BLOCK MASONRY SOURCE :QUICK BLOCKS STANDARD RATE
MASONRY THICKNESS
Rs. 8" THICK BLOCK MASONRY
61
sft
6" THICK BLOCK MASONRY
44
sft
5" THICK BLOCK MASONRY
41
sft
4" THICK BLOCK MASONRY
35
sft
3" THICK BLOCK MASONRY
32
sft
2" THICK BLOCK MASONRY
30
sft
PAVER BLOCKS SOURCE :ENVICRETE TYPE OF BLOCKS
STANDARD RATE Rs.
60-mm thick city grey
89
sft
60-mm thick city pigmented
100
sft
80-mm thick city grey
98
sft
80-mm thick city pigmented
114
sft
NATIONAL REFINERY LIMITED ENGINEERING DEPARTMENT
STANDARD RATES FOR CIVIL WORKS AGGREGATE PERCENTAGE CONSIDERED FOR OVERHEAD/INCOME TAX AND PROFIT ON EXECUTION COST
17
CONCRETE WORKS CONCRETE RATIOS
TOTAL EXECUTION COST
STANDARD RATE
cement
sand
crush
Rs.
Rs.
1
1
2
161.70
189.19
1
1.5
3
132.14
154.61
1
2
4
115.45
135.07
1
3
6
82.17
96.14
1
4
8
73.72
86.25
14.93
17.47
21.86
25.58
PLASTER-1NTERNAL 1
4 PLASTER-EXTERNAL
1
4
STANDARD RATES FOR CIVIL WORKS qty in cft
200.00
qty in sft
6,500.00
cement price per bag in Rs.
400.00
sand price per cft in Rs. crush price per cft in Rs.
25.00 30.00
water price per gallon in Rs.
1.00
aggregate percentage of overhesd/profit & income tax on execution cost
15.00
overall margin for overhead/profit
8.00
formwork rate
10.00
sft
CONCRETE WORKS
TOTAL EXECUTION COST
STANDARD RATE
15 15 15
33525 26850 23064 18900
38,553 30,878 26,523 21,736
1513
16645
19,142
108333 76556 61613 54943 46403 41593
39000 39000 39000 39000 39000 39000
147333 115556 100613 93943 85403 80593
169,433 132,889 115,705 108,035 98,213 92,682
162366 100658 73209 78000 69738
10 10 10 10 10
162376 100668 73219 78010 69748
186,733 115,769 84,202 89,712 80,210
crush
cement bags
sand-cft
crush-cft
cement
sand
crush
water
total
LABOUR
FORMWORK
MATERIAL COST
sand
MATERIAL QUANTITY
cement
CONCRETE RATIOS
1 1 1 1
1 1.5 2 3
2 3 4 6
58.80 42.80 33.60 23.60
74 80 84 88
148 160 168 176
23520 17120 13440 9440
1850 2000 2100 2200
4440 4800 5040 5280
653 476 373 262
30463 24396 20953 17182
3046 2440 2095 1718
1
4
8
18.20
90
180
7280
2250
5400
202
15132
243.75 162.50 122.20 104.00 81.25 69.55
325 390 455 487.5 520 520
97500 65000 48880 41600 32500 27820
8125 9750 11375 12188 13000 13000
0 0 0 0 0 0
2708 1806 1358 1156 903 773
365.30 243.75 176.80 146.25 122.20
488 18 21.0 715 780
146120 97500 70720 58500 48880
12188 450 525 17875 19500
0 0 0 0 0
4059 2708 1964 1625 1358
PLASTER-1NTERNAL 1 1 1 1 1 1
1 2 3 4 5 6
PLASTER-EXTERNAL 1 1 1 1 1
1 2 3 4 5
1
6
104.00
780
41600
19500
0
1156
62256
10
MORTAR MISC
EXECUTIO N COST
PROFIT OH
STANDA RD RATE PER SFT
6.9 5.0 4.6 3.9 3.6 3.4
52.9 38.0 35.4 30.2 27.6 25.9
7.9 5.7 5.3 4.5 4.1 3.9
60.8 43.6 40.7 34.7 31.7 29.8
BLOCK MASONRY SOURCE :QUICK BLOCKS
BLOCK SIZE
8 6 5 4 3 2
6 8 8 8 8 8
12 12 12 12 12 12
INSERT VALUES
AREA
NO. OF BLOCK
0.50 0.67 0.67 0.67 0.67 0.67
2.00 1.50 1.50 1.50 1.50 1.50
TOTAL COST OF LABOUR CHARGES BLOCK CHARGES B+L
17.00 17.00 15.50 13.50 13.00 12.00
6.0 5.0 5.0 4.0 3.0 3.0
46.0 33.0 30.8 26.3 24.0 22.5
PAVER BLOCKS SOURCE :ENVICRETE TYPE OF BLOCK
60-mm thick city grey 60-mm thick city pigmented 80-mm thick city grey 80-mm thick city pigmented
INSERT VALUES COST OF BLOCK
LABOUR CHARGES
SAND COST
EXECUTI ON COST
PROFIT OH
STANDARD RATE PER SFT
65.00 75.00 73.00 87.00
8.0 8.0 8.0 8.0
4.2 4.2 4.2 4.2
77.2 87.2 85.2 99.2
11.6 13.1 12.8 14.9
88.7 100.2 97.9 114.0
62266
71,605
Jun-08
AVERAGE PRICES FOR VARIOUS CONSTRUCTION INPUT ARTICLE
PRICE
UNIT
IRONOMETRY MILD STEEL-ANGLES
80,000
TONNE
MILD STEEL-SECTIONS
80,000
TONNE
MILD STEEL-PLATES
90,000
TONNE
MILD STEEL-IRON BARS
85,000
TONNE
WOODEN SLEEPERS TIMBER- TEAK
12,000
CFT
TIMBER - DIYAR
4,000
CFT
TIMBER- PARTAL
2,000
CFT
TIMBER - SHISHAM
1,500
CFT
CHIP BOARD-DENSITY 500(1/2 INCH)
25
SQ.FT
CHIP BOARD-DENSITY 600 (3/4 INCH)
30
SQ.FT
PLYWOOD-3mm
25
SQ.FT
PLYWOOD-4mm
30
SQ.FT
HARD BOARD
10
SQ.FT
LASANI BOARD
40
SQ.FT
TOR STEEL
70,000
TONNE
DEFORMED STEEL
75,000
TONNE
CONCRTE MATERIAL
BINDING WIRE
80
KG
CEMENT - OPC
320
50 KG
CEMENT - SRC
340
50 KG
SAND -FINE
22
CFT
SAND -COARSE
25
CFT
CRUSH AGGREGATE
30
CFT
GRAVELED STONE DUST
28
CFT
STONE SOLING
30
CFT
STONE BALLAST
28
CFT
MASONRY WORK CLAY BRICKS RED BRICKS CEMENT BLOCKS- 6x8x12 CEMENT BLOCKS- 4x8x12
ROAD / PAVEMENT WORK ASPHALT-80/100 GRADE
55,000
TONNE
FLOOR PAVERS-60 mm thick
60
SFT
FLOOR PAVERS-60 mm thick pigmented
70
SFT
FLOOR PAVERS-80 mm thick
75
SFT
FLOOR PAVERS-80 mm thick pigmented
85
KERB STONE - 6 x 12
SFT RFT
LABOUR COST
KERB STONE - 6 x 18
RFT PAINTS
PLASTIC EMULSION-CLASSIC
240
LITRE
MATT FINISH
250
LITRE
WEATHERSHIELD
250
LITRE
DISTEMPER-PAINTAX
140
LITRE
SYNTHETIC ENAMEL
240
LITRE
SANITARY FITTINGS W.C.INDIAN-GENERAL SIZE
2,000
W.C.INDIAN-SMALL SIZE
1,500
W.C.ENGLISH WITH FT-CITU
5,000
FLUSHING TANK
2,000
SEAT COVER
600
WASH BASIN WITH PADESTAL TOILET PAPER HOLDER-PLASTIC TOILET PAPER HOLDER-SS
3,000 700 1,500
TOWEL RAIL
500
SHOWER SET
6,000
GAS WATER HEATER-114 LITRE CAPACITY
14,000
GAS WATER HEATER-159 LITRE CAPACITY
15,000
GAS WATER HEATER-228 LITRE CAPACITY
16,000
ELECTRIC WATER HEATER-68 LITRE CAPACITY
9,000
ELECTRIC WATER HEATER-114 LITRE CAPACITY
11,000
ELECTRIC WATER HEATER-159 LITRE CAPACITY
15,000
TILES CEMENT - WHITE
500
40 KG
GLAZED TILES-SHABBIR
450
SQ.M
GLAZED TILES-CHINA
400
SQ.M
GLAZED TILES-6 x 6 / 8 x 8-inch
250
SQ.M
PORCELAIN-MASTER
800
SQ.M
PORCELAIN-CHINA
600
SQ.M
15
SFT
CEMENTED TILE ROOF SHEETS PVC POLYMAX CORRUGATED - 2mm THICK
65
SFT
FRP SHEETS-2mm
130
SFT
FRP SHEETS-3mm
150
SFT
FRP SHEETS-5mm
250
SFT
GI-22SWG
SFT
GI-18SWG
SFT
ACC SHEET
30
SFT
M.S. PIPE -254.4 mm dia x 3.2 mm thick
2,500
R.M.
M.S.PIPE-203.5mm x 3.2mm
2,000
R.M.
M.S.PIPE-152.4mm x 3.2mm
1,500
R.M.
M.S.PIPE
M.S.PIPE-127mm x 3.2mm
1,200
R.M.
PVC PIPE- 1/2" DIA
10
RFT
PVC PIPE- 3/4" DIA
14
RFT
PVC PIPE-1"DIA
22
RFT
PVC PIPE-1 1/4" DIA
27
RFT
PVC PIPE-1 1/2" DIA
33
RFT
PVC PIPE-2" DIA
36
RFT
PVC PIPE-3" DIA
58
RFT
PVC PIPE-4" DIA
150
RFT
PVC PIPE-5" DIA
230
RFT
PVC PIPE-6" DIA
285
RFT
cPVC -1/2" dia
20
RFT
cPVC -3/4" dia
32
RFT
cPVC -1" dia
50
RFT
GI PIPE- 1/2" DIA
22
RFT
GI PIPE- 3/4" DIA
28
RFT
GI PIPE-1"DIA
45
RFT
GI PIPE-1 1/4" DIA
54
RFT
GI PIPE-1 1/2" DIA
66
RFT
GI PIPE-2" DIA
75
RFT
GI PIPE-3" DIA
115
RFT
GI PIPE-4" DIA
300
RFT
GI PIPE-5" DIA
465
RFT
GI PIPE-6" DIA
585
RFT
RCC PIPE -6" DIA
80
RFT
RCC PIPE -9" DIA
100
RFT
RCC PIPE - 12" DIA
120
RFT
RCC PIPE-15" DIA
165
RFT
RCC PIPE-18" DIA
210
RFT
RCC PIPE-24" DIA
360
RFT
RCC PIPE-27" DIA
400
RFT
RCC PIPE-30" DIA
520
RFT
RCC PIPE-33" DIA
560
RCC PIPE-36" DIA
600
RFT
RCC PIPE-42" DIA
800
RFT
PVC PIPES
cPVC
GI PIPES
RCC PIPES
AVERAGE WAGES FOR VARIOUS CONSTRUCTION INDUSTRY MASON
600
Rs./ DAY
UNSKILLED LABOUR
300
Rs./ DAY
TILE FIXER
900
Rs./ DAY
TILE FIXER HELPER
450
Rs./ DAY
CARPENTER
600
Rs./ DAY
CARPENTER HELPER
400
Rs./ DAY
BLACKSMITH
800
Rs./ DAY
BLACKSMITH HELPER
400
Rs./ DAY
PLUMBER
800
Rs./ DAY
PAINTER
700
Rs./ DAY
ELECTRICIAN
800
Rs./ DAY
UNIT LABOUR RATES FOR VARIOUS ACTIVITIES PLASTER INTERNAL WORK
8
SFT
PLASTER EXTERNAL WORK
10
SFT
PAINT DISTEMPER WORK
3
SFT
PAINT MATT/ WS/ENAMEL WORK
5
REINFORCEMENT CUTTING/ BENDING / FIXING
3,000
SFT TONNE
BLOCK MASONRY-6 x 8 x 12
24
CFT
BLOCK MASONRY-4 x 8 x 12
27
CFT
6,000
SET
PLUMBING WORK
RENTAL COST OF MACHINERY ASPHALT MIXER MACHINE
5,000
DAY
CONCRTE MIXER MACHINE
2,000
DAY
LIFT MACHINE
1,000
DAY
EXCAVATOR
1,500
HOUR
SHOWEL
2,000
HOUR
DUMPER
4,000
DAY
ROAD ROLLER
3,000
DAY
VIBRATORY ROLLER
8,000
DAY
PUT ALLIED MATERIAL COST
STRY
METAL MEASUREMENTS
0.75 1 1 1.25 1.25 1.5 1.5 1.5 2 2 2.5 2.5
GAUGE
THICKNESS MM
WGT KG/SQM
WGT KG/SFT
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3.18 2.83 2.52 2.24 1.99 1.77 1.59 1.41 1.26 1.12 1.00 0.89 0.79 0.71 0.63 0.56 0.50 0.44 0.40 0.35 0.31
24.963 22.216 19.782 17.584 15.622 13.895 12.482 11.069 9.891 8.792 7.850 6.987 6.202 5.574 4.946 4.396 3.925 3.454 3.140 2.748 2.434
2.319 2.064 1.838 1.634 1.451 1.291 1.160 1.028 0.919 0.817 0.729 0.649 0.576 0.518 0.459 0.408 0.365 0.321 0.292 0.255 0.226
0.750 1 1 1.25 1.25 1.5 1.5 1.5 2 2 2.5 2.5
ANGLE SIZE 0.125 0.13 0.19 0.13 0.19 0.13 0.19 0.25 0.19 0.25 0.19 0.25
WT 0.263 0.362 0.521 0.462 0.666 0.558 0.812 1.050 1.100 1.440 1.830
ROAD CARPETING DESIGN road area thickness of pavement
1 75
sq.m mm
DESIGN sand-cft
chips-cft
PREMIX CARPET
0.83
0.83
SEAL COAT
0.15
0.29
TACK COAT
aggregate- asphalt-kg cft 1.67
5.06 1 0.75
ROAD CARPETING road area 1 thickness of pavement 75 thickness of eart fill 150 thickness of aggregate fill 150 thickness of stone fill 150 unit rate earth filling 100 stone chips 400 crush 450 stone 350 sand 380 asphalt 42 rent for road roller 5000 charges for mixer with labour and roller 15000 overhead percentage income tax commission
PREMIX CARPET aggregate-cu.m 0.1
SEAL COAT
0.01
TACK COAT
35 6 10
asphalt-kg 5.25
0.98
sq.m mm mm mm mm cu.m cu.m cu.m cu.m cu.m kg per day per day % % %
cost of chips cost of asphalt material cost 40.5 220.5 261
5.2
0.73
41.16
46.36
30.66
30.66
SUB GRADE COMPACTION EARTH FILLING AGGREGATE FILLING STONE FILLING
0.19
18.75
18.75
0.19 0.23
84.38 78.75
84.38 78.75
MISC labour cost 75
TOTAL EXECUTI ON COST 33.6 369.6
BID PRICE
INCOME TAX
COMM
RECEIVABLE
498.96
29.94
49.9
419.13
GAIN
%AGE REC'BLE VS 49.53 EXECUTI 13.4 ON COST
7.5
5.39
59.25
79.98
4.8
8
67.18
7.94
13.4
2.5
3.32 0
36.48
49.24
2.95
4.92
41.36
4.89
13.4
3.33
0.33
3.67
4.95
0.3
0.5
4.16
0.49
13.4
3.33
2.21
24.29
32.79
1.97
3.28
27.55
3.26
13.4
3.33 3.33
8.77 8.21
96.48 90.29
130.25 121.89
7.81 7.31
13.02 12.19
109.41 102.39
12.93 12.1
13.4 13.4
Civil Works at 2nd Shed,West Wharf-PPL 02-06-2008 Bill of Quantity S.NO.
ITEM
QTY
UNIT
1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9
Excavation Earth Filling PCC 1:4: 8 Concrete(SR) PCC 1:3: 6 Concrete(SR) Stone soling PCC flooring in 1:3:6 DPC Class C 1: 2: 4 Concrete(SR) STEEL REINFORCEMENT
6,082 6,820 1,000 1,448 7,266 7,266 530 1 8
cft cft cft cft cft cft rft job ton
18 15 150 170 50 170 40 550,000 145,000
109,476 102,300 150,000 246,160 363,300 1,235,220 21,200 550,000 1,160,000
8 6 80 90 32 90 25 300000 85000
48,656 40,920 80,000 130,320 232,512 653,940 13,250 300,000 680,000
48,656 40,920 80,000 130,320 232,512 653,940 13,250 300,000 680,000
1.10 1.11 1.12 1.13 1.14 1.15
Block masonry Block masonry-4" thick cement plaster cement plaster-external Facing tile strips-4" thick Structral steel work
5,500 990 8,375 6,775 573 36
sft sft sft sft sft ton
180 80 35 45 60 220,000
990,000 79,200 293,125 304,875 34,380 7,920,000
80 35 18 26 40 160000
440,000 34,650 150,750 176,150 22,920 5,760,000
440,000 34,650 150,750 176,150 22,920 3,456,000
1.16 1.17 1.18 1.19 1.20 1.21 1.22 1.23 1.24
PVC sheet Flooring in 1:2:4-2" thick Porcelain tile Glazed tiles Door shutter Wooden partition-11 ft height Wooden partition-5 ft height Aluminium sliding windows Aluminium sliding ventilators
9,000 6,960 6,570 1,770 1,050 5,380 315 1,268 12
sft sft sft sft sft sft sft sft sft
200 60 170 120 1,050 800 900 1,100 2,000
1,800,000 417,600 1,116,900 212,400 1,102,500 4,304,000 283,500 1,394,800 24,000
100 25 110 70 600 400 450 700 1200
900,000 174,000 722,700 123,900 630,000 2,152,000 141,750 887,600 14,400
1.25 1.26 1.27 1.28 1.29 1.30 1.31 1.32 1.33(a) 1.33(b) 1.34
Plastic emulsion paint Weather shield paint Graffiatto over wall PCC steps in 1:2:4-148 steps Termite treatment False ceiling mineral fibre Plinth protection -2" thick Marble steps Marble top-bath room Marble top-kitchen Grill for ACC
18,000 6,215 560 1 7,266 6,900 3,400 1 20 115 360
sft sft sft job sft sft sft job sft sft sft
20 25 50 59,200 25 120 125 37,000 180 180 200
360,000 155,375 28,000 59,200 181,650 828,000 425,000 37,000 3,600 20,700 72,000
10 12 30 29600 20 60 65 22200 120 120 100
180,000 74,580 16,800 29,600 145,320 414,000 221,000 22,200 2,400 13,800 36,000
6 300 6 1 3 5 3 1 10 18 4 3 1 3
each rft each each each each each each each each each each each each
1,500 200 2,000 15,000 12,000 15,000 3,000 10,000 1,500 800 1,000 2,000 10,000 1,000
9,000 60,000 12,000 15,000 36,000 75,000 9,000 10,000 15,000 14,400 4,000 6,000 10,000 3,000
1000 120 1000 10000 8000 10000 1000 6000 1000 500 500 1000 8000 500
6,000 36,000 6,000 10,000 24,000 50,000 3,000 6,000 10,000 9,000 2,000 3,000 8,000 1,500
2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14
Gully trap UPVC drain pipe -2" dia Intercepting trap-Master W.C.-Europeon W.C.-Asian Lavatory Basin Mirror Urinal Floor trap Bib cork Toilet paper holder Glass shelf Kitchen sink Towel rail
RATE
AMOUNT EXECUTION COST
IST C.FLOW
IST RB 109,476 102,300 150,000 246,160 363,300 1,235,220 21,200 275,000 580,000
2ND RB
3rd RB
4th RB
275,000 580,000 0 495,000 39,600 146,563 152,438 34,380 4,752,000 3,168,000 1,800,000 417,600 1,116,900 212,400 1,102,500 4,304,000 283,500 1,394,800 24,000 0 360,000 155,375 28,000 59,200
181,650 828,000 425,000 37,000 3,600 20,700 72,000 9,000 60,000 12,000 15,000 36,000 75,000 9,000 10,000 15,000 14,400 4,000 6,000 10,000 3,000
2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 2.28
Soap dispenser Tee cock Geyser Muslim shower G.I. pipe-2" dia G.I. pipe- 1/2" -1" dia Gate valve C.I. vent -3-4" dia RCC pipe 6-8" dia Manholes Septic tank RCC overhead tank Electric geyser Electric motor INCOME TAX-06% COMMISSION-05% TOTAL (EXECUTION+IT+COMM) SAVING
3 24 4 5 250 1 1 1 1 10 1 1 1 1
each each each each rft each each each each each each each each each
2,000 1,200 20,000 1,500 180 50,000 25,000 96,000 200,000 8,000 70,000 80,000 25,000 20,000
6,000 28,800 80,000 7,500 45,000 50,000 25,000 96,000 200,000 80,000 70,000 80,000 25,000 20,000 27,477,161
1500 800 15000 1000 100 30000 17000 70000 120000 5000 50000 60000 20000 15000
4,500 19,200 60,000 5,000 25,000 30,000 17,000 70,000 120,000 50,000 50,000 60,000 20,000 15,000 16,386,318 6,460,068.00 1,648,630 1,373,858 19,408,806 8,068,355
3,264,306 6,474,980 4,968,000
6,000 28,800 80,000 7,500 45,000 50,000 25,000 96,000 200,000 80,000 70,000 80,000 25,000 20,000 10,844,575 1,091,700