-in-process,
finished finished goods, goods, and and cost cost of of goods goods sold. sold. Adjust Adjust cost cost of of goods goods sold. sold. Recalculate Recalculate the the application application rate rate and and apply apply to to all all the the jobs jobs during during the the period. period.
Fall 2008-2009
Mugan
17/37
Accounting for Over- and Underabsorbed Overhead If Manufacturing Overhead is . . . UNDERABSORBED
Alternative 1 Close to Cost of Goods Sold
Alternative 2
INCREASE Cost of Goods Sold
INCREASE Work-in-Process Finished Goods Cost of Goods Sold
DECREASE Cost of Goods Sold
DECREASE Work-in-Process Finished Goods Cost of Goods Sold
(Applied OH is less than actual OH) OVERABSORBED (Applied OH is greater than actual OH)
Fall 2008-2009
Mugan
Allocation
18/37
Allocation Base IfIf overhead overhead costs costs are are accumulated accumulated in in aa single single cost cost pool pool and and allocated allocated using using aa single single allocation allocation base. base.
Single Single Overhead Overhead Cost Cost Pool Pool Application Rate
Products Fall 2008-2009
Mugan
19/37
Multiple Allocation Bases Many Manycompanies companiesuse useActivity ActivityBased BasedCosting Costingwhere wheremultiple multiplecost cost pools poolsand andaadifferent differentallocation allocationbase basefor foreach eachcost costpool. pool.
Overhead Overhead Cost CostPool Pool AA Application Rate A
Fall 2008-2009
Overhead Overhead Cost Cost Pool Pool BB
Overhead Overhead Cost CostPool Pool CC
Application Rate B
Products Mugan
Application Rate C
20/37
ABC and Multiple Allocation Bases
Improves planning and control. Activity Based Costing (ABC) is one method of using multiple allocation bases.
Fall 2008-2009
Mugan
21/37
Multistage Allocation Processes Overhead Overhead Cost CostPool Pool11
Overhead Overhead Cost CostPool Pool22
Overhead Overhead Cost CostPool Pool33
Overhead Overhead Cost CostPool Pool44
Separate Application Rates
Department DepartmentAA
Department DepartmentBB
Dept. Application Rates
Fall 2008-2009
Department DepartmentCC
Dept. Application Rates
Products Mugan
22/37
Process Costing Identical Identical units units of of product product are are produced produced in in aa continuous continuous flow flow through through aa series series of of manufacturing manufacturing steps steps or or processes. processes. Costs Costs are are assigned assigned to to completed completed units units transferred transferred out out of of the the process process and and to to incomplete incomplete units units remaining remaining in in the the process. process. Fall 2008-2009
Mugan
23/37
Process Costing Costs Costs are are accumulated accumulated for for aa period period of of time time for for products products in in work-in-process work-in-process inventory. inventory. Equivalent Equivalent units units is is aa concept concept expressing expressing these these partially partially completed completed products products as as aa smaller smaller number number of of fully fully completed completed products. products.
Fall 2008-2009
Mugan
24/37
Equivalent Units Two Twoone-half one-half completed completedproducts productsare are equivalent equivalent to toone onecompleted completedproduct. product.
+
=
So, So, 8,000 8,000units units 70 70percent percent complete complete are areequivalent equivalentto to5,600 5,600complete completeunits. units. Fall 2008-2009
Mugan
25/37
Equivalent Units Question For For the the current current period, period, Ames Ames started started 15,000 15,000 units units and and completed completed 10,000 10,000 units, units, leaving leaving 5,000 5,000 units units in in process process 30 30 percent percent complete. complete. How How many many equivalent equivalent units units of of production production did did Ames Ames have have for for the the period? period? a. a. 10,000 10,000 b. b. 11,500 11,500 c. c. 13,500 13,500 d. d. 15,000 15,000
Fall 2008-2009
Mugan
26/37
Equivalent Units Question For For the the current current period, period, Ames Ames started started 15,000 15,000 units units and and completed completed 10,000 10,000 units, units, leaving leaving 5,000 5,000 units units in in process process 30 30 percent percent complete. complete. How How many many equivalent equivalent units units of of production production did did Ames Ames have have for for the the period? period? a. a. 10,000 10,000 10,000 units + (5,000 units × .30) b. b. 11,500 11,500 = 11,500 equivalent units c. c. 13,500 13,500 d. d. 15,000 15,000
Fall 2008-2009
Mugan
27/37
Calculating and Using Equivalent Units of Production To calculate the cost per equivalent unit for the period:
Cost per equivalent
=
Costs for the period Equivalent units for the period
unit
Fall 2008-2009
Mugan
28/37
Equivalent Units Question Now Now assume assume that that Ames Ames incurred incurred $27,600 $27,600 in in production production costs costs for for the the 11,500 11,500 equivalent equivalent units. units. What What was was Ames’ Ames’ average average cost cost per per equivalent equivalent unit unit for for the the period? period? a. a. $1.84 $1.84 b. b. $2.40 $2.40 c. c. $2.76 $2.76 d. d. $2.90 $2.90 Fall 2008-2009
Mugan
29/37
Equivalent Units Question Now Now assume assume that that Ames Ames incurred incurred $27,600 $27,600 in in production production costs costs for for the the 11,500 11,500 equivalent equivalent units. units. What What was was Ames’ Ames’ average average cost cost per per equivalent equivalent unit unit for for the the period? period? a. a. $1.84 $1.84 $27,600 ÷ 11,500 equivalent units b. b. $2.40 $2.40 = $2.40 per equivalent unit c. c. $2.76 $2.76 d. d. $2.90 $2.90 Fall 2008-2009
Mugan
30/37
Equivalent Units Question What What portion portion of of the the $27,600 $27,600 in in production production costs costs was was assigned assigned to to work-in-process work-in-process inventory inventory and and what what amount amount was was assigned assigned to to completed completed units units for for the the period? period? a. a. $0 $0 and and $27,600 $27,600 b. b. $7,600 $7,600 and and $20,000 $20,000 c. c. $3,600 $3,600 and and $24,000 $24,000 d. d. $12,000 $12,000 and and $15,600 $15,600 Fall 2008-2009
Mugan
31/37
Equivalent Units Question Work-in-process: What portion of the $27,600 in production What portion of the $27,600 in production 1,500 equivalent units @ $2.40 = $3,600 costs costs was was assigned assigned to to work-in-process work-in-process inventory what Completed units: inventory and and what amount amount was was assigned assigned 10,000 equivalent $2.40 = $24,000 to units the period? to completed completed units for forunits the @ period? a. a. $0 $0 and and $27,600 $27,600 b. b. $7,600 $7,600 and and $20,000 $20,000 c. c. $3,600 $3,600 and and $24,000 $24,000 d. d. $12,000 $12,000 and and $15,600 $15,600 Fall 2008-2009
Mugan
32/37
Equivalent Units When When there there are are partially partially completed completed units units in in beginning beginning inventory, inventory, work work efforts efforts during during the the period period can can be be categorized categorized as as follows: follows:
Work Work to to complete complete beginning beginning work-in-process work-in-process Work Work on on units units started started and and completed completed during during the the period period ➌ ➌ Work Work on on units units in in ending ending work-in-process work-in-process ➊ ➊ ➋ ➋
Fall 2008-2009
Mugan
33/37
Equivalent Units - Example ACE started June with 250 partially completed units in work-in-process (30% complete). During June, ACE completed the units in work-in-process and started an additional 1,200 units. There were 300 units in ending work-in-process on June 30. They were 40% complete. How many total equivalent units did ACE produce during June?
Continue Fall 2008-2009
Mugan
34/37
Equivalent Units - Example
Since Since30% 30% of ofthe thework workwas was done doneon on these these units unitsin inMay, May, the the remaining remaining70% 70%of of the the work workis is done done in inJune. June. Fall 2008-2009
Mugan
35/37
Equivalent Units - Example
Since Since1,200 1,200units unitswere were started startedduring duringJune, June, and and 300 300 of of those thoseunits unitsare arestill still in inwork-in-process work-in-processon onJune June30, 30, 900 900 units unitswere werestarted startedand andcompleted completedduring duringJune. June. Fall 2008-2009
Mugan
36/37
Equivalent Units - Example
40% on these units in June. 40% of ofthe thework workwas was done done Mugan on these units in June. 37/37
Fall 2008-2009