Berthing Requirement For AC Coach Repair Shop 1:-Berthing requirement for stripping of AC Coaches a- 3 working days required for stripping of One AC coach b- Working days required for stripping of 30 Ac coaches=3x30=90 days c - Berthing capacity required for stripping of 30 AC coaches in 24 working days=90/24=3.75 =4 2:- Berthing requirement for corrosion repair of AC Coaches aAverage 11 working days required for corrosion repair of One AC coach bWorking days required for 12 AC coaches (40% of 30 AC coaches) corrosion repair=11x12=132 days cBerthing capacity required for corrosion repair of12 ACcoaches in 24 working days=132/24=5.5=6 3:- Berthing requirement for Furnishing of AC Coaches a14 working days required for Furnishing of One AC coach bWorking days required for Furnishing of 30 Ac coaches=14x30=420 cBerthing capacity required for Furnishing of 30 AC coaches in 24 working days=420/24=17.5 =18 4:- Berthing requirement for spray painting of AC Coaches a5 working days required for spray painting of One AC coach bWorking days required for spray painting of 30 Ac coaches=5x30=150 days cBerthing capacity required for spray painting of 30 AC coaches in 24 working days=150/24=6.25=6 Total Berthing Required For AC Coaches Repair Shop =4+6+18+6=34