Basic_pmp_formulas.ppt

  • Uploaded by: Lilian Barrey Moss
  • 0
  • 0
  • November 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Basic_pmp_formulas.ppt as PDF for free.

More details

  • Words: 542
  • Pages: 9
Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

When memorizing the formulas I have found it best to look for patterns. When I see the correct pattern I know the formula is correct. AC = ACWP PV = BCWS EV = BCWP

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

Ok lets build this. First is to see the pattern of 2 subtractions, 3 divides, 2 subtractions

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

Next see the pattern of Variance and Index. Cost, Schedule and Cost, Schedule.

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

Next see the pattern of Earned Value (EV). This used to be BCWP.

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

Next see the pattern of Actual Cost (AC) and Planned Value (PV) and how they alternate. Skip a line and its AC again.

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

Next see the pattern of Estimated at Completion (EAC). As well as Budget at Completion (BAC)

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

Not much left. Notice that CPI is divisor of EAC so find CPI skip a line and place it at the end of EAC formula. ETC and VAC don’t really match to anything, you just have to know where they go.

Formula Memorization Trick CV

=

EV

-

AC

SV

=

EV

-

PV

CPI =

EV

/

AC

SPI =

EV

/

PV

EAC =

BAC /

CPI

ETC =

EAC -

AC

VAC =

BAC -

EAC

This may look confusing but it worked great for me and I have had others tell me it worked for them as well.

Other Formulas to Know

• Communication Channels: N(N-1)/2 • Pert Mean: (Pessimistic + 4*Most Likely + Optimistic) / 6

• Standard Deviation: (Pessimistic – Optimistic) / 6 • Variance: ((Pessimistic – Optimistic) / 6) squared • Present Value or PV: Future Value / (1+ rate of return) to the power of n. Where n = periods of time.

More Documents from "Lilian Barrey Moss"