~ Comparison Report ~ Duration Activity ID
Activity Name
New Original Duration
Old Original Duration
SYDE5100
Switchyard Earthing Calculation, Layout & Detail Submission & Approval
16
60
SYDE5110
132kV Control Building Earthing Layout Submission & Approval
16
60
SYDE5120
GIS Earthing Layout Submission & Approval
16
60
SYDE6060
33kV Control Building Earthing Layout & Details Submission & Approval
16
50
New Start Date
Old Start Date
Dates Activity ID
Activity Name
*Finish dates remain the same (02 May 2019) SYDE5100
Switchyard Earthing Calculation, Layout & Detail Submission & Approval
9/Apr/19
4/Feb/19
SYDE5110
132kV Control Building Earthing Layout Submission & Approval
9/Apr/19
4/Feb/19
SYDE5120
GIS Earthing Layout Submission & Approval
9/Apr/19
4/Feb/19
SYDE6060
33kV Control Building Earthing Layout & Details Submission & Approval
9/Apr/19
4/Feb/19
~ Comparison Report ~ Activity Relationships Added/Deleted The following Predecessor Activity Relationships have been added to the project Activity Name
Relationship Lag
Relationship Type
Predecessor Activity Id
Predecessor Activity Name
SYDE5100
Switchyard Earthing Calculation, Layout & Detail Submission & Approval
128
Finish to Start
SYDE5130
Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval
SYDE6060
33kV Control Building Earthing Layout & Details Submission & Approval
72
Finish to Start
SYDE6030
33kV Control Building Support Layout Submission & Approval
SYDE5130
Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval
128
Finish to Start
SYDE5100
Switchyard Earthing Calculation, Layout & Detail Submission & Approval
SYDE6030
33kV Control Building Support Layout Submission & Approval
72
Finish to Start
SYDE6060
33kV Control Building Earthing Layout & Details Submission & Approval
Activity ID
The following Predecessor Activity Relationships been deleted from the project Activity Name
Relationship Lag
Relationship Type
Predecessor Activity Id
Predecessor Activity Name
SYDE5100
Switchyard Earthing Calculation, Layout & Detail Submission & Approval
96
Start to Start
SYDE5130
Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval
SYDE6060
33kV Control Building Earthing Layout & Details Submission & Approval
280
Start to Start
SYDE6030
33kV Control Building Support Layout Submission & Approval
SYDE5130
Switchyard Lightning Protection Calculation, Layout & Sections Submission & Approval
96
Start to Start
SYDE5100
Switchyard Earthing Calculation, Layout & Detail Submission & Approval
SYDE6030
33kV Control Building Support Layout Submission & Approval
280
Start to Start
SYDE6060
33kV Control Building Earthing Layout & Details Submission & Approval
Activity ID