YWCT Custom Cooling Towers 1

YWCT Custom Cooling Towers • Cooling Towers manufacturer for the industrial market since 1966 • Specialized in Tailor Made solutions • One stop shop • More than 1500 customers • Quality: ISO 9001: 2000 • Safety: IIOSH • ERP:SAP • A CTI member since 1980 2

Customers • • • • • • • • • • • • • • • • 3

Agan chemicals Air Products Bateman Litwin Engineering Baran Engineering Carmel Olefins Danieli Engineering Dead Sea Works Elta Electronice Industries Haifa Oil Refineries Ltd Intel Israel Aerospace Industries Israel Electric Machteshim Chemical Works Motorola Israel Ltd M+W Zander Nestle

• • • • • • • •

Paz Ashdod Oil Refineries Rotem Amfert Negev Siemens Water Tech. Soreq Nuclear Research Center Teva Pharmaceuticals Tower Semiconductors Uniliver Vishay

ORL REFINERIES

Year: 2006 Construction Material:Cement Concrete Water Flow: 8,000 m3/hr The task was to replace a 70year-old atmospheric cooling tower with a new, more efficient tower. A two-cell 14m X 14m tower was designed. As part of its deliverables, YWCT provided the refineries with a scale drawing of the concrete cement structure, and detailed drawings of the relevant piping.

4

DANIELI ENGINEERING Year: 2009 Construction: Hand Laid FRP Water Flow: 1,250 m3/hr Danieli Engineering, which specializes in the engineering of industrial plants and acts as general contractor for turnkey projects, asked for a ten-cell cooling tower for one of its water treatment plants in the Domenican Republic Specifications were clear: Danieli asked for an FRP cooling tower over a concrete basin with a splash PP fill. Design was according to field conditions – as requested

5

CARMEL OLEFINS Year: 2006 Construction Material: Cement Concrete Water Flow: 7,500 m3/hr As part of Carmel Olefins' (CO) expansion, YWCT was asked to increase the cooling capacity of both CO's ethylene plant and its polyethylene plant. A three-cell structure measuring 12m X 12m per cell was designed for the former, and a two-cell measuring 12m X 12m per cell was designed for the latter.

6

Nesher Power Plant

Year: 2008 Construction: Pultruded FRP Water Flow: 2,000 m3/hr Nesher is a manufacturer of cement. The hard conditions on site (which is full of corrosive dust), dictated a heard duty solution. Two cells pultruded FRP tower over concrete basin was designed and built.

7

Ludan Engineering

Year: 2008 Construction: Hand laid FRP Water Flow: 120 m3/hr Ludan Engineering needed a system to cool a Shell-N-Tube heat exchanger as part of a water treatment plant. YWCT provided a complete skid-mounted system that included two packaged cooling towers, redundant pumps, an automatic filter, and chemical dosing and bleeding system with all piping and gauges required as a plug-N-play system.

8

ROTEM AMFERT NEGEV PLANT Year: 1996 Construction Material: Cement Concrete, Wood Water Flow: 8,000 m3/hr High level of fluoride in the water dictated an extraordinary combination of a draft force concrete cement tower. The inner part of the concrete was fully coated with rubber in order to protect it from the fluoride. For the same reason, wood was chosen as infrastructure. All metal parts are made of HAST alloy.

9

SIEMENS Water Technology

Year: 2007 Construction: Hand Laid FRP YWCT was asked by Siemens Water Technologies Corp., USA to manufacture an FRP biofilter vessel based on Siemens' own design. YWCT designed and created the set of molds required for the work and delivered the vessel on spec, on time

10

BEN-GURION INTERNATIONAL AIRPORT Year: 2000 Construction Material:FRP and HDG Water Flow: 3,600 m3/hr In 1999, YWCT was asked to plan and build a cooling tower for the new terminal at BenGurion Airport (TLV). A concrete basin elevated from the ground was designed. The basin's height increased the efficiency of the pumps; and the space under the basin is utilized for storage. An HDG structure covered with pultruded FRP was erected over the basin

11

AZRIELY CENTER

Year: 2002 Construction Material:Cement Concrete Water Flow: 1,500 m3/hr In order to overcome an air circulation problem, YWCT designed a round concrete cement structure containing 24 centrifugal fan units that force the air outward.

12

Intel IDC9

Year: 2008 Construction: Hand Laid FRP Water Flow: 1,400 m3/hr As part of one of the first Green Building projects in Isreal YWCT was asked to provide 2100TN cooling towers. Noise level was decreased to minimum using a combination of quiet fans, VFDs and sound attenuators.

13

TOWER SEMI-CONDUCTOR

Year: 2001 Construction: Pultruded FRP Water Flow: 5,000 m3/hr A five-cell induced draft cooling tower made of pultruded FRP, made to comply with Tower Semiconductor's high standards. The structure was built on YWCT's premises, dismantled to three main parts, and reassembled on site.

14

Contact YWCT [email protected] www.customcoolingtowers.com 15