INDICE PAGINAS INTRODUCCIÓN ......................................................................................................................3 CAPITULO I ..............................................................................................................................4 GENERALIDADES DEL CENTRO DE PRÁCTICAS ................................................................4 1.1. Objetivos de las prácticas pre-profesionales ..................................................................4 1.1.1. Objetivo general: ......................................................................................................4 1.1.2. Objetivos específicos: ..............................................................................................4 1.2. Centro de prácticas pre-profesionales .........................................................................4 1.2.1 Datos generales ........................................................................................................4 1.2.2. Estructura orgánica de la obra .................................................................................6 1.2.3 Organigrama de la obra ............................................................................................7 1.2.4. Funciones del personal en obra .............................................................................7 1.3. Datos generales de la obra ......................................................................................... 11 1.4. Características del proyecto ........................................................................................ 11 1.4.1. De la ubicación: .................................................................................................... 11 1.4.2. Descripción del Proyecto: ..................................................................................... 12 1.5. Presupuesto del Proyecto: .......................................................................................... 15 Tabla 1. Presupuesto y total de inversión de infraestructura del proyecto ............................ 15 CAPÍTULO II .......................................................................................................................... 16 ACTIVIDADES DESARROLLADAS ....................................................................................... 16 2.1. Duración de las prácticas pre-profesionales ............................................................... 16 2.2. Relación de las actividades realizadas ....................................................................... 16 2.3. Descripción de las principales actividades: ................................................................. 16 2.3.1. Apoyo en la revisión del expediente técnico: ....................................................... 17 2.3.2. Apoyo en el replanteo de Planos de la Obra: ....................................................... 17 2.3.3. Apoyo en la elaboración de la Documentación Técnica de Obra: ....................... 18 2.3.4.
Apoyo en la revisión de Especificaciones Técnicas: ..................................... 18
2.3.6. Apoyo en la revisión y elaboración de los Informes Mensuales: .......................... 19 2.3.7. Apoyo en la revisión y elaboración de Valorización de Maquinarias: .................. 19 2.4. Procedimiento de las actividades realizadas en obra y oficina: .................................. 19 2.4.1. Actividades realizadas en el Colegio de Alto Rendimiento COAR: ...................... 19 CAPÍTULO III ......................................................................................................................... 23 APORTE TECNICO - ACADEMICO ...................................................................................... 23 3.1. Valorización de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA” ........... 23 3.2. Digitalizado del cuaderno de obras perteneciente a: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA” ........................................................................................................................... 23 3.3. Elaboración del Metrado de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA” .............................................. 23
2 3.4. Elaboración del Plano Final para la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA” .............................................. 24 CAPÍTULO IV ......................................................................................................................... 25 CONCLUSIONES Y RECOMENDACIONES ......................................................................... 25 4.1 CONCLUSIONES ......................................................................................................... 25 4.2 RECOMENDACIONES ................................................................................................ 25 BIBLIOGRAFIA ...................................................................................................................... 26 ANEXOS ................................................................................................................................ 27 Anexo 01…………………………………………………………………………………………..27 Anexo 02…………………………………………………………………………………………..27 Anexo 03…………………………………………………………………………………………..27 Anexo 04…………………………………………………………………………………………..27 Anexo 05…………………………………………………………………………………………..27 Anexo 06…………………………………………………………………………………………..27 Anexo 07…………………………………………………………………………………………..27 Anexo 08…………………………………………………………………………………………..27
INDICE DE TABLAS PAGINAS Tabla 1. Presupuesto y total de inversión de infraestructura del proyecto…………………………………………………………………………....15
INDICE DE FIGURAS PAGINAS
Figura 1. Ubicación departamental de la zona del proyecto…………………………...5 Figura 2. Fotografía Satelital de la zona donde se ejecuta la obra……………………5 Figura 3. Fotografía Satelital de la zona donde realice el trabajo de oficina…………6 Figura 4. Organigrama de la obra…………………………………………………………7 Figura 5. Ubicación del lugar donde se realizaron las practicas……………………..12 Figura 6. Ubicación del lugar donde se realizaron las practicas……………………..12 Figura 7. Ubicación del lugar donde se realizaron las practicas……………………..13
3
INTRODUCCIÓN El presente informe, tiene como finalidad describir el desarrollo de las actividades como practicante de ingeniería civil en el área de sub gerencia de obras para la ejecución de una obra de construcción.
La obra consistió en la construcción, mejoramiento y reforzamiento del colegio de alto rendimiento COAR de las aulas existentes y ambientes para el esparcimiento del alumnado en horas de receso.
Capítulo I, se encontraran todos los datos básico y principales de la obra e institución donde se realizó las practicas pre – profesionales, lo que se busca en este punto es describir el centro de trabajo en el que se desempeñó las labores de practicante.
Capítulo II: en esta parte se encontrará la información de todas las labores que se realizaron durante las horas de trabajo en el Área de Sub Gerencia de Obras. Cabe mencionar que la obra que figura en el contrato no fue la única en la que se desarrollaron las practicas, fueron un total de 3 obras en las que se realizó el apoyo como practicante durante el lapso de los 3 meses establecidos en el contrato.
Capítulo III: por ultimo en esta parte encontraremos el aporte para la institución mediante los trabajos que se desarrollaron de manera independiente y otras asignadas por el residente de obra (jefe inmediato).
4
CAPITULO I
GENERALIDADES DEL CENTRO DE PRÁCTICAS
1.1. Objetivos de las prácticas pre-profesionales 1.1.1. Objetivo general:
Consolidar mi formación profesional como ingeniero civil poniendo en práctica los conocimientos adquiridos durante mi formación académica.
1.1.2. Objetivos específicos:
Observar en campo el proceso constructivo de las actividades realizadas en obra y compararlos con el expediente técnico.
Fortalecer mis conocimientos sobre el manejo técnico y administrativo en el campo de la Ingeniería y construcción de Obras.
Tener conocimiento sobre el manejo de recursos humanos y materiales en toda obra civil.
1.2. Centro de prácticas pre-profesionales
El lugar donde se llevó la mayor parte de las prácticas pre profesional fue en las instalaciones del GOBIERNO REGIONAL DE TACNA, en la oficina de Sub Gerencia de Obras.
1.2.1 Datos generales Nombre de la obra: “AMPLIACIÓN DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”
5
Localización de la Obra
Código SNIP
: 373706
Departamento
: Tacna
Provincia
: Tacna
Distrito
: Tacna
Altitud
: 510 m.s.n.m.
Zona ecológica
: Baja
Región Geográfica
: Costa
Coordenadas
: 70.28° de longitud Oeste
: 18.05°de latitud Sur
Figura 1. Ubicación departamental de la zona del proyecto Fuente: Expediente Técnico.
Figura 2. Fotografía Satelital de la zona donde se ejecuta la obra Fuente: Google earth
6
GOB. REG. TACNA
Figura 3. Fotografía Satelital de la zona donde realice el trabajo de oficina Fuente: Google earth
1.2.2. Estructura orgánica de la obra Gerencia Regional de Infraestructura (GRI)
Está conformado por: Ing. Ulianov Farfán Kehuarucho: Gerente del área de infraestructura
Ing. Karina Nuñez Gonzales Sub Gerente de Obras Ing. Yuri Nilo Pacari Mamani Residente de Obra Ing. Adderly Alferez Quispe Asistente Técnico
7
1.2.3 Organigrama de la obra
Figura 4. Organigrama de la obra Fuente: Elaboración propia 1.2.4. Funciones del personal en obra a) Ingeniero supervisor
Responder por las funciones técnicas y Administrativas necesarias realizadas en la obra.
Dar conformidad a los procesos constructivos y atender a las consultas del Residente.
Validar los registros en el cuaderno de obra las incidencias de importancia para la obra (consultas, propuestas, incidentes, avances físicos y financieros); en el caso de la utilización de materiales, mano de obra y equipos.
Validar las anotaciones realizadas por el Residente en el Cuaderno de Obra, sobre causales de generación de modificaciones al expediente técnico
Confirmar la fecha de término de Obra.
Dar conformidad al expediente técnico de post-construcción y al de pre liquidación.
8
b) Ingeniero residente
Responder por las actividades técnicas y administrativas necesarias para ejecutar las obras.
Cumplir estrictamente con el expediente técnico y justificar cualquier modificación que advierta como necesaria para fines de una ejecución satisfactoria.
Requerir el abastecimiento de materiales y equipos en forma oportuna, de acuerdo con el cronograma de adquisición de materiales y requerimiento de los trabajos según corresponda.
Dar conformidad, mediante informes técnicos, a los servicios contratados cuando éstos hayan sido permitidos.
Registrar en el cuaderno de obra las incidencias de importancia para la obra (consultas, propuestas, incidentes, avances físicos y financieros); en el caso de la utilización de materiales, mano de obra y equipos. El registro debe ser diario.
Validar los registros de utilización de mano de obra y de equipos planteados por los responsables respectivos
Anotar en el cuaderno de obra las causales de generación de modificaciones al expediente técnico (plazo y presupuesto).
Elaboración de informes mensuales.
Presentar valorizaciones mensuales.
Formular y presentar el expediente técnico de post construcción.
c ) Asistente administrativo
Requerimiento de materiales de construcción: el asistente administrativo debe formular los cuadros de necesidades de acuerdo a las necesidades de la obra y conforme al presupuesto analítico del plan de trabajo aprobado, salvo cualquier modificación que disponga el residente de obra, asimismo los requerimientos deben realizarse a tiempo conforme al cronograma de adquisición de materiales.
9
Es responsabilidad del asistente administrativo realizar el seguimiento exhaustivo de los cuadros de necesidades en las diferentes fases de su trámite administrativo.
El asistente administrativo se encarga del cumplimiento de los trámites administrativos en la fecha adecuada dentro de la entidad responsable. Elabora informes, solicitudes que son dadas por el Ingeniero Residente de Obra.
d) Asistente técnico
El asistente técnico es la persona encargada de asistir al Ingeniero Residente de la Obra en aspectos técnicos, y otros que se sean asignados por el residente.
Se encarga de apoyar en la elaborar las valorizaciones mensuales de la obra, la planilla de metrados, y el control de avance físico y financiero. Asimismo, vela por el cumplimiento de la entrega de materiales, elabora cuadros de necesidades, solicitudes de cotización.
Apoyo en la elabora planos de replanteo, liquidación técnica de obra; en coordinación con Residente de Obra, y sirve como coordinador o nexo entre maestro de obra, almacenero y el Residente de Obra.
e)
Almacenero
Realizar el stock de materiales semanales.
Coordinar movimientos de materiales en obra.
Controlar diariamente el ingreso y salida de los materiales que ingresan a obra.
f)
Realizar las coordinaciones para el mantenimiento de equipos.
Responsable de la recepción de materiales llegados a la obra.
Coordinar con el equipo técnico sobre la calidad de los materiales.
Mantener ordenado y al día los registros de almacén.
Guardián
Encargado de salvaguardar los bienes ingresados en la obra y todo tipo de bien entrante y saliente en obra.
10
Relevo diario con almacén de obra.
Reporte diario a residencia.
g) Maestro de obra
Es la persona encargada de organizar a los trabajadores de acuerdo a sus conocimientos; tiene mucha experiencia en la construcción.
Control y seguimiento de la ejecución de obra.
Interpretación de planos.
Recepción y organización de materiales, zonas de reunión, talleres, etc.
Control de los medios y la maquinaria de obra.
Control de los materiales.
Supervisión y verificación de los procesos y resultados de los trabajos.
Control de calidad.
Control del cumplimiento de las medidas de prevención de riesgos laborales.
h) Operario
Es la persona especializada, sobre quien recae la responsabilidad de la correcta realización de alguna partida específica. Tiene la experiencia necesaria para su especialidad.
i)
Carpintero encofrador
Fierrero
Albañiles
Gasfitero
Electricista
Ebanistería
Operario de Equipos
Operario de maquinaria pesada
Oficial
Es el obrero que aún no ha alcanzado la plena calificación de la especialidad. Tiene regular experiencia.
11
j)
Peón
Obrero no calificado, apoyo y/o ayudantes, se desempeñan generalmente como excavadores, carretilleros, cargadores, limpieza y apoyo en general.
1.3. Datos generales de la obra
: “AMPLIACION DEL SERVICIO EDUCATIVO
Nombre del Proyecto
PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”
Modalidad
: Por Contrata
Ubicación
: Distrito de Tacna, Provincia Tacna
Supervisión
: Área de Supervisión del GRT
Residente
: Ing. Yuri Nilo Pacari Mamani
Monto De Ejecución De Obra
: S/. 2’648,503.70 Soles
Elaboración De Expediente
: S/. 52,282.00 Soles
Código Snip
: 373706
Plazo Ejecución Contractual
: 120 días Calendarios
1.4. Características del proyecto 1.4.1. De la ubicación: La obra se encuentra ubicado cerca de la Carretera Panamericana Sur
12
Figura 5. Ubicación del lugar donde se realizaron las practicas Fuente: Google earth.
1.4.2. Descripción del Proyecto:
Módulo 1: Servicio de alimentación
Figura 6. Ubicación del lugar donde se realizaron las practicas Fuente: Plano de Ubicación
13
Módulo 2: Residencia Módulo 3: Laboratorios Módulo 4: Servicios Higiénicos Construcción de Cerco Perimétrico y Caseta de Vigilancia Figura 7. Ubicación del lugar donde se realizaron las practicas Fuente: Plano de Ubicación
a) Módulo 1:
En el módulo 1 podemos encontrar la zona donde los escolares, profesores y otros miembros administrativos podrán almorzar y compartir las horas de esparcimiento.
Esta zona o área de trabajo ya se encontraba terminada casi en su totalidad cuando yo empecé mis labores de practicante y no pude ver mucho su proceso constructivo más si su avance plasmado en diagramas y valorizaciones. b) Módulo 2:
En esta zona se encontraran cuartos para a el los alumnos pues está claro que en colegio de alto rendimiento hay alumnado de toda la Región Tacna.
En estos momentos se han instalado en dicha zona las casetas de Residencia de obra provisionalmente. Esta zona durante mi labor de practicante aún no se encontraba construida solo habían conexiones sanitarias.
14
c) Módulo 3:
En este módulo se encontrara el área de Laboratorios con todo el implemento de material necesario y otorgado al Colegio de Alto Rendimiento.
La situación de esta área en el tiempo que estuve de practicante ya se encontraba construida y solo hacía falta la colocación de materiales que se solicitaron por la institución Colegio de Alto Rendimiento COAR.
d) Módulo 4:
En este módulo se encuentran los SSHH de las instalaciones del COAR para el uso de alumnos y profesores.
Esta área se encontraba en ejecución cuando entré de practicante a la obra pero hubo retrasos durante los 3 meses que me encontré ahí pues la falta de cemento era casi muy seguida y temporalmente se paralizaban labores.
e) Construcción de cerco perimétrico y caseta de vigilancia:
El cerco perimétrico se encarga de separar lavía pública y terrenos colindantes y cuenta con una caseta que se encontraba en ese entonces en construcción.
Durante mis 3 meses de practicante pude ver la ejecución de esta área o frente de trabajo pues faltaban detalles y la construcción de la caseta de vigilancia que constaba de una estructura de concreto armado.
15
1.5. Presupuesto del Proyecto: Presupuesto Base Actividades Generales Previas a la
70,057.72
Ejecución Módulo 1: Servicios de Alimentación
61,40762
Módulo 2: Residencia
272,623.74
Módulo 3: Laboratorios
116,073.29
Módulo 4: Servicios Higiénicos
49,751.13
Construcción de Cerco Perimétrico y
217,880.29
Caseta de Vigilancia Losa Deportiva
111,285.75
Áreas de Circulación
93,386.96
Instalaciones Sanitarias
246,045.21
Instalaciones Eléctricas
508,546.54
Mitigación y Control Ambiental
7,141.82 ************************
Costo Directo
1’754,200.06
Gastos Generales (11%)
192,962.01
Utilidad (6%)
105,252.00 ************************
Sub Total
2’052,414.07
IGV (18%)
369,434.53 ************************
Costo de Obra
2’421,848.60
Gastos de Estudio
52,282.00
Gastos de Supervisión (5%)
121,092.43
Gastos de Liquidación (1.2%)
29,062.18
Gastos Administrativos (1%)
24,218.49 ************************
Total de Presupuesto
2’648,503.70
Tabla 1. Presupuesto y total de inversión de infraestructura del proyecto Fuente: Modelo 3D del Expediente Técnico
16
CAPÍTULO II
ACTIVIDADES DESARROLLADAS
2.1. Duración de las prácticas pre-profesionales Las prácticas pre-profesionales se realizaron durante los meses de Junio, Julio, Agosto, Septiembre, en periodo continuo, siendo la fecha de inicio 5 de Junio del 2017 hasta el 5 de Septiembre del 2017. Las prácticas tuvieron una duración de 90 días calendario, cumpliendo con la cantidad mínima de 90 días en período continuo. 2.2. Relación de las actividades realizadas Las actividades realizadas en la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) TACNA” en calidad de practicante tanto en obra y oficina se detalla en los siguientes:
Revisión del Expediente Técnico.
Apoyo en el replanteo de planos de la obra.
Apoyo en la elaboración de la documentación técnica de obra.
Apoyo en la elaboración de los términos de referencia.
Apoyo en la elaboración de los informes mensuales.
Apoyo en la elaboración de valorización de personal, materiales.
Apoyo en la elaboración de valorización de maquinarias.
Apoyo en las actividades en obra.
Otras funciones encomendadas por el residente de obra.
17
2.3. Descripción de las principales actividades: 2.3.1. Apoyo en la revisión del expediente técnico: Como primera actividad se realizó el estudio del expediente técnico para tener conocimiento en qué consiste la obra y cuáles son las metas físicas que se tienen que cumplir al final de la obra.
Apoyo en la revisión de las especificaciones técnicas: Proceso constructivo Calidad de materiales Ensayos o parámetros de control de calidad Unidad de medida Formas de pago y valorizaciones
Apoyo en la revisión de planos para llevar el control de los niveles y la ubicación correcta de los elementos estructurales.
Apoyo en la revisión del Presupuesto, partidas y subpartidas.
Apoyo en la revisión de los precios unitarios, rendimientos y relación de insumos.
2.3.2. Apoyo en el replanteo de Planos de la Obra:
Apoyo al Residente de obra en las modificaciones en los planos de Instalaciones Sanitarias, Instalaciones Eléctricas de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”.
Apoyo en la revisión y elaboración de planos de elevaciones de los Servicios Higiénicos de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) TACNA” pues no existían planos de dichos detalles.
De igual manera se realizó el replanteo de otros planos referentes a obras distintas que se encontraban en ejecución durante las actividades de practicante, dichos replanteos de otras obras fueron asignadas por el Residente de obra (jefe inmediato) con el fin de adquirir más experiencia en el ámbito laboral.
18
2.3.3. Apoyo en la elaboración de la Documentación Técnica de Obra: Este punto consiste en labor administrativa asignada por el Residente de obra tales actividades fueron:
Escaneo de cuaderno de obras.
Fotocopiado de distintos documentos.
Foliado de expedientes técnicos e informes mensuales.
Ploteo de planos de obra.
Armado de informes mensuales.
Recepción de comprobantes de pago.
Envio de informes mensuales a supervisión.
2.3.4. Apoyo en la revisión de Especificaciones Técnicas: Apoyo en la revisión de Especificaciones Técnicas del Expediente técnico “AMPLIACIÓN DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”.
Uso del software SIGA (Sistema Integrado de Gestión Administrativa); cabe mencionar que su manejo es solo para personal del gobierno regional de Tacna.
La revisión de las especificaciones técnicas se realizó en base al uso y maniobrabilidad de los materiales que se emplean.
2.3.5. Apoyo en la verificación de Metrados de Obra:
Una de las actividades realizadas fue la verificación de los metrados de algunas partidas del expediente Técnico de la Obra “AMPLIACIÓN DEL SERVICIO
19
EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”, con el objeto de hacer los cuadros de necesidades de los materiales a utilizar en la obra, se debe mencionar que el tipo de metrado que se realizo fue mediante Software (Auto CAD). 2.3.6. Apoyo en la revisión y elaboración de los Informes Mensuales: Se fue otorgada por el Ingeniero Residente la responsabilidad de realizar la revisión del informe mensual ya elaborado, de encontrarse algún error debía hacerse una observación y notificarla inmediatamente al Ingeniero Residente o en su defecto al Asistente Técnico para la corrección inmediata para luego proceder a la presentación final ante la supervisión de la entidad. 2.3.7. Apoyo en la revisión y elaboración de Valorización de Maquinarias: Se realizó la valorización de la maquinaria del mes de junio y la revisión de la valorización de los meses de abril y mayo.
Para complementar dicho trabajo fue permitido la visita a obra por el Residente, para la obtención de imágenes de las maquinarias que se estaban empleando en obra. 2.4. Procedimiento de las actividades realizadas en obra y oficina: 2.4.1. Actividades realizadas en el Colegio de Alto Rendimiento COAR: 2.4.1.1. Actividad en Oficina: a) Primer mes:
Se realizaron labores de apoyo administrativo las cuales fueron asignadas por el Residente de obra (jefe directo), cabe resaltar que dichas actividades se desarrollaron en las instalaciones Gobierno Regional de Tacna ubicado en la dirección Hipolito Unanue 1269.
Las actividades consistieron en las siguientes:
Revisión del Expediente Técnico Obra “AMPLIACIÓN DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”.
20
Recepción y revisión de comprobantes de pago correspondiente a la obra “AMPLIACIÓN DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”.
Armado de informes mensuales (fotocopiado y armado físico)
Replanteo de planos correspondientes a las siguientes obras: “AMPLIACIÓN DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”. “MANTENIMIENTO DE LA VIA DE INGRESO AL DISTRITO DE ESTIQUE – PROVINCIA DE TARATA – TACNA 2016”.
Ploteo de los Replanteos.
Foleado de expedientes técnicos y cualquier otro documento administrativo.
Estas actividades se realizaron durante el mes de Junio del 2017, el Residente de Obra (jefe directo) al asignar estas tareas básicas puede evaluar las capacidades del practicante en el ámbito laboral rutinario de oficina, pues dichas tareas no demandan una complejidad en su desarrollo pero sirven para poder identificar el compromiso del practicante con cada trabajo asignado.
b) Segundo mes:
Durante el periodo del mes de Julio del 2017, la asignación de responsabilidades incrementa pues ya existe una imagen formada del practicante para con el Residente de Obra.
Las actividades consistieron en las siguientes:
Apoyo en la elaboración de informes mensuales de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”.
Apoyo en la revisión y elaboración de valorizaciones de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL
21
COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”, de los meses Enero, Febrero, Marzo (revisión) Abril, Mayo, Junio, Julio (elaboración).
Apoyo en la elaboración de planos de elevaciones, planos topográficos, dibujo de letras y señales de tránsito en AUTOCAD, la elaboración de los planos topográficos y de dibujo de señales de tránsito y letras de transito fue para la actividad: “MANTENIMIENTO DE LA VIA DE INGRESO AL DISTRITO DE ESTIQUE – PROVINCIA DE TARATA – TACNA 2016”.
Apoyo en la revisión y elaboración de valorizaciones de maquinarias de la Obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA, cabe resaltar que se realizó la valorización de la maquinaria del mes de junio y la revisión de la valorización de los meses de abril y mayo.
Obtención de kardex de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”, esto con el fin de digitalizar dicha información en la base de datos de la oficina.
Revisión del cuaderno de obras referente a la maquinaria usada en los meses de Abril, Mayo, Junio, julio y Agosto.
c) Tercer mes:
Durante el mes de Agosto del 2017 las actividades realizadas se llevaron a cabo dentro de las oficinas del Gobierno Regional de Tacna en el Área de Subgerencia de Obras y en la obra: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”.
Las actividades fueron las siguientes:
Apoyo en la elaboración del informe final de la Actividad: “MANTENIMIENTO DE LA VIA DE INGRESO AL DISTRITO DE ESTIQUE – PROVINCIA DE TARATA – TACNA 2016”.
22
Durante esta etapa de las prácticas, la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”, se vio en problemas administrativos en cuanto a la presentación del informe mensual correspondiente al mes de agosto.
Se realizó la digitalización del cuaderno de obras de la: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”, para una correcta revisión de los materiales y maquinarias usadas durante todo el proceso constructivo de la obra.
Apoyo en la modificación de los planos correspondientes a la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”.
Se realizó la revisión de los metrados de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”, se pidió una modificación en los planos (Replanteo) y por ende realizar un nuevo presupuesto.
Apoyo en la elaboración de las valorizaciones correspondientes a la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”, esta tarea se realizó en campo.
23
CAPÍTULO III
APORTE TECNICO - ACADEMICO Se procederá a mostrar las actividades que se realizaron: 3.1. Valorización de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA” Valorización del mes de Junio de la Obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA”
Revisar Anexo 01: Valorización COAR mes de Junio 2017
3.2. Digitalizado del cuaderno de obras perteneciente a: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA” En esta actividad se realizó el proceso de digitalizado del cuaderno de obra, pero solo desde el último cambio de residente siendo este el Ing. Yuri Nilo Pacari Mamani.
Revisar Anexo 02: Cuadro de maquinaria y equipos Revisar Anexo 03: Cuadro de mano de obra Revisar Anexo 04: Cuadro de materiales
3.3. Elaboración del Metrado de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA” En esta actividad se elaboró el metrado del replanteo de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA REGIÓN TACNA” Revisar Anexo 05: Metrado del rollizo de eucalipto Revisar Anexo 06: Metrado de instalaciones Sanitarias
24
3.4. Elaboración del Plano Final para la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA” En esta actividad se pidó una propuesta para el plano final de la actividad “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA REGIÓN TACNA”, que se tomaría en cuenta si dicho plano está correctamente elaborado. Revisar Anexo 07: Plano de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”
25
CAPÍTULO IV
CONCLUSIONES Y RECOMENDACIONES
4.1 CONCLUSIONES
Las Prácticas Pre profesionales realizadas en el Gobierno Regional de Tacna, Área de Sub Gerencia de Obras fueron beneficiosas para la madures profesional que se quiere lograr como ingeniero civil tanto en trabajo de gabinete (oficina) y en campo (lugar de la obra).
Durante la etapa de construcción se presentaron muchos factores que influyeron en el retraso de la obra, principalmente fueron la falta de materiales y la ausencia de maquinaria fueron los principales causales.
En la etapa del desarrollo de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”, se pudo aprender el correcto inventariado de los materiales y herramientas que se emplean para la construcción en este caso el mantenimiento del complejo La Agronomica.
El apoyo en la formulación de informes y otros documentos administrativos fueron de importancia para no generar retrasos en la presentación de esto.
El apoyo en los replanteos sirvió para obtener mayor habilidad con la elaboración de planos, de igual manera para llevar a cabo un correcto metrado y por ende realizar un presupuesto óptimo.
4.2 RECOMENDACIONES
Es necesario la organización y planificación en obra, la comunicación entre la parte técnica y la mano de obra, ya que de ello depende el logro y conclusión de una obra.
Planificar los trabajos de campo por medio de cronogramas que busquen el menor tiempo de desarrollo de las actividades a realizar. También se
26
observó que el avance de obra depende bastante del abastecimiento de materiales, de esta manera se recomienda solicitar por anticipado los materiales para la ejecución de una obra.
Es necesario fortalecer la parte administrativa pues durante la ejecución de la obra se pueden presentar inconvenientes con la elaboración y presentación de informes mensuales los cuales pueden llevar atrasados mucho tiempo ya que esto uno de los principales puntos negativos y que nunca deben ocurrir en cualquier tipo de obra ya sea ejecutada por una entidad pública o privada.
Es recomendable mejorar las instalaciones del Área de Sub Gerencia de Obras pues las oficinas se encuentran muy desordenadas esto debido a su reducido tamaño y por ende esto genera un ambiente poco favorable para un correcto desempeño de actividades dentro de las oficinas.
BIBLIOGRAFIA Reglamento Nacional de Edificaciones / ICG- 2016 Expediente Técnico del Proyecto: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA” Ramos J. /Costos y Presupuestos en Edificaciones/ Cámara Peruana de la Construcción/ 8va Ed. Lima – Perú - 2003. Ing. Jesús Ramos Salazar/Costos y Presupuestos en Edificaciones/ Lima - Perú: CAPECO 8va Ed. - 2006. Vargas Neumann, Julio; Torrealva, Daniel y Blondet, Marcial / Manual Básico del Ingeniero Residente en Edificación / Lima - Perú: CAPECO 1era Ed.- 2007. El Maestro de Obra, Tecnología de la Construcción / SENCICO. Tecnología del Concreto / Ing. Flavio Abanto Castillo. Manual de carreteras – Ministerio de transportes y comunicaciones (DG 2014)
27
ANEXOS: Anexo 01: Valorización COAR mes de Junio 2017. Anexo 02: Cuadro de maquinaria y equipos. Anexo 03: Cuadro de mano de obra. Anexo 04: Cuadro de materiales. Anexo 05: Metrado del rollizo de eucalipto. Anexo 06: Metrado de instalaciones Sanitarias. Anexo 07: Plano de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL - TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA - REGIÓN TACNA”. Anexo 08: Planos de la obra: “AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL, DEL COLEGIO DE ALTO RENDIMIENTO (COAR) – TACNA
ANEXOS
ANEXO 01: VALORIZACIÓN COAR MES DE JUNIO 2017. 1. VALORIZACION EXP. TECNICO
IT EM
01 01.01
D EC R IPC ION
UND
M ET .
P.U .
ACTIVIDADES GENERALES PREVIAS A LA EJECUCIÓN OBRAS PROVISIONALES
A C U M U LA D O A N T ER IOR
PA R C IA L
PA R C IA L
%
EJEC U T A D O JU N IO
PA R C IA L
%
79,093.69
78,280.77
98.97%
430.62
0.54%
20,641.76
20,443.52
99.04%
198.24
0.96%
A C U M U LA D O T OT A L
SA LD O POR EJEC U T A R
01.01.01
CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40X3.60 M.
und
1.00
1,029.31
1,029.31
1.00
1,029.31
100.00%
0.00
0.00
0.00%
1.00
0.00
01.01.02
CASETA DE ALMACEN, GUARDIANIA Y OFICINA DEL RESIDENTE
m2
68.25
136.32
9,303.84
68.25
9,303.84
100.00%
0.00
0.00
0.00%
68.25
0.00
01.01.03
VESTUARIO Y SSHH
m2
19.20
149.49
2,870.21
19.20
2,870.21
100.00%
0.00
0.00
0.00%
19.20
0.00
01.01.04
CERCO PROVISIONAL CON MALLA ARPILLERA
m
320.00
18.82
6,022.40
320.00
6,022.40
100.00%
0.00
0.00
0.00%
320.00
0.00
01.01.05
ENERGIA ELECTRICA PROVISIONAL
glb
1.00
885.00
885.00
0.86
761.10
86.00%
0.14
123.90
14.00%
1.00
0.00
01.01.06
AGUA Y DESAGÜE PROVISIONAL PARA LA CONSTRUCCION
glb
1.00
531.00
531.00
0.86
456.66
86.00%
0.14
74.34
14.00%
1.00
0.00
19,396.11
98.29%
0.00
0.00%
01.02
TRABAJOS PRELIMINARES
19,733.68
01.02.01
MOVILIZACION Y DESMOVILIZACION DE EQUIPO
glb
1.00
2,282.53
2,282.53
1.00
2,282.53
100.00%
0.00
0.00
0.00%
1.00
0.00
01.02.02
DESMONTAJE DE VENTANAS Y PUERTAS
m2
39.75
10.95
435.26
39.75
435.26
100.00%
0.00
0.00
0.00%
39.75
0.00
01.02.03
DESMONTAJE DE COBERTURA LIVIANA
m2
118.39
12.31
1,457.38
118.39
1,457.38
100.00%
0.00
0.00
0.00%
118.39
0.00
01.02.04
DESMONTAJE DE TABIQUERIA DRYWALL
m2
169.48
19.33
3,276.05
169.48
3,276.05
100.00%
0.00
0.00
0.00%
169.48
0.00
01.02.05
DESMONTAJE DE APARATOS SANITARIOS
und
2.00
25.48
50.96
2.00
50.96
100.00%
0.00
0.00
0.00%
2.00
0.00
01.02.06
DESMONTAJE DE ACCESORIOS SANITARIOS
und
1.00
12.06
12.06
1.00
12.06
100.00%
0.00
0.00
0.00%
1.00
0.00
01.02.07
DEMOLICION DE MESON DE CONCRETO
m3
2.71
70.86
192.03
2.71
192.03
100.00%
0.00
0.00
0.00%
2.71
0.00
01.02.08
DEMOLICION DE VIGAS Y COLUMNAS DE CºAº
m3
0.76
141.73
107.71
0.51
72.28
67.11%
0.00
0.00
0.00%
0.51
0.25
01.02.09
DEMOLICION DE ALBAÑILERIA
m2
25.08
10.20
255.82
15.18
154.84
60.53%
0.00
0.00
0.00%
15.18
9.90
01.02.10
DEMOLICION DE SOBRECIMIENTOS DE CONCRETO
m3
2.54
70.63
179.40
1.06
74.87
41.73%
0.00
0.00
0.00%
1.06
1.48
01.02.11
DEMOLICION DE PISOS DE CONCRETO SIMPLE INCL. CORTE
m2
17.56
14.17
248.83
17.56
248.83
100.00%
0.00
0.00
0.00%
17.56
0.00
01.02.12
ACARREO DE MATERIAL DEMOLIDO
m3
15.79
22.79
359.85
11.55
263.22
73.15%
0.00
0.00
0.00%
11.55
4.24
01.02.13
ELIMINACION DE MATERIAL DEMOLIDO C/MAQUINARIA
m3
15.79
9.23
145.74
15.79
145.74
100.00%
0.00
0.00
0.00%
15.79
0.00
01.02.14
TRAZO, NIVELES Y REPLANTEO PRELIMINAR GENERAL
m2
5,928.21
1.81
10,730.06
5,928.21
10,730.06
100.00%
0.00
0.00
0.00%
5928.21
0.00
22,256.90
98.77%
232.38
1.03%
01.03
SEGURIDAD Y SALUD
22,534.00
01.03.01
PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO
glb
1.00
2,500.00
2,500.00
1.00
2,500.00
100.00%
0.00
0.00
0.00%
1.00
0.00
01.03.02
EQUIPO DE PROTECCION INDIVIDUAL
und
30.00
466.40
13,992.00
30.00
13,992.00
100.00%
0.00
0.00
0.00%
30.00
0.00
01.03.03
EQUIPO DE PROTECCION COLECTIVO
glb
1.00
950.00
950.00
0.95
902.50
95.00%
0.04
38.00
4.00%
0.99
0.01
01.03.04
SEÑALIZACIÓN TEMPORAL DE SEGURIDAD ZONA DE TRABAJO
glb
1.00
1,662.00
1,662.00
0.95
1,578.90
95.00%
0.04
66.48
4.00%
0.99
0.01
01.03.05
CAPACITACION EN SEGURIDAD YSALUD
glb
1.00
2,500.00
2,500.00
0.96
2,400.00
96.00%
0.04
100.00
4.00%
1.00
0.00
01.03.06
RECURSO PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE glb EL TRABAJO 1.00
930.00
930.00
0.95
883.50
95.00%
0.03
27.90
3.00%
0.98
0.02
16,184.24
100.00%
0.00
0.00%
01.04
MOVIMIENTO DE TIERRAS
16,184.24
01.04.01
CORTE CON MAQUINARIA EN TERRENO NORMAL
m3
587.01
6.17
3,621.85
587.01
3,621.85
100.00%
0.00
0.00
0.00%
587.01
0.00
01.04.02
RELLENO Y COMPACTACION C/MAQUINARIA (MATERIAL PRESTAMO)
m3
133.79
45.30
6,060.69
133.79
6,060.69
100.00%
0.00
0.00
0.00%
133.79
0.00
01.04.03
CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE DM=10KM
m3
704.41
9.23
6,501.70
704.41
6,501.70
100.00%
0.00
0.00
0.00%
704.41
0.00
30
IT EM
02 02.01
D EC R IPC ION
UND
M ET .
P.U .
A C U M U LA D O A N T ER IOR
PA R C IA L
MODULO 01: SERVICIOS DE ALIMENTACION (AMPLIACION) TRABAJOS PRELIMINARES
PA R C IA L
%
EJEC U T A D O JU N IO
PA R C IA L
%
68,461.44
68,461.44
100.00%
0.00
0.00%
1,184.86
1,184.86
100.00%
0.00
0.00%
A C U M U LA D O T OT A L
SA LD O POR EJEC U T A R
02.01.01
TRAZO NIVELES Y REPLANTEO
m2
424.68
1.77
751.68
424.68
751.68
100.00%
0.00
0.00
0.00%
424.68
0.00
02.01.02
LIMPIEZA DE TERRENO MANUAL
m2
424.68
1.02
433.17
424.68
433.17
100.00%
0.00
0.00
0.00%
424.68
0.00
40.02
100.00%
0.00
0.00%
02.02
OBRAS DE CONCRETO SIMPLE
40.02
02.02.01
SARDINEL CONCRETO F'C=175 KG/CM2
m3
0.05
298.61
14.93
0.05
14.93
100.00%
0.00
0.00
0.00%
0.05
0.00
02.02.02
ENCOFRADO Y DESENCOFRADO NORMAL PARA SARDINEL DE CONCRETO
m2
0.94
26.69
25.09
0.94
25.09
100.00%
0.00
0.00
0.00%
0.94
0.00
1,884.07
100.00%
0.00
0.00%
02.03 02.03.01
OBRAS DE CONCRETO ARMADO
1,884.07
1,884.07
100.00%
0.00
0.00%
02.03.01.01
MESON: CONCRETO F'C=175 KG/CM2
m3
2.05
288.67
591.77
2.05
591.77
100.00%
0.00
0.00
0.00%
2.05
0.00
02.03.01.02
MESON: ENCOFRADO Y DESENCOFRADO NORMAL
m2
23.86
34.84
831.28
23.86
831.28
100.00%
0.00
0.00
0.00%
23.86
0.00
02.03.01.03
MESON: ACERO DE REFUERZO FY=4200 KG/CM2
kg
101.10
4.56
461.02
101.10
461.02
100.00%
0.00
0.00
0.00%
101.10
0.00
28,376.02
100.00%
0.00
0.00%
02.04
MESON DE CONCRETO
1,884.07
MUROS Y TABIQUES
28,376.02
02.04.01
TABIQUE DRYWALL MIXTO SUPERBOARD SQ 8MM Y SUPERBOARD PRO 8MM, PARANTES m2 DE 89MM, 81.24 C/AISLAMIENTO 132.84 ACUST.
10,791.92
81.24
10,791.92
100.00%
0.00
0.00
0.00%
81.24
0.00
02.04.02
TABIQUE DRYWALL SUPERBOARD SQ 8mm, PARANTES DE 89MM, C/AISLAMIENTO ACUST. m2
30.38
133.58
4,058.16
30.38
4,058.16
100.00%
0.00
0.00
0.00%
30.38
0.00
02.04.03
TABIQUE DRYWALL SUPERBOARD PRO 8mm, PARANTES DE 89MM, C/AISLAMIENTO ACUST. m2
81.03
132.10
10,704.06
81.03
10,704.06
100.00%
0.00
0.00
0.00%
81.03
0.00
02.04.04
TABIQUERIA DE MELAMINE E=18MM CON MARCO DE ALUMINIO INC. PUERTA
25.74
109.63
2,821.88
25.74
2,821.88
100.00%
0.00
0.00
0.00%
25.74
0.00
7,850.44
100.00%
0.00
0.00%
7,850.44
100.00%
0.00
0.00%
118.39
0.00
6,175.67
100.00%
0.00
0.00%
02.05 02.05.01 02.06
m2
CIELO RASO FALSO CIELO RASO C/BALDOSA ACUSTICA C/SUSPENCION REBAJADA
7,850.44 m2
118.39
66.31
PISOS
7,850.44
118.39
6,175.67
0.00
02.06.01
PISO DE CERAMICO 45 X 45CM ANTIDESLIZANTE
m2
105.29
51.14
5,384.53
105.29
5,384.53
100.00%
0.00
0.00
0.00%
105.29
0.00
02.06.02
PISO DE CERAMICO 30 X 30CM ANTIDESLIZANTE
m2
15.47
51.14
791.14
15.47
791.14
100.00%
0.00
0.00
0.00%
15.47
0.00
3,039.84
100.00%
0.00
0.00%
02.07
ZOCALOS Y CONTRAZOCALOS
3,039.84
02.07.01
ZOCALO DE CERAMICO 25 X 40 CM
m2
51.62
51.49
2,657.91
51.62
2,657.91
100.00%
0.00
0.00
0.00%
51.62
0.00
02.07.02
CONTRAZOCALO DE CERAMICO H=0.10m
m
17.40
21.95
381.93
17.40
381.93
100.00%
0.00
0.00
0.00%
17.40
0.00
538.07
100.00%
0.00
0.00%
0.00
0.00%
10.45
0.00
0.00
0.00%
02.08 02.08.01 02.09
REVESTIMIENTOS ENCHAPE CON CERAMICO EN MESON DE CONCRETO
538.07 m2
51.49
538.07
10.45
11,202.81
02.09.01
PUERTA DE MADERA CEDRO C/MARCO DE 2"x4
02.09.02
PUERTA CONTRAPLACADA DE MADERA CEDRO C/TRIPLAY DE 4 MM + MARCO CEDROm2 2X4"
02.10
10.45
CARPINTERIA DE MADERA m2
538.07
100.00%
11,202.81
100.00%
0.00
10.08
399.20
4,023.94
10.08
4,023.94
100.00%
0.00
0.00
0.00%
10.08
0.00
29.28
245.18
7,178.87
29.28
7,178.87
100.00%
0.00
0.00
0.00%
29.28
0.00
2,342.16
100.00%
0.00
0.00%
CERRAJERIA
2,342.16
02.10.01
CERRADURA TIPO PARCHE EN PUERTA - 03 GOLPES
und
4.00
100.12
400.48
4.00
400.48
100.00%
0.00
0.00
0.00%
4.00
0.00
02.10.02
CERRADURA TIPO PERILLA
und
12.00
49.89
598.68
12.00
598.68
100.00%
0.00
0.00
0.00%
12.00
0.00
02.10.03
BISAGRA CAPUCHINA ALUMINIZADA 4"x4"
pza
68.00
19.75
1,343.00
68.00
1,343.00
100.00%
0.00
0.00
0.00%
68.00
0.00
736.25
100.00%
0.00
0.00%
02.11
VIDRIOS, CRISTALES Y SIMILARES
736.25
02.11.01
VENTANA TIPO SISTEMA CON VIDRIO DOBLE INCOLORO Y MARCO DE ALUMINIO
m2
4.44
142.63
633.28
4.44
633.28
100.00%
0.00
0.00
0.00%
4.44
0.00
02.11.02
VIDRIO DOBLE EN PUERTAS
p2
10.76
9.57
102.97
10.76
102.97
100.00%
0.00
0.00
0.00%
10.76
0.00
4,365.03
100.00%
0.00
0.00%
02.12
PINTURA
4,365.03
02.12.01
PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES
m2
369.63
8.44
3,119.68
369.63
3,119.68
100.00%
0.00
0.00
0.00%
369.63
0.00
02.12.02
PINTURA BARNIZ 02 MANOS EN CARPINTERIA DE MADERA.
m2
78.72
15.82
1,245.35
78.72
1,245.35
100.00%
0.00
0.00
0.00%
78.72
0.00
726.20
100.00%
0.00
0.00%
726.20
100.00%
0.00
0.00%
424.68
0.00
02.13 02.13.01
03 03.01
VARIOS LIMPIEZA FINAL DE OBRA
726.20 m2
424.68
1.71
726.20
424.68
0.00
MODULO 02: RESIDENCIA
302,345.01
37,160.03
12.29%
13,655.15
0.00%
TRABAJOS PRELIMINARES
1,930.60
1,930.60
100.00%
0.00
0.00%
03.01.01
TRAZO NIVELES Y REPLANTEO
m2
691.97
1.77
1,224.79
691.97
1,224.79
100.00%
0.00
0.00
0.00%
691.97
0.00
03.01.02
LIMPIEZA DE TERRENO MANUAL
m2
691.97
1.02
705.81
691.97
705.81
100.00%
0.00
0.00
0.00%
691.97
0.00
11,601.84
97.06%
351.22
2.94%
362.41
72.31%
138.81
27.69%
14.66
0.00
03.02 03.02.01
MOVIMIENTO DE TIERRAS EXCAVACION MANUAL P/SARDINELES SUMERGIDOS
11,953.05 m3
14.66
34.19
501.23
10.60
4.06
IT EM
04 04.01
D EC R IPC ION
UND
M ET .
P.U .
A C U M U LA D O A N T ER IOR
PA R C IA L
MODULO 03: LABORATORIOS TRABAJOS PRELIMINARES
PA R C IA L
%
EJEC U T A D O JU N IO
PA R C IA L
%
128,972.24
3,788.13
2.94%
10,075.20
0.00%
569.86
569.86
100.00%
0.00
0.00%
A C U M U LA D O T OT A L
SA LD O POR EJEC U T A R
04.01.01
TRAZO NIVELES Y REPLANTEO
m2
204.25
1.77
361.52
204.25
361.52
100.00%
0.00
0.00
0.00%
204.25
0.00
04.01.02
LIMPIEZA DE TERRENO MANUAL
m2
204.25
1.02
208.34
204.25
208.34
100.00%
0.00
0.00
0.00%
204.25
0.00
3,218.27
88.01%
438.29
11.99%
04.02
MOVIMIENTO DE TIERRAS
3,656.56
04.02.01
EXCAVACION MANUAL P/SARDINELES SUMERGIDOS
m3
5.89
34.19
201.38
0.00
0.00
0.00%
5.89
201.38
100.00%
5.89
0.00
04.02.02
NIVELACION Y COMPACTACION PARA PISOS
m2
204.25
3.09
631.13
204.25
631.13
100.00%
0.00
0.00
0.00%
204.25
0.00
04.02.03
TERRAPLEN PARA PISOS E=0.10M
m2
204.25
12.44
2,540.87
204.25
2,540.87
100.00%
0.00
0.00
0.00%
204.25
0.00
04.02.04
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
7.06
22.57
159.34
2.05
46.27
29.04%
5.01
113.08
70.96%
7.06
0.00
04.02.05
ELIMINACION DE MATERIAL EXCEDENTE
m3
7.06
17.54
123.83
0.00
0.00
0.00%
7.06
123.83
100.00%
7.06
0.00
0.00
0.00%
9,045.25
82.34%
04.03
OBRAS DE CONCRETO SIMPLE
10,984.75
04.03.01
SARDINEL SUMERGIDO F'C=175 KG/CM2
m3
5.51
336.35
1,853.29
0.00
0.00
0.00%
2.80
942.25
50.84%
2.80
2.71
04.03.02
PISO DE CONCRETO F'C=175 KG/CM2 E=10CM..ACAB. CEMENTO PULIDO INC. CORTE m2
53.35
42.97
2,292.45
0.00
0.00
0.00%
36.78
1,580.31
68.94%
36.78
16.57
04.03.03
PISO DE CONCRETO F'C=175 KG/CM2 E=10CM..ACAB. FROTACHADO INC. CORTE
m2
150.90
38.65
5,832.29
0.00
0.00
0.00%
150.90
5,832.29
100.00%
150.90
0.00
04.03.04
ENCOFRADO Y DESENCOFRADO NORMAL PARA GRADAS Y PISOS
m2
20.64
33.45
690.41
0.00
0.00
0.00%
20.64
690.41
100.00%
20.64
0.00
04.03.05
SARDINEL CONCRETO F'C=175 KG/CM2
m3
0.38
298.61
113.47
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
0.38
04.03.06
ENCOFRADO Y DESENCOFRADO NORMAL PARA SARDINEL DE CONCRETO
m2
7.60
26.69
202.84
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
7.60
0.00
0.00%
358.82
4.16%
04.04 04.04.01
OBRAS DE CONCRETO ARMADO
8,627.15
0.00
0.00%
0.00
0.00%
04.04.01.01
MESON: CONCRETO F'C=175 KG/CM2
m3
5.27
288.67
1,521.29
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
5.27
04.04.01.02
MESON: ENCOFRADO Y DESENCOFRADO NORMAL
m2
99.32
34.84
3,460.31
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
99.32
MESON: ACERO DE REFUERZO FY=4200 KG/CM2
kg
317.30
4.56
1,446.89
0.00
0.00
0.00%
0.00
0.00
317.30
0.00
0.00%
04.04.01.03 04.04.02
MESON DE CONCRETO
6,428.49
CASETA DE CONCRETO
2,198.66
0.00
0.00%
358.82
16.32%
04.04.02.01
CASETA: CONCRETO F'C=175 KG/CM2
m3
2.25
329.31
740.95
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
2.25
04.04.02.02
CASETA: ENCOFRADO Y DESENCOFRADO NORMAL
m2
25.93
38.92
1,009.20
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
25.93
CASETA: ACERO DE REFUERZO FY=4200 KG/CM2
kg
98.36
4.56
448.52
0.00
0.00
0.00%
78.69
358.82
80.00%
78.69
19.67
0.00
0.00%
0.00
0.00%
04.04.02.03 04.05
MUROS Y TABIQUES
31,579.06
04.05.01
TABIQUE DRYWALL MIXTO SUPERBOARD SQ 8MM Y SUPERBOARD PRO 8MM, PARANTES m2 DE 89MM, 158.72 C/AISLAMIENTO 132.84 ACUST.
21,084.36
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
158.72
04.05.02
TABIQUE DRYWALL SUPERBOARD PRO 8mm, PARANTES DE 89MM, C/AISLAMIENTO ACUST. m2
42.72
132.10
5,643.31
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
42.72
04.05.03
CERRAMIENTO VERTICAL Y HORIZONTAL C/DRYWALL SUPERBOARD ST 8MM , PARANTES m2 DE 89MM 53.16
91.26
4,851.38
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
53.16
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
91.38
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
177.41
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
150.90
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
85.32
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
81.33
0.00
0.00%
0.00
0.00%
04.06 04.06.01 04.07 04.07.01 04.08 04.08.01 04.09 04.09.01 04.10 04.10.01 04.11
REVOQUES ENLUCIDOS Y MOLDURAS TARRAJEO EN INTERIORES Y EXTERIORES MEZCLA 1:5 C:A E=1.5CM
2,338.41 m2
91.38
25.59
CIELO RASO FALSO CIELO RASO C/BALDOSA ACUSTICA C/SUSPENCION REBAJADA
m2
177.41
66.31
PISOS PISO DE CERAMICO 45 X 45CM ANTIDESLIZANTE
m2
150.90
51.14
11,764.06
0.00
7,717.03
0.00
4,393.13 m2
85.32
51.49
REVESTIMIENTOS ENCHAPE CON CERAMICO EN MESON DE CONCRETO
0.00
7,717.03
ZOCALOS Y CONTRAZOCALOS ZOCALO DE CERAMICO 25 X 40 CM
2,338.41 11,764.06
4,393.13
0.00
4,187.68 m2
81.33
51.49
CUBIERTAS
4,187.68
0.00
7,373.24
0.00 0.00 0.00 0.00 0.00
04.11.01
COBERTURA PERFIL GRAN ONDA 1.10 m X 2.40 m E=1.40 mm
m2
155.66
21.87
3,404.28
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
155.66
04.11.02
CUMBRERAS P/COBERTURA
m
26.70
62.31
1,663.68
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
26.70
04.11.03
CANALETA DE PLANCHA GALVANIZADA INCLUYE COLOCACION
m
53.40
43.17
2,305.28
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
53.40
0.00
0.00%
0.00
0.00%
04.12
CARPINTERIA DE MADERA
5,540.28
04.12.01
PUERTA DE MADERA CEDRO C/MARCO DE 2"x4
04.12.02
PUERTA CONTRAPLACADA DE MADERA CEDRO C/TRIPLAY DE 4 MM + MARCO CEDROm2 2X4"
04.13
CARPINTERIA METALICA
m2
11.52
399.20
4,598.78
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
11.52
3.84
245.18
941.49
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
3.84
0.00
0.00%
0.00
0.00%
23,843.06
IT EM
10 10.01 10.01.01 10.02
D EC R IPC ION
UND
M ET .
P.U .
INSTALACIONES ELECTRICAS GENERALES TRABAJOS PRELIMINARES TRAZO, NIVELACION Y REPLANTEO INST. ELECTRICAS
m
974.63
2.15
MOVIMIENTO DE TIERRAS
A C U M U LA D O A N T ER IOR
PA R C IA L
PA R C IA L
%
EJEC U T A D O JU N IO
PA R C IA L
%
579,785.96
38,562.65
6.65%
14,946.88
0.00%
2,095.45
2,095.45
100.00%
0.00
0.00%
2,095.45
100.00%
15,623.33
74.22%
2,095.45
974.63
21,049.57
0.00
0.00
0.00%
5,426.51
25.78%
A C U M U LA D O T OT A L
SA LD O POR EJEC U T A R
974.63
0.00
10.02.01
EXCAVACION MANUAL DE ZANJA P/TUBERIAS
m3
233.91
27.36
6,399.78
175.20
4,793.47
74.90%
58.71
1,606.31
25.10%
233.91
0.00
10.02.02
EXCAVACION MANUAL DE HUECO PARA PUESTA A TIERRA
m3
10.00
46.47
464.70
7.50
348.53
75.00%
2.50
116.18
25.00%
10.00
0.00
10.02.03
CAMA DE APOYO PARA TUBERIA DE 10CM.
m2
389.85
9.78
3,812.73
291.79
2,853.66
74.85%
98.07
959.08
25.15%
389.85
0.00
10.02.04
RELLENO COMPACTADO CON MATERIAL PROPIO
m3
194.93
27.17
5,296.25
146.09
3,969.35
74.95%
48.84
1,326.90
25.05%
194.93
0.00
10.02.05
RELLENO CON ARENA FINA
m3
38.99
69.39
2,705.52
29.40
2,040.00
75.40%
9.59
665.78
24.61%
38.99
0.00
10.02.06
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
58.78
22.79
1,339.60
43.87
999.73
74.63%
14.91
339.87
25.37%
58.78
0.00
10.02.07
ELIMINACION DE MATERIAL EXCEDENTE
m3
58.78
17.54
1,031.00
35.27
618.60
60.00%
23.51
412.40
40.00%
58.78
0.00
0.00
0.00%
0.00
0.00%
10.03
ALAMBRES Y CABLES ELECTRICOS
73,649.55
10.03.01
CONDUCTOR CABLEADO 3-1X95+1X95MM2 N2XOH
m
270.00
181.08
48,891.60
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
270.00
10.03.02
CONDUCTOR CABLEADO 3X25+1X25+T10MM2 NHX-90
m
101.00
55.63
5,618.63
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
101.00
10.03.03
CONDUCTOR CABLEADO 3x6+1x6+T10 MM2 NHX-90
m
388.00
19.93
7,732.84
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
388.00
10.03.04
CONDUCTOR CABLEADO 2x10+T10 MM2 NHX-90
m
66.00
20.26
1,337.16
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
66.00
10.03.05
CONDUCTOR CABLEADO 2x6+T10 MM2 NHX-90
m
109.00
13.68
1,491.12
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
109.00
10.03.06
CONDUCTOR CABLEADO 2x6 MM2 N2XOH+1X4MM2 NH-80
m
284.28
5.79
1,645.98
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
284.28
10.03.07
CONDUCTOR CABLEADO 2X4+1X4 MM2 NH-80
m
336.00
7.57
2,543.52
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
336.00
10.03.08
CONDUCTOR CABLEADO 2X2.5+1X2.5 MM2 NH-80
m
668.00
6.15
4,108.20
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
668.00
10.03.09
CONDUCTOR CABLEADO 3X4+1X4 MM2 NH-80
m
30.00
9.35
280.50
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
30.00
0.00
0.00%
0.00
0.00%
10.04
ELECTRODUCTO DE PVC
72,517.62
10.04.01
SUMINIST. E INSTALACION DE ELECTRODUCTO HFT 20 mm
m
3,012.00
13.45
40,511.40
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
3012.00
10.04.02
SUMINIST. E INSTALACION DE ELECTRODUCTO HFT 35 mm
m
701.83
22.48
15,777.14
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
701.83
10.04.03
SUMINIST. E INSTALACION DE ELECTRODUCTO HFT 40 mm
m
80.80
31.45
2,541.16
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
80.80
10.04.04
SUMINIST. E INSTALACION DE ELECTRODUCTO HFT 90 mm
m
216.00
63.37
13,687.92
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
216.00
10.05
402.68
1.56%
0.00
0.00%
10.05.01
PLACAS Y ACCESORIOS SUMINIST. E INSTALACION DE SALIDA PARA CENTRO DE LUZ
pto
130.00
49.21
25,752.17 6,397.30
3.00
147.63
2.31%
0.00
0.00
0.00%
3.00
127.00
10.05.02
SUMINIST. E INSTALACION DE SALIDA PARA INTERRUPTOR UNIPOLAR
pto
53.00
51.01
2,703.53
2.00
102.02
3.77%
0.00
0.00
0.00%
2.00
51.00
10.05.03
SUMINIST. E INSTALACION DE SALIDA PARA TOMACORRIENTE
pto
84.00
51.01
4,284.84
2.00
102.02
2.38%
0.00
0.00
0.00%
2.00
82.00
10.05.04
SUMINIST. E INSTALACION DE SALIDA PARA LUZ DE EMERGENCIA
pto
37.00
51.01
1,887.37
1.00
51.01
2.70%
0.00
0.00
0.00%
1.00
36.00
10.05.05
SUMINIST. E INSTALACION DE TOMACORRIENTE DOBLE CON T/TIERRA
pza
73.00
69.89
5,101.97
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
73.00
10.05.06
SUMINIST. E INSTALACION DE TOMACORRIENTE DOBLE CON T/TIERRA A PRUEBA DEpza AGUA
11.00
72.24
794.64
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
11.00
10.05.07
SUMINIST. E INSTALACION DE INTERRUPTOR UNIPOLAR SIMPLE
pza
39.00
52.29
2,039.31
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
39.00
10.05.08
SUMINIST. E INSTALACION DE INTERRUPTOR UNIPOLAR DOBLE
pza
8.00
63.46
507.68
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
8.00
10.05.09
SUMINIST. E INSTALACION DE INTERRUPTOR UNIPOLAR TRIPLE
pza
2.00
47.46
94.92
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
2.00
10.05.10
SUMINIST. E INSTALACION DE INTERRUPTOR CONMUTACION SIMPLE
pza
4.00
49.89
199.56
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
4.00
10.05.11
SUMINIST. E INSTALACION DE CAJA DE PASO CUADRADA
pto
15.00
62.21
933.15
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
15.00
10.05.12
SUMINIST. E INSTALACION DE CAJA DE PASO Y CONEXIÓN
pto
15.00
53.86
807.90
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
15.00
IT EM
10.06
D EC R IPC ION
UND
M ET .
P.U .
28,068.06
PA R C IA L
%
EJEC U T A D O JU N IO
PA R C IA L
%
A C U M U LA D O T OT A L
SA LD O POR EJEC U T A R
0.00
0.00%
0.00
0.00%
10.06.01
SUMINIST. E INSTALACION ARTEF. FLUORESCENTE DOBLE 2X28W MASTER
pza
20.00
220.07
4,401.40
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
20.00
10.06.02
SUMINIST. E INSTALACION ARTEF. FLUORESCENTE DOBLE 2X28W MASTER INDIKO pza
22.00
165.77
3,646.94
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
22.00
10.06.03
SUMINIST. E INSTALACION BRAQUETE TIPO RSP L/AHORRADOR 2X18W
pza
26.00
153.97
4,003.22
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
26.00
10.06.04
SUMINIST. E INSTALACION DE LUZ DE EMERGENCIA LED 7.5W
pza
16.00
152.49
2,439.84
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
16.00
10.06.05
SUMINIST. E INSTALACION SPOT LIGHT LED 20W. P/EMPOTRAR
pza
23.00
180.07
4,141.61
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
23.00
10.06.06
SUMINIST. E INSTALACION GALAXIE L/AHORRADOR 2X18W
pza
23.00
180.07
4,141.61
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
23.00
10.06.07
SUMINIST. E INSTALACION REFLECTOR HALOGENURO METALICO 400W
pza
4.00
489.86
1,959.44
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
4.00
10.06.08
FAROLA TIPO ESPEFERICA E-35HALOGENURO METALICO 70W
pza
8.00
280.07
2,240.56
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
8.00
10.06.09
LUMINARIA VAPOR DE SODIO 70W
pza
4.00
273.36
1,093.44
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
4.00
0.00
0.00%
0.00
0.00%
10.07
LUMINARIAS Y ACCESORIOS ELECTRICOS
A C U M U LA D O A N T ER IOR
PA R C IA L
TABLERO DE DISTRIBUCION
14,176.80
10.07.01
TABLERO GENERAL TRIFÁSICO 12 CKTOS TG-02 SISTEMA DE BARRAS 380/230 V
1.00
2,041.45
2,041.45
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.02
TABLERO DE DISTRIBUCION TRIFÁSICO 8 CKTOS SISTEMA DE BARRAS 220/380V, TDA-01 und
1.00
1,251.45
1,251.45
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.03
TABLERO DE DISTRIBUCION TRIFASICO 8 CKTOS SISTEMA DE BARRAS 220V TDA-02und
1.00
1,560.85
1,560.85
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.04
TABLERO DE DISTRIBUCION TRIFÁSICO 10 CKTOS SISTEMA DE BARRAS 380V TDA-03und
1.00
1,285.15
1,285.15
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.05
TABLERO DE DISTRIBUCION MONOFASICO 4 CKTOS SISTEMA DE BARRAS 380V STDA-03.01 und
1.00
942.85
942.85
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.06
TABLERO DE DISTRIBUCION MONOFASICO 6 CKTOS SISTEMA DE BARRAS 220 - TDA-04 und
1.00
794.55
794.55
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.07
TABLERO DE DISTRIBUCION MONOFASICO 6 CKTOS TDA-05
1.00
763.65
763.65
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.08
SUB TABLERO DE DISTRIBUCION TRIFÁSICO 12 CKTOS SISTEMA DE BARRAS 230V TDA-06 und
1.00
1,351.75
1,351.75
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.09
SUB TABLERO DE DISTRIBUCION TRIFÁSICO 8 CKTOS SISTEMA DE BARRAS 380V STDA-06.01 und
1.00
930.05
930.05
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.10
TABLERO DE DISTRIBUCION TTRIFASICO 10 CKTOS SISTEMA DE BARRAS 220 - TDA-07 und
1.00
1,462.15
1,462.15
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.11
SUB TABLERO DE DISTRIBUCION TRIFÁSICO 6 CKTOS SISTEMA DE BARRAS 380V TDB-01 und ELECTROBOMBA 1.00 1,025.75
1,025.75
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.07.12
SUB TABLERO DE DISTRIBUCION TRIFASICO 6 CKTOS SISTEMA DE BARRAS 220V TDB-02 und ELECTROBOMBA 1.00 767.15
767.15
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
11,624.12
43.24%
1,672.06
6.22%
10.08
und
und
SISTEMA DE PROTECCION Y EMPALMES
26,881.48
10.08.01
SUMINIST. E INSTALACION DE EMPALME SUBTERRANEO
pto
60.00
71.79
4,307.40
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
60.00
10.08.02
SUMINIST. E INSTALACION DE CINTA VULCANIZANTE
pto
24.00
316.91
7,605.84
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
24.00
10.08.03
SUMINIST. E INSTALACION DE PUESTA A TIERRA
jgo
4.00
1,672.06
6,688.24
2.00
3,344.12
50.00%
1.00
1,672.06
25.00%
3.00
1.00
10.08.04
SUMINIST. E INSTALACION DE BUZON P/CONEXIÓN ELECTRICA
glb
9.00
920.00
8,280.00
9.00
8,280.00
100.00%
0.00
0.00
0.00%
9.00
0.00
1,545.54
24.68%
0.00
0.00%
10.09
OTROS
6,262.06
10.09.01
POSTE C.A.C. 9/300
und
2.00
772.77
1,545.54
2.00
1,545.54
100.00%
0.00
0.00
0.00%
2.00
0.00
10.09.02
PASTORAL Fo Go PS/1.00/0.50/ 1 1/2'' DIAM C/ABRAZADERA
und
4.00
124.25
497.00
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
4.00
10.09.03
POSTE ORNAMENTAL DE TUBO DE FoNo 4'' X 4M
und
8.00
302.44
2,419.52
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
8.00
10.09.04
PRUEBA Y MEDICIONES ELECTRICAS
glb
2.00
900.00
1,800.00
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
2.00
0.00
0.00%
0.00
0.00%
10.10
RED PRIMARIA
10.10.01
TRANSFORMADOR DE POTENCIA 75KVA TRIFASICO 10/0.40-0.23 KV
10.10.02
CONDUCTOR CABLEADO N2XOH 1X50MM2
10.10.03 10.10.04 10.11 10.11.01
20,384.66 und
1.00
16,337.24
16,337.24
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
m
80.00
39.15
3,132.00
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
80.00
TABLERO DE DISTRIBUCION C/ABRAZADERA
cjto
1.00
560.30
560.30
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
DESMONTAJE TRANSFORMADOR 50 KVA
und
1.00
355.12
355.12
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
7,271.53
4.94%
4,761.31
3.24% -19.68
INSTALACIONES DE COMUNICACIONES
147,074.32
1,801.23
85.74%
1,479.13
0.00%
10.11.01.01
MOVIMIENTO DE TIERRAS EXCAVACION MANUAL DE ZANJA P/TUBERIAS
m3
36.00
27.36
2,100.72 984.96
31.92
873.33
88.67%
23.76
650.07
66.00%
55.68
10.11.01.02
CAMA DE APOYO PARA TUBERIA DE 10CM.
m2
6.00
9.78
58.68
5.32
52.03
88.67%
1.32
12.91
22.00%
6.64
-0.64
10.11.01.03
RELLENO COMPACTADO CON MATERIAL PROPIO
m3
30.00
27.17
815.10
26.70
725.44
89.00%
28.98
787.39
96.60%
55.68
-25.68
10.11.01.04
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
6.00
22.79
136.74
3.83
87.29
63.83%
0.80
18.23
13.33%
4.63
1.37
10.11.01.05
ELIMINACION DE MATERIAL EXCEDENTE
m3
6.00
17.54
105.24
3.60
63.14
60.00%
0.60
10.52
10.00%
4.20
1.80
IT EM
10.14.03
D EC R IPC ION
UND
M ET .
P.U .
1,100.82
PA R C IA L
%
EJEC U T A D O JU N IO
PA R C IA L
%
A C U M U LA D O T OT A L
SA LD O POR EJEC U T A R
0.00
0.00%
1,100.82
0.00%
10.14.03.01
SARDINEL SUMERGIDO F'C=175 KG/CM2
m3
0.74
336.35
248.90
0.00
0.00
0.00%
0.74
248.90
100.00%
0.74
0.00
10.14.03.02
PISO DE CONCRETO F'C=175 KG/CM2 E=10CM..ACAB. CEMENTO PULIDO INC. CORTEm2
16.93
42.97
727.48
0.00
0.00
0.00%
16.93
727.48
100.00%
16.93
0.00
10.14.03.03
ENCOFRADO Y DESENCOFRADO NORMAL PARA GRADAS Y PISOS
3.72
33.45
124.43
0.00
0.00
0.00%
3.72
124.43
100.00%
3.72
0.00
0.00
0.00%
1,279.86
0.00%
10.14.04
OBRAS DE CONCRETO SIMPLE
A C U M U LA D O A N T ER IOR
PA R C IA L
m2
OBRAS DE CONCRETO ARMADO
1,279.86
10.14.04.01
SARDINEL SUMERGIDO: CONCRETO F'C=175 KG/CM2
m3
0.57
336.35
191.72
0.00
0.00
0.00%
0.57
191.72
100.00%
0.57
0.00
10.14.04.02
LOSA ARMADA: CONCRETO F'C=175 KG/CM2
m2
3.77
42.97
162.00
0.00
0.00
0.00%
3.77
162.00
100.00%
3.77
0.00
10.14.04.03
LOSA ARMADA: ENCOFRADO Y DESENCOFRADO NORMAL
m2
24.71
33.45
826.55
0.00
0.00
0.00%
24.71
826.55
100.00%
24.71
0.00
10.14.04.04
LOSA ARMADA: ACERO DE REFUERZO FY=4200 KG/CM2
kg
21.84
4.56
99.59
0.00
0.00
0.00%
21.84
99.59
100.00%
21.84
0.00
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
46.53
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
13.80
0.00
0.00%
0.00
0.00%
10.14.05 10.14.05.01 10.14.06 10.14.06.01 10.14.07
MUROS Y TABIQUES
6,146.61
TABIQUE DRYWALL SUPERBOARD PRO 8mm, PARANTES DE 89MM, C/AISLAMIENTOm2 ACUST.
46.53
132.10
ZOCALOS Y CONTRAZOCALOS CONTRAZOCALO DE CERAMICO H=0.10m
6,146.61
0.00
302.91 m
13.80
21.95
CUBIERTAS
302.91
0.00
698.13
0.00 0.00
10.14.07.01
COBERTURA PERFIL GRAN ONDA 1.10 m X 2.40 m E=1.40 mm
m2
21.46
21.87
469.33
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
21.46
10.14.07.02
CANALETA DE PLANCHA GALVANIZADA INCLUYE COLOCACION
m
5.30
43.17
228.80
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
5.30
0.00
0.00%
0.00
0.00%
10.14.08
CARPINTERIA METALICA
2,006.38
10.14.08.01
TIJERAL T-6 C/PERFIL GALVANIZADO INC. IZADO Y MONTAJE
und
5.00
186.94
934.70
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
5.00
10.14.08.02
VIGUETA VG-1 C/PERFIL GALVANIZADO INC. MONTAJE
m
53.00
8.89
471.17
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
53.00
10.14.08.03
PUERTA METALICA C/MALLA COCADA SEGUN DETALLE
m2
4.16
104.36
434.14
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
4.16
10.14.08.04
VENTANA METALICA C/MALLA COCADA
m2
1.92
86.65
166.37
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.92
0.00
0.00%
0.00
0.00%
10.14.09
CERRAJERIA
258.12
10.14.09.01
CERRADURA TIPO PARCHE EN PUERTA - 03 GOLPES
und
1.00
100.12
100.12
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
1.00
10.14.09.02
BISAGRA CAPUCHINA ALUMINIZADA 4"x4"
pza
8.00
19.75
158.00
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
8.00
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
93.06
0.00
0.00%
0.00
10.14.10 10.14.10.01 10.14.11
PINTURA PINTURA LATEX EN MUROS INTERIORES Y EXTERIORES
785.43 m2
93.06
8.44
VARIOS
785.43
0.00
293.62
0.00
0.00
0.00%
244.61
0.00%
10.14.11.01
CURADO DE ESTRUCTURAS HORIZONTALES
m2
20.71
1.14
23.61
0.00
0.00
0.00%
20.71
23.61
100.00%
20.71
10.14.11.02
JUNTA DE 3/4" CON RELLENO MATERIAL ELASTOMERICO
m
13.80
17.00
234.60
0.00
0.00
0.00%
13.00
221.00
94.20%
13.00
0.80
10.14.11.03
LIMPIEZA FINAL DE OBRA
m2
20.71
1.71
35.41
0.00
0.00
0.00%
0.00
0.00
0.00%
0.00
20.71
11
7,779.35
95.82%
150.71
0.00%
11.01
MITIGACION Y CONTROL AMBIENTAL CAPACITACION PERMANENTE AL PERSONAL SOBRE SALUD AMBIENTAL
mes
3.00
450.00
1,350.00
2.88
1,296.00
96.00%
0.08
36.00
2.67%
2.96
0.04
11.02
CONTROL DE DESECHOS SOLIDOS
m2
200.00
5.09
1,018.00
192.30
978.81
96.15%
2.90
14.76
1.45%
195.20
4.80
11.03
READECUACION AMBIENTAL DE CASETA DE GUARDIANIA,ALMACEN Y OFICINA DEL RESIDENTE, m2 VESTUARIO 87.50 Y SS.HH. 3.42
299.25
80.60
275.65
92.11%
3.20
10.94
3.66%
83.80
3.70
11.04
CONTROL DE PROPAGACION DE PARTICULAS VOLATILES
m2
1,173.08
551.35
1,123.18
527.89
95.75%
0.00
0.00
0.00%
1123.18
49.90
11.05
REVISION PERIODICA DEL BUEN FUNCIONAMIENTO DE LOS EQUIPOS
mes
3.00
300.00
900.00
2.87
861.00
95.67%
0.08
24.00
2.67%
2.95
0.05
11.06
HABILITACION DE AREAS DE DESMONTE
glb
1.00
2,500.00
2,500.00
0.96
2,400.00
96.00%
0.02
50.00
2.00%
0.98
0.02
11.07
MITIGACION DE RUIDOS
glb
1.00
1,500.00
1,500.00
0.96
1,440.00
96.00%
0.01
15.00
1.00%
0.97
0.03
1.00 2.00
COSTO DIRECTO GASTOS GENERALES (11.00 %) ==============================
3.00
SUB PRESUPUESTO (CD + GG)
4.00 5.00 6.00 7.00 8.00 9.00
GASTOS DE ESTUDIO (2.41 % SP) GASTOS DE SUPERVISION (5.00 % SP) GASTOS DE LIQUIDACION GASTOS ADMINISTRATIVOS (1.00 % SP) ==============================
PRESUPUESTO TOTAL
8,118.60
0.47
1,954,072.39 S/. 214,947.96 ============
648,491.86 S/. 71,334.10 ============
S/. 2,169,020.35
S/. 719,825.97
S/. 52,282.00 S/. 108,451.02 S/. 26,028.24 S/. 21,690.20 ============
S/. 2,377,471.81
33.19%
104,193.83 S/. 11,461.32 ============
S/. 115,655.14
5.33%
2. VALORIZACION MAYORES METRADOS:
ITEM
DECRIPCION
UND
MET.
P.U.
ACUMULADO ACTUAL
PARCIAL
PARCIAL
%
ejecutado junio
PARCIAL
%
SALDO POR EJECUTAR
PARCIAL
%
08.03.02
CURADO DE ELEMENTOS HORIZONTALES
m2
91.44
1.14
104.24
70.23
80.07
76.81%
70.23
80.07
76.81%
21.21
24.18
08.03.03
SOLAQUEO EN BORDES DE VEREDAS DE CONCRETO
m2
13.08
5.22
68.28
13.08
68.28
100.00%
13.08
68.28
100.00%
0.00
0.00
0.00%
0.00
0.00%
0.00
0.00%
6,747.47
100.00%
08.04
INSTALACION DE AREAS VERDES
6,747.47
23.19%
08.04.01
MULLIDO DE CAMPO
m2
168.96
3.42
577.84
0.00
0.00
0.00%
0.00
0.00
0.00%
168.96
577.84
100.00%
08.04.02
SUMINISTRO Y ESPARCIDO DE TIERRA DE CHACRA
m3
33.80
69.51
2,349.44
0.00
0.00
0.00%
0.00
0.00
0.00%
33.80
2,349.44
100.00%
08.04.03
SUMINISTRO E INSTALACION DE CESPED
m2
168.96
22.61
3,820.19
0.00
0.00
0.00%
0.00
0.00
0.00%
168.96
3,820.19
100.00%
31,930.15
16,340.28
51.18%
17,615.53
55.17%
14,314.62
44.83%
9,884.67
1,012.39
10.24%
1,012.39
10.24%
8,872.29
89.76%
3,213.79
511.95
15.93%
511.95
15.93%
2,701.84
84.07% 73.96%
09 09.02 09.02.01
INSTALACIONES SANITARIAS INSTALACION DE SISTEMA AGUA FRIA MOVIMIENTO DE TIERRAS
09.02.01.01
EXCAVACION DE ZANJAS
m3
13.70
39.07
535.26
3.57
139.40
26.04%
3.57
139.40
26.04%
10.13
395.86
09.02.01.02
CAMA DE APOYO PARA TUBERIA E=0.10M.
m
85.63
14.28
1,222.80
20.00
285.60
23.36%
20.00
285.60
23.36%
65.63
937.20
09.02.01.03
RELLENO CON MATERIAL PROPIO
m3
10.28
27.17
279.31
3.20
86.94
31.13%
3.20
86.94
31.13%
7.08
192.36
68.87%
09.02.01.04
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
29.33
22.57
661.98
0.00
0.00
0.00%
0.00
0.00
0.00%
29.33
661.98
100.00%
09.02.01.05
ELIMINACION DE MATERIAL EXCEDENTE
m3
29.33
17.54
514.45
0.00
0.00
0.00%
0.00
0.00
0.00%
29.33
514.45
100.00%
6,170.44
92.50%
09.02.02
RED DE AGUA FRIA
6,670.88
76.64%
500.44
7.50%
500.44
7.50%
09.02.02.03
RED DE DISTRIBUCION TUBERIA DE 1" PVC-SAP
m
140.47
19.51
2,740.57
20.00
390.20
14.24%
20.00
390.20
14.24%
120.47
2,350.37
85.76%
09.02.02.04
RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP.
m
16.74
14.10
236.03
0.00
0.00
0.00%
0.00
0.00
0.00%
16.74
236.03
100.00%
09.02.02.05
CODO 90° PVC SAP C-10 D=2"
und
1.00
21.48
21.48
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
21.48
100.00%
09.02.02.07
CODO 90° PVC SAP C-10 D=1"
und
82.00
16.78
1,375.96
0.00
0.00
0.00%
0.00
0.00
0.00%
82.00
1,375.96
100.00%
09.02.02.09
CODO 90° PVC SAP C-10 D=1/2"
und
1.00
13.78
13.78
8.00
110.24
800.00%
8.00
110.24
800.00%
-7.00
-96.46
-700.00%
09.02.02.10
TEE PVC SAP C-10 D=2"
und
7.00
17.78
124.46
0.00
0.00
0.00%
0.00
0.00
0.00%
7.00
124.46
100.00%
09.02.02.11
TEE PVC SAP C-10 D=1"
und
57.00
16.38
933.66
0.00
0.00
0.00%
0.00
0.00
0.00%
57.00
933.66
100.00%
09.02.02.14
REDUCCION PVC SAP 1" A 1/2"
und
73.00
16.78
1,224.94
0.00
0.00
0.00%
0.00
0.00
0.00%
73.00
1,224.94
100.00%
21,788.38
15,327.90
70.35%
16,603.15
76.20%
5,185.24
23.80%
15,107.08
15,327.90
101.46%
15,327.90
101.46%
-220.81
-1.46% -2.72%
09.03 09.03.01
SISTEMA DE DESAGUE MOVIMIENTO DE TIERRAS
09.03.01.01
EXCAVACION DE ZANJAS
m3
161.60
39.07
6,313.71
166.00
6,485.62
102.72%
166.00
6,485.62
102.72%
-4.40
-171.91
09.03.01.02
CAMA DE APOYO PARA TUBERIA E=0.10M.
m
207.61
14.28
2,964.67
207.61
2,964.67
100.00%
207.61
2,964.67
100.00%
0.00
0.00
0.00%
09.03.01.03
RELLENO CON MATERIAL PROPIO
m3
207.61
27.17
5,640.76
209.41
5,689.67
100.87%
209.41
5,689.67
100.87%
-1.80
-48.91
-0.87%
09.03.01.04
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
4.66
22.79
106.20
4.66
106.20
100.00%
4.66
106.20
100.00%
0.00
0.00
0.00%
09.03.01.05
ELIMINACION DE MATERIAL EXCEDENTE
m3
4.66
17.54
81.74
4.66
81.74
100.00%
4.66
81.74
100.00%
0.00
0.00
0.00%
0.00
0.00%
1,275.25
19.09%
5,406.05
80.91%
09.03.02
RED DE DESAGÜE
6,681.30
09.03.02.04
SUMINISTRO E INSTALACION DE TUBERIA PVC SAL 4"
m
47.84
19.55
935.27
0.00
0.00
0.00%
0.00
0.00
0.00%
47.84
935.27
100.00%
09.03.02.05
SUMINISTRO E INSTALACION DE TUBERIA PVC SAL 2"
m
235.61
16.03
3,776.83
0.00
0.00
0.00%
0.00
0.00
0.00%
235.61
3,776.83
100.00%
09.03.02.07
CODO PVC SAL 4"X45°
pza
3.00
12.85
38.55
0.00
0.00
0.00%
4.00
51.40
133.33%
-1.00
-12.85
-33.33%
09.03.02.09
CODO PVC SAL 2"X45°
pza
49.00
9.35
458.15
0.00
0.00
0.00%
49.00
458.15
100.00%
0.00
0.00
0.00%
09.03.02.10
CODO PVC SAL 2"X90°
und
125.00
11.78
1,472.50
0.00
0.00
0.00%
65.00
765.70
52.00%
60.00
706.80
48.00%
257.09
0.00
0.00%
0.00
0.00%
257.09
100.00%
257.09
0.00
0.00%
0.00
0.00%
257.09
100.00%
257.09
100.00%
09.04 09.04.01 09.04.01.01
10 10.03
INSTALACION DE SISTEMA DE AGUA CALIENTE RED DE AGUA CALIENTE SALIDA DE AGUA CALIENTE CON TUBERIA DE CPVC 1/2"
m
14.75
17.43
INSTALACIONES ELECTRICAS GENERALES ALAMBRES Y CABLES ELECTRICOS
257.09
0.00
0.00
0.00%
0.00
0.00%
25,310.71
3,238.31
12.79%
3,238.31
12.79%
22,072.40
87.21%
2,301.65
0.00
0.00%
0.00
0.00%
2,301.65
100.00%
0.00
14.75
10.03.07
CONDUCTOR CABLEADO 2X4+1X4 MM2 NH-80
m
170.00
7.57
1,286.90
0.00
0.00
0.00%
0.00
0.00
0.00%
170.00
1,286.90
100.00%
10.03.08
CONDUCTOR CABLEADO 2X2.5+1X2.5 MM2 NH-80
m
165.00
6.15
1,014.75
0.00
0.00
0.00%
0.00
0.00
0.00%
165.00
1,014.75
100.00%
0.00
0.00%
0.00
0.00%
591.15
100.00%
10.05
PLACAS Y ACCESORIOS
591.15
DECRIPCION
ITEM
UND
P.U.
MET.
ACUMULADO ACTUAL
PARCIAL
%
PARCIAL
ejecutado junio
%
PARCIAL
SALDO POR EJECUTAR
%
PARCIAL
10.05.01
SUMINIST. E INSTALACION DE SALIDA PARA CENTRO DE LUZ
pto
5.00
49.21
246.05
0.00
0.00
0.00%
0.00
0.00
0.00%
5.00
246.05
100.00%
10.05.02
SUMINIST. E INSTALACION DE SALIDA PARA INTERRUPTOR UNIPOLAR pto
1.00
51.01
51.01
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
51.01
100.00%
10.05.03
SUMINIST. E INSTALACION DE SALIDA PARA TOMACORRIENTE
pto
2.00
51.01
102.02
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
102.02
100.00%
10.05.05
SUMINIST. E INSTALACION DE TOMACORRIENTE DOBLE CON T/TIERRA
pza
2.00
69.89
139.78
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
139.78
100.00%
10.05.07
SUMINIST. E INSTALACION DE INTERRUPTOR UNIPOLAR SIMPLE
pza
1.00
52.29
52.29
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
52.29
100.00%
0.00
0.00%
0.00
0.00%
2,832.21
100.00%
10.06
2,832.21
LUMINARIAS Y ACCESORIOS ELECTRICOS
10.06.04
SUMINIST. E INSTALACION DE LUZ DE EMERGENCIA LED 7.5W
pza
1.00
152.49
152.49
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
152.49
100.00%
10.06.06
SUMINIST. E INSTALACION GALAXIE L/AHORRADOR 2X18W
pza
4.00
180.07
720.28
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
720.28
100.00%
10.06.07
SUMINIST. E INSTALACION REFLECTOR HALOGENURO METALICO 400W pza
4.00
489.86
1,959.44
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
1,959.44
100.00%
920.00
33.33%
920.00
33.33%
1,840.00
66.67%
920.00
33.33%
920.00
33.33%
1,840.00
66.67%
2,318.31
75.00%
2,318.31
75.00%
2,318.31
75.00%
2,318.31
75.00%
0.00
0.00%
0.00
0.00%
10.08 10.08.04 10.09 10.09.01 10.11
2,760.00
SISTEMA DE PROTECCION Y EMPALMES SUMINIST. E INSTALACION DE BUZON P/CONEXIÓN ELECTRICA
glb
3.00
920.00
und
4.00
772.77
1.00
3,091.08
OTROS POSTE C.A.C. 9/300
2,760.00 3,091.08
3.00
13,734.62
INSTALACIONES DE COMUNICACIONES
1.00 3.00
2.00
772.77 1.00
25.00%
772.77
25.00%
13,734.62
100.00%
0.00
0.00%
0.00
0.00%
1,236.17
100.00%
10.11.01.01
EXCAVACION MANUAL DE ZANJA P/TUBERIAS
m3
19.68
27.36
538.44
0.00
0.00
0.00%
0.00
0.00
0.00%
19.68
538.44
100.00%
10.11.01.03
RELLENO COMPACTADO CON MATERIAL PROPIO
m3
25.68
27.17
697.73
0.00
0.00
0.00%
0.00
0.00
0.00%
25.68
697.73
100.00%
0.00
0.00%
0.00
0.00%
217.02
100.00%
0.00
0.00%
0.00
0.00%
217.02
100.00%
0.00
0.00%
0.00
0.00%
12,281.43
100.00%
10.11.01
10.11.03 10.11.03.06 10.11.06
1,236.17
MOVIMIENTO DE TIERRAS
217.02
SALIDA, CONDUCTOS Y/O TUBERIAS SUMINIST. E INSTALACION DE CAJA PASE DE 8'' X 8'' X 3''
und
6.00
36.17
PUNTO DE RED DE UN PUERTO
10.11.06.03
CABLEADO
11
MITIGACION Y CONTROL AMBIENTAL
12
AMPLIACION DE LOS SERVICIOS HIGIENICOS
0.00
12,281.43
CABLEADO ESTRUCTURADO
10.11.06.01
217.02
0.00
6.00
pto
7.00
261.21
1,828.47
0.00
0.00
0.00%
0.00
0.00
0.00%
7.00
1,828.47
100.00%
m
952.00
10.98
10,452.96
0.00
0.00
0.00%
0.00
0.00
0.00%
952.00
10,452.96
100.00%
48,494.91 S/. 5,334.44 ============
48,254.65 S/. 5,308.01 ============
1.00 2.00
COSTO DIRECTO GASTOS GENERALES (11.00 %) ==============================
96,749.53 S/. 10,642.45 ============
47,219.66 S/. 5,194.16 ============
3.00
SUB PRESUPUESTO (CD + GG)
S/. 107,391.98
S/. 52,413.82
S/. 53,829.35
S/. 53,562.66
4.00 5.00 6.00 7.00 8.00 9.00
GASTOS DE ESTUDIO (2.41 % SP) GASTOS DE SUPERVISION (5.00 % SP) GASTOS DE LIQUIDACION GASTOS ADMINISTRATIVOS (1.00 % SP) ==============================
S/. 0.00 S/. 5,369.60 S/. 0.00 S/. 0.00 ============
S/. 0.00 S/. 2,620.69 S/. 0.00 S/. 0.00 ============
S/. 0.00 S/. 2,691.47 S/. 0.00 S/. 0.00 ============
S/. 0.00 S/. 2,678.13 S/. 0.00 S/. 0.00 ============
PRESUPUESTO TOTAL
S/. 112,761.58
S/. 55,034.52
S/. 56,520.82
S/. 56,240.80
48.81%
50.12%
49.88%
3. VALORIZACION PARTIDAS NUEVAS:
ITEM
09 09.02 09.02.02
DECRIPCION
UND
ACUMULADO ACTUAL
MET.
INSTALACIONES SANITARIAS INSTALACION DE SISTEMA AGUA FRIA RED DE AGUA FRIA
PARCIAL
%
ejecutado junio
PARCIAL
%
SALDO POR EJECUTAR
PARCIAL
%
30,616.03
62.46%
39,719.59
81.04%
9,294.31
18.96%
80.32
0.57%
4,335.91
30.94%
9,676.52
69.06%
80.32
0.78%
4,335.91
42.08%
5,966.89
57.92%
09.02.02.21
CODO DE 1/2" DE F.G.
und
83.00
4.00
41.08
4.82%
60.00
616.20
72.29%
23.00
236.21
27.71%
09.02.02.22
CODO F.G. D=3/4" CON ROSCA
und
13.00
0.00
0.00
0.00%
0.00
0.00
0.00%
13.00
185.51
100.00%
09.02.02.23
TUBO PVC SAP C-10 D=3/4" CON ROSCA
m
35.00
0.00
0.00
0.00%
35.00
295.75
100.00%
0.00
0.00
0.00%
09.02.02.24
TUBO DE F.G. DE 1/2" PESADO
m
10.00
0.00
0.00
0.00%
0.00
0.00
0.00%
10.00
219.80
100.00%
09.02.02.25
CODO PVC SAP C-10 D=3/4" CON ROSCA
und
13.00
0.00
0.00
0.00%
13.00
79.30
100.00%
0.00
09.02.02.26
CRUCETA PVC SAP C-10 D=1" CON ROSCA
und
4.00
0.00
0.00
0.00%
4.00
68.00
100.00%
0.00
0.00
0.00%
09.02.02.27
UNION UNIVERSAL PVC SAP C-10 D=2"
und
6.00
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
39.60
100.00%
09.02.02.28
UNION SIMPLE PVC SAP C-10 D=2" C/R
und
45.00
0.00
0.00
0.00%
0.00
0.00
0.00%
45.00
3,064.50
100.00%
09.02.02.29
UNION SIMPLE PVC SAP D=1" C/R
und
15.00
0.00
0.00
0.00%
15.00
331.50
100.00%
0.00
0.00
0.00%
09.02.02.30
UNION UNIVERSAL PVC SAP C-10 D=1/2"
und
12.00
0.00
0.00
0.00%
12.00
73.20
100.00%
0.00
0.00
0.00%
09.02.02.31
UNION SIMPLE F.G. D=1/2''
und
12.00
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
817.20
100.00%
09.02.02.32
TAPON MACHO F.G. SAP C-10 D=1/2"
und
101.00
0.00
0.00
0.00%
101.00
1,007.98
100.00%
0.00
0.00
0.00%
09.02.02.33
TAPON MACHO PVC SAP C-10 D=3/4"
und
20.00
0.00
0.00
0.00%
0.00
0.00
0.00%
20.00
130.00
100.00%
09.02.02.34
TAPON HEMBRA PVC SAP C-10 D=2"
und
2.00
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
13.00
100.00%
09.02.02.35
TAPON HEMBRA PVC SAP C-10 D=1"
und
10.00
0.00
0.00
0.00%
4.00
26.00
40.00%
6.00
39.00
60.00%
09.02.02.36
TAPON HEMBRA PVC SAP C-10 D=1/2"
und
36.00
0.00
0.00
0.00%
36.00
304.56
100.00%
0.00
0.00
0.00%
09.02.02.37
TAPON HEMBRA F.G. D=1/2"
und
4.00
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
30.36
100.00%
09.02.02.38
REDUCCION PVC SAP C-10 1" A 3/4"
und
12.00
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
96.00
100.00%
09.02.02.39
REDUCCION PVC SAP C-10 2" A 3/4"
und
2.00
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
16.00
100.00%
09.02.02.40
NIPLE PVC SAP C-10 3/4" X 2"
und
52.00
0.00
0.00
0.00%
0.00
0.00
0.00%
52.00
312.00
100.00%
09.02.02.41
NIPLE PVC SAP C-10 1" X 2"
und
56.00
0.00
0.00
0.00%
56.00
336.00
100.00%
0.00
0.00
0.00%
09.02.02.42
NIPLE PVC SAP C-10 1/2" X 2"
und
24.00
0.00
0.00
0.00%
0.00
0.00
0.00%
24.00
144.00
100.00%
09.02.02.43
LLAVE DE PASO PVC SAP 1"
und
15.00
4.00
39.24
26.67%
15.00
147.15
100.00%
0.00
0.00
0.00%
09.02.02.44
LLAVE DE PASO PVC SAP 1/2"
und
6.00
0.00
0.00
0.00%
0.00
0.00
0.00%
6.00
58.86
100.00%
09.02.02.45
LLAVE DE PASO DE BRONCE D=3/4"
und
13.00
0.00
0.00
0.00%
13.00
127.53
100.00%
0.00
0.00
0.00%
09.02.02.46
GRIFO DE RIEGO 3/4"
und
13.00
0.00
0.00
0.00%
0.00
0.00
0.00%
13.00
302.77
100.00%
09.02.02.47
CAJA MEDIDOR DE AGUA
und
13.00
0.00
0.00
0.00%
13.00
922.74
100.00%
0.00
0.00
0.00%
09.02.02.48
UNION UNIVERSAL CON ROSCA PVC SAP C-10 3/4"
und
26.00
0.00
0.00
0.00%
0.00
0.00
0.00%
26.00
262.08
100.00%
09.02.03
TANQUE ELEVADO Y ACCESORIOS
0.00
0.00%
0.00
0.00%
0.00
0.00%
3,709.63
100.00%
09.02.03.04
VALVULAS ESFERICAS METALICAS D=1 1/2''
und
2.00
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
83.96
100.00%
09.02.03.05
NIPLE DE PVC SAP CON ROSCA 1 1/2" X 2 1/2"
und
12.00
0.00
0.00
0.00%
0.00
0.00
0.00%
12.00
112.92
100.00%
09.02.03.06
BUSHING PVC SAP C-10 CON ROSCA 2" A 1 1/2"
und
3.00
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
24.00
100.00%
09.02.03.07
BUSHING PVC SAP C-10 CON ROSCA 1 1/2" A 3/4"
und
2.00
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
16.00
100.00%
09.02.03.08
BUSHING PVC SAP C-10 CON ROSCA 1 1/2" A 1"
und
3.00
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
24.00
100.00%
09.02.03.13
NIPLE ROMPE AGUAS F.G. C-10 CON ROSCA 1 1/2" A 14"
und
1.00
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
20.48
100.00%
09.02.03.11
TUBO PVC SAP C-10 CON ROSCA 1 1/2"
m
42.00
0.00
0.00
0.00%
0.00
0.00
0.00%
42.00
275.94
100.00%
09.02.03.10
CODO PVC SAP C-10 CON ROSCA 1 1/2"
und
15.00
0.00
0.00
0.00%
0.00
0.00
0.00%
15.00
180.00
100.00%
09.02.03.12
VALVULA DE INGRESO CON BOLLA FLOTADORA METALICA 1 1/2"
und
1.00
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
57.15
100.00%
09.02.03.14
VALVULA DE PIE DE BRONCE CON CANASTILLA DE 1 1/2"
und
2.00
0.00
0.00
0.00%
0.00
0.00
0.00%
2.00
114.30
100.00%
09.02.03.09
TEE PVC SAP C-10 CON ROSCA 1 1/2"
und
5.00
0.00
0.00
0.00%
0.00
0.00
0.00%
5.00
50.00
100.00%
ITEM
09.04.02 09.04.02.04 09.04.02.04.01
DECRIPCION
UND
ACUMULADO ACTUAL
MET.
OTROS POZO SEPTICO - REPARACION MOVIMIENTO DE TIERRAS
PARCIAL
%
ejecutado junio
PARCIAL
%
SALDO POR EJECUTAR
PARCIAL
%
30,535.71
100.00%
30,535.71
100.00%
0.00
0.00%
4,436.29
100.00%
4,436.29
100.00%
0.00
0.00%
2,333.64
100.00%
2,333.64
100.00%
0.00
0.00%
09.04.02.04.01.01
CORTE CON MAQUINARIA EN TERRENO NORMAL
m3
43.87
43.87
270.68
100.00%
43.87
270.68
100.00%
0.00
0.00
0.00%
09.04.02.04.01.02
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
52.64
52.64
1,199.67
100.00%
52.64
1,199.67
100.00%
0.00
0.00
0.00%
09.04.02.04.01.03
ELIMINACION DE MATERIAL EXCEDENTE
m3
52.64
52.64
863.30
100.00%
52.64
863.30
100.00%
0.00
0.00
0.00%
255.09
100.00%
255.09
100.00%
0.00
0.00%
255.09
100.00%
255.09
100.00%
0.00
0.00%
464.76
100.00%
464.76
100.00%
0.00
0.00%
464.76
100.00%
464.76
100.00%
0.00
0.00%
741.96
100.00%
741.96
100.00%
0.00
0.00%
741.96
100.00%
741.96
100.00%
0.00
0.00%
640.84
100.00%
640.84
100.00%
0.00
0.00%
640.84
100.00%
640.84
100.00%
0.00
0.00%
26,099.42
100.00%
26,099.42
100.00%
0.00
0.00%
1,577.39
100.00%
1,577.39
100.00%
0.00
0.00%
09.04.02.04.02 09.04.02.04.02.01 09.04.02.04.03 09.04.02.04.03.01 09.04.02.04.04 09.04.02.04.04.01 09.04.02.04.05 09.04.02.04.05.01 09.04.02.05 09.04.02.05.01
OBRAS PRELIMINARES LIMPIEZA DEL TANQUE SEPTICO
glb
1.00
1.00
RESANE DE GRIETAS CON ADITIVO RESANE DE GRIETAS Y CANGREJERAS CON ADITIVOS
glb
1.00
1.00
TARRAJEO TARRAJEO INTERIOR CON IMPERMEABILIZANTE Y PUENTE DE ADHERENCIA glb
1.00
1.00
OTROS PINTURA EPOXICA
glb
1.00
1.00
TANQUE SEPTICO MOVIMIENTO DE TIERRAS
1.00 1.00 1.00 1.00
0.00 0.00 0.00 0.00
09.04.02.05.01.01
EXCAVACION MASIVA A MAQUINA EN TERRENO NORMAL CON MAQUINARIA. m3
29.85
29.85
309.84
100.00%
29.85
309.84
100.00%
0.00
0.00
0.00%
09.04.02.05.01.02
NIVELACION INTERIOR Y APISONADO MANUAL FONDO DE EXCAVACIONES m2
10.66
10.66
148.17
100.00%
10.66
148.17
100.00%
0.00
0.00
0.00%
09.04.02.05.01.03
ACARREO DE MATERIAL EXCEDENTE HASTA 30 MTS
m3
35.82
35.82
816.34
100.00%
35.82
816.34
100.00%
0.00
0.00
0.00%
09.04.02.05.01.04
ELIMINACION DE MATERIAL EXCEDENTE
m3
35.82
35.82
303.04
100.00%
35.82
303.04
100.00%
0.00
0.00
0.00%
24,522.03
100.00%
24,522.03
100.00%
09.04.02.05.02
CONCRETO ARMADO
0.00
09.04.02.05.02.01
CONCRETO EN TANQUE SEPTICO F'C=210 KG/CM2 + ADITIVO IMPERMEABILIZANTE m3
20.10
20.10
9,354.54
100.00%
20.10
9,354.54
100.00%
0.00
0.00
0.00%
09.04.02.05.02.02
ENCOFRADO Y DESENCOFRADO CARAVISTA EN TANQUE SEPTICO
m2
78.60
78.60
5,339.30
100.00%
78.60
5,339.30
100.00%
0.00
0.00
0.00%
09.04.02.05.02.03
ACERO GRADO 60 EN TANQUE SEPTICO
kg
1,523.75
1523.75
9,828.19
100.00%
1523.75
9,828.19
100.00%
0.00
0.00
0.00%
44,653.62
27.12%
120,011.50
72.88%
10 10.03
INSTALACIONES ELECTRICAS GENERALES
42,876.27
ALAMBRES Y CABLES ELECTRICOS
0.00
0.00%
0.00
0.00%
21,642.80
100.00%
10.03.10
CONDUCTOR CABLEADO 3X10 + 1X10 + T10MM2 N2XOH
m
165.83
0.00
0.00
0.00%
0.00
0.00
0.00%
165.83
4,756.00
100.00%
10.03.11
CONDUCTOR CABLEADO 3X6 + 1X6 + T10MM2 NHX-90
m
90.00
0.00
0.00
0.00%
0.00
0.00
0.00%
90.00
2,221.20
100.00%
10.03.12
CONDUCTOR CABLEADO 3X1X35 + 1X35 + T10MM2 N2XOH
m
72.50
0.00
0.00
0.00%
0.00
0.00
0.00%
72.50
4,870.55
100.00%
10.03.13
CONDUCTOR CABLEADO 3X1X16 + 1X16 + T10MM2 N2XOH
m
107.50
0.00
0.00
0.00%
0.00
0.00
0.00%
107.50
3,729.18
100.00%
10.03.14
CONDUCTOR CABLEADO 2X6 + T10MM2 N2XOH
m
253.23
0.00
0.00
0.00%
0.00
0.00
0.00%
253.23
4,732.87
100.00%
10.03.15
BIPLASTOFLEX NLT 2X4 MM2
m
100.00
0.00
0.00
0.00%
0.00
0.00
0.00%
100.00
1,333.00
100.00%
29,804.96
84.99%
29,804.96
84.99%
5,262.50
15.01%
10.04
ELECTRODUCTO DE PVC
10.04.05
SUMINISTRO E INSTALACION DE ELECTRODUCTO PVC SAP 3/4"
m
3,624.00
3080.40
20,638.68
85.00%
3080.40
20,638.68
85.00%
543.60
3,642.12
15.00%
10.04.06
SUMINISTRO E INSTALACION DE ELECTRODUCTO PVC SAP 1"
m
70.00
59.20
470.64
84.57%
59.20
470.64
84.57%
10.80
85.86
15.43%
10.04.07
SUMINISTRO E INSTALACION DE ELECTRODUCTO PVC SAP 1 1/4"
m
252.00
214.20
5,569.20
85.00%
214.20
5,569.20
85.00%
37.80
982.80
15.00%
10.04.08
SUMINISTRO E INSTALACION DE ELECTRODUCTO PVC SAP 2"
m
130.00
110.50
1,038.70
85.00%
110.50
1,038.70
85.00%
19.50
183.30
15.00%
10.04.09
SUMINISTRO E INSTALACION DE ELECTRODUCTO PVC SAP 3"
m
168.00
142.80
2,087.74
85.00%
142.80
2,087.74
85.00%
25.20
368.42
15.00%
0.00
0.00%
0.00
0.00%
5,462.94
100.00%
0.00
0.00%
0.00
0.00%
5,462.94
100.00%
10.06 10.06.10
LUMINARIAS Y ACCESORIOS ELECTRICOS SUMINISTRO E INSTALACION ARTEF. FLUORESCENTE DOBLE 2X36W REJILLA pza P/EMP
42.00
0.00
0.00
42.00
ITEM
ACUMULADO ACTUAL
10.11.03.18
SUMINIST. E INSTALACION DE CAJA PASE DE F° G° 4'' X 4' X 3''
und
3.00
0.00
0.00
0.00%
0.00
0.00
0.00%
3.00
50.73
100.00%
10.11.03.19
SUMINIST. E INSTALACION DE CAJA PASE DE F° G° 8'' X 8' X 3''
und
7.00
0.00
0.00
0.00%
0.00
0.00
0.00%
7.00
191.87
100.00%
10.11.07.03
SALIDA DE AUDIO
und
14.00
0.00
0.00
0.00%
0.00
0.00
0.00%
14.00
524.58
100.00%
10.11.07.04
SALIDA DE SENSORES DE HUMO
und
4.00
0.00
0.00
0.00%
0.00
0.00
0.00%
4.00
213.56
100.00%
10.11.07.05
SALIDA DE FREE WARE
und
1.00
0.00
0.00
0.00%
0.00
0.00
0.00%
1.00
82.39
100.00%
0.00
0.00%
0.00
0.00%
5,855.00
100.00%
0.00
0.00%
0.00
0.00%
5,855.00
100.00%
0.00
0.00%
0.00
0.00%
15,795.57
100.00%
0.00
0.00%
0.00
0.00%
15,795.57
100.00%
0.00
0.00%
0.00
0.00%
7,978.41
100.00%
0.00
0.00%
0.00
0.00%
7,978.41
100.00%
0.00
0.00%
0.00
0.00%
1,440.00
100.00%
0.00
0.00%
0.00
0.00%
1,440.00
100.00%
0.00
0.00%
0.00
0.00%
49,379.67
100.00%
0.00
0.00%
0.00
0.00%
49,379.67
100.00%
3,000.00
58.52%
3,000.00
58.52%
2,126.63
41.48%
0.00
0.00%
0.00
0.00%
888.08
100.00%
10.11.11.01 10.11.12 10.11.12.01 10.11.13 10.11.13.01 10.11.14 10.11.14.01 10.11.15 10.11.15.01 10.14
SISTEMA INALAMBRICO EXTERIOR SISTEMA INALAMBRICO EXTERIOR
glb
1.00
0.00
SISTEMA DE AUDIO SISTEMA DE AUDIO
glb
1.00
0.00
SISTEMA CONTRA INCENDIO CENTRAL DE HUMOS
glb
1.00
0.00
CERTIFICACION CERTIFICACION DE PUNTOS DE RED
glb
1.00
0.00
SISTEMA DE VIGILANCIA CAMARA DE SEGURIDAD
und
1.00
0.00
CASETA PARA GRUPO ELECTROGENO
10.14.07
CUBIERTAS
PARCIAL
%
0.00 0.00 0.00 0.00 0.00
PARCIAL
%
SALDO POR EJECUTAR
UND
10.11.11
MET.
ejecutado junio
DECRIPCION
1.00 1.00 1.00 1.00 1.00
PARCIAL
%
10.14.07.03
COBERTURA PERFIL GRAN ONDA 1.09 X 2.44 E= 5 mm
m2
21.46
0.00
0.00
0.00%
0.00
0.00
0.00%
21.46
683.72
100.00%
10.14.07.04
CANALETA DE PLANCHA GALVANIZADA INCLUYE COLOCACION
m
5.30
0.00
0.00
0.00%
0.00
0.00
0.00%
5.30
204.37
100.00%
0.00
0.00%
0.00
0.00%
1,238.55
100.00%
10.14.08
CARPINTERIA METALICA
10.14.08.05
TIJERAL T-6 C/PERFIL METALICO INC. IZADO Y MONTAJE
10.14.08.06
CORREAS DE F° N° 60 X 40 X 1.2 MM
10.14.12 10.14.12.01
5.00
0.00
0.00
0.00%
0.00
0.00
0.00%
5.00
987.45
100.00%
m
32.40
0.00
0.00
0.00%
0.00
0.00
0.00%
32.40
251.10
100.00%
3,000.00
100.00%
3,000.00
100.00%
0.00
0.00%
3,000.00
100.00%
3,000.00
100.00%
0.00
0.00%
7,943.27
28.92%
19,518.38
71.08%
49.83
35.73%
89.64
64.27%
49.83
35.73%
307.85
306.09%
MODULO 01: SERVICIOS DE ALIMENTACION ACONDICIONAMIENTO INSTALACIONES ELECTRICAS MODULO 01
11
MITIGACION Y CONTROL AMBIENTAL
12
AMPLIACION DE LOS SERVICIOS HIGIENICOS
12.01
und
glb
1.00
1.00
7,943.27
OBRAS PROVISIONALES
12.01.01 12.02
NIVELACION Y COMPACTACION DEL TERRENO
m2
52.63
18.80
MOVIMIENTO DE TIERRAS
12.02.01 12.03
EXCAVACION DE ZANJA
m3
1.38
4.22
12.04
LOSA DE CONCRETO F'C=150 KG/CM2 E=10CM.
m2
52.63
12.05
MURO DE SOGA LADRILLO BLOCKER II CON CEMENTO-ARENA 1:5
m2
192.06
12.06
COBERTURA CON PLANCHA DE CALAMINA GALVANIZADA Y REFUERZOSm2 DE MADERA 61.22 DUCHAS PROVISIONALES
glb
12.06.02
BAÑOS PROVISIONALES
glb
1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00
1.00 1.00
35.73%
307.85
306.09% 42.35%
4,535.40
42.35%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
3,050.19
70.00%
0.70
1,525.10
70.00%
0.70
1,525.10
70.00%
22.29 0.00 0.00
INSTALACIONES DE RED DE AGUA Y DESAGUE
12.06.01
49.83
306.09%
COBERTURA
12.05.01
35.73%
307.85
TABIQUERIA
12.04.01
49.83
4,535.40
CONCRETO SIMPLE
12.03.01
1.00
COSTO DIRECTO GASTOS GENERALES (11.00 %) ============================== SUB PRESUPUESTO (CD + GG)
96,736.15 S/. 10,640.98 ============ S/. 107,377.12
GASTOS DE ESTUDIO (2.41 % SP) GASTOS DE SUPERVISION (5.00 % SP) GASTOS DE LIQUIDACION GASTOS ADMINISTRATIVOS (1.00 % SP) ============================== PRESUPUESTO TOTAL
S/. 0.00 S/. 5,368.86 S/. 0.00 S/. 0.00 ============ S/. 112,745.98
18.59%
18.80 4.22
307.85
306.09%
4,535.40
42.35%
4,535.40
42.35%
0.00
0.00%
0.00
0.00%
0.00
0.00%
0.00
0.00%
3,050.19
70.00%
0.70
1,525.10
70.00%
0.70
1,525.10
70.00%
22.29 0.00 0.00
107,617.06 S/. 11,837.88 ============ S/. 119,454.93 S/. 0.00 S/. 5,972.75 S/. 0.00 S/. 0.00 ============ S/. 125,427.68
20.68%
0.00
33.83 -2.84 30.34
89.64
64.27%
-207.27
-206.09%
-207.27
-206.09%
6,174.80
57.65%
6,174.80
57.65%
7,152.31
100.00%
7,152.31
100.00%
5,001.67
100.00%
5,001.67
100.00%
1,307.23
30.00%
0.30
653.61
30.00%
0.30
653.61
30.00%
192.06 61.22
412,730.77 S/. 45,400.38 ============ S/. 458,131.16 S/. 0.00 S/. 22,906.56 S/. 0.00 S/. 0.00 ============ S/. 481,037.71
79.32%
4. RESUMEN: D ESCR IPCION
MON T O
EXPED IEN T E T ECN ICO S/ .2,169,020.35 D ED U CT IVO -S/ .300,798.22 AD ICION AL N ° 01 - MAYOR ES MET R AD OS S/ .107,391.98 AD ICION AL N ° 02 - PAR T ID AS N U EVAS S/ .577,586.06 ============ PR ESU PU EST O T OT AL MOD IFICAD O S/ .2,553,200.16
AVAN CE ACU MU LAD O AL MES AN T ER IOR
S/.719,825.97 S/.0.00 S/.0.00 S/.0.00 ============ S/.719,825.97
33.19% 0.00% 0.00% 0.00% 28.19%
AVAN CE D EL PR ESEN T E MES
S/.115,655.14 S/.0.00 S/.52,413.82 S/.107,377.12 ============ S/.275,446.09
AVAN CE ACU MU LAD O
5.33% 0.00% 48.81% 18.59% 10.79%
S/.835,481.11 S/.0.00 S/.52,413.82 S/.107,377.12 ============ S/.995,272.05
38.52% 0.00% 48.81% 18.59% 38.98%
SALD O POR EJECU T AR
S/.1,333,539.24 S/.0.00 S/.54,978.16 S/.470,208.94 ============ S/.1,858,726.33
61.48% 0.00% 51.19% 81.41% 72.80%
5. CUADRO COMPARATIVO DE AVANCE DE OBRA:
CUADRO COMPARATIVO DE AVANCE DE OBRA OBRA PROPIETARIO RESIDENTE INSPECTOR P. DE EJECUCION
: : : : :
AMPLIACION DEL SERVICIO EDUCATIVO PROVISIONAL DEL COLEGIO DE ALTO RENDIMIENTO (COAR) - TACNA GOBIERNO REGIONAL DE TACNA ING.YURI NILO PACARI MAMANI ING.YANETT LOMBARDI FUENTES 180 DIAS CALENDARIOS
INICIO DE OBRA FEBRERO 2017 MARZO 2017 ABRIL 2017 MAYO 2017 JUNIO 2017 JULIO 2017 AGOSTO 2017 TOTAL
8 7 6 5 4 3 2 1 1
MES
VALORIZACION PROGRAMADO % PARC. ACUMUL. 0.00 0.00% S/.62,360.95 2.44% S/.62,360.95 S/.201,764.08 7.90% S/.264,125.03 S/.209,457.90 8.20% S/.473,582.94 S/.247,559.56 9.70% S/.721,142.50 S/.365,533.59 14.32% S/.1,086,676.08 S/.979,512.66 38.36% S/.2,066,188.74 S/.487,011.36 19.07% S/.2,553,200.27
PARCIAL 0.00
2,553,200.27
% ACUM. 0.00% 2.44% 10.34% 18.55% 28.24% 42.56% 80.93% 100.00%
PARCIAL S/. S/. S/. S/. S/. S/. S/. S/.
VALORIZACION EJECUTADA % PARC. ACUMUL.
62,360.95 201,806.89 209,457.90 246,200.23 275,446.09 995,272.05
0.00% 2.44% 7.90% 8.20% 9.64% 10.79% 0.00% 0.00%
S/. S/. S/. S/. S/. S/. S/. S/.
62,360.95 264,167.83 473,625.74 719,825.97 995,272.05 995,272.05 995,272.05
VALOR. EJECUTADO
% ACUM. 0.00% 2.44% 10.35% 18.55% 28.19% 38.98% 38.98% 38.98%
6. CUADRO COMPARATIVO:
CUADRO COMPARATIVO DE AVANCE FISICO DE OBRA EJECUCION DE AVANCE FISICO VALORIZADO MENSUAL
S/.3,000,000.00 S/.2,553,200.27
S/.2,500,000.00
S/.2,066,188.74
S/.2,000,000.00
S/.1,500,000.00 S/.1,086,676.08 S/.995,272.05 S/.995,272.05 S/.995,272.05 S/.721,142.50
S/.1,000,000.00 S/.473,582.94 S/.500,000.00
S/.264,125.03 S/.62,360.95
S/.-
Ejecutado Programado
S/.719,825.97 S/.473,625.74
S/.264,167.83
S/.62,360.95
S/.INICIO DE OBRA
FEBRERO 2017
MARZO 2017
ABRIL 2017
MAYO 2017
JUNIO 2017
JULIO 2017
AGOSTO 2017
S/.-
S/.62,360.9
S/.264,167.
S/.473,625.
S/.719,825.
S/.995,272.
S/.995,272.
S/.995,272.
-
S/.62,360.95
S/.264,125.0
S/.473,582.9
S/.721,142.5
S/.1,086,676
S/.2,066,188
S/.2,553,200
PLAZO DE EJECUCION FISICA DE LA OBRA
ANEXO 02: CUADRO DE MAQUINARIA Y EQUIPOS:
MAQUINARIA Y EQUIPOS MES DE ABRIL
DECRIPCION
CAMIONETA VOLQUETE N°1 VOLQUETE N°2 VOLQUETE N°3 MEZCLADORA N°1 MEZCLADORA N°2 CAMION CISTERNA RETRO ESCAVADORA CARGADOR FRONTAL
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1
1
1
1
1
1
1
1
1
1
1
1
1
1 02:00
1 03:45
1
1
1
1
1 06:00 06:00
1
1
06:35
07:10
05:15
04:00
06:15
05:40
08:05
08:05
08:05 04:10
05:10
05:30 03:30
08:00 01:00
07:20 04:50
06:15
06:40 05:25
03:40 03:10
04:30
04:00
VALORIZACION JULIO
UND
dia HM HM HM HM HM HM HM HM
1 04:00 04:00 04:00 03:00
05:30 04:15 06:10 03:40 01:45 05:00 03:00 06:50
02:00
%
23 15:45 10:00 4:00 11:05 22:05 3:00 18:20 9:30
01:00
04:00
METRADO MONTO (S/.)
05:30
MAQUINARIA Y EQUIPOS MES DE MAYO DECRIPCION
CAMIONETA VOLQUETE N°1 VOLQUETE N°2 VOLQUETE N°3 MEZCLADORA N°1 MEZCLADORA N°2 CAMION CISTERNA RETRO ESCAVADORA CARGADOR FRONTAL RODILLO LISO
UND
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
dia HM HM HM HM HM HM HM HM HM
1
1
1
1 05:30 05:10
1
1
08:10 06:05 05:05 02:25 03:10 06:50 06:50
1
1
1
1
05:35 07:15
07:45
04:50
04:20 05:50 02:30
1
1
1 04:00
1
1
1 04:50
1
1 01:15
1
1
1
1
1
1
04:00
03:00
04:50
02:20
03:30
04:15
02:00
06:05
08:10
07:20
05:10
04:20
04:50
01:50
01:50
05:00
04:00
03:30
05:00
VALORIZACION JULIO METRADO
1
04:30
03:00
MONTO (S/.)
%
25 15:35 5:10 0:00 12:55 1:05 6:10 12:30 9:30 3:00
MAQUINARIA Y EQUIPOS MES DE JUNIO
DECRIPCION
CAMIONETA VOLQUETE N°1 VOLQUETE N°2 VOLQUETE N°3 MEZCLADORA N°1 MEZCLADORA N°2 CAMION CISTERNA RETRO ESCAVADORA CARGADOR FRONTAL RODILLO LISO
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
VALORIZACION JULIO
UND
dia HM HM HM HM HM HM HM HM HM
1
1
1
1 03:00 04:00
1
1
1
1
1
1
04:40 04:10 04:00
07:10
04:50
07:30
04:00
04:00 05:00
02:00
02:30
03:00
01:10 04:50 04:00
06:05 07:40 06:15 06:00 06:25
02:50
04:00
02:00 04:00 01:00 02:30
02:00
02:00
1 03:00
04:00
1
1
1
1
1
1
1 01:00
1
01:05
06:15
04:30
02:30
03:55
07:20 04:10
06:50 04:00 02:00
04:00 01:00
1
04:00
1
1
05:40
06:15 02:00
METRADO MONTO (S/.)
22 12:30 4:00 0:00 15:15 4:10 0:10 6:00 10:00 0:00
%
ANEXO 03: CUADRO DE MANO DE OBRA:
ABRIL ITEM
DECRIPCION
CAPATAZ OPERARIO OFICIAL PEON
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1 14 3 14
1 14 3 14
1 14 3 14
1 14 3 14
1 14 3 14
1 14 3 14
1 14 3 14
1 17 3 17
1 19 3 17
1 19 3 17
1 18 3 16
1 22 4 22
1 23 4 22
1 23 4 22
1 22 4 21
1 22 4 22
1 22 4 22
1 22 4 22
1 22 4 22
1 22 4 22
1 22 4 22
1 22 4 22
1 22 4 22
MAYO ITEM
DECRIPCION
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
d
l
m
m
j
v
s
d
l
m
m
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
CAPATAZ OPERARIO OFICIAL PEON
1 22 4 21
1 23 3 21
1 23 4 20
1 23 4 21
1 23 4 21
1 22 4 21
1 22 4 20
1 22 4 21
1 22 4 21
1 22 4 20
1 22 4 21
1 16 4 10
1 16 4 11
1 16 4 11
1 16 4 11
1 16 4 11
1 16 4 11
1 16 3 10
1 16 4 11
1 16 4 11
1 16 4 11
1 16 4 11
1 15 3 8
1 15 4 11
JUNIO ITEM
DECRIPCION
CAPATAZ OPERARIO OFICIAL PEON
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
d
l
m
m
j
v
s
d
l
m
m
J
V
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1 14 3 10
1 14 3 10
1 14 3 10
1 14 3 10
1 14 5 8
1 13 5 9
1 13 5 9
1 13 5 9
1 13 4 9
1 12 5 9
1 12 5 9
1 13 5 9
1 13 5 9
1 13 5 9
1 13 5 9
1 11 4 9
1 11 4 9
1 11 4 9
1 11 4 9
1 11 4 9
1 8 3 8
1 8 3 8
1 8 3 8
1 8 3 8
1 15 3 11
ANEXO 04: CUADRO DE MATERIALES:
MATERIAL ABRIL INGRESO: ITEM
DECRIPCION
ARENA GRUESA ARENA FINA PIEDRA 1/2'' PIEDRA BASE HORMIGON CEMENTO LADRILLO EQUIPO MULTIFUNCIONAL COP/IMP BOTA DE JEBE CAMISA LENTES TRANSPARENTES ZAPATO PUNTA DE ACERO CASCO DE SEGURIDAD CORTAVIENTOS PANTALON DRILL ZAPATO DIELECTRICO GUANTE BADANA GUANTE CUERO GUANTE JEBE GUANTE DIELECTRICO MASCARILLA 3 PLIEGUES FRANELA 1m CESÉD AMERICANO PETROLEO ADHESIVO EPOXICO EN GEL ADITIVO EPOXICO P/CONCRETO BOLSA DE POLIETILENO 97cm CALVIVA NACIONAL CINTA FLEXIBLE PARA SELLADO CLORO LIQUIDO DETERGENTE GRANULADO X 1kg IMPRIMANTE P/MEMBRANA ASFALTICA LACA DESMOLDEADORA X 1gln PINTURA ASFALTICA IMPERMEABLE POLIESTIRENO EXPLANDIDO DE 1.2X2.4X1.04 RECUBRIMIENTO ACRILICO IMPERMEABLE
UND
m3 m3 m3 m3 m3 und und und und und und und und und und und und und und und pqt m m2 gln und kg ciento kg m lts und gln und gln und kg
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
15
15
15
15
15
20 15
15
15 2000
385 1 20 40 100 30 22 55 40 2 50 80 30 3 4 100 45 200 2 5 1 20 25 12 1 3 3 2 55 44
15 15 15
30 15
30 15
30
VALORIZACION JULIO METRADO
120 15 105 20 45 2000 385 1 20 40 100 30 22 55 40 2 50 80 30 3 4 100 45 200 2 5 1 20 25 12 1 3 3 2 55 44
MONTO (S/.)
%
MATERIAL ABRIL SALIDA: DECRIPCION
CEMENTO PIEDRA 1/2'' ZARANDEADA HORMIGON ARENA FINA ARENA GRUESA CINTA AISLANTE CINTA TEFLON CINTA DE SEGURIDAD WINCHA 8mts BROCHA DE 3'' DISCO CORTE METAL 7'' DISCO CORTE 7 1/4'' GUANTE BADANA GUANTE CUERO GUANTE JEBE CASCO DE SEGURIDAD ZAPATO DE SEGURIDAD BOTA JEBE ALAMBRE N°8 ALAMBRE N°16 CALAMINA GALVANIZADA BIDON AGUA MINERAL BISAGRAS 4X2 BISAGRAS 4X4 PALO EUCALIPTO PANTALON DRILL PROTECTOR SOLAR JABON LIQUIDO JABONERA PAPEL HIGIENICO PAPELERA CORTA VIENTOS CAMISA EQUIPO MULTIFUNCIONAL COP/IMP GASOLINA PETROLEO CANCADADO LADRILLO PLANCHA TRIPLAY 8mm PLANCHA TRIPLAY 4mm
UND
und m3 m3 m3 m3 und und und und und und und und und und und und und kg kg und und und und und und und und und pqt und und und und gln gln und und und und
S
D
1
2
15
L
M
M
J
V
S
D 9
3
4
5
6
7
8
52
30 10 10
48 10 10
20
25 8
6
L
M
M
J
V
13
14
10
11
12
39
94
70
7
S
D
15
16
50
15 15
L
M
M
J
V
S
D
17
18
19
20
21
22
23
105 154 132 115 137 61 15 15 15 15
L 24
77 15
M
M
J
V
S
D
25
26
27
28
29
30
119 123 136 122 90 15 15 30 15
15 15
15
15
2
15 1
30
15
5 1
1
1 1
1 1 1
1
1
1
1
1 1 4
3
8
1
1 1
13
38
6 2
3
4 2
27
3
30
3
18
1
1
8 1
69
3
2 2 8 8 15
1 1 25
3
2
1
39 40
3 1 1
9
2 1 1 1
2 1
1
1
3
1
9 9 3
2
17
6
10
9
52
12
3
3
2
4
2
2
2 2 1
2 1 1
1 1 1
2
1
2
2
2 2
12
2
25 3 2
25 3
2 3 3
6 40
3
60
60
1 6 1 2 3 1 1 70
2 45
224
231 231 231 182 180 319 2 1 6
1 1
6
1 15
2 3
12
1
41 39
2
6 2
2 1
3
8
2 12
265 165 363 1
385
13
2 2
1 30
2 36
2
399 484 448 330 462 2.64 1
1
2 17
2 7
2
4 60
4 4
506 297 308 154 88 10 8 1
5 88 1
VALORIZACIO N JULIO METRADO
1820 133 72 30 120 3 5 3 2 1 6 3 15 36 10 19 22 7 255 156 6 48 2 7 8 49 200 1 6 1 2 55 49 1 34 338 0 6342.64 20 12
MATERIAL MAYO INGRESO: DECRIPCION
UND
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
METRADO
15
15
1
61 15 30 0 0 500 8 0 23 26 4 27 8 17 8 42 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 400 0 0 0 0 160 320 24 80 0 1 0 0 0 0 0 0
ARENA GRUESA m3 ARENA FINA m3 PIEDRA 1/2'' m3 PIEDRA BASE m3 HORMIGON m3 CEMENTO und CEMENTO CONDUCTIVO X25gr und LADRILLO und SPOT PARA LAMPARA DICROICA PARA ADOSAR 20W LUZund CALIDA LUMINARIA A TIPO BRAQUETE CON FOCO AHORRADOR DE und 18 WPHILIPS LUMINARIA CON LAMPARA DE VAPOR DE SODIO DE 70Wund PHILIPS LUMINARIA CIRCULAR 2x18WPARA ADOSAR und LAMPARA REFLECTORA 400W 220V und LAMPARA LUZ DE EMERGENCIA 2 FAROS und FAROLA ESFERICA PHILIPS und EQUIPO FLUORECENTE LINEAL 2x36W und EQUIPO MULTIFUNCIONAL COP/IMP und BOTA DE JEBE und CAMISA und LENTES TRANSPARENTES und ZAPATO PUNTA DE ACERO und CASCO DE SEGURIDAD und CORTAVIENTOS und PANTALON DRILL und ZAPATO DIELECTRICO und GUANTES BADANA und GUANTES CUERO und GUANTES JEBE und GUANTES DIELECTRICO und MASCARILLA 3 PLIEGUES pqt FRANELA 1m m CESÉD AMERICANO m2 PETROLEO gln ADHESIVO EPOXICO EN GEL und ADITIVO EPOXICO P/CONCRETO kg BOLSA DE POLIETILENO 97cm ciento CALVIVA NACIONAL kg CINTA TEFLON 2.5'' und CINTA TEFLON 3/4'' und CINTA AISLANTE VULCANIZANTE DE 19m und CINTA AISLANTE DE 22mm x 5mm und CINTA FLEXIBLE PARA SELLADO m CINTA PLASTICA DE SEÑALIZACION und CLORO LIQUIDO lts DETERGENTE GRANULADO X 1kg und IMPRIMANTE P/MEMBRANA ASFALTICA gln LACA DESMOLDEADORA X 1gln und PINTURA ASFALTICA IMPERMEABLE gln POLIESTIRENO EXPLANDIDO DE 1.2X2.4X1.04 und
15
15 15
15
15
150 350 8 23 26 4 27 8 17 8 42
200
200
160 320 24 80 1
VALORIZACION JULIO MONTO (S/.)
%
MATERIAL MAYO SALIDA: DECRIPCION
CEMENTO PIEDRA 1/2'' ZARANDEADA HORMIGON ARENA FINA ARENA GRUESA CINTA AISLANTE CINTA TEFLON CINTA DE SEGURIDAD WINCHA 5mts WINCHA 8mts BROCHA DE 3'' DISCO CORTE METAL 7'' DISCO CORTE 7 1/4'' DISCO CORTE 7 1/8'' DISCO PARA CONCRETO GUANTE BADANA GUANTE CUERO GUANTE JEBE CASCO DE SEGURIDAD ZAPATO DE SEGURIDAD ZAPATO DI ELECTRICO BOTA JEBE ALAMBRE N°8 ALAMBRE N°16 CALAMINA GALVANIZADA BIDON AGUA MINERAL BISAGRAS 4X2 BISAGRAS 4X4 PALO EUCALIPTO PANTALON DRILL PROTECTOR SOLAR JABON LIQUIDO JABONERA PAPEL HIGIENICO PAPELERA CORTA VIENTOS CAMISA EQUIPO MULTIFUNCIONAL COP/IMP GASOLINA
UND
und m3 m3 m3 m3 und und und und und und und und und und und und und und und und und kg kg und und und und und und und und und pqt und und und und gln
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
62
55
62
98 15
17
21
16
35
12
28
38
13
69
34
26
83
27 15
15
15
108 120
104 23
106 73
47
15 15
15
10
1 100 50
40
10
10
10
1 2
2
1 1 1
1
1
1 1
1
1
2 1
2
2
1
3 1
1
1 1
7 1
1
1 1
2 2
1
2
1 1
1 3
2
2
1 1
1 1 1
1 1 8 60
1
3
1
1 1
1 8 5
2
2
1
1 21
3
1
30 9
11 1
5
4
3
1
2
3
4 100
8
1
1
10
2
10
1
5
2
2
20 15 60 1
50
3
4
4
50
2
2
4
32
2
2
5
3
2
1
30
4
1
2
3
2
4
2
3
2
VALORIZACION JULIO METRADO
1194 113 0 15 70 1 220 0 1 1 11 1 3 6 1 20 13 3 1 1 1 4 119 181 0 32 0 0 20 15 222 1 0 0 0 0 0 0 57
MONTO (S/.)
%
MATERIALES INGRESO JUNIO: DECRIPCION
UND
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
ARENA GRUESA m3 ARENA FINA m3 PIEDRA 1/2'' m3 PIEDRA BASE m3 HORMIGON m3 CEMENTO und CEMENTO CONDUCTIVO X25gr und LADRILLO und SPOT PARA LAMPARA DICROICA PARA ADOSAR 20W LUZund CALIDA LUMINARIA A TIPO BRAQUETE CON FOCO AHORRADOR DE und 18 WPHILIPS LUMINARIA CON LAMPARA DE VAPOR DE SODIO DE 70Wund PHILIPS LUMINARIA CIRCULAR 2x18WPARA ADOSAR und LAMPARA REFLECTORA 400W 220V und LAMPARA LUZ DE EMERGENCIA 2 FAROS und FAROLA ESFERICA PHILIPS und EQUIPO FLUORECENTE LINEAL 2x36W und EQUIPO MULTIFUNCIONAL COP/IMP und BOTA DE JEBE und CAMISA und LENTES TRANSPARENTES und ZAPATO PUNTA DE ACERO und CASCO DE SEGURIDAD und CORTAVIENTOS und PANTALON DRILL und ZAPATO DIELECTRICO und GUANTE BADANA und GUANTE CUERO und GUANTE JEBE und GUANTE DIELECTRICO und MASCARILLA 3 PLIEGUES pqt FRANELA 1m m CESÉD AMERICANO m2 PETROLEO gln ADHESIVO EPOXICO EN GEL und ADITIVO EPOXICO P/CONCRETO kg BOLSA DE POLIETILENO 97cm ciento CALVIVA NACIONAL kg CINTA TEFLON 2.5'' und CINTA TEFLON 3/4'' und CINTA AISLANTE VULCANIZANTE DE 19m und CINTA AISLANTE DE 22mm x 5mm und CINTA FLEXIBLE PARA SELLADO m CINTA PLASTICA DE SEÑALIZACION und
15
15
30
15
15
15 300 300
200
VALORIZACION JULIO METRADO
60 0 0 0 45 600 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 200 0 0 0 0 0 0 0 0 0 0
MONTO (S/.)
%
MATERIALES DE SALIDA JUNIO: DECRIPCION
CEMENTO PIEDRA 1/2'' ZARANDEADA HORMIGON ARENA FINA ARENA GRUESA CINTA AISLANTE CINTA TEFLON CINTA DE SEGURIDAD WINCHA 5mts WINCHA 8mts BROCHA DE 3'' DISCO CORTE METAL 7'' DISCO CORTE 7 1/4'' DISCO CORTE 7 1/8'' DISCO PARA CONCRETO GUANTES BADANA GUANTES CUERO GUANTES JEBE GUANTES DI ELECTRICOS CASCO DE SEGURIDAD ZAPATOS DE SEGURIDAD ZAPATOS DI ELECTRICO BOTAS DE JEBE ALAMBRE N°8 ALAMBRE N°16 CALAMINA GALVANIZADA BIDON AGUA MINERAL BISAGRAS 4X2 BISAGRAS 4X4 PALO EUCALIPTO PANTALON DRILL PROTECTOR SOLAR JABON LIQUIDO JABON DE TOCADOR JABONERA PAPEL HIGIENICO PAPELERA CORTA VIENTOS CAMISA DRILL EQUIPO MULTIFUNCIONAL COP/IMP GASOLINA PETROLEO CANCADADO LADRILLO LADRILLO HERCULES LADRILLO PASTELERO PLANCHA TRIPLAY 4'' PLANCHA TRIPLAY 8mm PLANCHA TRIPLAY 4mm PLANCHA TRIPLAY 18mm PLANCHA TRIPLAY 18''X1.22X2.44 PLANCHA TRIPLAY 4''X1.22X2.44
UND
und m3 m3 m3 m3 und und und und und und und und und und und und und und und und und und kg kg und und und und und und und und und und pqt und und und und gln gln und und und und und und und und und und
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
S
D
L
M
M
J
V
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
17
43
32
76
53
37
7
22
15
15
15
15
15
15
30
44
15
15
5
10
35
15
10
25
18
4
10
1
1
5
17
10
1 1
1
1 1
1 2
1
1 1
3
2
1
1
1
1
2
6 2
1 2 1 1
1
1
1
1
2
2
28
5
1 12
1
2 69
2 1
2
2 16
1 10
2
7 35
1
2
1
1
1
1
2
3 20
2 7
2 25
1
2 22
1
2 25
2
2
210
1 2
4
4
3
3
3
3
3 11
3 11
28
2
2 30
2
VALORIZACION JULIO METRADO
361 0 45 15 60 0 164 0 2 0 1 3 3 0 0 8 10 8 1 0 3 0 4 0 0 0 11 0 0 0 6 56 0 3 0 3 0 0 6 0 43 299 0 0 0 210 0 0 1 10 0 0
MONTO (S/.)
%
ANEXO 05: METRADO DEL ROLLIZO DE EUCALIPTO
DESCRIPCION
UNIDAD
NRO VECES
TUBO F°N° Ø 2 1/2'' X 3MM Proyección de V- TUBO 1 1/2'' X 2'' Proyección de V- TUBO 2 1/2'' X 2 1/2'' Tensor de cable acerado 1/4''
und und und und
11 80 30 11
Establo Ca1 - Ca8 en los extremos
und
10
MEDIDAS LARGO
ANCHO
ALTO
PARCIAL
SECTOR 06: Jusfamiento de animales
TOTAL
588.28 7.15 3.94 3.94 6.93
<= m <= m <= m <= m
78.65 315.2 118.2 76.23
SECTOR 09: Sector Agropecuario 01 puntales verticales de 6''
146.34
m m m m m m
Establo Ca1 - Ca8 en el medio
und
5
Establo O8 - 14 en los extremos
und
8
Establo O8 - O14 en el medio
und
8
Establo O15 - O22 en los extremos
und
10
Establo O15 - O22 en el medio
und
5
Establo Ca1 - Ca8
und
50
Establo Ca1 - Ca8
und
60
Establo O8 - 14
und
80
Establo O8 - 14
und
105
Establo O15 - O22
und
50
Establo O15 - O22
und
60
2.75
rollizo puertas tronco transversal
und
30
1.50
Establo Ca1 - Ca8
und
10 16 10
3.10
=> => => => => =>
3.80 4.33 3.80 4.33 3.80 4.33
38.00 21.65 30.40 34.64 38.00 21.65
rollizo horizontales 4''
1,203.75
m => 2.75
m => 2.75
m =>
<=m <=m
150.00 165.00 240.00 288.75 150.00 165.00 45.00
<=m <=m <=m
31.00 49.60 31.00
3.00
<=m 3.00
<=m 3.00
rollizo techo de 4''
111.60 Establo O8 - O14
und
Establo O15 - O22
und
rollizo hechado sentodo horizontal Establo Ca1 - Ca8
und
3.10 3.10
rollizo techo de 2''
244.95 rollizo hechado sentodo horizontal Establo O8 - O14
und
rollizo hechado sentodo horizontal Establo O15 - O22
und
Establo Ca1 - Ca8
und
Establo O8 - O14
und
Establo O15 - O22
und
rollizo techo tronco vertical pequeño
und
Establo V1 - V10, extremo exterior
und
3 3 3 10 16 10 36
3.06 3.06 3.06
0.30
m => 19.33 m => 11.00 m => 11.00
57.99 33.00 33.00 30.60 48.96 30.60 10.80
m m m m
33.00 41.80 33.00 41.80
<=m <=m <=m <=m
SECTOR 10: Sector Agropecuario 02 puntales verticales de 4''
149.60 Establo V1 - V10, extremo interior
und
Establo V11 - V20, extremo exterior
und
Establo V11 - V20, extremo interior
und
Establo V1 - V10
und
11 11 11 11
=> => => =>
3.00 3.80 3.00 3.80
rollizo horizontales 4''
276.20 Establo V1 - V10
und
Establo V11 - V20
und
Establo V11 - V20
und
rollizo puertas tronco transversal
und
rollizo hechado sentodo horizontal
und
rollizo hechado sentodo vertical
und
rollizo para techo 2 aguas
und
rollizo interior transversal
puntales verticales C01-C02 puntales verticales C02-C03 puntales verticales C03-C04 puntales verticales C04-C05 puntales verticales C05-C06 puntales verticales C06-C07 puntales verticales C07-C08 puntales verticales C08-C09 puntales verticales C09-C10 puntales verticales C10-C11 puntales verticales C11-C12 puntales verticales C12-C13 puntales verticales C13-C14 puntales verticales C01-C16 puntales verticales C16-C17 puntales verticales C17-C14
20 11 20 11 20
<=m m => 4.10 3.90 <=m m => 4.10 1.50 <=m
78 45.1 78 45.1 30
3.90
rollizo techo de 2''
258.52
11 5
m => 5.32 m => 40.00
58.52 200.00
und
22 22
m => 7.27 m => 4.07
159.94 89.54
und und und und und und und und und und und und und und und und
6 6 6 6 2 5 5 5 2 7 6 7 6 6 7 5
m m m m m m m m m m m m m m m m
rollizo techo de 4''
249.48
SECTOR 12: Corral para toros puntales verticales de 4''
208.8 => => => => => => => => => => => => => => => =>
2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4 2.4
14.40 14.40 14.40 14.40 4.80 12.00 12.00 12.00 4.80 16.80 14.40 16.80 14.40 14.40 16.80 12.00
ANEXO 06: METRADO DE INSTALACIONES SANITARIAS
descripcion
N° de veces
unidad
17
dimenciones ancho
parcial
total
und
17
17
7 9 1
und und und
7 9 1
7 9 1
7 8 3 2
und und und und
7 8 3 2
7 8 3 2
1
m
337.63
337.63
17 3 1
und und und
17 3 1
17 3 1
10 2 2 2
und und und und
10 2 2 2
10 2 2 2
1 1
m m
170.53 88.94
170.53 88.94
largo
alto
SUMINISTRO DE AGUA SUMINISTRO DE ACCESORIOS Valvula tipo compuerta ACCESORIOS DE REDES DE AGUA codo 90° PVC SAP C-10 1/2'' Tee PVC SAP C-10 1/2'' Reduccion de 3/4''a 1/2'' INSTALACION DE APARATOS SANITARIOS Instalacion de lavadero de concreto Instalacion de lavadero de concreto mas escurridero instalacion de tanque elevado pozo de concreto INATALACION DE RED DE DISTRIBUCION tuberia de agua fria PVC - SAP Ø 1/2'' SISTEMA DE DRENAJE ACCESORIOS DE REDES DE DRENAJE DE AGUA CAJA DE 30X60 Yee codo 45° INSTALACION DE APARATOS SANITARIOS Instalacion de lavadero de concreto caja de rejistro de lodos caja de drenaje Tanque biodijestor INATALACION DE RED DE DRENAJE Tuberia PVC Ø 4'' Tuberia PVC Ø 2''
337.63
170.53 88.94
ANEXO 07: Plano de la actividad: “MANTENIMIENTO DE LA FERIA REGIONAL AGRONÓMICA E INDUSTRIAL TACNA EN EL DISTRITO GREGORIO ALBARRACÍN, PROVINCIA TACNA REGIÓN TACNA
53