Comparison Report.xlsx

  • Uploaded by: Eileen Hiu Xing Yee
  • 0
  • 0
  • April 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Comparison Report.xlsx as PDF for free.

More details

  • Words: 376
  • Pages: 2
~ Comparison Report ~ Duration Activity ID

Activity Name

New Original Duration

Old Original Duration

SYDE5100

Switchyard Earthing Calculation, Layout & Detail Submission & Approval

16

60

SYDE5110

132kV Control Building Earthing Layout Submission & Approval

16

60

SYDE5120

GIS Earthing Layout Submission & Approval

16

60

SYDE6060

33kV Control Building Earthing Layout & Details Submission & Approval

16

50

New Start Date

Old Start Date

Dates Activity ID

Activity Name

*Finish dates remain the same (02 May 2019) SYDE5100

Switchyard Earthing Calculation, Layout & Detail Submission & Approval

9/Apr/19

4/Feb/19

SYDE5110

132kV Control Building Earthing Layout Submission & Approval

9/Apr/19

4/Feb/19

SYDE5120

GIS Earthing Layout Submission & Approval

9/Apr/19

4/Feb/19

SYDE6060

33kV Control Building Earthing Layout & Details Submission & Approval

9/Apr/19

4/Feb/19

~ Comparison Report ~ Activity Relationships Added/Deleted The following Predecessor Activity Relationships have been added to the project Activity Name

Relationship Lag

Relationship Type

Predecessor Activity Id

Predecessor Activity Name

SYDE5100

Switchyard Earthing Calculation, Layout & Detail Submission & Approval

128

Finish to Start

SYDE5130

Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval

SYDE6060

33kV Control Building Earthing Layout & Details Submission & Approval

72

Finish to Start

SYDE6030

33kV Control Building Support Layout Submission & Approval

SYDE5130

Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval

128

Finish to Start

SYDE5100

Switchyard Earthing Calculation, Layout & Detail Submission & Approval

SYDE6030

33kV Control Building Support Layout Submission & Approval

72

Finish to Start

SYDE6060

33kV Control Building Earthing Layout & Details Submission & Approval

Activity ID

The following Predecessor Activity Relationships been deleted from the project Activity Name

Relationship Lag

Relationship Type

Predecessor Activity Id

Predecessor Activity Name

SYDE5100

Switchyard Earthing Calculation, Layout & Detail Submission & Approval

96

Start to Start

SYDE5130

Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval

SYDE6060

33kV Control Building Earthing Layout & Details Submission & Approval

280

Start to Start

SYDE6030

33kV Control Building Support Layout Submission & Approval

SYDE5130

Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval

96

Start to Start

SYDE5100

Switchyard Earthing Calculation, Layout & Detail Submission & Approval

SYDE6030

33kV Control Building Support Layout Submission & Approval

280

Start to Start

SYDE6060

33kV Control Building Earthing Layout & Details Submission & Approval

Activity ID

Related Documents

Comparison
May 2020 20
Comparison
October 2019 34
Comparison
May 2020 30
Comparison
June 2020 20
Comparison
November 2019 33
Comparison
November 2019 36