INDEX RATE ANALYSIS FIRST HALF OF 2004 IN

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

DEMOLISHER EXCAVATOR CONCRETOR BLOCK MASONRY BRICKLAYER MASON PAVIOR PLASTERER ROOFER CARPENTER & JOINTER PAINTER & DECORATOR BRASS FOUNDER IRON MONGER TINKER PLUMBER MISCELLANEOUS ANGLE IRON ALUMINIUM WORK

Analysis (page)

Summary (page)

1--9

1--3

10--11

4--4

12--23

5--7

24--24

7--7

25--30

8--9

31--31

9--9

32--33

10--10

34--39

11--12

40--42

13--13

43--58

14--17

59--64

18--19

65--68

20--21

69--69

22--22

70--71

22--22

72--86

23--26

87--90

27--27

91--95

28--29

96--99

30--30

Analysis 1st half - Mullaitivu

Page 2 of 473 SUMMARY. APPROVED B.S.R FOR THE FIRST HALF 0F 2004 IN DEMOLISHER. NO 1/1

DESCRIPTION OF WORK

UNIT

RATE (1st)

Cube

973.00

m3

344.00

Cube

778.00

and debris cleared.

m3

275.00

Ceiling, existing removed materials stacked

Sqr

247.00

and debris cleared.

m2

26.60

Cement concrete demolished, and debris

Sqr

1667.00

cleared away.

m2

179.00

suspended floors reinforcement removed and

Sqr

2408.00

debris cleared.

m2

259.00

Aluminium Alloy removed from roof or walls

Sqr

281.00

and stacked.

m2

30.20

Corrugated sheets iron or asbestos or aluminium alloy

Sqr

304.00

removed from roofs or walls of 2 storeyed buildings

m2

33.00

No

371.00

No

556.00

No

57.00

- do -

No

86.00

Down pipes, 4" to 6" dia G.I old or decayed,

L.ft

3.90

removed from existing building and stacked.

L.m

12.80

Brick work in Cement, demolished brick stacked and debris cleared.

2/1

5/2

6/2

7/2

8/2

9/3

11/3

Brick work in lime, demolished brick stacked

Cement concrete, reinforced demolished in

Corrugated Sheets, Iron, Asbestoes or

Door or Window, size up to 40 S.ft removed from existing walls and door or stacked.

12/3

Doors for window, size over 40 S.ft removed - do -

13/4

- do -

Door or window, sash only, up to 40 S.ft removed from existing walls and stacked.

14/4

Door or window, sash only, over 40 S.ft - do -

15/4

Analysis 1st half - Mullaitivu

Page 3 of 473

16/4

Drains demolished and debris cleared

L.ft

12.00

18/5

Fence uprooted, barbed wire rolled up and all materials stacked (length of fencing to

L.ft

18.00

measured).

L.m

59.00

Analysis 1st half - Mullaitivu

Page 4 of 473 NO 19/5

DESCRIPTION OF WORK

UNIT

RATE (1st)

Floors brick paved, demolished and debris

Sqr

278.00

cleared away.

m2

30.00

No

371.00

Sq.ft

16.90

removed and stacked.

m2

182.00

Gutter, Eaves, removed and stacked from roofs of

L.ft

2.40

single story buildings.

L.m

7.90

Gutter, Eaves removed from roofs of two storeyed

L.ft

3.60

buildings and stracked.

L.m

11.80

Partitions removed and stacked at side, including

Sq.ft

14.20

making goodnes two walls and floors.

m2

153.00

26/7

Lime plastering shipped and debris cleared away.

Sqr

139.00

27/4

Rendering cement, chipped and debris cleared away

Sqr

416.00

from brick walls and floors.

m2

45.00

Rendering cement, chipped and debris cleared away

Sqr

625.00

from cement concrete floors and walls.

m2

67.00

materials and cleaning debris in single storey

Sqr

524.00

building.

m2

56.00

Roof, removing tiles and timber stacking serviceable

Sqr

719.00

material and cleaning debris in two storeyed building.

m2

77.00

20/6

Gate sash removed and stacked after demolishing cement concrete blocks or removing posts and separating pintols (demolishing brick work where necessary paid for separately).

21/6

22/6

23/6

25/7

28/8

29/8

30/8

32/9

Glass panes in doors, windows and fanlights

Roofing removing tiles and timber stacking, serviceable

Rubble masonry in cement, demolished rubble stacked and debris cleared away.

33/9

Rubble masonry in lime demolished rubble stacked and debris cleared away

Analysis 1st half - Mullaitivu

Cube

1216.00

m3

430.00

Cube

778.00

m3

275.00

Page 5 of 473

34/9

Tiles glazed demolished and debris cleared away.

Sqr

741.00

35/10

Tiles calicut or half round, removed from roof of

Sqr

195.00

single storey buildings and stacked.

m2

21.00

Tiles calicut of half round removed from

Sqr

292.00

roof of 2 storeyed buildings and stacked.

m2

31.00

36/10 NO 28

DESCRIPTION OF WORK

40/11

RATE (1st)

Tiles calicut of half round removed from roof of two storeyed buildings and stacked.

39/11

UNIT

Sqr

224.00

work, stacking serviceable materials single storey

Sqr

931.00

building (and debris cleared away in single).

m2

100.00

Ceiling asbestos removing including timber frame

Sqr

1125.00

work,

m2

121.00

Valance/ Barge boarding removed materials stacked

L.ft

2.40

and debris cleared away in single storey building.

L.m

7.90

Valance/ Barge boarding removed

L.ft

3.60

L.m

11.80

Sq.ft

542.00

m2

58.00

Ceiling asbestoes removing including timber frame

- do -

- do -

in two

storeyed building. 41/11

42/11

- do -

- do - in 2 storeyed building. 43/12

Cement plastering, soffit chipped and debris cleared away.

Analysis 1st half - Mullaitivu

Page 6 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU EXCAVATOR. NO 1

DESCRIPTION OF WORK

UNIT

RATE (1st)

Drains, earth, in any soil except rock requiring blasting cut to gradient and

cube

529.00

m3

187.00

cube

622.00

m3

220.00

cube

725.00

m3

256.00

Filling under floor with gravel or other

cube

3001.00

approved quality of filling spread water

m3

1060.00

cube

2314.00

m3

818.00

cube

205.00

shaped as directed soil deposited within site. 2/13

Excavation in any soil except rock requiring blasting part returnfill in and ram, and surplus disposed of within site as directed.

4/14

Filling under floor with gravel or other approved quality of filling, spread, watered and well rammed in 3" layers with available earth.

6/14

and rammed in 3" layers (material not available at site). 7/15

8/15

External Filling.(Material not available at site)

External Filling.(Material available at site)

Analysis 1st half - Mullaitivu

Page 7 of 473 m3

73.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU CONCRETOR. NO 1/15

DESCRIPTION OF WORK Cement concrete 1:3:6 with 2" metel, above one cube (shuttering paid for seperately).

2/15

Cement concrete 1:3:6 (2") upto one cube shuttering paid for seperately.

3/15

Cement concrete 1:2 1/2:5 (1") above one cube (shuttering paid for seperately).

2a/16

Cement concrete 1:3:6 (1 1/2") above 1 cube (shuttering paid for seperately).

2c/16

Cement concrete 1:3:6 (1") above 1 cube (shuttering paid for seperately).

Analysis 1st half - Mullaitivu

UNIT

RATE (1st)

Cube

20647.00

m3

7296.00

Cube

21388.00

m3

7558.00

Cube

22842.00

m3

8071.00

Cube

20840.00

m3

7364.00

Cube

21353.00

m3

7545.00

Page 8 of 473 4/16

Cement concrete 1:2 1/2:5 (1") upto one cube

Cube

23583.00

m3

8333.00

Cube

24675.00

m3

8719.00

Cube

25416.00

m3

8981.00

inclusive of 1/2" cement rendering 1:3 and expansion

L.ft

286.00

joints as necessary excavation (without ramp).

L.m

938.00

Lintol cement concrete 1:2:4 (3/4") 4 1/2"x6"

L.ft

120.00

(Reinforcement paid seperately).

L.m

394.00

Lintol cement concrete 1:2:4 (3/4") 9"x6" (Reinforcement

L.ft

162.00

paid seperately).

L.m

531.00

Lintol cement concrete 1:2:4 (3/4") 9"x9" )Reinforcement

L.ft

218.00

paid seperately).

L.m

715.00

No

315.00

No

118.00

reinforced with expended metal and 1/2" cement rendered

S.ft

111.00

1:2 (R/F paid for seperately).

m2

1195.00

(shuttering paid for seperately). 5/16

Cement concrete 1:2:4 (3/4") above one cube (shuttering paid for seperately).

6/16

Cement concrete 1:2:4 (3/4") upto one cube (shuttering paid for seperately).

11/18

Drains, semi circular, in cement concrete 1:3:6 (1") 9" wide and 9" average depth, with 3" thick sides and base

12/19

13/19

14/20

19/22

Padstones, cement concrete 1:2:4 (3/4") precast or in situ.Size 1-6x1-1 1/2x0-6

19a/22

Padstones, cement concrete 1:2:4 (3/4") precast or in situ.Size 1-6x0-6x0-6

21/23

Slabs over drain, cement concrete 3" thick 1:2:4(3/4")

NO 21a/23

25a/25

23/24

DESCRIPTION OF WORK

UNIT

RATE (1st)

Slabs over drain, cement concrete 3" thick 1:2:4(3/4") reinforced with expended metal and 1/2" cement rendered

S.ft

79.00

1:2 (R/F paid for seperately).

m2

850.00

Cement concrete 1:1 1/2:3 (3/4").

Cube

27551.00

m3

9735.00

No

29.00

Supr stone, cement concrete 1:2:4 (3/4") for door posts supplied and fixed.

Analysis 1st half - Mullaitivu

Page 9 of 473

25/25

Cement concrete 1:2 1/2":5(1") using mixer and vibrator (shuttering paid for

Cube

24048.00

m3

8498.00

Cube

26830.00

m3

9481.00

Cube

27571.00

m3

9742.00

Cube

28682.00

m3

10135.00

Cube

26700.00

m3

9435.00

Cube

27441.00

m3

9696.00

Cube

28552.00

m3

10089.00

Sqr

3988.00

m2

429.00

Sq.ft

60.00

9"x9"x4" 4 ft heigh I.e 4 1/2" ft box).

m2

646.00

Shuttering for footing and walls etc.

Sq.ft

16.00

m2

172.16

Sq.ft

43.00

m2

463.00

seperately). 26/25

Cement concrete 1:2:4(3/4") in column shafts (Reinforcement shuttering and finishes paid for seperately) in guard floor using mixer and vibrator.

27/25

28/25

29/26

Cement concrete as per Item 61 in 1st floor.

Cement concrete as per Item 61 in 2nd floor.

Cement concrete 1:2:4 (3/4") in beams in ground floor (reinforcements shuttering and finishes paid for seperately) using mixer and vibrator.

30/26

31/26

32/26

33/27

33a/27

34/27

Cement concrete as per Item 29 in 1st floor.

Cement concrete as per Item 29 in 2nd floor.

Shuttering for floor slab concrete and dismantling.

Shuttering for column shaft and diamantling (for column

Shuttering for beam including dismantling (12"x18" beam 20 ft long).

35/28

Cement concrete 1:2"4(3/4") lintol in ground floor Reinforcement and shuttering paid for seperately using mixer and vobrator.

NO

DESCRIPTION OF WORK

Analysis 1st half - Mullaitivu

Cube

26678.00

m3

9427.00

UNIT

RATE (1st)

Page 10 of 473 36/28

37/28

38/29

Cement concrete lintols as per Item (71) in 1st floor.

Cube

27419.00

m3

9689.00

4" thick R..C.C 1:2:4 (3/4") in first floor slab (reinforcement

Sqr

8838.00

and shuttering paid seperately) using mixer and vibrator.

m2

951.00

5" thick R.C.C in 1st floor

Sqr

10712.00

m2

1153.00

1/2" cement rendering 1:3 with necessary expension, joints

L.ft

0.00

and excavation, but without ramp

L.m

0.00

Drains in cement concrete 1:3:6(1") as above

L.ft

463.00

But with ramp 2' 6" wide

L.m

1518.00

Cube

16630.00

sand 1:5 mix

m3

5876.00

4" thick cement sand block 1:6 mix masonry

Sqr

6081.00

in cement sand 1:5 mix

m2

655.00

- do 39/29

- do - do -

Drains semi circular in cement concrete 1:3:6 (1") wide and 9" average depth, 3" thick sides and base, inclusive of

40/29

BLOCK MASONRY 1

2

Cement sand block in 1:6 mix in cement

Analysis 1st half - Mullaitivu

Page 11 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU BRICKLAYER. NO 2/30

DESCRIPTION OF WORK Brick work in cement mortar (1:5) above 1 cube (up to 1st

16820.00

m3

5943.00

Cube

17690.00

m3

6251.00

Cube

18559.00

m3

6558.00

Sqr

6593.00

m2

710.00

Sqr

6982.00

m2

752.00

Extra over Item 2-5 and 9-11 for brick

Cube

584.00

work from 1st floor level up 2nd floor.

m3

206.00

Sqrs

195.00

1st floor level to 2nd floor.

m2

21.00

Coping, brick in cement 1:5 weathered and throated on

L.ft

117.31

4 1/2" walls, cement renedered 1/2", 1:3 complete.

L.m

384.00

Coping, brick in cement 1:5 weathered throated on 9" walls

L.ft

164.00

and 1/2" cement rendered 1:3 complete.

L.m

538.00

Doors or window inserted in existing walls including

No

4121.00

as necessary, including necessary excavation (apron paid

L.ft

329.00

for seperately).

L.m

1079.00

3/30

- do -

up to one cube

- do -

- do -

6/31

7/32

12/33

14/34

19/35

20/35

24/37

RATE (1st)

Cube

floor level).

4/31

UNIT

Brick work in cement mortar 1:5 in piers (in ground floor).

Brick work 4 1/2" thick in cement mortar 1:5 above 1 square.

- do -

up to one Sqrs.

Extra over Items 6-8 for brickwork from

Making. 25/37

Drains brick in cement 1:5,9" average depth 12" wide and cement rendered 1/2" thick 1:3 complete with expansion joints

Analysis 1st half - Mullaitivu

Page 12 of 473 26/38

Drains brick in cement 1:5,6" average depth 9" wide and cement rendered 1/2" thick 1:3 complete with expansion joints

28/38

30/39

as necessary, including necessary excavation (apron paid

L.ft

217.00

for seperately).

L.m

712.00

cement mortar 1:5 rendered 1/2" cement 1:2 with foundation

L.ft

170.00

6" below ground.

L.m

558.00

Steps 12" wide and 6" to 9" high masonary or brick work in

Brick work in cement and sand 1:8 in foundation and upto D.P.C.

31/40

Brick work in cement and sand 1:8 in super structure in ground floor.

Analysis 1st half - Mullaitivu

Cube

15894.00

m3

5616.00

Cube

16357.00

m3

5780.00

Page 13 of 473 NO

DESCRIPTION OF WORK

32/40

- do -

33/40

- do -

in 1st floor.

in 2nd floor.

UNIT

RATE (1st)

Cube

16941.00

m3

5986.00

Cube

18108.00

m3

6399.00

MASON. NO 1/41

DESCRIPTION OF WORK Random Rubble Masonary in cement mortar 1:5 above 1 cube.

2/41

- do -

up to one cube.

Analysis 1st half - Mullaitivu

UNIT

RATE (1st)

Cube

15823.00

m3

5591.00

Cube

16379.00

m3

5788.00

Page 14 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU PAVIOR. NO 1/43

2/43

5/44

12/46

DESCRIPTION OF WORK

UNIT

RATE (1st)

Exapansion joints in brick floors, filled with bitumen

L.ft

7.00

and sand.

L.m

23.00

Exapansion joints in concrete floors filled with bitumen and

L.ft

17.00

sand(to full depth of concrete and rendering).

L.m

56.00

Floors, cement concrete 1:2 1/2:5(1") 3" cement rendered 1/2",

Sqr

7868.00

1:2, with expansion joints filled with cement and sand.

m2

611.00

Tiles glazed colour 6"x6" with all specials, supplied and

S.ft

107.00

fixed to walls including raking plaster and bedding in

m2

847.00

Tiles glazed(colour)6"x6", with all

S.ft

128.00

specials, supplied and fixed to walls

m2

1378.00

Tiles 8"x8", pressed of approved pattern and

S.ft

125.00

colour, supplied and fixed.

m2

1350.00

cement mortar 1:2. 12/46

including raking plaster and bedding in cement mortar 1:2. 12d/46

Analysis 1st half - Mullaitivu

Page 15 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU PLASTERER. NO 4/139

DESCRIPTION OF WORK Cracks in wall, plastered in cement 1:3

RATE (1st)

L.ft

12.00

m

39.00

Flashing or plaster bands laid over tiles

L.ft

20.00

4" to 6" wide on roof in cement and lime

L.m

66.00

Rendering cement 1/2", 1:2 above 1

Sqr

1971.00

Square.

m2

212.00

Rendering cement 1/2", 1:2 upto 1 square

Sqr

2110.00

m2

227.00

Sqr

1716.00

m2

185.00

Sqr

1855.00

m2

200.00

Rendering, cement 3/4", 1:2 above 1

Sqr

2790.00

Square.

m2

300.00

Rendering, cement 3/4", 1:2 upto 1 square

Sqr

2975.00

m2

320.00

after chipping 2" to 4" wide 9/141

UNIT

mortar 1:1:4 14/142

15/142

16/143

17/143

18/143

19/143

Rendering cement 1/2", 1:3 above 1 Square.

Rendering cement 1/2", 1:3 upto 1 Square

Analysis 1st half - Mullaitivu

Page 16 of 473

20/144

21/144

22/144

25/145

26/145

Rendering, cement 3/4", 1:3 above 1

Sqr

2493.00

Square.

m2

268.00

Rendering, cement 3/4", 1:3 upto 1 square

Sqr

2679.00

m2

288.00

cement finished smooth with Carborandum

Sqr

587.00

stone

m2

63.00

Rendering, cement, floating coat using Red

Rendering cement 3/4", 1:2 with Pudlo 5lbs

Sqrs

3228.00

to 100 lbs cement

m2

347.00

Skirting in cement mortar 1:3, 1/2"x4"

L.ft

30.00

projected or flush with wall, and

L.m

98.00

Red cement floating, including forming

L.ft

51.00

groove.

L.m

167.00

including forming groove. 27/145

Skirting in cement mortar 1:3, 1/2"x6" projected or flush with all finished with

NO 28/146

29/146

29a/146

DESCRIPTION OF WORK

29c/146

29d/146

RATE (1st)

3/8" thick plastering to RCC beams, slab

Sqrs

2601.00

soffit in cement sand 1:3 .with lime putty

m2

280.00

Sqrs

3681.00

finished smooth with 2 coats of hot tar.

m2

396.00

3/8" thick cement and sand plastering to

Sqrs

2348.00

m2

253.00

Sqrs

1615.00

m2

174.00

Sqrs

1681.00

m2

181.00

Cracks in wall Plastered in cement 1:3

L.ft

13.00

after chipping 2" to 4" wide

L.m

42.00

D.P.C. 3/4" thick in cement, sand 1:2

column and beam 29b/146

UNIT

1/2" thick cement plastering 1:4 mix

5/8" thick cement plastering 1:4 mix

Analysis 1st half - Mullaitivu

Page 17 of 473 29e/146

Plinth plastering 1/2" thick 1:3 cement and sand with red cement floating

Sqrs

2303.00

m2

248.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU ROOFER. NO 5/49

DESCRIPTION OF WORK

UNIT

RATE (1st)

Corrugated asbestos sheet roofing on special upper cl. Timber/kempas purlines supplied and fixed complete including treating timber with wood preservative two coats (ridging measured seperately).

7/50

Corrugated asbestos sheet fixed to roof or wall on existing frame work with

Analysis 1st half - Mullaitivu

Sqrs

10298.00

m2

1109.00

Page 18 of 473 necessary coach screws and limpet

Sqrs

4705.00

m2

506.00

Cement and lime mortar 1:1:4, Coloured

L.ft

78.00

to match tiles.

L.m

256.00

cement and lime mortar 1:1:4 coloured

L.ft

49.00

to match tiles (tiles available at site)

L.m

161.00

fitting ridges fixed complete with

L.ft

149.00

roofing screws or hook bolts.

L.m

489.00

No

28.00

storey Building.

No

24.00

Tiles calicut pattern supplied and laid

Sqr

2750.00

in any Building.

m2

296.00

Tiles, calicut pattern, laid in any

Sqr

185.00

Buildings(tiles available at site).

m2

20.00

Shifting and re-laying calicut pattern

Sqr

370.00

tiles.

m2

40.00

Supplying and laying half round tiles

Sqr

2649.00

on the existing asbestos roof.

m2

285.00

washers, or hook bolts.& with 2 coats wood Preservative to existing frame work 18/53

19/53

21/54

26/55

Ridging, calicut pattern bedded in

Ridging, Calicut Pattern bedded in

Ridging with asbestos cement close

Tiles, calicut pattern, flat supplied and laid up to 5 tiles in single storey building

27/56

Tiles, calicut pattern flat supplied and laid (above 5 and up to 25) in single

30/56

31/56

43/53

44/59

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU CARPENTER & JOINTER. NO

DESCRIPTION OF WORK

Analysis 1st half - Mullaitivu

UNIT

RATE (1st)

Page 19 of 473 8/63

Boards, Barge, Valance, Fascia, 3/4" to 1" thick in class.II Local timber fixed complete with necessary Brass screws new or

12/64

3/61A

14/65

renewed above 1 C.ft.( 9" width) with 1 coat

L.ft

95.00

primer & 2 coat of enamel painting

L.m

310.00

available fixed including cutting and

s.ft

42.00

minor repairs.with 2 coats enamel painting

m2

452.00

2"x1/2" plain chamfered, fixed with brass

L.ft

11.00

screws

L.m

36.00

Sqr

12087.00

m2

1299.68

bothways Rate to include 2 coats tarnap to

Sqr

14211.00

timber and 2 coats emulsion

m2

1530.00

Boardes, Barge, Valance, Facia,

Beadings, Class I local timber 1 1/2" to

Ceiling asbestos, flat fixed with clout headed nails to 4"x2" joists at 4'crs & 2"x 2" bearers at 2' crs of spl.upper class. Timber/ kempas including 1 1/2" x 1/2" cover fillets and 2 1/2" x 1/2" coves of Halmills timber. Rate to include 2 coats tarnap to joists and bearers primer and '2 coats of enamel painting to beadings 'and mouldingd 2 coats of white washing to ceiling. Making holes in wall and fixing joists and bearers 'Per 1.95 Sqrs (15'-0"x13'-0").

14a/65

Ceiling asbestos, flat in eves fixed with clout headed nails to 2" x 2"& 2"x1" spacer bearers not exceading 2'-0 centrs both ways bearers of spl.upper class/ kempus timber including Aluminium beading 1" wide with Rubber fillets fixed not exceedaing 2'-0" crs

paint to abestos sheet 14b/65

Ceiling asbestos, flat fixed with clout headed nails to 4"x2" joists 4'-0 crs & 2"x2" bearers of spl.upper class/kempus timber 2'-0" crs and 2"x1" spacer bearers not exceding 2'-0crs including Aluminium beading 1" wide with

Analysis 1st half - Mullaitivu

Page 20 of 473 rubber fillets not exceeding 2'-0 crs fixed bothways

Sqr

14911.00

Rate to include 2 coats tarnap to timber

m2

1603.00

and 2 coats emulsion paint to abestos sheet NO 14c/65

14d/65

14e/65

26/68A

28/69

DESCRIPTION OF WORK

UNIT

RATE (1st)

As per Item No.14 with only 2"x2"beares

Sqr

10874.00

in eaves ceiling.

m2

1171.00

2 coats of oil paint to beading and

Sqr

1018.00

moulding.

m2

109.46

Ceiling, upper side cleaned and debris

Sqr

92.00

cleared away.

m2

10.00

with brass screws and plugs new or

L.ft

16.00

renewed.

L.m

54.00

7/8" thick sashes in class1 timber

S.ft

394.00

with brass fittings.

m2

4234.00

Sash only, in class 1 timber

S.ft

252.00

fixed with brass furniture.

m2

2717.00

upper Class timber/kempas fixed complete

S.ft

509.00

with brass furniture.

m2

5472.00

Battened sash only 1" to 11/8" thick in sp.

S.ft

377.00

upper class timber/kempas fixed completed with

m2

4061.00

-do-

-do-

White washing to ceiling 2 coats and

Cove mouldings Cl.I 2 1/2"x1 1/2" fixed

Doors or Windows, ledged, braced and battened with grooved and tongured joint,3 3/4" x 2 3/4" frames in spl upper class / kempas and 3/4" to

30/70

32/70

- do -

- do -

Doors or Windows, framed and battened, sash 1" to 1 1/8" thick in Special

32a/70

brass fittings 42/74

Doors or Windows, glazed and/or pannelled with 3 3/4"x2 3/4" frames and

Analysis 1st half - Mullaitivu

Page 21 of 473

44/75

1 1/8" to 1 1/4" sashes in special upper

S.ft

479.00

Class I timber/kempas fixed.

m2

5155.00

in Special upper class timber/kempas with brass

S.ft

416.00

furniture.

m2

4474.00

upper class timber/kempas, fixed complete with

S.ft

425.00

brass furniture.

m2

4568.00

Doors or Windows, glazed or pannelled sash only 1 1/8" to 1 1/4" thick

44a/75

Doors pannelled and terllised/B.R.C. weld mesh No. 32 with 3 3/4"x2 3/4" frames and 1 1/8" thick sashes in special

NO 52/78

53/78

DESCRIPTION OF WORK

UNIT

RATE (1st)

Doors pannelled with 3 3/4"x2 3/4" frames and 1 - 1 1/8"sashes in Special upper

S.ft

487.00

Class timber /kempasfixed.with brass fittings

m2

5244.00

Door or Window, removing easing and

Per

re-fixing.

sash

171.00

Per sash

67.00

short lengths with special upper Class

L.ft

304.00

timber/kempas.

L.m

997.12

Reepers 2"x1" in Class I timber supplied

L.ft

12.00

and fixed new or renewed with iron

L.m

41.00

L.ft

11.00

L.m

36.00

class/Kempus frame work complete with ridges,

Sqr

14294.00

hips etc.

m2

1539.00

54/78

Door or Window, easing only.

55/79

Door or Window frames renewed in

Assume 3'-0" Length of frame renewed 100/92

nails, up to 100 L.ft (shiffting of tiles paid for seperately). re-fixed in new position. 101/92

- do -

- do -

over 100 L.ft. Per 100 L.ft 107/94

Roof with calicut pattern tiles on spl upper

Analysis 1st half - Mullaitivu

Page 22 of 473

107a/94

gable end roof

- do -

Sqr

12093.00

- do -.

m2

1302.00

required sizes and fixed in roof and

C.ft

436.00

other carpentry work.

m3

15387.00

renewed in roof and other carpentry

C.ft

1861.00

work.

m3

65672.00

2" apart diagonally or horizontally and

S.ft

504.00

vertically on 4"x2" Milla timber framing.

m2

5425.00

Door frame 4"x3" in spl upper class timber/kempas

S.ft

239.00

supplied and fixed in position

m2

2575.00

Timber fixed or renewed in post and frames

C.ft

2152.00

- do 117/97

121/98

135/101

138/102

118/97

Timber available, sorted out, cut to

Timber special upper Class/kempas fixed or

Trellis partition with 1/2"x1/2" laths fixed

NO 140/103

DESCRIPTION OF WORK

UNIT

RATE (1st)

Door 1 1/4" thick plywood ordinary sash single (ordinary finish) hung on 4"x3"

140a/103

142/104

frame in Special upper class timber/kempas and

S.ft

321.00

complete with brass furniture with mortice lock

m2

3458.00

As per Item No 140 -do- -do- but with marine type

S.ft

365.00

2'3"x6'9".

m2

3927.00

Supplying and fixing Plywood door 1 1/4" thick

S.ft

207.00

single (Ordinary finish) to the existing frame

m2

2230.00

S.ft

219.00

m2

2356.00

with brass fittings with mortice lock 143/104

-do-

-do-

plywood Marine type 1 1/4" thick

single hung to existing frame with fitting

Analysis 1st half - Mullaitivu

Page 23 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU PAINTER & DECORATOR. NO 13/165

DESCRIPTION OF WORK

ground. Lettering 2" to 3" - do 15/166

Lettering 4" to 5" - do -

23/168

RATE (1st)

Lettering 1" to 1 1/2" painted in sinhalese English or Tamil, including painting

14/165

UNIT Per Letter

- do -

Per

- do -.

Letter

- do - do -.

Painting, enamel paint including washing

Analysis 1st half - Mullaitivu

42.00

50.00

Per Letter

70.00

Page 24 of 473

24/168

25/168

25a/168

27/169

cleaning and smoothing down with sand

Sqr

741.00

paper, 1 coat.

m2

80.00

Painting enamel paint

- do -

Sqr

1415.00

- do -

2 coats.

m2

152.00

Painting New wood 1 Coat primer & 2 Coats

Sqr

2114.00

Enamel paint

m2

228.00

Painting new wood work and 2 coats of

Sqr

1405.00

enamel paint.

m2

151.00

Painting Steel work, 1 coat, with

Sqr

616.00

Anticrosive paint including removing

m2

66.00

oxide including removing scale and

Sqr

1136.00

wire brushing.

m2

122.00

Painting walls with emulsion paint 1 coat

Sqr

534.00

(new coat).

m2

58.00

Painting walls with weather shield 1 coat

Sqr

607.00

( New work )

m2

65.00

Painting walls with Emulsion paint, 2

Sqr

957.00

coats (new work).

m2

103.00

Painting walls with 2 coats of weather shield paint

Sqr

1118.00

( New work )

m2

120.00

coat including preparing surface of old

Sqr

625.00

work.

m2

67.00

scale and wire brushing. 28/169

30/169

30a/169

31/170

31a/170

32/170

Painting Steel work, 2 coats, with Red

Painting walls with Emulsion paint, 1

NO 32a/170

DESCRIPTION OF WORK

UNIT

RATE (1st)

Painting walls with weather shield paint

Sqr

698.00

1 coat ( Old work )

m2

75.00

Sqr

1049.00

m2

113.00

33/170

- do 2 coats

- do - do -

- do -.

Analysis 1st half - Mullaitivu

Page 25 of 473

33a/170

40/172

41/172

44/173

45/173

49/174

50/174

Painting walls with weather shield paint

Sqr

1210.00

2 coat ( Old work )

m2

130.00

Tarnap or other wood preservative,

Sqr

253.00

applied to wood work 1 coat (old work).

m2

27.00

Tarnap or other wood preservative,

Sqr

460.00

applied to wood work 2 coats (new work).

m2

50.00

Varnishing with best copal varnish after

Sqr

867.00

washing down and sand papering 1 coat.

m2

93.00

- do -

- do -

Sqr

1507.00

- do -

2 coats.

m2

162.00

storey buildings 1 coat, including

Sqr

120.00

patching and preparing surface.

m2

12.90

- do -

Sqr

208.00

- do -.

m2

22.00

White or colourwashing walls of single

- do 2 coats

Analysis 1st half - Mullaitivu

Page 26 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU BRASS FOUNDER. Item 4/127

Description

Unit

RATE (1st)

Bolts barrel 4", brass oxidised heavy quality supplied and fixed with brass screws.

6/128

- do -

6"

- do 18/130

- do -

- do -

4"x4"

- do - do -

31/133

170.00

No

154.00

No

102.00

No

300.00

No

379.00

No

277.00

Set

128.00

No

56.00

No

869.00

But hinges 4"x3" brass oxidised heavy quality

- do 29a/132

No

Fanlight Catches brass oxidised heavy

supplied and fixed with brass screws complete. 29/132

185.00

Casement stays 10", brass oxidised heavy

quality with brass screws fixed complete. 27/132

No

Casement fastner with mortice plate, brass oxidised

quality supplied and fixed. 21/131

138.00

- do -

heavy quality supplied and fixed with brass screws. 19/130

No

- do - do -

4"x2 1/2"

- do - do -

Hinges centre pivot (consisting of 2 pieces) brass oxidised heavy quality supplied and fixed with brass screws complete.

31a/133

Rings, brass 1 3/4" to 1 1/2" supplied and fixed to doors and windows with brass screws.

51/137

Lock Mortice Vinion /concord single supplied and fixed.

52/137

Lock Mortice Vinion/concord double, supplied

Analysis 1st half - Mullaitivu

Page 27 of 473 and fixed. 53/137

53a/137

No

2066.00

No

3728.00

Mortice Lock Union ( English) double supplied and fixed.

Item

1442.00

Mortice Lock Union ( English) single supplied and fixed.

54/137

No

Description

Unit

RATE (1st)

Lock Night Latch supplied and fixed with duplicate keys approved quality

No

601.00

63/123

Tor steel rods in reinforcing.

Kg

128.00

64/123

Tor steel rods reinforcement in foundation

Kg

123.00

63a/123

Mild Steel rods in reinforcing lintols or beams.

Kg

126.00

64a/123

Mild Steel rods in Foundation .

Kg

121.00

Analysis 1st half - Mullaitivu

Page 28 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU IRON MONGER. Item 49/119

DESCRIPTION OF WORK

Pair

298.00

No

636.00

window frame at 4" cetres & painted

L.ft

60.00

with one coat red lead & 2 coats aluminium

L.m

199.00

1/2" dia

L.ft

37.00

L.m

124.00

Locks, rim 6" iron, superior quality, heavy type, s/f. with iron screws complete.

67/123

67e/123

RATE (1st)

Hinges T, 10" Iron, heavy quality supplied and fixed with iron screws complete.

60/121

Unit

M.S.Bars 5/8" dia supplied & fixed in

- do -

- do -

Analysis 1st half - Mullaitivu

Page 29 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU TINKER. Item 9/150

DESCRIPTION OF WORK

Unit

RATE (1st)

Flashing G.I.22 B.W.G. 1'6" wide, fixed with 6" turned up along, and top edge

29/156

tucked well into wall in cement and

L.ft

152.00

lime mortar.

L,m

498.00

tarred, joints soldered and cement,

L.ft

342.00

lime filletting complete.

L,m

1121.00

boarding sheet tarred, joints soldered and

L.ft

572.00

cement lime filletting complete.

L,m

1875.00

Gutters, Valley 20 B.W.G 36" wide, renewed on existing board, sheets

34/158

-Do-

renewed including 1" thick timber

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU PLUMBER. Item

DESCRIPTION OF WORK

Unit

RATE (1st)

1/179

Ball valve 1/2" supplied and fixed

No

165.00

2/179

Ball valve 3/4" supplied and fixed

No

231.00

13/181

Wash' Basin, Lavatory, 22"x16" with one tap,

No

2979.00

No

485.00

water plug, new brackets, supplied & fixed complete. (Additional tap, trap, and outlet pipe paid for seperately). 17/182

Basin, sink or urinal including all fittings removed and walls made good

Analysis 1st half - Mullaitivu

Page 30 of 473

31/185

Closet, pedestal type available at site, fixed with cement concrete after breaking concrete floor and making good and connections to soil and flush pipes

32/186

No

889.00

No

612.00

No

6891.00

No

2022.00

No

866.00

No

232.00

No

619.00

No

2061.00

No

785.00

Closet, pedestal type, disconnecting and plugging sewer connection and making good all affected walls and floors

34/186

Closet, pedestal type, with low level glazed earthenware flushing cistern flush pipe, double plastic sheet cover, 1/2" stop cork, trap etc. supplied & fixed completed.

35/186

Closet squatting type, with trap supplied & fixed.

36/187

Closet, squatting type, removed, sewer connections plugged and floor made good.

40/188

Cocks, brass bib 1/2" supplied & fixed (Heavy quality).

66/193

Flushing Cistern fixed complete low level (Ceremics).meterial available

66a/193

Flushing cistern, low level, plastic supplied and fixed complete.

86/197

Mirror, bath room type, supplied & fixed to wall with Rawl plugs and plastic frames.

Item

Description

147/214

Shower rose, 6" pvc supplied & fixed.

153/215

Sink, glazed, earthenware 24"x15"x8"

Unit

RATE (1st)

No

599.00

No

2936.00

supplied and fixed with waste plug, complete (pedestal paid seperately).

Analysis 1st half - Mullaitivu

Page 31 of 473 147a/214

Towel rail 2'-0" long 3/4" dia chromium plated.

171/219

173/220

No

410.00

fixed to wall with rawl plugs.

No

293.00

Stop cocks, 1/2" supplied & fixed

No

234.00

No

267.00

No

280.00

No

433.00

No

463.00

Plastic L.D. make).

No

538.00

As per Item No. 178a (Gate valve 2")

No

1005.00

No

#N/A

plugs.

No

320.00

Pipes pvc 1/2" supplied & fixed.

L.ft

13.00

L.m

42.00

L.ft

20.00

L.m

65.00

L.ft

39.00

L.m

129.00

L.ft

28.00

Soap tray, white porcelain, supplied and

Plastic L.D. make). 174/220

Stop cocks, 3/4" supplied and fixed. Plastic L.D. make).

175/220

Stop cocks, 1" supplied and fixed. Plastic L.D. make).

176/220

Stop cocks, 1 1/4" supplied and fixed. ( Plastic L.D. Model )

177/220

Stop cocks, 1 1/2" supplied and fixed. Plastic L.D. make).

178/221

178a/221

Stop cocks, 2" supplied and fixed.

English make 178b/221

Non return valve English 2" dia

200/228

Tooth brush holder, chromium plated supplied and fixed to wall with Rawl

292/240 293/240

294/240

294a/240

Pipes pvc 3/4" supplied & fixed.

Pipes pvc 1" supplied & fixed 1000 type.

pipes pvc 1" supplied & fixed 600 type.

Analysis 1st half - Mullaitivu

Page 32 of 473 L.m Item 295/240

295a/240

Description Pipes pvc 1 1/4" supplied & fixed 1000 type.

Pipes pvc 1 1/4" supplied & fixed 600 type.

Unit

92.00 RATE (1st)

L.ft

53.00

L.m

175.00

L.ft

42.00

L.m

138.00

296/241

Pipes pvc 1 1/2" supplied & fixed.

L.ft

73.00

296a/241

pvc pipe 1 1/2" (1000 type) supplied &

L.ft

65.00

fixed with out excavation.

L.m

213.00

pvc pipe 1 1/2" (600 type) supplied &

L.ft

47.00

fixed with excavation.

L.m

154.00

pvc pipe 1 1/2" (600 type) supplied &

L.ft

38.00

fixed with out excavation.

L.m

126.00

Pipes pvc 2" (1000 type) supplied & fixed.

L.ft

118.00

With excavation

L.m

388.00

pvc pipe 2" (1000 type) supplied &

L.ft

110.00

fixed with out excavation.

L.m

361.00

pvc pipe 2" (600 type) supplied &

L.ft

71.00

fixed with excavation.

L.m

233.00

pvc pipe 2" (600 type) supplied &

L.ft

63.00

fixed with out excavation.

L.m

206.00

Eaves gutters 6" square type pvc fixed

L.ft

88.00

with PVC brackets. (1' - 6 " Crs)

L.m

288.00

Down Pipe 3 1/2" Dia P.V.C Fixed with

L.ft

81.00

Wooden Plug to wall etc.

L.m

264.00

PVC 4" ( 600 type ) pipe supplied and fixed on walls

L.ft

227.00

L.m

743.00

296b/241

296c/240

297/241

297a/241

297b/241

297c/241

310/243

311/244

311a/244

Analysis 1st half - Mullaitivu

Page 33 of 473 5/245

Drains, pvc 400 type 4" laid on cement concrete 6" thick upto 2'-0" depth of

13/246

invert including excavation and cement

L.ft

357.00

concrete haunching (1:3:6 - 1" metal).

L.m

1171.00

No

627.00

Gulley pvc 6" supplied & fixed including gulley box.

Item 18/247

Description

Unit

RATE (1st)

Manhole 2'x2' and upto 2'-0" deep, 9" thick brick in cement 1:3 walls & cement rendered 1/2" (1:2) with 6" cement conc. foundation 1:3:6 (1" metal) including forming channels but without cover.

19/247

- do -.

Manhold 3' 6" x 2' 3" & 4' to 6' deep 9" thick -do

23/248

5097.00

No

8842.00

No

13518.00

no

797.00

Manhole 3'6"x2'3" & 2'0" to 4'0" deep - do -

20/248

No

-do-

Manhole cover reinforced concrete 3" thick 2'-0x2'-0" approx. supplied & fixed reinforced with 1/4" dia M.S.rods at 3" centres both ways.

26/249

Wire dome for 2" pipe supplied and fixed

no

85.00

1/D

110mm PVC inspection joint supplied and fixed

No

533.00

2D

110mm PVC inspection "Y" joint supplied and fixed

No

611.00

3D

110mm PVC Bend ( 11 Deg.) supplied and fixed

No

246.00

4D

110mm PVC Bend ( 22 Deg.) supplied and fixed

No

250.00

5D

110mm PVC Bend ( 60 Deg.) supplied and fixed

No

341.00

6D

110mm PVC Bend ( 88 Deg.) supplied and fixed

No

485.00

7D

110mm PVC "T" Junction supplied and fixed

No

744.00

Analysis 1st half - Mullaitivu

Page 34 of 473

8D

110mm PVC "Y" Joint supplied and fixed

No

713.00

9D

50mm Bottle trap supplied and fixed

No

302.00

10D

110mm PVC Inspection bend supplied and fixed

No

557.00

11D

63mm PVC "Y" Joint supplied and fixed

No

86.00

12D

110mm PVC Elbow supplied and fixed

No

457.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU MISCELLANEOUS Item 6/251

15/253

Description

Unit

RATE (1st)

Fence barbed wire ,14 gauge, 4 points, 3" sparts, supplied and fixed in

L.ft

4.20

existing timber posts with G.I staples.

L.m

13.80

per post

808.00

per post

901.00

per post

4818.00

Intermediate fence posts or structs, cement concrete 1:1 1/2:3(3/4") reinforced with 4 Nos. 1/4 dia. M.S.rods 5'-7" high square section 4" to 6" fixed complete as per drawing No.68 of 22.07.1936.

16/253 17/253

- do -

- do -

7'6" high

- do -.

End post and strut for Type barbed wire fence fixed complete in cement concrete as per Drg. 68 of 1936.

18/254

Fence barbed wire, 7 strands 14 B.W.G with 4 points at 3" centres and R.C.C posts (1:2:4) 3/4" metal reinforced with 4 Nos. 1/4 rods with 14 B.W.G

Analysis 1st half - Mullaitivu

Page 35 of 473 stirrups at 8" centres including post to be fixed at 8'-0 crs' excavation cement concrete foundation '1:3:6(1 1/2") metal to corner posts and 'structs and straining bolts, all as per type 'plan 68 of 22.07.1936 structs to be 'reinforced with 4 Nos. 3/8" rods and 'corner posts

18A/254

with 4 Nos. 1/2" rods. ( including

L.ft

208.00

white washing 2 coats)

L.m

683.00

- Do - do -

- do -

- do -

- do -

L.ft

214.00

- do -

L.m

703.00

No

292.00

L.ft

111.00

6 Strands

- do 19/254

- do - do -

Straining Bolts 1/2" dia made and fixed 18" long (Approx).

21/255

Well, bailing out water 5' to 7' dia. Upto 20' depth including cleaning well.

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU ANGLE IRON Item 1/A

Description

Unit

RATE (1st)

Supplying and fixing 50mmx50mmx6mm thick Angle iron purlin fixed to wall at not exeeding 900mm centres and joints should be bolted with 2Nos 12mm dia bolts and nuts other site welding with cleats minimum length 450mm in next reduced angle iron including two coats of Anticorrosive paint as directed & including anchoring purlins with 2 nos

2/A

3/A

10mm tor steel welded to purlins where ever necessary and

L.ft

121.00

with 1:2:4 concreting.

L.m

397.00

62.5mmx62.5mmx6mm Angle iron purlin

L.ft

145.00

-DO-

L.m

474.00

L.ft

173.00

-DO-

75mm x 75mm x 6mm Angle Iron purlin

Analysis 1st half - Mullaitivu

Page 36 of 473 -DO4/A

-DO-

L.m

569.00

End Truss-2/50mm x 50mm x 6mm

L.ft

363.00

Per 7'-0" including 1:2:4(3/4) concreting 2nos

L.m

1192.00

End Truss-2/62.5mm x 62.5mm x 6mm

L.ft

403.00

-DO-

L.m

1323.00

End Truss-2/75mm x 75mm x 6mm

L.ft

455.00

-DO-

L.m

1491.00

& bolts & nuts

No

41.00

31mm x 6mm - Flat Iron - 1'-0" long

No

49.00

2/3" x 3" x 1/4"(2/75mm x 75mm x 6mm)

L.ft

453.00

angle iron slope beam including 1:2:4(3/4")

L.m

1485.00

Supplying & fixing 'H' iron 6" x 3" 6mm

L.ft

#N/A

with necessary cleats to housing props

L.m

#N/A

Supplying & fixing ' H ' Iron 8" x 4"

L.ft

81.00

(6mm) with necessary cleats -do-

L.m

265.00

12mm dia 9" long welded to end truss with 2 coats of anticorrosive paint 5/A

6/A

7/A

-DO-

-DO-

25mm x 6mm - Flat Iron - 1'-0" long weld to end purlin as bracket to fix valance board with two coats of anticorrosive paint

8/A

-DO9/A

-DO-

concreting with 4 nos 16mm 9" long Rag bolt with 2 nos 9"x9" 10mm Ms base plate 10/A

including 2 coats of anticorrosive painting 11/A Item 12/A

Description G.I. Gate with 12'-0" x 4'-6" hight 2 Nos sashes made out of 1 1/2" dia G.I. heavy quality frame with 6mm M.S. rod welded 3" c/c both ways all as per Drg. No. 409853 fixed with 9" x 9" RCC pillar in 1:2:4(3/4") concrete 4Y12 reinforced and R6 at 6" crs. stirrups rate include for Excavation base concrete footing R/F with Y10 @ 8" c/c both way 5/8" thick 1:4 plastering 4 Nos. pintol and stirrups locking divice barrel bolt etc. and 2 coats

Analysis 1st half - Mullaitivu

Unit

RATE (1st)

Page 37 of 473 Anticorrosive paint and 2 coats enamel paint

per piller

& 2 coats ofwhite washing to pillers as directed

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN ALUMINIUM WORK

Analysis 1st half - Mullaitivu

21610.00

Page 38 of 473 Item 1/AL

2/AL

3/AL

4/AL

5/AL

6/AL

7/AL

Description Aluminium Partition with sliding door

Unit

RATE (1st)

S.ft

353.00

m2

3797.00

S.ft

610.00

m2

6569.00

S.ft

143.00

m2

1544.00

S.ft

735.00

m2

7906.00

Al Double hung Door with panneled and

S.ft

733.00

glazed

m2

7885.00

Al single hung Door with fully glazed

S.ft

702.00

m2

7550.00

Al Single hung Door with panneled and

S.ft

700.00

glazed

m2

7528.00

Aluminium Casement with project

Aluminium Door frame only

Aluminium door fully glazed double hung

Analysis 1st half - Mullaitivu

Page 39

RATE ANALYSIS FIRST HALF OF 2004 IN DEMOLISHER. No 1/1

Qty

Unit Code

Description Brick work in cement, demolished brick stacked and debris cleared.

Unit Rate

Rate

Amount

Per cube 2 1/2

Days

2/1

257 labourer Allow for scaffolding Over heads Per cube Say Rs Per cube Per m3 Say Per m3

325.00

812.50 40.63

853.13 119.44 972.56 973.00 343.82 344.00

Brick work in lime, demolished brick - do - do -. Per cube 2

Days

5/2

257 Labourer Allow for scaffolding Over heads Per cube Say Per cube Per m3 Say Per m3

325.00

650.00 32.50

682.50 95.55 778.05 778.00 274.91 275.00

Ceiling,existing,removed materials stacked and debris cleared. Per Sqrs. 1 1/2 3

Hour Hour

6/2

214 Carpenter 257 Labourer Allow for scaffolding Over heads Per square Say per sqrs Per m2 Say Per m2

475.00 325.00

89.06 121.88 6.09

217.03 30.38 247.42 247.00 26.59 26.60

Cement concrete demolished, and debris cleared away. Per Sqrs (6" floor) 4 1/2

No

Qty

Day Day

257 Labourers 257 Labourer for Transporting Over heads Say per Sqrs/ 0.5 cube Say per sqrs Rs Per m2 Say per m2 Unit Code Description

Analysis 1st half - Mullaitivu

325.00 325.00

Unit Rate

1,300.00 162.50

Rate

1,462.50 204.75 1,667.25 1,667.00 179.44 179.00 Amount

Page 40 7/2

Cement concrete,reinforced,demolished in suspended floors,reinforcement removed and debris cleared. Per Sqrs. (4" floor) 6 1/2

Day Day

257 Labourers 257 Labourers for Transporting Over heads Per Sqrs/ per 1/3 cube Say per Sqrs/ per 1/3 cube Per m2 Say per m2

8/2

325.00 325.00

1,950.00 162.50

475.00 325.00

118.75 121.88 6.09

2,112.50 295.75 2,408.25 2,408.00 259.20 259.00

Corrugated sheets, Iron, Asbestoes or Aluminium Alloy, removed from roof or walls and stacked. For single storey Per Sqrs. 2 3

Hour Hour

214 Blacksmith 257 Labourer Allow for scaffolding Over heads Per square Say per Sqrs Per m2 Say per m2

9/3

246.72 34.54 281.26 281.00 30.25 30.20

Corrugated sheets asbestos or aluminium alloy removed from roofs or walls of 2storeyed buildings Per square 2 3 0.5

Hrs Hrs Hrs

214 Blacksmith 257 Labourer 257 Labourer (add for extra Height) Allow for scaffolding Overheads per square Say per square per m2 Say per m2

11/3

118.75 121.88 20.31 6.09

267.03 37.38 304.42 304.00 32.72 33.00

Door or window,size up to 40 S.ft removed from existing walls and stacked per door or window. Per No. 2

No

475.00 325.00 325.00

Qty

1/2Day 257 Labourers Over heads Per No Say Rs

Unit Code

325.00

Description

Analysis 1st half - Mullaitivu

Unit Rate

325.00

Rate

325.00 45.50 370.50 371.00

Amount

Page 41

12/3

Door window, size over 40 S.ft removed - do - do Per No. 3

1/2Day 257 Labourers Over heads Per No Say Rs

13/4

325.00

487.50

487.50 68.25 555.75 556.00

475.00 325.00

29.69 20.31

475.00 325.00

44.53 30.47

325.00

40.63

40.63 5.69 3.86 3.90 12.79 12.80

812.50

105.63

105.63

Door or window, sash only, upto 40 S.ft removed from existing walls and stacked. Per Sash. 1/2 1/2

Hour Hour

14/4

50.00 7.00 57.00 57.00

Door or window, sash only, over 40 S.ft - do - do Per Sash. 3/4 3/4

Hour Hour

15/4

214 Carpenter 257 Labourer Over heads Per sash Say Rs

75.00 10.50 85.50 86.00

Down pipes, 4" to 6" dia. G.I old or decayed, removed from existing building and stacked.

1

16/4 0.13

No 18/5

214 Carpenter 257 Labourer Over heads Per sash Say Rs

Qty

Hour

Per 12.0 L.ft. 257 Labourer Over heads Per L.ft Say per L.ft. Per L.m Say per L.m.

Drains demolished and debris cleared. Per 10.0 L.ft Cube Brick in cement demolished (as in Item A.1 less scaffolding) Over heads Per L.ft Say per L.ft. Per L.m Say per L.m. Unit Code Description Fence uprooted, Barbed wire rolled up and all materials stacked (length of fencing to measured).

Analysis 1st half - Mullaitivu

Unit Rate

Rate

14.79 12.04 12.00 39.36 39.40 Amount

Page 42 Per 50 L.ft. (6 posts) 3 2

Hour Day

257 Labourers 257 Labourers Over heads Per L.ft Say per L.ft. Per L.m Say per L.m.

19/5

325.00 325.00

121.88 650.00

650.00

162.50 81.25

771.88 108.06 17.60 18.00 59.04 59.00

Floors brick paved, demolished and debris cleared away. Per Sqrs 3" thick 1/4

Cube

demolition as in item 2 (less scaffolding). Add 50% for extra difficulty. Overheads Per square 3" thick Say per Sqrs Per m2 Say per m2

20/6

243.75 34.13 277.88 278.00 29.92 30.00

Gate sash removed and stacked after demolishing cement concrete blocks or removing posts and separating pintles (demolishing brick work where necessary paid for seperately). 2

1/2Days 257 Labourers Overheads Per No Say Rs

21/6

325.00

325.00

325.00 45.50 370.50 371.00

475.00

89.06

89.06 12.47 101.53 16.92 16.90 182.08 182.00

Glass panes in doors and windows and fanlight removed and stacked. Per 6 S.ft.

No 22/6

1 1/2

Hour

214 Carpenter Over heads Per 6 S.ft Per S.ft Say per S.ft. Per m2 Say per m2

Qty

Unit Code

Description Gutter, eaves, removed and stackedfrom roof of single storeyed building Per 40.0 L.ft.

Analysis 1st half - Mullaitivu

Unit Rate

Rate

Amount

Page 43

2

1Hour 257 Labourers Allow for scaffolding Over heads Per 40 L.ft Per L.ft Say per L.ft. Per L.m Say per L.m.

23/6

325.00

81.25 4.06

85.31 11.94 97.26 2.43 2.40 7.87 7.90

Gutter, eaves, removed from roofs of 2 storeyed building and stacked. Per 40.0 L.ft. 2

1Hour 257 Labourers Add 50% Allow for scaffolding 5% Over heads Per L.ft Say per L.ft. Per L.m Say per L.m.

25/7

325.00

81.25 40.63 6.09

127.97 17.92 3.65 3.60 11.81 11.80

Partitions removed and stacked at site, including making good to walls and floors. Per 105.0 Sq.ft. 1 2 1/4

Day Day Day

214 Carpenter 257 Labourers 214 Mason Allow for cement, sand etc. Over heads Per S.ft Say per S.ft. Per m2 Say per m2

26/7

475.00 325.00 475.00

475.00 650.00 118.75 65.00

1,308.75 183.23 14.21 14.20 152.89 153.00

Lime plastering chipped and debris cleared away. Per Sqrs. 3

No 27/4

Qty

Hour

257 Labourer Overheads Per square Say per Sqrs Per m2 Say per m2

Unit Code

325.00

Description Rendering, cement, chipped and debris cleared away from brick walls and floors. Per Sqrs.

Analysis 1st half - Mullaitivu

Unit Rate

121.88

Rate

121.88 17.06 138.94 139.00 14.96 15.00

Amount

Page 44

9 Hour

257 Labourer Over heads Per square Say per Sqrs Per m2 Say per m2

28/8

325.00

365.63

325.00

365.63 182.81

365.63 51.19 416.81 416.00 44.78 45.00

Rendering, cement, shipped and debris cleared away from cement concrete floors and walls. Per Sqrs. 9

Hour

257 Labourer Add 50% Over heads Per square Say per sqrs per m2 Say per m2

29/8

548.44 76.78 625.22 625.00 67.28 67.00

Roof, removing tiles and timber, stacking serviceable material and cleaning debris in single storeyed building. Per Sqrs. 1/4 Day 214 Carpenter 4 1/4Day 257 Labourers Allow for scaffolding Over heads Per square Say per square Per m2 Say per m2

30/8

475.00 325.00

118.75 325.00 16.25

460.00 64.40 524.40 524.00 56.40 56.00

Roof, removing tiles and timber - do - do - in 2 storeyed buildings. Per Sqrs. 1/4 Day 214 Carpenter 4 1/4Day 257 Labourer 2 1/4Day 257 Labourer Allow for scaffolding Over heads Per square Say per square Per m2 Say per m2

No 32/9

Qty

Unit Code

Description Rubble masonary in cement, demolished, rubble stacked and debris cleared. Per Cube.

Analysis 1st half - Mullaitivu

475.00 325.00 325.00

Unit Rate

118.75 325.00 162.50 24.38

Rate

630.63 88.29 718.91 719.00 77.40 77.00 Amount

Page 45

2 1/2

Day

257 Labourer Add 25% Allow for scaffolding Over heads Per cube Say per cube Per m3 Say per m3

33/9

325.00

812.50 203.13 50.78

1,066.41 149.30 1,215.70 1,216.00 429.68 430.00

Rubble masonry in lime demolished rubble stacked and debris cleared away Per Cube 2

Day

257 Labourer Allow for scaffolding Overheads Per cube Say per Cube Per m3 Say per m3

34/9

325.00

650.00 32.50

682.50 95.55 778.05 778.00 274.91 275.00

Tiles, glazed demolished and debris cleared. Per Sqrs. 2

Day

257 Labourer Overheads Per Square Say per square Per m2 Say per m2

35/10

325.00

650.00

325.00

162.50 8.13

650.00 91.00 741.00 741.00 79.76 80.00

Tiles calicut or half round, removed from roof of single storeyed buildings and stacked at site. Per Sqrs. 4

No 36/10

Qty

Hour

257 Labourer Allow for scaffolding Over heads Per square Say per square Per m2 Say per m2

Unit Code

Description Tiles calicut of half round removed from roof of 2 storeyed buildings and stacked. Per Sqrs.

Analysis 1st half - Mullaitivu

Unit Rate

Rate

170.63 23.89 194.51 195.00 20.99 21.00

Amount

Page 46 4 2

Hour Hour

39/11

325.00 325.00

162.50 81.25 12.19

255.94 35.83 291.77 292.00 31.43 31.00

Ceiling Asbestoes, removing including timber frame work, stacking serviceable materials storeyed building- (and debris cleared away in single).

1 1

Day Day

40/11

1 1 1/4

Day Day Day

41/11

2

No 42/11

257 Labourer 257 Labourer Allow for scaffolding Overheads Per square Say per square Per m2 Say per m2

Qty

1Hour

Unit

Per Sqrs. 214 Carpenter 257 Labourer Allow for scaffolding Over heads Per square Say Rs Per m2 Say per m2 Ceiling Asbestoes removing including timber frame work - do - do in 2 storeyed building. Per Sqrs. 214 Carpenter 257 Labourer 257 Labourer (02) Allow for scaffolding Over heads Per square Say per square Per m2 Say per m2 Valance/Barge boarding removed, materials stacked and debris cleared away in single storeyed building. Per 40.0 L.ft 257 Labourer Allow for scaffolding Over Heads Per L.ft Say per L.ft. Per L.m Say per L.m. Code Description Valance/Barge boarding removed - do - do in 2 storeyed building.

475.00 325.00

475.00 325.00 325.00

325.00

Unit Rate

475.00 325.00 16.25

475.00 325.00 162.50 24.38

81.25 4.06

Rate

816.25 114.28 930.53 931.00 100.22 100.00

986.88 138.16 1,125.04 1,125.00 121.10 121.00

85.31 11.94 2.43 2.40 7.87 7.90 Amount

Per 40.0 L.ft. 2

11/2hr 257 Labourer Scaffolding

325.00

Analysis 1st half - Mullaitivu

121.88 6.09

127.97

Page 47 Over Heads Per L.ft Say per L.ft. Per L.m. Say per L.m. 43/12

17.92 3.65 3.60 11.81 11.80

Cement plastering, soffit chipped, and debris cleared away. Per Sqrs. 1 1/8

Day

257 Labourer Add 25% for extra difficulty Allow for scaffolding 5% Over Heads Per square Say per square Per m2 Say per m2

325.00

365.63 91.41 18.28

475.31 66.54 541.86 542.00 58.34 58.00

RATE ANALYSIS FIRST HALF OF 2004 IN EXCAVATOR No 1

Qty

Unit Code

Description Drains, earth, in any soil except rock requiring blasting cut to gradient and shaped as directed soil deposited within site.

Analysis 1st half - Mullaitivu

Unit Rate

Rate

Amount

Page 48

1 3/8 1/3

day no

1 5/8 1/3

day no

1 3/4

day

2/13

4/14

1/3

6/14

1 2

Cube day

1/3

No 7/15

Qty

1 1/2 1/3

Unit

Per Cube. 257 Labourer 325 24 Basket 52.5 Overheads Per Cube Say per cube Per m3 Say per m3 Excavation in any soil except rock requiring blasting part returnfill in and ram, and surplus disposed of within site as directed. Per Cube. 257 Labourer 325 24 Basket 52.5 Overheads Per Cube Say per cube Per m3 Say per m3 Filling under floor with gravel or other approved quality of filling, spread, watered and well rammed in 3" layers with available earth. Per Cube. 257 Labourer 325 413 Allow for water 50 24 Basket 52.5 Overheads Per Cube Say per cube Per m3 Say per m3 Filling under floor with gravel or other approved quality of filling spread water and rammed in 3" layers (material not available at site). Per Cube. 61 Earth 1850 257 Labourer 325 Allow for compactive 10% 65 413 Allow for water 50 24 Basket 52.5 Overheads Per Cube Say per cube Per m3 Say per m3 Code Description Unit Rate External Filling.(Material not available at site)

Per Cube. Cube 61 Earth day 257 Labourer no 24 Basket Overheads Per Cube

1850 325 52.5

Analysis 1st half - Mullaitivu

446.88 17.50

528.13 17.50

568.75 50.00 17.50

1,850.00 650.00 65.00 50.00 17.50

Rate

1,850.00 162.50 17.50

464.38 65.01 529.39 529.00 186.93 187.00

545.63 76.39 622.01 622.00 219.79 220.00

636.25 89.08 725.33 725.00 256.18 256.00

2,632.50 368.55 3,001.05 3,001.00 1,060.42 1,060.00 Amount

2,030.00 284.20 2,314.20

Page 49 Say per cube Per m3 Say per m3

8/15

2,314.00 817.67 818.00

External Filling.(Material available at site)

1/2 1/3

day no

Per Cube. 257 Labourer 24 Basket Overheads Per Cube Say per Cube Per m3 Say per m3

325 52.5

162.50 17.50

180.00 25.20 205.20 205.00 72.51 73.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU CONCRETOR. No 1/15

Qty

Unit

Description Cement concrete 1:3:6 with 2" metal, above one cube. (Shuttering paid for seperately). Per Cube.

Analysis 1st half - Mullaitivu

Unit Rate

Rate

Amount

Page 50

11.25 Cwts 46 Cement 0.56 Cube 197 Sand 1 Cube 137 2" Metal 1 Day 214 Mason 8 Day 257 Labourer 2/3 24 Basket 410 Allow for water Over heads Per cube Say per cube Per m3 Say per m3 2/15

520.00 2100.00 7850.00 475.00 325.00 52.50 125.00

5,850.00 1,176.00 7,850.00 475.00 2,600.00 35.00 125.00

18,111.00 2,535.54 20,646.54 20,647.00 7,295.76 7,296.00

Cement concrete 1:3:6 (2") upto 1 cube. (Shuttering paid for seperately). Per Cube. As in Item 1 Add 25% of Cost of labourer Over heads Per cube Say per cube Per m3 Say per m3

18,761.00 2,626.54 21,387.54 21,388.00 7,557.60 7,558.00

Cement concrete 1:2 1/2:5 (1") above 1 cube (Shuttering paid for seperately). Per Cube.

3/15

13.6 0.6 1 1 8 2/3

No 2a/16

18,111.00 650.00

Qty

Cwts Cube Cube Day Day

46 197 136 214 257 24 410

Unit

Cement Sand 1" metal Mason Labourer Baskets Allow for water Over heads Per cube Say per cube Per m3 Say per m3

520.00 2100.00 8470.00 475.00 325.00 52.50 125.00

Description Cement concrete 1:3:6 (1 1/2") above 1 cube (shuttering paid for seperately).

Unit Rate

7,072.00 1,260.00 8,470.00 475.00 2,600.00 35.00 125.00

Rate

Per Cube. 11.25 1 0.56 2/3

Cwt cube cube No

46 135 197 24

Cement Metal (1 1/2") Sand Basket

520.00 8020.00 2100.00 52.50

Analysis 1st half - Mullaitivu

5,850.00 8,020.00 1,176.00 35.00

20,037.00 2,805.18 22,842.18 22,842.00 8,071.38 8,071.00

Amount

Page 51

1 8

day day

410 Allow for water 214 Mason 257 Labourer Over heads Per cube Say per cube per m3 Say per m3

2c/16

125.00 475.00 325.00

125.00 475.00 2,600.00

520.00 8470.00 2100.00 52.50 125.00 475.00 325.00

5,850.00 8,470.00 1,176.00 35.00 125.00 475.00 2,600.00

18,281.00 2,559.34 20,840.34 20,840.00 7,363.96 7,364.00

Cement concrete 1:3:6 (1") above 1 cube (shuttering paid for seperately). Per Cube. 11.25 1 0.56 2/3

Cwt cube cube

1 8

day day

46 136 197 24 410 214 257

4/16

Cement 1" Metal Sand Basket Allow for water Mason Labourer Over heads Per cube Say per cube per m3 Say per m3

18,731.00 2,622.34 21,353.34 21,353.00 7,545.23 7,545.00

Cement concrete 1:2 1/2:5 (1") upto one cube (Shuttering paid for seperately). Per Cube. As in Item 3 Add 25% of Cost of labourer Over heads Per cube Say per cube Per m3 Say per m3

No 5/16

Qty

Unit Code

20,037.00 650.00

Description Unit Rate Cement concrete 1:2:4 (3/4") above 1 cube (Shuttering paid for seperately).

Rate

Per Cube. 16 0.6 1 1

Cwts 46 Cement Cube 197 Sand Cube 138 3/4" metal Day 214 Mason

520.00 2100.00 8830.00 475.00

Analysis 1st half - Mullaitivu

8,320.00 1,260.00 8,830.00 475.00

20,687.00 2,896.18 23,583.18 23,583.00 8,333.22 8,333.00

Amount

Page 52 8 2/3

Day

257 Labourer 24 Basket 410 Allow for water Over heads Per cube Say per cube Per m3 Say per m3

6/16

325.00 52.50 125.00

2,600.00 35.00 125.00

21,645.00 3,030.30 24,675.30 24,675.00 8,719.08 8,719.00

Cement concrete 1:2:4 (3/4") upto 1 cube (Shuttering paid for seperately). Per Cube. As in Item 5 Add 25% of Cost of Labourer Over heads Per cube Say per cube Per m3 Say per m3

11/18

21,645.00 650.00

22,295.00 3,121.30 25,416.30 25,416.00 8,980.92 8,981.00

Drains, semi circular, in cement concrete 1:3:6 (1") 9" wide and 9" average depth, with 3" thick sides and base, inclusive of 1/2" cement rendering 1:3 and expansion joints as necessary, including necessary excavation (without ramp). Per 10.0 L.ft. 1.25 0.06 0.08 1/2 1 1/2 1/2

No 12/19

Cwts Cube Cube Day Day Day Day

46 197 136 214 257 214 257

Cement Sand 1" metal Mason Labourer Mason (Rendering) Labourer (Rendering) Allow for shuttering, baskets etc.10% Over heads Per 10 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m.

Qty

Unit Code

0.3 0.01 0.02 14

Cwts 46 Cement Cube 197 Sand Cube 138 3/4" metal S.ft 182 Planks (1/4 new cost)

520.00 2100.00 8470.00 475.00 325.00 475.00 325.00

Description Unit Rate Lintol cement concrete 1:2:4 (3/4") 4 1/2"x6" (Reinforcement paid for seperately) with form work Per 10.0 L.ft.

Analysis 1st half - Mullaitivu

520.00 2100.00 8830.00 50.00

650.00 126.00 677.60 237.50 325.00 237.50 162.50 96.25

Rate

156.00 21.00 176.60 175.00

2,512.35 351.73 2,864.08 286.41 286.00 938.08 938.00 Amount

Page 53

2 2 2 2

Hour Hour Hour Hour

13/19

0.6 Cwts 0.02 Cube 0.035 Cube 17 S.ft 2 2 2 2

Hour Hour Hour Hour

1.35 0.04 0.08 34

Cwts Cube Cube S.ft

3 3 1/2 1/2

Hour Hour Day Day

Qty

Unit

14/20

No 19/22

0.58 Cwts 0.02 Cube 0.035 Cube 12 S.ft 2 Hour 2 Hour

Allow for use of timber props and nails 40.63 Carpenter 475.00 Labourer 325.00 Mason 475.00 2 Labourers 325.00 Over heads Per 10 L.ft Per L.ft Say per L.ft Per L.m. Say per L.m. Lintol, cement concrete 1:2:4 (3/4") 9"x6" (Reinforcement paid for seperately). with form work Per 10.0 L.ft. 46 Cement 520.00 197 Sand 2100.00 138 3/4" metal 8830.00 182 Planks (1/4 new cost) 50.00 Allow for use of timber props & nails water etc 65.63 214 Carpenter 475.00 257 Labourer 325.00 214 Mason 475.00 257 2 Labourers 325.00 Over heads Per 10 L.ft Per L.ft Say per L.ft. Say per L.m. Lintol, cement, concrete, 1:2:4 (3/4"), 9"x9" (Reinforcement paid for seperately). with form work Per 15.0 L.ft. 46 Cement 520.00 197 Sand 2100.00 138 3/4" Metal 8830.00 182 Planks (1/4 new cost) 50.00 Allow for nails & props & water. 90.63 214 Carpenter 475.00 257 Labourer 325.00 257 Labourer (02) 325.00 214 Mason 475.00 Over heads Per 15 L.ft Per L.ft Say per L.ft Say per L.m Code Description Unit Rate Padstones, cement, concrete 1:2:4 (3/4" metal) precast or in situ. Per 4 Nos. = Size 1-6x1-1 1/2x0-6 46 Cement 520.00 197 Sand 2100.00 138 3/4" Metal 8830.00 182 Planks (1/4 new cost) 50.00 214 Mason 475.00 257 Labourer (02) 325.00 214 257 214 257

Analysis 1st half - Mullaitivu

40.63 118.75 81.25 118.75 162.50

312.00 42.00 309.05 212.50 65.63 118.75 81.25 118.75 162.50

702.00 84.00 706.40 425.00 90.63 178.13 121.88 325.00 237.50

Rate

301.60 42.00 309.05 150.00 118.75 162.50

1,050.48 147.07 1,197.54 119.75 120.00 393.60 394.00

1,422.43 199.14 1,621.56 162.16 162.00 531.00

2,870.53 401.87 3,272.40 218.16 218.00 715.00 Amount

Page 54 allow for water Over heads Per 4 Nos. Per No. Say per No. 19a/22

20.31

20.31

520.00 2100.00 8830.00 50.00 325.00 475.00

88.40 21.00 88.30 75.00 81.25 59.38

1,104.21 154.59 1,258.80 314.70 315.00

Padstones, cement, concrete 1:2:4 (3/4" metal) precast or in situ. Per 4 Nos. - Size - 1-0x0-6x0-6 .17 Cwts 46 Cement 0.01 Cube 197 Sand .01 Cube 138 3/4" Metal 6 S.ft 182 Planks (1/4 new cost) 2 hour Labour 1 hour mason

413.33 57.87 471.19 117.80 118.00

Overheads Per 4 Nos Per no Say per No 21/23

Slabs over drain, cement concrete 3" thick, 1:2:4 (3/4" metal) reinforced with expended metal and 1/2" cement rendered 1:2 (R/F paid for seperately). Per 15.0 S.ft. 0.6 0.02 0.04 16 2 2

Cwts Cube Cube S.ft Hour Hour

46 197 138 182 214 257

Cement( For slab) Sand 3/4" Metal Shuttering planks (1/4 new cost) Mason Labourer (02)

0.23 0.01 1 1

Cwts 46 Cement(For rendering) Cube 200 Sand Hour 214 Mason Hour 257 Labourer 414 Allow for water Over heads Per 15 S.ft Per S.ft Say per S.ft. Per M2 Say Per M2 Unit Code Description Slabs over drain, cement concrete 2" thick, 1:2:4 (3/4" metal) reinforced with expended metal and 1/2" cement rendered 1:2 (R/F paid for seperately). Per 15 L.ft As in item 21 ('2" concrete for slab x 2/3) Cwts 46 Cement(For rendering) Cube 200 Sand Hour 214 Mason

520.00 2100.00 8830.00 50.00 475.00 325.00

312.00 42.00 353.20 200.00 118.75 162.50

520.00 2100.00 475.00 325.00 25.00

119.60 21.00 59.38 40.63 25.00

1,188.45

No 21a/23

Qty

0.23 0.01 1

Analysis 1st half - Mullaitivu

Unit Rate

520.00 2100.00 475.00

Rate

792.30 119.60 21.00 59.38

1,454.05 203.57 1,657.62 110.51 111.00 1,194.83 1,195.00 Amount

Page 55 1

Hour

257 Labourer Allow for water Over heads Per 15 S.ft Per S.ft Say per S.ft. Per M2 Say Per M2

25a/25

40.63 5.08

1,037.98 145.32 1,183.30 78.89 79.00 850.38 850.00

Cement concrete 1:1 1/2:3 (3/4").

23 0.82 0.42 1 6 1/3

Cwt cube cube day day day

2/3

Per Cube. 46 Cement 138 3/4" Metal 197 Sand 214 Mason 257 Labourer 97 Hire of mixure, vibrator etc. 410 Allow for water 24 Basket Over heads Per cube Say per cube Per m3 Say per m3

23/24

No 25/25

325.00 5.08

520.00 11,960.00 8830.00 7,240.60 2100.00 882.00 475.00 475.00 325.00 1,950.00 4500.00 1,500.00 125.00 125.00 52.50 35.00

24,167.60 3,383.46 27,551.06 27,551.00 9,735.34 9,735.00

Spur Stones, cement concrete 1:2:4 (3/4") for door posts supplied and fixed. Per 10.0 Stone. 138 3/4" Metal 197 Sand Allow for moulds 46 Cement 214 Mason 257 Labourer Over heads Per 10 Stones Per Stone Say per stone

0.15 0.07

Cu.ft Cu.ft

0.03 2 2

Cwt Hour Hour

Qty

Unit Code

Description Cement concrete 1:2 1/2:5 (1") using concrete mixer and vibrator (Shuttering paid for seperately).

88.30 21.00 32.50 520.00 475.00 325.00

Unit Rate

13.25 1.47 32.50 15.60 118.75 81.25

Rate

Per cube. 14 0.6 1

Cwts 46 Cement Cube 197 Sand Cube 136 1" Metal

520.00 2100.00 8470.00

Analysis 1st half - Mullaitivu

7,280.00 1,260.00 8,470.00

262.82 36.79 299.61 29.96 29.00

Amount

Page 56 1 6 2/3

Day Day

1/3

Day

214 257 24 410 97

26/25

475.00 325.00 52.50 125.00 4500.00

475.00 1,950.00 35.00 125.00 1,500.00

21,095.00 2,953.30 24,048.30 24,048.00 8,497.53 8,498.00

Cement concrete 1:2:4 (3/4") in Column shafts (Reinforcements shuttering and finishes paid for seperately) in ground floor using mixer and vibrator.

18 0.6 1 1 6 2/3

Cwts Cube Cube Day Day

1/3

Day

Per Cube. Cement 520.00 Sand 2100.00 3/4" Metal 8830.00 Mason 475.00 Labourer 325.00 Basket 52.50 Allow for water and curing 125.00 97 Hire ofmixer,vibrator,wagesof operator and fuel. 4500.00 Over heads Per cube Say per cube Per m3 Say per m3

46 197 138 214 257 24

27/25

9,360.00 1,260.00 8,830.00 475.00 1,950.00 35.00 125.00 1,500.00

23,535.00 3,294.90 26,829.90 26,830.00 9,480.57 9,481.00

Cement concrete as per Item 26 in 1st floor.

2

No 28/25

Mason Labourer Basket Allow for water and curing Hire of mixer, vibrator,wages of operator fuel Over heads Per cube Say per cube Per m3 Say per m3

Qty

5

Day

As per Item 26 257 Labourer Over heads Per cube Say per cube Per m3 Say per m3

23535.00 23,535.00 325.00 650.00

Unit Code

Day

Description Cement concrete as per Item 26 in 2nd floor. As per Item 26 257 Labourer Over heads Per cube Say per cube Per m3 Say per m3

Analysis 1st half - Mullaitivu

Unit Rate

Rate

23535.00 23,535.00 325.00 1,625.00

24,185.00 3,385.90 27,570.90 27,571.00 9,742.40 9,742.00

Amount

25,160.00 3,522.40 28,682.40 28,682.00 10,134.98 10,135.00

Page 57 29/26

Cement concrete 1:2:4 (3/4") in beams in ground floor (reinforcements shuttering and finishes paid for seperately) using mixer and vibrator.

36 1.2 1.8 2 1/2 16 1 1/3

Cwts Cube Cube Day Day

2/3

Day

46 197 138 214 257 24 411 97

Per 2 Cube. Cement Sand 3/4" Metal Mason Labourer Basket Allow for water and curing Hire of concrete mixer vibrators, Operators Salary, fuel

520.00 18,720.00 2100.00 2,520.00 8830.00 15,894.00 475.00 1,187.50 325.00 5,200.00 52.50 70.00 250.00 250.00 4500.00

3,000.00 46,841.50 6,557.81 53,399.31 26,699.66 26,700.00 9,434.63 9,435.00

Over heads Per 2 cube Per cube Say per cube Per m3 Say per m3 30/26

Cement concrete as per Item 29 in 1st floor. Per Cube.

2

31/26

5

No 32/26

Qty

Day

As per Item (29) per cube 257 Labourer Over heads Per cube Say per cube Per m3 Say per m3

Cement concrete as per Item 29 in 2 nd floor. Per 1Cube. As per Item 29 per cube Day 257 Labourer Over heads Per cube Per Cube Say per cube Per m3 Say per m3 Unit Code Description Shuttering for floor slab concrete and dismantling.

23420.75 23,420.75 325.00 650.00

23420.75 23,420.75 325.00 1,625.00

Unit Rate

Rate

Per Sqrs. 115 50 30 2 1/4

S.ft 57 Planks Rubber(1/2new cost) L.ft 123 4"x2" Class II joists (1/10 cost) props 19 30 props (10-12) feet 4"x2" coconut (1/15cost) Ibs 267a Wire nails 2" Gallon 147 Mould oil

Analysis 1st half - Mullaitivu

20.00 40.00 300.00 36.50 100.00

1,150.00 200.00 600.00 73.00 25.00

24,070.75 3,369.91 27,440.66 27,441.00 9,696.47 9,696.00

25,045.75 3,506.41 28,552.16 28,552.16 28,552.00 10,089.05 10,089.00 Amount

Page 58 1 3

Day Day

214 Carpenter 257 Labourer Over heads Per square Say per sqrs Per m2 Say per m2

33/27

475.00 975.00

50.00 13.00 100.00 13.00 32.50 300.00 475.00 325.00

206.25 32.50 3.00 5.20 32.50 50.00 178.13 121.88

20.00 36.50 100.00 475.00 325.00

860.00 73.00 12.50 118.75 81.25

3,498.00 489.72 3,987.72 3,988.00 429.28 429.00

Shuttering for column shaft and dismantling (for column 9"x9"x4 ft. heigh I.e 4 1/2 ft. box). Per 12.0 Sq.ft. 1"planks/15mm plywood/Ginisappu 1/4 cost 2"x2" Class II battens (1/6 cost) Mould oil 3/8" dia 18" bolts, nuts and washers(1/15 cost) Allow for screws and nails Props 19 Coconut rafters (1/30 cost) Day 214 Carpenter Day 257 Labourer Over heads Per 12 S.ft Per S.ft Say per S.ft. Per m2 Say per m2:-

16 1/2 S.ft 15 L.ft 0.03 gal 6 Nos 5 3/8 3/8

182 300 147 301

33a/27

No 34/27

475.00 325.00

629.45 88.12 717.57 59.80 60.00 645.86 646.00

Shuttering for footing and walls etc.

57 267a 147 214 257

Per 80 S.ft Rubber planks ( 1/2 new cost) 2" Nails Mould Oil Carpenter Labourer overheads Per 80 S.ft per S,ft Say per Sft Say per m2

86 2 1/8 1/4 1/4

S.ft Lbs Gal Day Day

Qty

Unit Code

86 200 14 7 1/8 1

Per 80.0 Sq.ft. S.ft 182 Ginisapu planks / Plywood 15mm thick 1/4 cost L.ft 300 2"x2" Class II timber 1/4cost No 19 Coconut rafters(each 10' ) (1/20 cost) Ibs 267a 2" to 3" wire nails Glns 147 Mould oil day 257 Labourer

Description Unit Rate Shuttering for beam including dismantling (12"x18" beam 20 ft. long).

Analysis 1st half - Mullaitivu

50.00 13.00 300.00 36.50 100.00 325.00

Rate

1,075.00 650.00 210.00 255.50 12.50 325.00

1,145.50 160.37 1,305.87 16.32 16.00 172.16

Amount

Page 59 1

Day

214 Carpenter Over heads Per 80 S.ft of beam surface ( 3 sides) There 1 S.ft of beam surface (3 sides) Say per S.ft. Say per m2

35/28

475.00

520.00 2100.00 8830.00 475.00 325.00 125.00 52.50 4500.00

9,360.00 1,260.00 7,947.00 475.00 1,950.00 125.00 35.00 2,250.00

3,003.00 420.42 3,423.42 42.79 43.00 463.00

Cement concrete 1:2:4(3/4") lintol in ground floor (reinforcement and shuttering paid for seperately) using mixer and vibrator.

18 0.6 0.9 1 6

Cwt Cube Cube Day Day

2/3 1/2

No Day

46 197 138 214 257 410 24 97

36/28

Per Cube. Cement Sand Metal Mason Labourer Allow for water and curing Basket Hire of mixer, vibrator, wages of operators & fuel Over heads Per cube Say per cube Per m3 Say per m3

23,402.00 3,276.28 26,678.28 26,678.00 9,426.86 9,427.00

Cement concrete lontols as per Item (35) in 1st floor.

2

No 37/28

475.00

Qty

Day

Per Cube.35 As per Item 35 in groung floor 257 Labourer Over heads Per cube Say per cube Per m3 Say per m3

Unit Code

23402.00 23,402.00 325.00 650.00

Description Unit Rate 4" thick R.C.C 1:2:4 (3/4") in first floor slab (reinforcement and shuttering paid for seperately) using mixer and bibrator.

Per 8.0 Sqrs. 45 1/3 Cwts 46 Cement 2.4 Cube 138 Metal 3/4" 1.6 Cube 197 Sand 1 Day 97 Hire of mixer, vibrator with operator and fuel 4 Day 214 Mason

Analysis 1st half - Mullaitivu

Rate

520.00 23,573.33 8830.00 21,192.00 2100.00 3,360.00 4500.00 4,500.00 475.00 1,900.00

24,052.00 3,367.28 27,419.28 27,419.00 9,688.69 9,689.00

Amount

Page 60 22

Day

1 4/5

No

257 Labourer 411 Allow for water curing 24 Basket Over heads Per 8 Sqrs Per Sqrs Say per Sqrs Per m2 Say per m2

38/29

5" thick R.C.C in 1st floor - do - do -

325.00 250.00 52.50

Qty

Unit Code

40/29

62,019.83 8,682.78 70,702.61 8,837.83 8,838.00 951.35 951.00

- do - do - do -

8.0 Sqrs. 56 2/3 Cwt 46 Cement 3 Cube 138 Metal 3/4" 2 Cube 197 Sand 4 Day 214 Mason 25 Day 257 Labourer 411 Allow for water curing 1 Day 97 Hire of mixer vibrator operators wages and fuel 2 1/5 No 24 Basket Over heads Per 8 Sqrs Per Sqrs Say per Sqrs Say Per m2 per cube Say per cube

No

7,150.00 250.00 94.50

Description

520.00 29,466.67 8830.00 26,490.00 2100.00 4,200.00 475.00 1,900.00 325.00 8,125.00 375.00 375.00 4500.00 4,500.00 52.50

Unit Rate

115.50

Rate

75,172.17 10,524.10 85,696.27 10,712.03 10,712.00 1,153.00 25,708.80 25,708.00

Amount

Drains in cement concrete 1:3:6(1") as above But with ramp 2' 6" wide Per 10 L.ft

6.25 C.ft 25 S.ft

Drains as per Item 39 1:3:6 (1") Concrete 1:3 Rendering Per 10 L,ft

Analysis 1st half - Mullaitivu

213.53 17.16

2,864.08 1,334.56 429.00 4,627.64

Page 61 Say per L.ft Say per L.m

463.00 1,518.00

BLOCK MASONRY 1

Cement sand block in 1:6 mix in cement sand 1:5 mix Per Cube

12 1 3

Casting of blocks Cwt 46 Cement Cube 197 Sand fine Day 214 Mason

Analysis 1st half - Mullaitivu

520.00 2100.00 475.00

6,240.00 2,100.00 1,425.00

Page 62 6

1.5 0.10 2 2

Day

257 Labourer 411 Allow for water for curing & mould

Cwt 46 Cement Cube 197 Sand Day 214 Mason Day 257 Labourer Allow for scaffolding Overheads Per cube Say per Cube Per m3 Say per m3

2

325.00 250.00

1,950.00 250.00

520.00 2100.00 475.00 325.00

780.00 210.00 950.00 650.00 32.50

14,587.50 2,042.25 16,629.75 16,630.00 5,876.33 5,876.00

4" thick cement sand block 1:6 mix masonry in cement sand 1:5 mix

3 Cwt 46 0.333 Cube 197 1 Day 214 2 Day 257 410 1 0.07 1 2

Cwt 46 Cube 197 Day 214 Day 257

Per Sqr Casting of blocks Cement Sand Mason Labourer Allow for water for curing & mould Masonry Cement Sand Mason Labourer Allow for scaffolding Overheads Per sqr Say per sqr Per m2 Say per m2

520.00 2100.00 475.00 325.00 125.00

1,560.00 699.30 475.00 650.00 125.00

520.00 2100.00 475.00 325.00

520.00 147.00 475.00 650.00 32.50

5,333.80 746.73 6,080.53 6,081.00 654.52 655.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU BRICKLAYER No 2/30

Qty

Unit

Description Brick work in cement Mortar (1:5) above 1 cube (up to 1st floor level).

Unit Rate

Rate

Per Cube. 1450

No

41 Bricks Add 10% wastage

Analysis 1st half - Mullaitivu

5.70

8,265.00 826.50

Amount

Page 63 23 3.7

Cu.ft Cwts

3 5

Day Day

3/30

197 46 410 214 257

Sand Cement Allow for water Mason Labourer Allow for scaffolding 5% of Labour Over heads per cube Say per cube Per m3 Say per m3

2100.00 520.00 125.00 475.00 325.00

483.00 1,924.00 125.00 1,425.00 1,625.00 81.25

14,754.75 2,065.67 16,820.42 16,820.00 5,943.46 5,943.00

Brick work in cement mortar (1:5) up to 1 cube (up to 1st floor level). Per Cube.

3/4 1 1/4

Day Day

4/31

No 6/31

As in Item 2 214 Mason 257 Labourer Over heads Per cube Say per cube Per m3 Say per m3

14,754.75 14,754.75 475.00 356.25 325.00 406.25

15,517.25 2,172.42 17,689.67 17,690.00 6,250.88 6,251.00

Brick work in cement mortar 1:5 in piers (in ground floor).

1 1/2 2 1/2

Day Day

Qty

Unit

Per Cube. As in Item 2 214 Mason 257 Labourer Over heads Per cube Say per Cube Per m3 Say per m3

14,754.75 14,754.75 475.00 712.50 325.00 812.50

Description Brick work 4 1/2" thick in cement mortar 1:5 above 1 Square

Unit Rate

Rate

Per Sqrs. 550

No

9 1.3

C.ft Cwt

41 Bricks Add 10% wastage 197 Sand 46 Cement 412 Allow for water

Analysis 1st half - Mullaitivu

5.70 2100.00 520.00 75.00

3,135.00 313.50 189.00 676.00 75.00

16,279.75 2,279.17 18,558.92 18,559.00 6,557.95 6,558.00

Amount

Page 64 1 1/2 2

Day Day

214 Mason 257 Labourer Allow for scaffolding Over heads Per square Say per sqrs Per m2 Say per m2

7/32

475.00 325.00 32.50

712.50 650.00 32.50

5,783.50 475.00 325.00

5,783.50 178.13 162.50

325.00 24.38

487.50 24.38

325.00 8.13

162.50 8.13

5,783.50 809.69 6,593.19 6,593.00 709.69 710.00

Brick work 4 1/2" thick in cement 1:5 up to 1 square. Per Sqrs.

3/8 1/2

Day Day

12/33

1 1/2

Day

As in Item 6 214 Mason 257 Labourer Over heads Per square Say per Sqrs Per m2 Say per m2 Extra over Item 2 for brick work from 1st floor level up 2nd floor. Per Cube. 257 Labourer Add for scaffolding Over heads Per cube Say per cube Per m3 Say per m3

14/34

511.88 71.66 583.54 584.00 206.36 206.00

Extra over Items 6-8 for brickwork from 1st floor level to 2nd floor. Per Sqrs. 1/2

No 19/35

6,124.13 857.38 6,981.50 6,982.00 751.56 752.00

Day

257 Labourer Add for scaffolding Over heads Per square Say per Sqrs Per m2 ay per m2

Qty

Unit Code

Description Coping, brick in cement 1:5, weathered and threated on 4 1/2" walls, cement rendered 1/2", 1:3 complete.

400 0.23 5.1 6 6

Per 100.0 L.ft. No 41 Bricks Cube 200 Sand Cwts 46 Cement Day 214 Mason Day 257 Labourer

Unit Rate

5.70 2100.00 520.00 475.00 325.00

Analysis 1st half - Mullaitivu

Rate

2,280.00 483.00 2,652.00 2,850.00 1,950.00

170.63 23.89 194.51 195.00 20.99 21.00 Amount

Page 65 412 Allow for water Over heads Per 100 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m 20/35

75.00

5.70 2100.00 520.00 475.00

381.90 69.30 374.40 356.25 12.19 243.75

10,290.00 1,440.60 11,730.60 117.31 117.00 383.76 384.00

Coping, brick in cement 1:5, weathered threated, on 9" walls and 1/2" cement rendered 1:3 complete.

67 3.3 0.72 3/4

No Cu.ft Cwts Day

3/4

Day

Per 10.0 L.ft. Bricks Sand Cement Mason Allow for water 257 Labourer Over heads Per 10 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m. 41 200 46 214

24/37

325.00

1,437.79 201.29 1,639.08 163.91 164.00 537.92 538.00

Door or Window inserted in existing walls including making, opening and making good to floor and walls (Lintol or Arch, and door or window paid seperately).

1/2 190 3 0.52 1 1 0.75 5 1/2 1

No 25/37

75.00

Qty

1/4 200 1

Per No. 2 Labourer Bricks Sand Cement Mason Labourer Cement( for rendering) Sand Mason allow for water Day 257 Labourer Over heads Per No Say per No Unit Code Description Drains, brick incement 1:5,9" average depth 12" wide, and cement rendered 1/2" thick 1:2 complete with expansion joints as necessary excavation (apron paid for seperately).

Day No C.ft Cwts Day Day Cwts Cu.ft Day

Day No Cwt

257 41 200 46 214 257 46 200 214

Per 10.0 L.ft. 257 Labourer (for excavation) 41 Bricks ( for building drain) 46 Cement

Analysis 1st half - Mullaitivu

325.00 5.70 2100.00 520.00 475.00 325.00 520.00 2100.00 475.00 325.00

Unit Rate

325.00 5.70 520.00

325.00 1,083.00 63.00 270.40 475.00 325.00 390.00 105.00 237.50 16.25 325.00

Rate

81.25 1,140.00 520.00

3,615.15 506.12 4,121.27 4,121.00 Amount

Page 66 6 1 1/4

Cu.ft Day

1 1/4

Day

200 Sand 214 Mason Allow for water 5% of labour 257 Labourer Over heads Per 10 L.ft Per L.ft Say per L.ft. Per L.m Say per L.m

26/38

No 28/38

2100.00 475.00 325.00

126.00 593.75 20.31 406.25

2,887.56 404.26 3,291.82 329.18 329.00 1,079.12 1,079.00

Drains, brick in cement 1:5 6"-9" average depth and 9" wide, cement rendered 1/2" 1:2 complete with expansion (apron paid for seperately).

1/4 100 4 0.68 1

Day Nos Cu.ft Cwts Day

1

Day

Qty

257 41 200 46 214 414 257

Unit Code

Per 10.0 L.ft. Labourer(for excavation) Bricks(For Building drain) Sand Cement Mason Allow for water Labourer Over heads Per 10 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m.

Description Steps, 12" wide and 6" to 9" high masonary or brick work in cement mortar 1:3 rendered 1/2" cement 1:2 with foundation 6" below ground.

325.00 5.70 2100.00 520.00 475.00 325.00

Unit Rate

81.25 570.00 84.00 353.60 475.00 16.25 325.00

Rate

Per 10.0 L.ft. 120 0.6 4

No Cwt Cu.ft

41 Bricks 46 Cement 200 Sand

5.70 520.00 2100.00

Analysis 1st half - Mullaitivu

684.00 312.00 84.00

1,905.10 266.71 2,171.81 217.18 217.00 711.76 712.00

Amount

Page 67 1/2

Day

1/2

Day

30/39

214 Mason Allow for water 5% of labour 257 Labourer Over heads Per 10 L.ft Per L.ft Say per L.ft Per L.m. Say per L.m.

325.00

237.50 8.13 162.50

1,488.13 208.34 1,696.46 169.65 170.00 557.60 558.00

Brick work in cement sand 1:8 in foundation and up to D.P.C. Per Cube. 41 Bricks Add 10% for breakage 2 1/3 Cwt 46 Cement 0.375 Cube 197 Sand 3 Day 214 Mason 4 Day 257 Labourer 410 Allow for water Over heads Per cube Say per cube Per m3 Say per m3 1450

No

31/40

5.70 520.00 2100.00 475.00 325.00 125.00

8,265.00 826.50 1,213.33 787.50 1,425.00 1,300.00 125.00

13,942.33 1,951.93 15,894.26 15,894.00 5,616.25 5,616.00

Brick work in cement sand 1:8 in superstructure in ground floor.

1450 2 1/3 3/8 3 5

No 32/40

475.00

Qty

1 1/2

Per Cube. 41 Bricks Add 10% for breakage Cwt 46 Cement Cube 197 Sand Day 214 Mason Day 257 Labourer 410 Allow for water Allow for scaffolding 5% of labour Over heads Per cube Say per cube Per m3 Say per m3 No

Unit

Day

5.70 520.00 2100.00 475.00 325.00 125.00 81.25

Description Brick work in cement and sand 1:8 in 1st floor. Per Cube. As per Item 31 Per cube 257 Labourer Allow for extra scaffolding and water 5% of labour

Over heads Per cube

Analysis 1st half - Mullaitivu

8,265.00 826.50 1,213.33 787.50 1,425.00 1,625.00 125.00 81.25

Rate

14,348.58 2,008.80 16,357.39 16,357.00 5,779.86 5,780.00

Amount

14,348.58 14,348.58 325.00 487.50 24.38

24.38

14,860.46 2,080.46 16,940.92

Page 68 Say per cube Per m3 Say per m3

33/40

16,941.00 5,986.22 5,986.00

Brick work in cement and sand 1:8 in 2nd floor.

4 1/2

Day

Per Cube. As per Item No. 31 257 Labourer Allow for extra scaffolding 5% of labour Over heads Per cube Say per cube Per m3 Say per m3

14,348.58 14,348.58 325.00 1,462.50 73.13 73.13

15,884.21 2,223.79 18,108.00 18,108.00 6,398.59 6,399.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU MASON. No

Qty

1/41

Unit

Description

Rate

Random Rubble Masonary in cement Mortar 1:5 above 1 cube. Per Cube. 1

Cube 139 Rubble

5715.00

Analysis 1st half - Mullaitivu

5,715.00

Amount

Page 69 0.45 7.25 3 6

Cube 197 Sand Cwts 46 Cement Day 214 Mason 412 Allow for water Day 257 Labourer Over heads Per cube Say per cube Per m3 Say per m3

2/41

2100.00 520.00 475.00 75.00 325.00

945.00 3,770.00 1,425.00 75.00 1,950.00

13,880.00 1,943.20 15,823.20 15,823.00 5,591.17 5,591.00

Randam rubble masonary in cement mortar 1:5 up to 1 cube. Per Cube. As in item 1 Add 25% on labour. Over heads Per Cube Say per cube Per m3 Say per m3

13,880.00 13,880.00 487.50

14,367.50 2,011.45 16,378.95 16,379.00 5,787.63 5,788.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU PAVIOR. No

Qty

Unit

1/43

Description

Rate

Exapansion joints in brick floors, filled with bitumen and sand. Per 20.0 L.ft. 1

Hour

214 Mason

475.00

Analysis 1st half - Mullaitivu

59.38

Amount

Page 70 1

Hour

257 Labourer Allow for sand and bitumen 50% of labour Over heads Per 20 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m.

2/43

2 2 1/4 1/4

Hour 214 Hour 257 Cu.ft 200 Gallon 32

0.25 0.18 5 1 1/4 3 1/2

Cube 136 Cube 197 Cwts 46 Day 214 412 Day 257

Qty

Unit Code

5/44

No 12/46

400 2 1/2 0.11 1

no

236a

Cwts 46 Cube 200 Day 215

Exapansion joints in concrete floors filled with bitumen and sand (to full depth of concrete and rendering). Per 20.0 L.ft. Mason Labourer Sand Bitumen Over heads Per 20 L.ft Per L.ft Say per L.ft. Per L.m. Say Per L.m. Floors ,cement concrete 1:21/2:5 (1") 3" thick cement rendered 1/2", 1:2, with expansion joints filled with cement and sand. Per Sqrs. 1" Metal Sand Cement Mason Allow for water Labourer Over heads Per square Say per Sqrs Per m2 Say per m2

Description Tiles glazed(colour)6"x6", with all specials, supplied and fixed to walls including raking plaster and bedding in cement mortar 1:2. Per 100 Sq.ft. Tiles 6"x6" colour Add 25% for specials wastage in cutting etc. Cement Sand Special mason

Analysis 1st half - Mullaitivu

325.00

40.63 20.31

475.00 325.00 2100.00 347.00

118.75 81.25 5.25 86.75

8470.00 2100.00 520.00 475.00 75.00 325.00

2,117.50 378.00 2,600.00 593.75 75.00 1,137.50

Unit Rate

15.00 520.00 2100.00 475.00

Rate

6,000.00 1,500.00 1,300.00 231.00 475.00

120.31 16.84 137.16 6.86 7.00 22.96 23.00

292.00 40.88 332.88 16.64 17.00 55.76 56.00

6,901.75 966.25 7,868.00 7,868.00 846.93 847.00

Amount

Page 71 2 2

Day Day

214 Mason 257 Labourer 415 Allow for white cement for painting Over heads Per 100 S.ft Per S.ft Say per Sq.ft per m2: Say per m2:

12d/46

240 1 1/4 7 1 2 3

Nos Cwts Cu.ft Day Day Day

189 46 200 215 214 257 415 414

475.00 325.00 100.00

Tiles 8"x8", pressed of approved pattern and colour, supplied and fixed. Per 100.0 S.ft. floor tiles (8"x8") (including wastage) 32.00 Cement 520.00 Sand 2100.00 Special mason 475.00 Mason 475.00 Labourer 325.00 Allow for coloured cement 100.00 Allow for clearing 25.00 Over heads Per 100 S.ft Per S.ft Say per S.ft. Say per m2

950.00 650.00 100.00

7,680.00 650.00 147.00 475.00 950.00 975.00 100.00 25.00

11,206.00 1,568.84 12,774.84 127.75 128.00 1,377.83 1,378.00

11,002.00 1,540.28 12,542.28 125.42 125.00 1,350.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU PLASTERER. No

Qty

Unit

4/139

Description

Unit Rate

Rate

Cracks in wall, plastered in cement 1:3 after chipping 2" to 4" wide Per 10 L.ft 0.5

hour

214 Mason

475.00

Analysis 1st half - Mullaitivu

29.69

Amount

Page 72 1 0.04

hour cwt

257 Labourer 46 Cement Allow for sand Overheads Per 10 L.ft Per 1 L.ft Say per L.ft Per L.m Say per L.m

9/141

325.00 520.00

40.63 20.80 10.16

101.27 14.18 115.45 11.54 12.00 39.36 39.00

Flashing or plaster bands laid over tiles 4" to 6" wide on roof in cement and lime mortar 1:1:4 Per 20 Lft 1 Cft 200 Sand 0.16 Cwt 46 Cement 1/6 Bushel 126 Lime 1.5 Hrs 214 Mason 3 Hrs 257 Labourer Overheads Per 20 Lft Per Lft Per Lm Say Per Lm

14/142

2100.00 520.00 257.00 475.00 325.00

21.00 83.20 42.83 89.06 121.88

520.00 2100.00 475.00 325.00

780.00 105.00 356.25 487.50

357.97 50.12 408.09 20.00 65.60 66.00

Rendering cement 1/2", 1:2 above 1 Square. Per Sqrs.

No 15/142

1.5 5 3/4 1 1/2

Cwts Cu.ft Day Day

46 200 214 257

Qty

Unit Code

Cement Sand Mason Labourer Over heads Per square Say per sqrs. Per m2 Say per m2

Description Rendering cement 1/2", 1:2 upto 1 square

Unit Rate

Rate

1,728.75 242.03 1,970.78 1,971.00 212.16 212.00

Amount

Per Square As in Item 14 Add 25% on labour Overheads Per square Say per square Per m2

Analysis 1st half - Mullaitivu

1,728.75 121.88

1,850.63 259.09 2,109.71 2,110.00 227.13

Page 73 Say per m2 16/143

227.00

Rendering cement 1/2", 1:3 above 1 Square. Per Sqrs. 1.07 5 3/4 1 1/2

Cwts Cu.ft Day Day

46 200 214 257

17/143

Cement Sand Mason Labourer Over heads Per square Say per sqrs. Per m2 Say per m2

520.00 2100.00 475.00 325.00

556.40 105.00 356.25 487.50

1,505.15 210.72 1,715.87 1,716.00 184.71 185.00

Rendering cement 1/2", 1:3 upto 1 Square Per Square As in Item 16 Add 25% on labour Overheads Per square Say per square Per m2 Say per m2

18/143

1,505.15 121.88

1,627.03 227.78 1,854.81 1,855.00 199.66 200.00

Rendering, cement 3/4", 1:2 above 1 Square. Per Sqrs.

No 19/143

2.25 7 1/4 1 2

Cwts Cu.ft Day Day

46 200 214 257

Qty

Unit Code

Cement Sand Mason Labourer Over heads Per Square Say per sqrs Per m2 Say per m2

520.00 2100.00 475.00 325.00

Description Unit Rate Rendering, cement 3/4", 1:2 upto 1 square

1,170.00 152.25 475.00 650.00

Rate

2,447.25 342.62 2,789.87 2,790.00 300.32 300.00

Amount

Per square As in Item 18 Add 25% on labour Overheads Per sqr Say per sqr Per m2

Analysis 1st half - Mullaitivu

2,447.25 162.50

2,609.75 365.37 2,975.12 2,975.00 320.24

Page 74 Say per m2 20/144

320.00

Rendering, cement 3/4", 1:3 above 1 Square. Per Sqrs. 1.75 7 1/4 1 2

Cwts Cu.ft Day Day

46 200 214 257

21/144

Cement Sand Mason Labourer Over heads Per square Say per Sqrs. Per m2 Say per m2

520.00 2100.00 475.00 325.00

910.00 152.25 475.00 650.00

2,187.25 306.22 2,493.47 2,493.00 268.35 268.00

Rendering, cement 3/4", 1:3 upto 1 square Per Sqrs As in Item 20 Add 25% on labour Overheads Per sqr Say per sqr Per m2 Say per m2

22/144

2,187.25 162.50

2,349.75 328.97 2,678.72 2,679.00 288.34 288.00

Rendering, cement, floating coat, using Red cement finished smooth. Per Sqrs.

No 25/145

0.14 1 1 1

cwt Kg Hour Hour

46 192 214 257

Qty

Unit Code

Grey cement Red cement Mason Labourer Over heads Per Square Say per sqrs. Per m2 Say per m2

520.00 342.00 475.00 325.00

Description Unit Rate Rendering cement 3/4", 1:2 with Pudlo 5lbs to 100 lbs cement

72.80 342.00 59.38 40.63

Rate

514.80 72.07 586.87 587.00 63.19 63.00

Amount

Per sqr

12

lbs

As in Item 18 191 Pudlo Overheads Per sqr Say per sqr

32

Analysis 1st half - Mullaitivu

2,447.25 384.00

2,831.25 396.38 3,227.63 3,228.00

Page 75 Per m2 Say per m2 26/145

347.43 347.00

Skirting in cement mortar 1:3, 1/2"x4" projected or flush with wall, and including forming groove.with red cement floating Per 10.0 L.ft. 0.22 0.07 2 2

Cu.ft Cwts Hour Hour

200 46 214 257

27/145

Sand Cement Mason Labourer add red cement floating as 22/144( x 0.042) Over heads Per 10 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m.

2100.00 520.00 475.00 325.00

4.62 36.40 118.75 81.25 21.62

262.64 36.77 299.41 29.94 30.00 98.40 98.00

Skirting in cement mortar 1:3, 1/2"x6" projected or flush with all finished with Red cement floating, including forming groove. Per 10.0 L.ft.

No 28/146

As in Item 26 x 3/2 192 Red cement 214 Mason Over heads Per 10 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m.

0.06 1/2

Kg hrs

Qty

Unit Code

Description 3/8" thick plastering to RCC beams, slab soffit in cement sand 1:3 .with limeputty

Per sqr 0.8 Cwt 46 Cement 0.05 Cube 200 Sand 0.40 Bushel 126 Lime 2.0 Day 214 Mason 2.0 Day 257 Labourer Allow for Scaffolding

Analysis 1st half - Mullaitivu

393.96 342 475

Unit Rate

520 2100 257 475 325

393.96 20.52 29.69

Rate

416.00 105.00 102.80 950.00 650.00 32.50

444.17 62.18 506.35 50.64 51.00 167.28 167.00

Amount

Page 76 414 Allow for water Overheads Per sqr Say per sqr Per m2 Say m2 29/146

25.00

520 2100 475 347 325 75

1,170.00 231.00 593.75 347.00 812.50 75.00

520 2100 475 325

416.00 105.00 831.25 650.00 32.50 25.00

2,281.30 319.38 2,600.68 2,601.00 279.98 280.00

D.P.C. 3/4" thick in cement, sand 1:2 finished smooth with 2 coats of hot tar.

2.25 11 1 1/4 1 2 1/2

Cwts Cu.ft Day Gal Day

46 200 214 32 257 412

29a/146

0.8 0.05 1.75 2

Cwt 46 Cube 200 Day 214 Day 257 414

No 29b/146

25

Qty

Unit Code

0.90 5.0 0.75 1.50

Cwt C.ft Day Day

46 200 214 257

Per Sqrs. Cement Sand Mason bitumen Labourer Allow for fire wood and water Over heads Per square Say per sqrs. Per m2 Say per m2

3/8" thick cement and sand plastering to column and beam and soffit Per sqr Cement Sand Mason Labourer Allow for scaffolding Allow for water Overheads Per sqr Say per sqr per m2 Say per m2 Description 1/2" thick cement plastering 1:4 mix Per Sqr Cement Sand Mason Labourer Overheads Per sqr Say per sqr per m2

25

Unit Rate

520 2100 475 325

Analysis 1st half - Mullaitivu

Rate

468.00 105.00 356.25 487.50

3,229.25 452.10 3,681.35 3,681.00 396.23 396.00

2,059.75 288.37 2,348.12 2,348.00 252.76 253.00 Amount

1,416.75 198.35 1,615.10 1,615.00 173.85

Page 77 Say per m2 29c/146

174.00

5/8" thick cement plastering 1:4 mix Per Sqr 0.93 0.07 0.75 1.50

Cwt 46 Cement Cube 200 Sand Day 214 Mason Day 257 Labourer Overheads Per sqr Say per sqr Per m2 Say per m2

29d/146

520 2100 475 325

483.60 147.00 356.25 487.50

520 475 325 2100

20.80 29.69 40.63 21.00

520 2100 475 325

556.40 105.00 356.25 487.50 514.80

1,474.35 206.41 1,680.76 1,681.00 180.92 181.00

Cracks in wall Plastered in cement 1:3 after chipping 2" to 4" wide

0.04 0.5 1.0 1.0

Cwt Hrs Hrs Cft

46 214 257 200

29e/146

Per 10 Lft Cement Mason Labourer Allow for sand Overheads Per 10 Lft Per Lft Say per Lft Per Lm Say per Lm

112.11 15.70 127.81 12.78 13.00 41.92 42.00

Plinth plastering 1/2" thick 1:3 cement and sand with red cement floating per Sqr 1.07 5 0.75 1.5

Cwt C.ft Day Day

46 200 214 257

Cement Sand Mason Labourer Red cement floating as item 22 Overheads Per sqr Say Rs Per m2 Say Rs

2,019.95 282.79 2,302.74 2,303.00 247.87 248.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU ROOFER. No 5/49

Qty

Unit

Description Corrugated asbestos sheet roofing on special upper cl. Timber / kempus purlines supplied and fixed complete including treating timber with wood preservative two coats (ridging measured seperately). Per 3.60 Sqrs.

Analysis 1st half - Mullaitivu

Unit Rate

Rate

Amount

Page 78 420 S.ft 13 1/4 Cu.ft 72 Nos 1 1/4 Day 1 1/4 Day 3 2 2 1/2 3/4

Hour Days Days Gal Day

15 246 198 214 257 415 257 214 257 268a 257

7/50

No 18/53

420 72 6 2 2 0.5 0.75

Sq.ft 15 Nos. 198 Hour 257 Days 214 Days 257 gal 268a Days 257

Qty

Unit

9 No 194 2 Cu.ft 200 1/3 Bushel 126 1/3 Cwt. 46 1/4 Day 214 1/4 Day 257

Asbestos sheet Timber in purlins Roofing screws and washers Carpenter(Fixing Purlins) Labourer Allow for spikes for purlins Labourer(2) (hosting sheet) Carpenter (fixing sheet) Labourer Wood preservative Labourer Over heads Per 3.6 Sqrs. Per Sqrs. Say per sqrs. Per m2 Say per m2 Corrugated asbestos sheet fixed to roof or wall on existing frame work with necessary coach screws and limpet washers, or hook bolts.& with 2 coats wood Preservative to existing frame work Per 3.60 Sqrs. Asbestoes sheets. Drive screws 4 1/2"&washers Labourers. Carpenter Labourers. Wood preservative Labourers. Overheads Per 3.6 Sqrs. Per Sqrs. Say per sqrs. Per m2 Say per m2

Description Ridging, calicut pattern bedded in Cement and lime mortar 1:1:4, Coloured to match tiles. Per 12.0 L.ft. Ridge tiles Sand Lime Cement Mason Labourer Allow for colouring powder

Analysis 1st half - Mullaitivu

29 12,180.00 1250 16,562.50 6 432.00 475 593.75 325 406.25 100 100.00 325 243.75 475 950.00 325 650.00 315 157.50 325 243.75

29 12,180.00 6 432.00 325 243.75 475 950.00 325 650.00 315 157.50 325 243.75

Unit Rate

35 2100 257 520 475 325 10

Rate

315.00 42.00 85.67 173.33 118.75 81.25 10.00

32,519.50 4,552.73 37,072.23 10,297.84 10,298.00 1,108.50 1,109.00

14,857.00 2,079.98 16,936.98 4,704.72 4,705.00 506.46 506.00

Amount

826.00

Page 79 Over Heads Per 12 L.ft. Per L.ft Say per L.ft. Per L.m. Say per L.m 19/53

Ridging, Calicut Pattern bedded in cement and lime mortar 1:1:4 coloured to match tiles (tiles available at site) Per 12.0 L.ft. As in item 18 Less tiles Over heads Per 12 L.ft. Per L.ft. Say per L.ft. Per L.m. Say per L.m.

21/54

826.00

826.00 315.00

511.00 71.54 582.54 48.55 49.00 160.72 161.00

Ridging with asbestos cement close fitting ridges fixed complete with roofing screws or hook bolts. Per 13'-4" L.FT Asbestos ridging Roofing screws 4 1/2" Carpenter Labourers Over heads Per 13' 4" L.ft Per L..ft. Say per L.ft Per L.m. Say per L.m. Tiles, calicut pattern, flat supplied and laid up to 5 tiles in single storey building Per 3 tiles.

4 16 2 2

pairs Nos Hour Hour

14 198 214 257

3 1/2

Nos Hour

70 Tiles. 257 Labourer Over heads Per 3 tiles Per tiles Say per tiles

Qty

Unit

26/55

No 27/56

115.64 941.64 78.47 78.00 255.84 256.00

Description Tiles, calicut pattern flat supplied and laid (above 5 and up to 25) in single storey Building.

363 6 475 325

1,452.00 96.00 118.75 81.25

18 325

54.00 20.31

Unit Rate

Rate

1,748.00 244.72 1,992.72 149.49 149.00 488.72 489.00

74.31 10.40 84.72 28.24 28.00 Amount

Per 15.0 tiles. 15 1

Nos Hour

70 Tiles. 257 Labourer Over Heads Per 15 tiles Per tiles

18 325

Analysis 1st half - Mullaitivu

270.00 40.63

310.63 43.49 354.11 23.61

Page 80 Say per tile 30/56

24.00

Tiles calicut pattern supplied and laid in any Building. Per Sqrs. 125 1/4

Nos. Day

31/56

1/4

Day

43/59

1

Day

44/59

320 3/8

Nos. Day

70 Tiles. 257 Labourers (02) Over heads Per Square Say per sqrs. Say per m2 Tiles, calicut pattern, laid in any Buildings(tiles available at site). Per Sqrs. 257 Labourer (02) Overheads Per Sqrs. Say per sqrs. Per m2 Say per m2 Shifting and re-laying calicut pattern tiles. Per Sqrs. 257 Labourer Over heads Per Sqrs. Say per Sqrs. Per m2 Say per m2 Supplying and laying half round tiles on the existing asbestos roof. Per Sqrs. 91 Half round tiles. 257 Labourers (02) Overheads Per Sqrs. Say per sqrs. Per m2 Say per m2

18 325

2,250.00 162.50

325

162.50

162.50 22.75 185.25 185.00 19.91 20.00

325

325.00

325.00 45.50 370.50 370.00 39.83 40.00

6.5 325

2,080.00 243.75

2,412.50 337.75 2,750.25 2,750.00 296.00

2,323.75 325.33 2,649.08 2,649.00 285.15 285.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU CARPENTER AND JOINER. No 8/63

Qty

Unit

Description

Unit Rate

Boards, Barge, Valance, Fascia, 3/4" to 1" thick in class.I Local timber fixed complete with necessary Brass screws new or renewed above 1 C.ft.( 9" width) with 1 coat primer & 2 coat of enamel painting

Analysis 1st half - Mullaitivu

Rate

Amount

Page 81

82.5 4 2 1/2 1 1/2

Per 100.0 L.ft. Sq.ft 35 3/4" planks Doz 207b Brass screws 2" Scaffolding Day 214 Carpenter Day 257 Labourer sqrs painting as per item 25/168 Overheads Per 100 L.ft. Per L.ft. Say Rs. Per Lm Say Rs.

12/64

1/2 1/2 1/2 4 1.5

day 214 day 214 day 257 Doz 207b sqrs

3/61A

No 14/65

Boardes, Barge, Valance, Facia, available fixed including cutting and minor repairs.with 2 coats enamel painting per 100 l.ft (9"x1") Carpenter Carpenter Labourer Screws, 2" brass painting as per item 24/168 Over heads Per 75 Sq.ft or 100 l.ft Per Sq.ft. Say Rs. Per m2 Say per m2

50 69.00 475 325 1,854.25

4,125.00 276.00 8.13 950.00 162.50 2,781.38

475 475 325 69 1,241.28

237.50 237.50 162.50 276.00 1,861.91

3.25 52.5 475 325

341.25 210.00 237.50 162.50

8,303.00 1,162.42 9,465.42 94.65 95.00 310.47 310.00

2,775.41 388.56 3,163.97 42.19 42.00 451.92 452.00

Beadings, Class I local timber 1 1/2" to 2"x1/2" plain chamfered, fixed with brass screws

105 4 0.5 0.5

L.ft Doz Day Day

Qty

Unit

354 40a 214 257

Per 100 L.ft Fillets Screws 1 1/2" brass Carpenter Labourer Overheads Per 100 L.ft Per L.ft Say per L.ft Per Lm Say per Lm

Description Unit Rate Ceiling asbestos, flat fixed with clout headed nails to 4"x2" joists at 4'crs & 2"x 2" bearers at 2' crs of spl.upper class. Timber /kempus including 1 1/2" x 1/2" cover fillets and 2 1/2" x 1/2" coves of Halmills timber. Rate to include 2 coats tarnap to joists and bearers primer and '2 coats of enamel painting to beadings 'and mouldingd 2 coats of white washing to ceiling. Making holes in wall and fixing joists and

Analysis 1st half - Mullaitivu

Rate

951.25 133.18 1,084.43 10.84 11.00 35.57 36.00 Amount

Page 82

4.2 3.8 1 1 1/2 1 1/2

Cu.ft Cu.ft Lb. Day Day

246 245 150 214 257

2 2

Hour Hour

214 257 413

1/3 1/2

Gallon 268a Day 257

210 1/4 1 1 1/2

Sq.ft Lb. Day Day

13 153 214 257

125 6 3/4 3/4

L.ft Doz Day Day

25 40a 214 257

60 1/4 1/4

L.ft 147a Day 214 Day 257

0.25 bushel 216 1 Day 214 1 Day 257 1/4 Gall. 65 1 3/4 Day 214 413

No 14a/65

Qty

Unit

bearers 'Per 1.95 Sqrs (15'-0"x13'-0"). Timber.(4"x2") Timber.(2"x2") 2" nails Carpenter Labourer Fixing joists in wall and making good holes Mason Labourer Allow for cement and sand. Treating Timber with tarnap. Wood preservative. Labourer Cutting and nailing sheets. Asbestos sheets G.I. nails 3/4" Carpenter Labourer Fixing beading Beading Screws 1 1/2" Brass Carpenter Labourer Fixing cove mouldings Mouldings. Carpenter Labourer to assist White Washing Lime Painter Labourer Paint(Primer under coat and oil paint) Painter Allow for scaffolding Allow for brushes. Over heads Per 1.95 Sqrs Per Sqrs Say Rs. Say m2

1250.00 1250.00 34.00 475.00 325.00

5,250.00 4,750.00 34.00 712.50 487.50

475.00 325.00 50.00

118.75 81.25 50.00

315.00 325.00

105.00 162.50

18.00 34.00 475.00 325.00

3,780.00 8.50 475.00 487.50

4.00 52.50 475.00 325.00

500.00 315.00 356.25 243.75

4.50 475.00 325.00

270.00 118.75 81.25

270.00 475.00 325.00 1785.00 475.00 93.44 50.00

67.50 475.00 325.00 446.25 831.25 93.44 50.00

Description Unit Rate Ceiling asbestos, flat in eves fixed with clout headed nails to 2" x 2"& 2"x1" spacer bearers not exceading 2'-0 centrs both ways bearers of spl.upper class/ kempus timber including Aluminium beading 1" wide with Rubber fillets fixed not exceedaing 2'-0" crs bothways Rate to include 2 coats tarnap to timber and 2 coats emulsion paint to abestos sheet 65'-0"x3'-0" = 195 sq.ft

Analysis 1st half - Mullaitivu

Rate

20,675.94 2,894.63 23,570.57 12,087.47 12,087.00 1,299.68

Amount

Page 83

6.50 72 1 2 2

Cu.ft L.ft Lb. Day Day

245 193 150 214 257

2 2

Hour Hour

214 257 413

1/3 1/2

Gallon 268a Day 257

210 1/4 1 1 1/2

Sq.ft Lb. Day Day

13 153 214 257

300 6 300 2 2

L.ft Doz L.ft Day Day

397 40a 408 214 257

0.67 Gallon 64 2 Day 214

No 14b/65

Qty

Unit

Per 1.95 Sqrs Timber.2"x2" 2"x1"reppers 2" nails Carpenter Labourer Fixing joists in wall and making good holes Mason Labourer Allow for cement and sand. Treating Timber with tarnap. Wood preservative. Labourer Cutting and nailing sheets. Asbestos sheets G.I. nails 3/4" Carpenter Labourer Fixing Aluminium rubber beading Beading Aluminium Screws 3/4" Rubber Beading Carpenter Labourer Emulsion Painting Emulsion Paint Painter Allow for scaffolding Allow for brushes. Over heads Per 1.95 Sqrs Per Sqrs Say Rs. Per m2 Say m2

1250.00 8.00 34.00 475.00 325.00

8,125.00 576.00 34.00 950.00 650.00

475.00 325.00 50.00

118.75 81.25 50.00

315.00 325.00

105.00 162.50

18.00 34.00 475.00 325.00

3,780.00 8.50 475.00 487.50

12.80 52.50 3.00 475.00 325.00

3,840.00 315.00 900.00 950.00 650.00

1415.00 475.00 101.56 50.00

948.05 950.00 101.56 50.00

Description Unit Rate Ceiling asbestos, flat fixed with clout headed nails to 4"x2" joists 4'-0 crs & 2"x2" bearers of spl.upper class/kempus timber 2'-0" crs and 2"x1" spacer bearers not exceding 2'-0crs including Aluminium beading 1" wide with rubber fillets not exceeding 2'-0 crs fixed bothways Rate to include 2 coats tarnap to timber and 2 coats emulsion paint to abestos sheet

Analysis 1st half - Mullaitivu

Rate

24,308.11 3,403.14 27,711.25 14,210.90 14,211.00 1,529.71 1,530.00

Amount

Page 84

4.2 3.8 1 60.0 2 2

Cu.ft Cu.ft Lb. L.ft Day Day

246 245 150 193 214 257

2 2

Hour Hour

214 257 413

1/3 1/2

Gallon 268a Day 257

210 1/4 1 1 1/2

Sq.ft Lb. Day Day

13 153 214 257

260 6 260 2 2

L.ft Doz L.ft Day Day

397 40a 408 214 257

0.67 2

gal Day

64 214 415

No 14c/65

Qty

Unit

6 1/2

Cu.ft

1/4

Day

Per 1.95 Sqrs Timber. 4"x2" Timber. 2"x2" 2" nails reepes Carpenter Labourer Fixing joists in wall and making good holes Mason Labourer Allow for cement and sand. Treating Timber with tarnap. Wood preservative. Labourer Cutting and nailing sheets. Asbestos sheets G.I. nails 3/4" Carpenter Labourer Fixing Aluminium beading Beading Aluminium Screws 3/4" Rubber Beading Carpenter Labourer Emulsion Painting Emulsion Paint Painter Allow for scaffolding Allow for brushes. Over heads Per 1.95 Sqrs Per Sqrs Say Rs. Say m2

Description As per Item No.14 with only 2"x2"beares in eaves ceiling. -do- -do65'-0"x3'-0" = 195 sq.ft Per 1.95 Sqrs. As per Item No.14 Less for Timber 245 Timber 2"x2" Less for Timber work 214 Carpenter

Analysis 1st half - Mullaitivu

1250.00 1250.00 34.00 8.00 475.00 325.00

5,250.00 4,750.00 34.00 480.00 950.00 650.00

475.00 325.00 50.00

118.75 81.25 50.00

315.00 325.00

105.00 162.50

18.00 34.00 475.00 325.00

3,780.00 8.50 475.00 487.50

12.80 52.50 3.00 475.00 325.00

3,328.00 315.00 780.00 950.00 650.00

1415 475.00 101.56 100.00

948.05 950.00 101.56 100.00

Unit Rate

Rate

20,675.94 10,000.00 10,675.94 1250 8,125.00 475

118.75

25,505.11 3,570.72 29,075.83 14,910.68 14,911.00 1,603.00

Amount

18,800.94

Page 85 1/4

Day

257 Labour

325

81.25

475 270 1785 50 325 475 16.25 50

59.38 67.50 223.13 50.00 325.00 950.00 16.25 50.00

325

81.25

Over heads Rate per Sqrs Per 1.95 Sqrs. Per Sqre Say Per Sqr say per M2 14d/65

1/8 Day 214 0.25 Bushel 216 1/8 Gall. 65 413 1 Day 257 2 day 214 413

14e/65

No 26/68A

White washing to ceiling 2 coats and 2 coats of oil paint to beading and moulding. Per 1.95 Sqrs Painter preparing surfaces Lime Oil paint Allow for sand paper Labourer Painter Allow for scafolding Allow for brush Over Heads Per 1.95 Sqrs Per Sqrs Say Rs. Per M2

Ceiling, upper side cleaned and debris cleared away. 257 Labourer Over heads Per Square Say Rs. Per m2

1/4

Day

Qty

Unit

55 20 1 1/2 3/4 1 1/2

L.ft 147a nos 184 Hour 214 Day 257 Doz 207b

Description Cove mouldings Cl.I 2 1/2"x1 1/2" fixed with brass screws and plugs new or renewed. Per 50 L.ft Cove mouldings Wood plugs Mason Labourer Screws 2" Over heads

Analysis 1st half - Mullaitivu

Unit Rate

4.5 2 475 325 69

Rate

247.50 40.00 89.06 243.75 103.50

200.00 18,600.94 2,604.13 21,205.07 21,205.00 10,874.36 10,874.00 1,171.00

1,741.25 243.78 1,985.03 1,017.96 1,018.00 109.46

81.25 11.38 92.63 92.00 10.00

Amount

723.81 101.33

Page 86 Per 50 L.ft Per L.ft Say Rs Say per L.m

28/69

No 30/70

825.15 16.50 16.00 54.00

Doors or Windows, ledged, braced and battened with grooved and tongured joint,3 3/4" x 2 3/4" frames in spl.upper class timber/kempus & 3/4" to 7/8" thick sashes in class1 timber with brass fittings. Per 2-6x6-6 = 16.25 Sft 1.5 21 3 2 4

Cu.ft S.ft Doz Nos Nos

3 1.25

Day Day

3 2 2 0.5

no no doz doz

Qty

246 182 40a 220 199 414 214 257 119 23 40a 40d 414

Unit

Timber for frames spl. Upper class 1" Planks (Ginnisappu) Brass screw 1 1/2" Spur. Stones Rawl plugs and 2" screws Allow for Dowels Carpenter Labourer Fittings T- hinges 10" 6" Barrel bolt 1 1/2" screws 1" screws Allow sand paper 14% Over heads Per 16.25 Sq.ft Per Sq.ft Say per S.ft Per m2 Say per m2

1250 50 52.5 22.5 15 25 475 325

1,875.00 1,050.00 157.50 45.00 60.00 25.00 1,425.00 406.25

58 120 52.5 45 25

174.00 240.00 105.00 22.50 25.00

Description - do - do Sash only, in class 1 timber fixed with brass furniture.

Unit Rate

Rate

Per 14.4 Sft 21 3 1/2 2 1/4

Sq.ft Doz Doz Day

182 40a 40d 214

1" Planks(Ginnisappu) Screws 1 1/2" Screws 1" Carpenter

Analysis 1st half - Mullaitivu

50 52.5 45 475

1,050.00 157.50 22.50 1,068.75

5,610.25 785.44 6,395.69 393.58 394.00 4,234.30 4,234.00

Amount

Page 87 1

Day

3 2 2 0.5

Nos Nos Doz Doz

257 414 119 23 40a 40d

32/70

1.5 Cu.ft 246 8 S.ft 181 13 1/4 S.ft 182b 2 Doz 207a 1/2 Doz 40d 414 2.5 Day 214 1.25 Day 257 2 Nos 220 4 Nos 199 1.5 pair 22 1 Nos 196 0.75 Day 214 0.375 Day 257 414

No 32a/70

Qty

8 13.25 2 0.5 2.5

Unit

Labourer Allow for sand paper etc T-hinges-10" 6" Barrel bolt 11/2" screws 1" screws Over heads Per 14.4 S.ft Per S.ft Say Rs Say per m2

Doors or Windows, framed and battened, sash 1" to 1 1/8" thick in Special upper Class timber/kempus fixed complete with brass furniture. Per 16.25 sq.ft Timber 1 1/4" Planks 3/4" Planks 1 1/4" brass screws 1" Screws Allow dowels Carpenter Labourer Spur stone Rawl plugs 4"Brass hinges 6" rim lock Carpenter (frame) Labourer Allow for sand paper etc. Over heads Per 16.25 S.ft Per S.ft Say Rs Say per m2

325 25 58 120 52.5 45

325.00 25.00 174.00 240.00 105.00 22.50

1250 135 105 45 45 25 475 325 22.5 15 79 446 475 325 25

1,875.00 1,080.00 1,391.25 90.00 22.50 25.00 1,187.50 406.25 45.00 60.00 118.50 446.00 356.25 121.88 25.00

Description Unit Rate Battened sash only 1" to 11/8" thick in sp. upper class timber/kempus fixed completed with brass fittings

Per 14.4 sq.ft sq.ft 181 11/4" planks sq.ft 182b 3/4" planks Doz 207a 11/4" brass screw Doz 40d 1" brass screw Day 214 Carpenters

Analysis 1st half - Mullaitivu

135 105 45 45 475

Rate

1,080.00 1,391.25 90.00 22.50 1,187.50

3,190.25 446.64 3,636.89 252.56 252.00 2,717.00

7,250.13 1,015.02 8,265.14 508.62 509.00 5,472.00

Amount

Page 88 1.25 1.5 1

Day Pair No

257 22 196 414

42/74

Labourers 4" brass hinges 6" Rim Lock Allow for sand paper Over head Per 14.4 sq.ft per 1sq.ft say per sq.ft per m2 Say per m2

325 79 446 25

406.25 118.50 446.00 25.00

1250 135 105 19 3.25 50 22.5 15 50 475 325 475 325

2,125.00 2,430.00 735.00 266.00 146.25 500.00 45.00 60.00 50.00 356.25 121.88 2,850.00 568.75

136 136 120 525 52.5 45 25

408.00 136.00 120.00 525.00 210.00 90.00 25.00

Doors or windows,glazed & or pannelled with 3 3/4"x2 3/4" frames & 1 1/8" to 1 1/4"sashes in special upper class local timber/kempus fixed

1.7 18 7 14 45 10 2 4

C.ft S.ft S.ft L.ft L.ft S.ft Nos Nos

3/4 3/8 6 1.75

Day Day Day Day

3 1 1 1 4 2

pairs Nos Nos Nos Doz Doz

246 181 182b 205 354 81 220 199 413 214 257 214 257 94 117 23 142 40a 40d 414

Per 28 S.ft (4'-0"x7'-0") Timber in frames 1 1/4"-1 1/2" Planks 3/4" Planks 1 1/2"x1 1/2" Sash bars Fillets Glass panes Spur. Stones Rawl plugs and screws Allow for Dowels Carpenter (frame) Labourer Carpenter (sash) Labourer Fittings 4"x3" brass hinges 10" Skilton bolt 6" barrel bolt concord 11/2" Brass screws 1" Brass screws Allow for sand paper Over heads Per 28 S.ft Per S.ft Say Rs Say per m2

No 44/75

4,767.00 667.38 5,434.38 377.39 377.00 4,060.69 4,061.00

Qty

Unit

Description Unit Rate Doors or Windows, glazed or pannelled sash only 1 1/8" to 1 1/4" thick in Special upper class timber/kempus with brass furniture. Per 24.7 Sq.ft (3'-7 1/2"x6'-9 3/4") Timber and glass panes as in Item 42 Labourer as in Item 42 Fitting as in item 42 Over heads Per 24.7 Sq.ft

Analysis 1st half - Mullaitivu

Rate

4,077.25 3,418.75 1,514.00

10,254.13

1,514.00 11,768.13 1,647.54 13,415.66 479.13 479.00 5,155.00

Amount

9,010.00 1,261.40 10,271.40

Page 89 Per Sq.ft Say Rs Say per m2

44a/75

1.65 11 6 7 1/2

No 52/78

2 3/4 3/4 3.187

Cu.ft 246 S.ft 181 S.ft 182b S.ft 409 415 Nos 220 day 214 day 257 day 214

1.500 1.000 2.000 0.500

pair Nos Doz Doz

1

day

Qty

Unit

1.65 14 11 2 4

C.ft S.ft S.ft No No

95 142 40A 40D 414 257

246 181 182b 220 199 415

415.85 416.00 4,474.00

Doors pannelled and terllised/B.R.C. weld mesh No. 32 with 3 3/4"x2 3/4" frames and 1 1/8" thick sashes in special upper class timber/kempus, fixed complete with brass furniture. Per 21 S.ft Timber in frame 1250 1 1/4" Planks 135 3/4" Planks 105 Weldmesh 10 Allow for Dowels 100 Spur stones 22.5 Carpenter 475 Labour 325 Carpenter 475 FITTING 4" Brass hinges 205 Mortice lock 525 1 1/2" Brass screws 52.5 1" Brass screws 45 Allow for sand paper 25 Labour 325 Over heads Per 21 S.ft Per S.ft Say Rs Say per m2

Description Unit Rate Doors pannelled with 3 3/4"x2 3/4" frames and 1 - 1 1/8"sashes in Special upper Class timber fixed/kempus.with brass fittings Per 21.0sq.ft Timber 1250 1 1/8" Planks 135 3/4" Planks 105 Spur Stones 22.5 Rawl plugs and screws 15 Allow for Dowels 100

Analysis 1st half - Mullaitivu

2,062.50 1,485.00 630.00 75.00 100.00 45.00 356.25 243.75 1,513.83 307.50 525.00 105.00 22.50 25.00 325.00

Rate

2,062.50 1,890.00 1,155.00 45.00 60.00 100.00

7,821.33 1,094.99 8,916.31 424.59 425.00 4,568.00

Amount

Page 90 3/4 3/8 4 1 1/4

Day Day Day Day

214 257 214 257

1 1/2 1 2 0.5

pair No Doz Doz

94 142 40a 40d 414

53/78

475 325 475 325

356.25 121.88 1,900.00 406.25

136 525 52.5 45 25

204.00 525.00 105.00 22.50 25.00

475 325

89.06 60.94

475

59.38

1250 475

562.50 237.50

8,978.38 1,256.97 10,235.35 487.40 487.00 5,244.00

Door or Window, removing easing and re-fixing. 1 1/2 1 1/2

Hour Hour

214 Carpenter 257 Labourer Over heads Per sash Say Rs

54/78

150.00 21.00 171.00 171.00

Door or Window, easing only. 1

Hour

214 Carpenter Over heads Per sash Say Rs

55/79

No 100/92

Carpenter Labourer Carpenter Labourer fitting 4"x3" Brass hinges Mortice lock concord 1 1/2" Brass screws 1" - Do Allow for sand paper Over heads Per 21 S.ft Per S.ft Say Rs Say per m2

59.38 8.31 67.69 67.00

Door or Window frames renewed in short lengths with special upper Class timber/kempus. Assume 3'-0" Length of frame renewed 0.45 1/2

Cu.ft Day

Qty

Unit

55 1 1 1/8

L.ft Hour Hour Lbs

246 Timber 4" x 3" 214 Carpenter Over heads Per 3 l.ft Per l.ft Say Rs Say per L.m

193 214 257 150

Description Unit Rate Reepers 2"x1" in Class I timber/kempus supplied and fixed new or renewed with iron nails, up to 100 L.ft (shiffting of tiles paid for seperately). Per 50 l.ft Reepers 8 Carpenter 475 Labourer 325 Nails 2" 34 Over heads

Analysis 1st half - Mullaitivu

Rate

440.00 59.38 40.63 4.25

800.00 112.00 912.00 304.00 304.00 997.12 Amount

544.25 76.20

Page 91 Per 50 L.ft Per L.ft Say Rs Say per L.m 101/92

100 1 1/2 1 1/2 1/4

107/94

L.ft Hour Hour Lbs

193 214 257 150

- do over 100 L.ft. Per 100 L.ft Reepers Carpenter Labourer Nails 2" Over heads Per 100 L.ft Per L.ft Say Rs Say per L.m

620.45 12.41 12.00 41.00 - do -

8 475 325 34

800.00 89.06 60.94 8.50

958.50 134.19 1,092.69 10.93 11.00 36.00

Roof with calicut pattern tiles on spl upper class/Kempus frame work complete with ridges, hips etc. Per 6 sqrs 34 660 750 52 8 2 2 1/2 3 8 10 4 3 3 1 1/2 1 1/2

No 107a/94

Qty

27 660 750 35 7 2 2 1/4 1

Cu.ft 246 Timber L.ft 193 Reepers sp . Upper class No 70 Tiles No 194 Ridge tiles Lbs 267a 6" wire nails Lbs 267a 2" wire nails Gal 268a Wood preservative Cwt 46 Cement Cu.ft 200 Sand 413 Allow for colouring powder etc Day 214 Carpenter Day 257 Labourer Day 257 Labourer Day 257 Labourer Day 214 Mason Day 257 Labourer Over heads Per 6 Sqrs Per square Say per sqr Per m2 Say per m2 Unit Description gable end roof - do - do - do -. Cu.ft 246 Timber L.ft 193 2"x1" Reeper sp .upper class Nos 70 Tile Nos 194 Ridge tiles Lbs 267a 6" Wire nails Lbs 150 2" Nails Gal 268a Wood preservative Cwt 46 Cement

Analysis 1st half - Mullaitivu

1250 42,500.00 8 5,280.00 18 13,500.00 35 1,820.00 36.5 292.00 36.5 73.00 315 787.50 520 1,560.00 2100 168.00 50 50.00 475 4,750.00 325 1,300.00 325 975.00 325 975.00 475 712.50 325 487.50

Unit Rate

Rate

1250 33,750.00 8 5,280.00 18 13,500.00 35 1,225.00 36.5 255.50 34 68.00 315 708.75 520 520.00

75,230.50 10,532.27 85,762.77 14,293.80 14,294.00 1,538.62 1,539.00 Amount

Page 92 0.06

9 3 3/4 2 3/4 3 1 1

Cube 197 Sand 413 Allow for colouring powder etcs Labour frame work Day 214 Carpenter Day 257 Labourer Treating work Day 257 Labourer Laying Day 257 Labourer Ridging Day 214 Mason Day 257 Labourer Over heads Per 6 Sqrs Per sqrs Say Rs Say per m2

117/97

3 1

Hour Hour

121/98 5/6

No

Cu.ft

Qty

Unit

2 310 20 1

Cu.ft L.ft L.ft Lb

4

Day

Timber available, sorted out, cut to required sizes and fixed in roof and other carpentry work. Per 5/6 Cu.ft 214 Carpenter 257 Labourer 415 Allow for nails, spikes etc Over heads Per 5/6 Cu.ft Per Cu.ft Say Rs Say per m3 Timber special upper Class fixed or renewed in roof and other carpentry work. 246 Timber Labourer as in Item 117 Over heads Per 5/6 Cu.ft Per Cu.ft Say Rs Say per m3

135/101

246 205 26 150 414 214

Description Trellis partition with 1/2"x1/2" laths fixed 2" apart diagonally or horizontally and vertically on 4"x2" Milla timber framing. Per 24 S.ft (6'-0"x4'-0") 4"x2" Timber 1/2"x1/2" Laths 2"x1/2" Beading 1" Nails Allow for 2" nails Carpenter

Analysis 1st half - Mullaitivu

2100 50

126.00 50.00

475 325

4,275.00 1,218.75

325

893.75

325

975.00

475 325

475.00 325.00

475 325 100

178.13 40.63 100.00

1250 318.75

1,041.67 318.75

Unit Rate

1250 19 4 34 25 475

Rate

2,500.00 5,890.00 80.00 34.00 25.00 1,900.00

63,645.75 8,910.41 72,556.16 12,092.69 12,093.00 1,302.00

318.75 44.63 363.38 436.05 436.00 15,387.00

1,360.42 190.46 1,550.88 1,861.05 1,861.00 65,672.00

Amount

Page 93 1/2

Day

257 Labourer 414 Allow for 4 plugs fixed to walls Over heads Per 24 S.ft Per S.ft Say Rs Say per m2

325 25

162.50 25.00

10,616.50 1,486.31 12,102.81 504.28 504.00 5,425.00

Door frame 4"x3" in spl upper class timber/kempus supplied and fixed in position

138/102

per'16.25 Sft 1.7 1 1 1/2 1/8

Cu.ft Day Day day Day

2 4

Nos Nos

246 214 257 214 214 412 220 98

118/97

No 140/103

Timber Carpenter Labourer Mason Labourer Allow for cement sand Spur stones Rawl plug Over heads Per 16.25 S.ft Per s.ft Say per sft Per m2 Say per m2

1250 475 325 475 475 75 22.5 17.5

2,125.00 475.00 325.00 237.50 59.38 75.00 45.00 70.00

1,250.00 475.00 325

625.00 237.50 81.25

3,411.88 477.66 3,889.54 239.36 239.00 2,575.09 2,575.00

Timber fixed or renewed in post and frames special upper class/kempus Per 1/2 Cu.ft 0.5 0.5 0.25

c.ft Day Day

Qty

Unit

1.6 2 4

Cu.ft Nos Nos

1

Day

246 Timber 214 Carpenter 257 Labourer Overheads per 1/2 c.ft per c.ft Say per c.ft Per m3 Say per m3

246 220 98 414 214

Description Unit Rate Door 1 1/4" thick plywood ordinary sash single (ordinary finish) hung on 4"x3" frame in Special upper class timber/kempus and complete with brass furnishers & lock Per 22.75 sq.ft (3'-3"x7'-0") Timber 1250 Spur stone 22.5 Rawl plugs 17.5 Allow for dowels 25 Carpenter 475

Analysis 1st half - Mullaitivu

Rate

2,000.00 45.00 70.00 25.00 475.00

943.75 132.13 1,075.88 2,151.75 2,152.00 75,929.99 75,930.00

Amount

Page 94 1 1/8 1/8

Day Day Day

1 1/2 Pairs 1 Nos 1 Nos 1 Nos 1 Doz 2 Doz 1 Doz

No 140a/103

1 0.5 0.5

No Day Day

Qty

Unit

1.6 2 4

Cu.ft No No

1 1 0.13

Day Day Day

257 Labourer 214 Mason 257 Labourer fittings 94 4"x3" Brass hinges 117 10" skelton bolt 23 6" Barrel bolt 142 Mortice lock 40a 11/2" Brass screw 40d 1" - Do 40c 3/4" -Do 413 Allow for cement Door sash plywood (ordinary finish) 188 plywood door ( 6'-9" x 2'-9") 214 Carpenter 257 Labourer Over heads Per 22.75 Sq.ft Per s.ft Say per s.ft per m2 Say per m2

246 220 98 414 214 257 214

Description As per Item No 140 but with marine type 2'-8"x 7'-0" Per 18.62sq.ft Timber Spur Stone Rawl plug Allow for Dowels Carpenter Labour Mason

Analysis 1st half - Mullaitivu

325 475 325

325.00 59.38 40.63

136 136 120 525 52.5 45 31.5 50

204.00 136.00 120.00 525.00 52.50 90.00 31.50 50.00

1765 475 325

1,765.00 237.50 162.50

Unit Rate

1,250.00 22.50 17.50 25.00 475.00 325.00 475.00

Rate

2,000.00 45.00 70.00 25.00 475.00 325.00 61.75

6,414.00 897.96 7,311.96 321.40 321.00 3,457.80 3,458.00

Amount

Page 95 0.13

Day

1 0.5 0.5 1.5 2 2 1 2 1

no Day Day pair Nos Nos Doz Doz Doz

142/104

1 1/2 Pairs 1 Nos 1 Nos 1 Nos 1 Doz 2 Doz 1 Doz

No 143/104

1 0.5 0.5

No Day Day

Qty

Unit

1 0.5 0.5 1.5 2

Nos Day Day pair Nos

257 Labour 325.00 Marine Door Sash 187 Ply wood Door 1,848.00 214 Carpenter 475.00 257 Labour 325.00 94 4" x 3" Brass hinges 136.00 23 6" barrel bolt 120.00 60 Draw rings 25.00 40a 11/2" Brass screw 52.50 40d 1" - do 45.00 40c 3/4" -do31.50 Over head Per18.62 Sq.ft Per Sq.ft Say Rs Say per m2 per m2 Supplying and fixing Plywood door 1 1/4" thick single (Ordinary finish) to the existing frame with brass fittings 2' 9" x 6' 9" = 18.56 S.ft 94 4"x3" Brass hinges 136.00 117 10" skelton bolt 136.00 23 6" Barrel bolt 120.00 142 Mortice lock 525.00 40a 11/2" Brass screw 52.50 40d 1" - Do 45.00 40c 3/4" -Do 31.50 413 Allow for cement 50 Door sash plywood (ordinary finish) 188 plywood door ( 6'-9" x 2'-9") 1765 214 Carpenter 475 257 Labourer 325 Over heads Per 18.56 S.ft Per S.ft Say Per S.ft Per m2 Say Per m2

Description Unit Rate -do- -do- plywood Marine type 1 1/4" thick single hung to existing frame with fitting

187 214 257 94 23

2' 3" x 6' 9" = 15.18S.ft Marine Door Sash Ply wood Door Carpenter Labour 4" x 3" Brass hinges 6" barrel bolt

Analysis 1st half - Mullaitivu

1848 475 325 136 120

42.25 1,848.00 237.50 162.50 204.00 240.00 50.00 52.50 90.00 31.50

5,960.00 834.40 6,794.40 364.90 365.00 3,927.40 3,927.00

204.00 136.00 120.00 525.00 52.50 90.00 31.50 50.00 1,765.00 237.50 162.50

Rate

1,848.00 237.50 162.50 204.00 240.00

3,374.00 472.36 3,846.36 207.24 207.00 2,229.56 2,230.00

Amount

Page 96 2 1 2 1

Nos Doz Doz Doz

60 40a 40d 40c

Draw rings 11/2" Brass screw 1" - do 3/4" -doOverheads Per 15.18 S.ft Per S.ft Say per S.ft Per m2 Say per m2

25 52.5 45 31.5

50.00 52.50 90.00 31.50

2,916.00 408.24 3,324.24 218.99 219.00 2,355.96 2,356.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU PAINTER & DECORATOR. No

Qty

Unit

1

Hour

13/165

Description Lettering 1" to 1 1/2" painted in sinhalese English or Tamil, including painting ground. Per 6 letters 206 Signboard painter

Analysis 1st half - Mullaitivu

Unit Rate

375

Rate

46.88

Amount

Page 97 416 Allow for painting background 2 coats 414 Allow for brushes paint etc Over heads Per 6 letters Per letter Say Rs 14/165

1

Hour

15/166

1

Hour

23/168

0.17 5

No

gal Hour

Lettering 2" to 3" - do - do - do -. Per 5 letters 206 Signboard painter 414 Allow for brushes, paint 416 Allow for painting backround 2 coats Over heads Per 5 letters Per letter Say Rs Lettering 4" to 5" - do - do - do -. Per 4 letters 206 Signboard painter 413 Allow for brushes, paint etc 416 Allow for painting backround 2 coats Over heads Per 4 letters Per letter Say Rs Painting, enamel paint including washing cleaning and smoothing down with sand paper, 1 coat. Per square 171 Oil paint 214 Painter cleaning down and painting 413 Allow for brushes sand paper washing soda Over heads Per square Say Rs Per m2 Say per m2

Qty

Unit Code

0.17 4

gal Hour

24/168

Description Painting enamel paint - do - do 2 coats. Per square 1st coat as in Item 23 171 Paint ( 2 nd coat ) 214 Painter 413 Allow for brushes etc Over heads Per square Say per Sqr

Analysis 1st half - Mullaitivu

150 25

150.00 25.00

375 25 150

46.88 25.00 150.00

375 50 150

46.88 50.00 150.00

1785 475 50

303.45 296.88 50.00

Unit Rate

650.33 1785 475 50

Rate

650.33 303.45 237.50 50.00

221.88 31.06 252.94 42.16 42.00

221.88 31.06 252.94 50.59 50.00

246.88 34.56 281.44 70.36 70.00

650.33 91.05 741.37 741.00 79.80 80.00

Amount

1,241.28 173.78 1,415.05 1,415.00

Page 98 Per m2 Say per m2 25/168

0.17 0.33 2

gal gal Day

190 65 214 413

25a/168

0.33 1.25

gal Day

27/169

0.17 5

No

gal Hour

65 214 413

Painting New wood 1 Coat primer & 2 Coats Enamel paint Per sqrs Primer Enamel paint Painter Allow Sand paper & brushes Over heads Per square Say per Sqr Per m2 Say per m2 Painting new wood work and 2 coats of enamel paint. Per square Gloss paint(enamel) Painter Allow for sand paper brushes etc Over heads Per square Say per sqr Per m2 Per m2

Painting Steel work, 1 coat, with Anticrosive paint including removing scale and wire brushing. Per square 12b Anticrosive paint 214 Painter pareparing surface and painting 413 Allow for brushes Over heads Per square Say per sqr per m2 Say per m2

Qty

Unit Code

0.17 4

gal Hour

28/169

152.32 152.00

Description Painting Steel work, 2 coats, with Red oxide including removing scale and wire brushing. Per square 1st coat as in Item 27 12b Paint 214 Painter 414 Allow for brushes etc Over heads Per square Say per sqr

Analysis 1st half - Mullaitivu

1560 1785 475 50

265.20 589.05 950.00 50.00

1785 475 50

589.05 593.75 50.00

1139 475 50

193.63 296.88 50.00

Unit Rate

540.51 1139 475 25

Rate

540.51 193.63 237.50 25.00

1,854.25 259.60 2,113.85 2,114.00 227.56 228.00

1,232.80 172.59 1,405.39 1,405.00 151.28 151.00

540.51 75.67 616.18 616.00 66.33 66.00

Amount

996.64 139.53 1,136.16 1,136.00

Page 99 Per m2 Say per m2

30/169

Painting walls with emulsion paint 1 coat (new coat). 0.17 3

gal Hour

30a/169

0.17 3

gal Hour

31/170

0.14 2 1/2

No 31a/170

122.30 122.00

gal Hour

64 Emulsion paint 214 Painter 413 Allow for brushes Over heads Per square Say per sqr per m2 Say per m2 Painting walls with weather shield 1 coat ( New work ) Per square 63 weather shield paint 214 Painter 413 Allow for brushes etc Overheads Per Sqr Say Per Sqr Per m2 Say Per m2 Painting walls with Emulsion paint, 2 coats (new work). Per square 1st coat as in Item 30 64 Emulsion paint 214 Painter 414 Allow for brushes etc Over heads Per square Say per sqr Per m2 Say per m2

Qty

Unit Code

0.14 2.5

gal Hrs

1415 475 50

240.55 178.13 50.00

1790 475 50

304.30 178.13 50.00

468.68 1415 475 25

468.68 198.10 148.44 25.00

Description Unit Rate Painting walls with 2 coats of weather shield paint ( New work ) Per square 1 st coat as in Iten 30a 63 2 nd coat w.s. paint 1790 214 Painter 475 413 Allow for brushes 50 Over heads Per square Say per sqr Per m2

Analysis 1st half - Mullaitivu

Rate

532.43 250.60 148.44 50.00

468.68 65.61 534.29 534.00 57.51 58.00

532.43 74.54 606.96 607.00 65.34 65.00

840.21 117.63 957.84 957.00 103.10 103.00

Amount

981.46 137.40 1,118.87 1,118.00 120.44

Page 100

32/170

1/2

Hour

32a/170

0.5

Hrs

33/170

33a/170

0.5

No 40/172

Hrs

Qty

Unit

0.25 2

gal Hour

Say per m2 Painting walls with Emulsion paint, 1 coat including preparing surface of old work. Per square As I Item 30 214 Painter 413 Allow for wire brushes sand paper etc Over heads Per square Say per sqr Per m2 Say per m2 Painting walls with weather shield paint 1 coat ( Old work ) Per square As I Item 30a 214 Painter for preparing surface 413 Allow for wire brushes Over heads Per square Say per sqr Per m2 Say per m2 - do - do 2 coats - do - do -. Per square As in Item 31 Preparing surface as in Item 32 Over heads Per square Say per sqr Per m2 Say per m2 Painting walls with weather shield paint 2 coat ( Old work ) Per square As in Item 31a 214 Painter for preparing surface 413 Allow for wire brushes Over heads Per square Say per sqr Per m2 Say per m2 Code Description Tarnap or other wood preservative, applied to wood work 1 coat (old work). Per square 268a Wood preservative 214 Painter 414 Allow for brushes etc Over heads Per square Say per sqr Per m2 Say per m2

Analysis 1st half - Mullaitivu

120.00

468.68 475 50

468.68 29.69 50.00

532.43 475 50

532.43 29.69 50.00

840.21 79.69

840.21 79.69

475 50

981.46 29.69 50.00

Unit Rate

315 475 25

Rate

78.75 118.75 25.00

548.36 76.77 625.13 625.00 67.29 67.00

612.11 85.70 697.81 698.00 75.11 75.00

919.90 128.79 1,048.69 1,049.00 112.88 113.00

1,061.15 148.56 1,209.71 1,210.00 130.22 130.00 Amount

222.50 31.15 253.65 253.00 27.30 27.00

Page 101

41/172 0.45 4

Tarnap or other wood preservative, applied to wood work 2 coats (new work). Per square gal 268a Wood preservative Hour 214 Painter 414 Allow for brushes Over heads Per square Say per sqr Per m2 Say per m2

141.75 237.50 25.00

325 475 50 1756

121.88 237.50 50.00 351.20

760.58 1756 475 25

760.58 298.52 237.50 25.00

404.25 56.60 460.85 460.00 49.61 50.00

Varnishing with best copal varnish after washing down and sand papering 1 coat. Per sqrs

44/173

3 4

Hour Hour

0.2

gal

45/173

0.17 4

No 49/174

315 475 25

Qty

gal Hour

257 214 413 260

Labourer Painter Allow for sandpaper, brushes etc Varnish Over heads Per square Say per sqr Per m2 Say per m2

- do - do Per square 1st coat as in Item 44 260 Varnish 214 Painter 414 Add for brushes etc Over heads Per square Say per sqr Per m2 Say per m2

Unit Code

1 Day 214 1 Day 257 3/4 Bushel 216 1/4 Lb 85 414 1/4 Lb 269

760.58 106.48 867.06 867.00 93.33 93.00

- do 2 coats.

Description White or colourwashing walls of single storey buildings 1 coat, including patching and preparing surface. Per 10 sqrs Painter Labourer Boiled lime Glue Allow for brushes Yellow Ochre Over heads

Analysis 1st half - Mullaitivu

Unit Rate

475 325 270 86 25 0

Rate

475.00 325.00 202.50 21.50 25.00 0.00

1,321.60 185.02 1,506.62 1,507.00 162.18 162.00

Amount

1,049.00 146.86

Page 102 Per 10 sqrs Per square Say per sqr Per m2 Say per m2

50/174 1 3/4 Day 214 1 3/4 Day 257 1 1/4 Bushel 216 1/2 Lb 85 413 1/2 Lb 269

1,195.86 119.59 120.00 12.87 12.90

- do 2 coats Per 10 squares Painter Labourer Lime Glue Allow for brushes etc Yellow Ochre Over heads Per 10 squares Per square Say Rs Per m2 Say per m2

- do - do -. 475 325 270 86 50 0

831.25 568.75 337.50 43.00 50.00 0.00

1,830.50 256.27 2,086.77 208.68 208.00 22.46 22.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU BRASS FOUNDER. No

Qty

Unit Code

1 1/2 1/3

Per No no 22 4" Brass barrel bolt Doz 207a 1" screws brass hr 214 Carpenter

4/127

Description Bolts barrel 4", brass oxidised heavy quality supplied and fixed with brass screws.

Analysis 1st half - Mullaitivu

Unit Rate

79 45 475

Rate

79.00 22.50 19.79

Amount

121.29

Page 103 Over heads Per No Say Rs 6/128

1

120.00 42.29

1 1/3 3/4

Casement fastner with mortice plate, brass oxidised heavy quality supplied and fixed with brass screws. Per No no 45 Casement fastner 90.00 Doz 207a 1" Screws 45 hr 214 Carpenter 475 Over heads Per No Say Rs

90.00 15.00 44.53

1 1/3 1/2

Casement stays 10", brass oxidised heavy quality supplied and fixed. Per No No 44 10" Casement stay Doz 207a 1" Screws hr 214 Carpenter Over heads Per No Say Rs

90 45 475

90.00 15.00 29.69

1 1/3 3/4

Fanlight Catches brass oxidised heavy quality with brass screws fixed complete. Per No No 66 Fanlight Catch Doz 40d 1" Screws hr 214 Carpenter Over heads Per No Say Rs

30 45 475

30.00 15.00 44.53

Qty

Unit Code

19/130

21/131

No 27/132

- do 6" - do - do - do Per No 23 6" Brass barrel bolt. Screws and labour as in Item 4 Over heads Per No Say Rs

120 42.29

18/130

1 1 3/4 3/4

no

16.98 138.27 138.00

Description Unit Rate But hinges 4"x3" brass oxidised heavy quality supplied and fixed with brass screws complete. Per No Pair 94 Hinges per pair 136 Doz 40a 1 1/2" screws 52.5 hr 214 Carpenter 475 hr 257 Labour 325 Over heads Per No Say Rs

Analysis 1st half - Mullaitivu

Rate

136.00 52.50 44.53 30.47

162.29 22.72 185.01 185.00

149.53 20.93 170.47 170.00

134.69 18.86 153.54 154.00

89.53 12.53 102.07 102.00

Amount

263.50 36.89 300.39 300.00

Page 104 29/132

1

Pair

29a/132

1

Pair

- do 4"x4" - do - do - do Per No 95 4" x 4" hinges per pair Screws and labour as in Item 27 Over heads Per No Say Rs - do 4"x2 1/2" - do - do Per No 95a 4"x2 1/2" hinges per pair Screws and labour as in Item 27 Over heads Per No Say Rs

31/133

31a/133

1 1/4 1/4

52/137

205.00 127.50

115.5 127.50

115.50 127.50

45 45 475 325

90.00 33.75 59.38 40.63

26.25 31.5 475

26.25 7.88 14.84

332.50 46.55 379.05 379.00

- do -

243.00 34.02 277.02 277.00

Hinges centre pivot (consisting of 2 pieces) brass oxidised heavy quality supplied and fixed with brass screws complete. 2 3/4 1 1

No 51/137

205 127.50

Set Doz hr hr

47 40d 214 257

3" Centre pivots, set of 4 pieces 1" Screws Carpenter Labourer Over heads Per set of 4 Nos Per set of 2 Nos

Rings, brass 1 3/4" to 1 1/2" supplied and fixed to doors and windows with brass screws. Per No no 198a Ring 1 1/2" Doz 40c Brass Screws 3/4" hr 214 Carpenter Over heads Per No Say Rs

Qty

Unit Code

Description Lock Mortice Vinion single supplied and fixed. Per No 142 Mortice Lock (single) 214 Carpenter Over heads Per No Say Rs

1 1/2

No Day

Lock Mortice Vinion double, supplied and fixed.

Analysis 1st half - Mullaitivu

Unit Rate

525 475

Rate

525.00 237.50

223.75 31.33 255.08 128.00

48.97 6.86 55.82 56.00

Amount

762.50 106.75 869.25 869.00

Page 105

1 1

No Day

790 475

790.00 475.00

No Day

Mortice Lock Union ( English) single supplied and fixed. Per No 145 Mortice Lock Union (single) 214 Carpenter Over heads Per No Say Rs

1575 475

1,575.00 237.50

No Day

Mortice Lock Union ( English) double supplied and fixed. Per No 146 Mortice Lock Union (double) 214 Carpenter Over heads Per No Say Rs

2795 475

2,795.00 475.00

53/137

1 1/2

54/157

1 1

53a/137

1 0.5

No Day

1

Cwt.

1 1 1

day day lbs

Qty

Unit

1

Cwt.

3/4 3/4 1

day day lbs

63/123

No 64/123

Per No 143 Mortice Lock (double) 214 Carpenter Over heads Per No Say Rs

Lock Night Latch supplied and fixed with duplicate keys approved quality Per No 144 Lock Night Latch 290 214 Carpenter 475 Overheads Per No Say per no Tor steel rods in reinforcing. Per cwt. 249 Tor steel rods 4330 Allow for 10% Wastage 433 215 Smith 475 257 Labour 325 31 14 B.W.G. Wire 40 Over heads Per cwt. Say per Cwt per kg Say per kg Code Description Unit Rate Tor steel rods reinforcement in foundation Per cwt. 249 Tor steel rods 4330 Allow for 10% Wastage 433 215 Smith 475 257 Labour 325 31 14 B.W.G. Wire 40 Over heads Per cwt. Say per cwt Per kg

Analysis 1st half - Mullaitivu

290.00 237.50

4,330.00 433.00 475.00 325.00 40.00

Rate

4,330.00 433.00 356.25 243.75 40.00

1,265.00 177.10 1,442.10 1,442.00

1,812.50 253.75 2,066.25 2,066.00

3,270.00 457.80 3,727.80 3,728.00

527.50 73.85 601.35 601.00

5,603.00 784.42 6,387.42 6,387.00 127.75 128.00 Amount

5,403.00 756.42 6,159.42 6,159.00 123.19

Page 106 Say per kg 63a/123 1

Cwt

140

1 1 1

day day lbs

215 257 31

64a/123 1

Cwt

140

3/4 3/4 1

day day lbs

215 257 31

123.00

Mild Steel rods in reinforcing lintols or beams. Per cwt. Mild Steel rods 4240 Allow westage 10% 424.00 Smith 475 Labour 325 14 B.W.G. Wire 40 Over heads Per cwt. Say per cwt Per kg Say per kg Mild Steel rods in Foundation . Per cwt. Mild Steel rods Allow westage 10% Smith Labour 14 B.W.G. Wire Over heads Per cwt. Say per cwt Per kg Say per kg

4240 424 475 325 40

4,240.00 424.00 475.00 325.00 40.00

4,240.00 424.00 356.25 243.75 40.00

5,504.00 770.56 6,274.56 6,275.00 125.50 126.00

5,304.00 742.56 6,046.56 6,047.00 120.93 121.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU IRONMONGER. No

Qty

Unit Code

1 1 1/2 1 1/4 1 1/4

Pair doz hr hr

49/119 119 40a 214 257

Description Hinges T, 10" Iron, heavy quality supplied and fixed with iron screws complete. Per Pair 10" hinges 1 1/2" Screws Carpenter Labourer Over heads

Analysis 1st half - Mullaitivu

Unit Rate

58 52.5 475 325

Rate

58.00 78.75 74.22 50.78

Amount

261.75 36.65

Page 107 Per Pair Say Rs 60/121

No 67/123

298.40 298.00

1 0.5 1 1/2

Locks, rim 6" iron, superior quality, heavy type, s/f. with iron screws complete. Per no no 196 6" Rim lock doz 40d 1" Brass Screws Hour 214 Carpenter Over heads Per no Say Rs

Qty

Unit Code

0.17 1 1 1

cwt hr hr hr

67e/123 0.09

cwt

140 214 257 214 414

446 45 475

Description Unit Rate M.S.Bars 5/8" dia supplied & fixed in window frame at 4" cetres & painted with one coat red lead & 2 coats aluminium Per'4 Rods or 17 l.ft M.S.Rods 4240 Carpenter 475 Labourer 325 Painter 475 Allow for paint 25 Over heads Per 17 L.ft Per L.ft Say Rs Say per L.m

1/2" dia - do 140 M.S.Rods Labour paint etc. as in Item 67 Over heads Per 17 L.ft Per L.ft Say Rs Say per L.m

446.00 22.50 89.06

Rate

720.80 59.38 40.63 59.38 25.00

557.56 78.06 635.62 636.00

Amount

905.18 126.72 1,031.90 60.70 60.00 199.00

- do 4240 184.38

381.60 184.38

565.98 79.24 645.21 37.95 37.00 124.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU TINKER. No 9/150

Qty

Unit Code

23 4

s.ft hrs

Description Flashing G.I.22 B.W.G. 1' 6" wide, fixed with 6" turned up along, and top edge tucked well into wall in cement and lime mortar.

Per 14 L.ft 74 22 B.W.G sheets 215 Tinker cutting & bending to shape and

Analysis 1st half - Mullaitivu

Unit Rate

55 475

Rate

1,265.00 237.50

Amount

Page 108

1 5

hr hrs

214 257 413 413

29/156

No 34/158

fixing in place Mason, caulking Labour, assisting tinker and mason Allow for cement sand etc Allow for lead Overheads Per 14 L.ft PerL.ft Say per Lft Per Lm Say per L.m

475 325 50 50

59.38 203.13 50.00 50.00

75 475 325 50 90 325 325 475 325 520 270 2100 325

5,400.00 237.50 162.50 50.00 30.00 162.50 40.63 118.75 162.50 83.20 45.00 21.00 81.25

1,865.00 261.10 2,126.10 151.86 152.00 498.11 498.00

Gutters, Valley 20 B.W.G 36" wide, renewed on existing board, sheets tarred, joints soldered and cement, lime filletting complete.

72 1/2 1/2

S.ft day day

73 214 257 413 232 257 257 214 257 46 216 200 257

1/3 4 1 2 4 0.16 1/6 1 2

gal hrs hrs hrs hrs Cwts Bus Cu.ft hrs

Qty

Unit Code

72 1 1 1

S.ft Ibs day day

35 267a 214 257

Per 22 L.ft G.I. Sheets Tinker Labourer Allow for nails, soldering materials etc Coaltar Labourer Labourer Mason Labourer Cement Lime Sand Labourer Overheads Per 22 L.ft Per L.ft Say per L.ft Per L.m Say Per L.m

Description Unit Rate -Do- renewed including 1" thick timber boarding sheet tarred, joints soldered and cement lime filletting complete. per 22 l.ft As per Item 29 6,594.83 1" thick boarding 50 Wire nails 1" 36.5 Carpenter 475 Labourer 325 Overheads Per 22 L.ft

Analysis 1st half - Mullaitivu

Rate

6,594.83 3,600.00 36.50 475.00 325.00

6,594.83 923.28 7,518.10 341.73 342.00 1,120.88 1,121.00

Amount

11,031.33 1,544.39 12,575.71

Page 109 Per L.ft Say per L.ft Per L.m Say per L.m

571.62 572.00 1,874.92 1,875.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU PLUMBER. No 1/179

Qty

Unit Code

1 0.5 0.5

No Hrs Hrs

Description Ball valve 1/2" supplied and fixed

355 1/2" Ball valve 214 Plumber 257 Labourer Overheads Per no. Say

Unit Rate

94.5 475 325

Analysis 1st half - Mullaitivu

Rate

94.50 29.69 20.31

Amount

144.50 20.23 164.73 165.00

Page 110

2/179

Ball valve 3/4" supplied and fixed 1

No

356 3/4" Ball valve Labourer as in Item 1 Overheads Per no Say

13/181

152.25 50.00

202.25 28.32 230.57 231.00

Wash Basin, Lavatory, 22"x16" with one tap, water plug, new brackets, supplied & fixed complete. (Additional tap, trap, and outlet pipe paid for seperately). 1

No

4 1 1

No Hrs Hrs

0.75 0.75

Day Day

1 1

Hrs Hrs

263 22"x16" basin complete with brackets, tap etc. and transport fixing plugs in wall 184 Plugs 214 Mason 257 labourer Fixing basin and taps 214 Plumber 257 labourer Making holes in wall and making good 214 Mason 257 labourer 414 Allow for screws, cement, red lead etc. Over heads Per No Say Rs

17/182

1780

1,780.00

2 475 325

8.00 59.38 40.63

475 325

356.25 243.75

475 325 25

59.38 40.63 25.00

475 325 475 325 25

178.13 121.88 59.38 40.63 25.00

2,613.00 365.82 2,978.82 2,979.00

Wash 'Basin, sink or urinal including all fittings removed and walls made good 3 3 1 1

No 31/185

152.25

Hrs Hrs Hrs Hrs

214 257 214 257 414

Plumber ( removing basin, brackets and pipes ) Labourer ( to assist ) Mason ( making godd to walls and floor ) Labourer ( to assist ) Allow for cement, lime etc. Overheads Per no. Say

Qty

Unit Code

Description Unit Rate Closet, pedestal type available at site, fixed with cement concrete after breaking concrete floor and making good and connections to soil and flush pipes

0.25

Cwt

0.75 0.75

Day Day

Cement Allow for metal,sand, red lead hemp etc. Plumber Labourer Overheads

46 413 214 257

Analysis 1st half - Mullaitivu

520 50 475 325

Rate

130.00 50.00 356.25 243.75

425.00 59.50 484.50 485.00

Amount

780.00 109.20

Page 111 Per No Say 32/186

889.20 889.00

Closet, pedestal type, disconnecting and plugging sewer connection and making good all affected walls and floors 1/6

Cwt

0.5 0.5

Day Day

46 413 214 257

34/186

cement Allow for metal, sand etc, Plumber Labourer Overheads Per No Say

520 50 475 325

86.67 50.00 237.50 162.50

4100 367.5 420 62 39.8 105 100 50 475 325

4,100.00 367.50 420.00 62.00 39.80 105.00 100.00 50.00 475.00 325.00

700 50 520 50 475 325

700.00 50.00 173.33 50.00 475.00 325.00

536.67 75.13 611.80 612.00

Closet, pedestal type, with low level glazed earthenware flushing cistern flush pipe, double plastic sheet cover, 1/2" stop cork, trap etc. supplied & fixed completed. 1 1 1 1 1 1

no Item no Item no no

1 1

day day

35/186 1 no 1/3 Cwt 1 day 1 day

50 358 359 360 361 227 415 413 214 257

Low level closet suite Fittings Seat cover ( Double ) Brackets Flush bend 1/2" stop cock Allow for transport Cement, Metal, Sand etc. (Item 31) Plumber Labourer Over heads Per No Say Rs Closet squatting type, with trap supplied & fixed. 222 Squatting pan & trap 413 Allow for transport 46 Cement 413 Allow for metal, sand etc. 214 Plumber 257 Labourer Over heads Per No Say Rs

Qty

Unit Code

Description Closet, squatting type, removed, sewer connections plugged and floor made good.

1/2

Cwt

1/2 1/2

day day

Cement Allow for metal, and sand etc. Plumber Labourer Over heads

36/187

46 415 214 257

Analysis 1st half - Mullaitivu

Unit Rate

520 100 475 325

Rate

260.00 100.00 237.50 162.50

6,044.30 846.20 6,890.50 6,891.00

1,773.33 248.27 2,021.60 2,022.00 Amount

760.00 106.40

Page 112 Per No Say Rs 40/188

Cocks, brass bib 1/2" supplied & fixed (Heavy quality). 1

no

1/3 1/3

hour hour

36 414 214 257

66/193

1/2" brass bib cock Allow for solvant Plumber Labourer Over heads Per No Say Rs

145 25 475 325

145.00 25.00 19.79 13.54

2 475 325 25 475 325

8.00 59.38 40.63 25.00 237.50 172.50

2 475 325 25 1265 475 325 10

8.00 59.38 40.63 25.00 1,265.00 237.50 162.50 10.00

203.33 28.47 231.80 232.00

Flushing Cistern fixed complete low level '(Ceremics). 4 1 1

No hour hour

1/2 1/2

day day

184 214 257 414 214 257

66a/193

No 86/197

866.40 866.00

4 1 1

No hour hour

1 1/2 1/2

no day day

Qty

184 214 257 414 183 214 257 417

Unit Code

1

no

2

hour

Plugs Mason Labourer Allow for cement etc. Plumber Plumber's mate at allow for solvent cement Over heads Per No Say Rs

Flushing cistern, low level, plastic supplied and fixed complete. Plugs Mason Labourer Allow for cement etc. Low level plastic cistern Plumber Plumber's mate Allow for cement etc. Over heads Per No Say Rs

Description Mirror, bath room type, supplied & fixed to wall with Rawl plugs and plastic frames.

141 Mirror with fittings 413 Allow for Rawl plugs and screws 214 Plumber Over heads Per No

Analysis 1st half - Mullaitivu

Unit Rate

520 50 475

Rate

520.00 50.00 118.75

543.00 76.02 619.02 619.00

1,808.00 253.12 2,061.12 2,061.00

Amount

688.75 96.43 785.18

Page 113 Say Rs 147/214

Shower rose, 3" jet supplied & fixed. 1 0.25 0.25

no Hrs Hrs

314 6" Shower rose 214 Plumber 257 Labourer Over heads Per No Say Rs

153/215

500 475 325

500.00 14.84 10.16

2100 50 475 325 25

2,100.00 50.00 237.50 162.50 25.00

275 475 25

275.00 59.38 25.00

173 475 25

173.00 59.38 25.00

525.00 73.50 598.50 599.00

Sink, glazed, earthenware 24"x15"x8" supplied and fixed with waste plug, complete (pedestal paid seperately). 1

no

1/2 1/2

day day

211 413 214 257 414

147a/214

Sink 24"x15"x8" with waste plug & chain Allow for transport Plumber labourer Allow for cement Over heads Per No Say Rs

2,575.00 360.50 2,935.50 2,936.00

Towel rail 2'-0" long 3/4" dia chromium plated. 1 1

no hour

250 Chromium plated towel rail 214 Plumber 414 Allow for rawl plug & screws Over heads Per No Say Rs

171/219

359.38 50.31 409.69 410.00

Soap tray, white porcelain, supplied and fixed to wall with rawl plugs. 1 1

No 173/220

785.00

no hour

218 Soap tray 214 Plumber 414 Allow for rawl plugs and screws Over heads Per No Say Rs

Qty

Unit Code

Description Stop cocks, 1/2" supplied & fixed Plastic L.D. make).

1 1/2 1/2

no hour hour

1/2" Stop cock Plumber Labourer Allow for solvert cement Over heads Per No

227 214 257 413

Analysis 1st half - Mullaitivu

Unit Rate

105 475 325 50

Rate

105.00 29.69 20.31 50.00

257.38 36.03 293.41 293.00

Amount

205.00 28.70 233.70

Page 114 Say Rs 174/220 1

no

175/220 1

no

176/220 1

no

177/220 1

no

178/221 1

No 178a/221

no

234.00

Stop cocks, 3/4" supplied and fixed. Plastic L.D. make). 309 3/4" stop cock Labour etc. as in Item 173 Over heads Per No Say Rs Stop cocks, 1" supplied and fixed. Plastic L.D. make). 310 1" stop cock Labour etc. as in Item 173 Over heads Per No Say Rs Stop cocks, 1 1/4" supplied and fixed. ( Plastic L.D. Model ) 311 1 1/4" stop cock Labour etc. as in Item 173 Over heads Per No Say Rs Stop cocks, 1 1/2" supplied and fixed. Plastic L.D. make). 312 1 1/2" stop cock Labour etc. as in Item 173 Over heads Per No Say Rs Stop cocks, 2" supplied and fixed. Plastic L.D. make). 313 2" stop cock Labour etc. as in Item 173 Over heads Per No Say Rs

Qty

Unit Code

1 5/8 5/8

No Hour Hour

308 214 257 414

Description As per Item No. 178a (Gate valve 2") English make Gate valve 2" Plumber Mate (labour) Allow for cement Over heads Per No Say Rs

Analysis 1st half - Mullaitivu

134.4 100.00

134.40 100.00

145.6 100.00

145.60 100.00

280 100.00

280.00 100.00

306 100.00

306.00 100.00

372 100.00

372.00 100.00

Unit Rate

357 475 325 25

Rate

357.00 296.88 203.13 25.00

234.40 32.82 267.22 267.00

245.60 34.38 279.98 280.00

380.00 53.20 433.20 433.00

406.00 56.84 462.84 463.00

472.00 66.08 538.08 538.00

Amount

882.00 123.48 1,005.48 1,005.00

Page 115

178b/221

Non return valve English 2" dia 1 5/8 5/8

No Hour Hour

Non Return Valve English 2" dia. 214 Plumber 257 Mate (labour) 414 Allow for cement Over heads Per No Say Rs

200/228

1 1

no hour

248 214 414

292/240 100

L.ft

7

2 2

hour hour

214 257 413

293/240

No 294/240

100

L.ft

10

2 2

hour hour

214 257 413

Tooth brush holder, chromium plated supplied and fixed to wall with Rawl plugs. Tooth brush holder Plumber Allow for Rawl plugs & holder Over heads Per No Say Rs Pipes pvc 1/2" supplied & fixed. Per 100 L.ft. 1/2" pipe Add 25% for specials Plumber Labourer Allow for sol. Cement petrol blow lamp etc. Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs Pipes pvc 3/4" supplied & fixed. Per 100 L.ft. 3/4" pipe Add 25% for specials Plumber Labourer Allow for sol. Cement petrol blow lamp etc. Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs

#N/A 475 325 25

#N/A 37.11 25.39 25.00

196 475 25

196.00 59.38 25.00

7 175 475 325 50

700.00 175.00 118.75 81.25 50.00

12

1,200.00 300.00 118.75 81.25 50.00

475 325 50

Qty

Unit Code

Description Pipes pvc 1" supplied & fixed 1000 type.

Unit Rate

100

L.ft

5

19

1 1/2 3/4 3 3

day day hour hour

257 257 214 257 413

1" pipe Add 25% for specials Labourer ( for excavation) Labourer ( for Back Filling) Plumber Labourer Allow for sol. Cement petrol blow lamp etc.

Analysis 1st half - Mullaitivu

325 325 475 325 50

Rate

1,900.00 475.00 487.50 243.75 178.13 121.88 50.00

#N/A #N/A #N/A #N/A

280.38 39.25 319.63 320.00

1,125.00 157.50 1,282.50 12.83 13.00 42.07 42.00

1,750.00 245.00 1,995.00 19.95 20.00 65.44 65.00 Amount

3,456.25

Page 116 Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs 294a/240

pipes pvc 1" supplied & fixed 600 type. 100

L.ft

6

1 1/2 3/4 3 3

day day hour hour

257 257 214 257 413

295/240

No 295a/240

483.88 3,940.13 39.40 39.00 129.24 129.00

1" pipe Add 25% for specials Labourer Labourer Plumber Labourer Allow for sol. Cement petrol blow lamp etc. Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs

11 325 325 475 325 50

1,100.00 275.00 487.50 243.75 178.13 121.88 50.00

2,456.25 343.88 2,800.13 28.00 28.00 91.84 92.00

Pipes pvc 1 1/4" supplied & fixed 1000 type. 100

L.ft

4 4

hour hour

3

1 1/4" pipe Add 25% for specials Labour for Exc. & Refill as Per 294 257 Plumber 214 Labourer 413 Allow for sol. Cement petrol blow lamp etc. Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs

Qty

Unit Code

100

L.ft

4 4

hour hour

28 731.25 325 475 50

Description Unit Rate Pipes pvc 1 1/4" supplied & fixed 600 type.

4

1 1/4" pipe Add 25% for specials Labour for Exc. & Refill as Per 294 214 Plumber 257 Labourer 413 Allow for sol. Cement petrol blow lamp etc. Over heads

Analysis 1st half - Mullaitivu

20 731.25 475 325 50

2,800.00 700.00 731.25 162.50 237.50 50.00

Rate

2,000.00 500.00 731.25 237.50 162.50 50.00

4,681.25 655.38 5,336.63 53.37 53.00 175.04 175.00

Amount

3,681.25 515.38

Page 117 Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs 296/241

4,196.63 41.97 42.00 137.65 138.00

Pipes pvc 1 1/2" supplied & fixed.

100

L.ft

4 4

hour hour

Excavation & Refilling as in Item 294 1 1/2" pipe (1000 type) Add 25% for specials 214 Plumber 257 Labourer 413 Allow for sol. Cement petrol blow lamp etc. Over heads Per 100 L.ft. 1

731.25 42 475 325 50

731.25 4,200.00 1,050.00 237.50 162.50 50.00

Say Rs Per L.ft Say Rs Per L.m 296a/241

pvc pipe 1 1/2" (1000 type) supplied & fixed with out excavation. As per Item 296 Less Excavation 294 Over heads Per 100 L.ft.

6,431.25

6,431.25 731.25

Say Rs Per L.ft Say Rs Per L.m 296b/241

5,700.00 798.00 6,498.00 64.98 65.00 213.13 213.00

pvc pipe 1 1/2" (600 type) supplied & fixed with excavation. 100

No 296c/241

6,431.25 900.38 7,331.63 73.32 73.00 240.48 240.00

Qty

L.ft

2

Unit Code

1 1/2" pvc 600 type 25% Specials Labour & etc as per 294 Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs

Description pvc pipe 1 1/2" (600 type) supplied & fixed with out excavation. As per Item 296b Less Excavation as per 294 Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m

Analysis 1st half - Mullaitivu

27 731.25

Unit Rate

4,106.25

2,700.00 675.00 731.25

Rate

4,106.25 731.25

4,106.25 574.88 4,681.13 46.81 47.00 153.54 154.00

Amount

3,375.00 472.50 3,847.50 38.48 38.00 126.20

Page 118 Say Rs 297/241

100

L.ft

5 5

hour hour

Pipes pvc 2" (1000 type) supplied & fixed. With excavation Excavation & Refilling as in Item 294 8 2" pipe Add 25% for specials 214 Plumber 257 Labourer 414 Allow for sol. Cement petrol blow lamp etc. Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs

297a/241

pvc pipe 2" (1000 type) supplied & fixed with out excavation. As per Item 297 Less Excavation 294 Over heads Per 100 L.ft. Per L.ft Say Rs Per L.m Say Rs

297b/241

731.25 73 475 325 25

731.25 7,300.00 1,825.00 296.88 203.13 25.00

10,381.25 10,381.25 731.25

10,381.25 1,453.38 11,834.63 118.35 118.00 388.18 388.00

9,650.00 1,351.00 11,001.00 110.01 110.00 360.83 361.00

pvc pipe 2" (600 type) supplied & fixed with excavation. 100

No 297c/241

126.00

Qty

L.ft

9

Unit Code

2" pvc (600 type) 25% Specials Labour & etc. As per 294 Over heads Per 100 L.ft. Per No Say Rs Per L.m Say Rs

Description pvc pipe 2" (600 type) supplied & fixed with out excavation. As per Item 297b Less Excavation as per 294 Over heads Per 100 L.ft. Per L.ft Say Rs

Analysis 1st half - Mullaitivu

44

Unit Rate

6,231.25

4,400.00 1,100.00 731.25

Rate

6,231.25 731.25

6,231.25 872.38 7,103.63 71.04 71.00 233.00 233.00

Amount

5,500.00 770.00 6,270.00 62.70 63.00

Page 119 Per L.m Say Rs 310/243

24.5 1 1/2 1 1/2 17 1 1 3

L.ft No No No Nos. No tin doz

2 2

hour hour

161 157 159 158 317 160 318 40c 415 214 257

311/244

2 length 370 1 No 371 2 No 368 2 No 372 4 No 21 4 No 373 0.66 Doz 40c 1 1/2 tin 318 2 2 2 2

No 5/245

Qty

hrs hrs hrs hrs

214 257 214 257

Unit Code

5

cube

0.67 0.10

cube cube

205.66 206.00

Eaves gutters 6" square type pvc fixed with PVC brackets. (1' - 6 " Crs) Per 24.0 L.ft PVC gutter 6" End cap Mitre joint Gutter joiners pvc gutter brackets running head 50 grm solvent cement 3/4" screws Brass Allow for scaffolding Plumber Labour Over heads Per 24 L.ft. Per L.ft Say Lft Per Lm Say Lm Down Pipe 3 1/2" Dia P.V.C Fixed with Wooden Plug to wall etc. Per 24.0 L.ft 3 1/2" Dia PVC Pipe Socket 3 1/2" Dia Bends 3 1/2" Dia Elbow 3 1/2" Dia Wooden Block Clips 3 1/2" Dia 3/4" Brass Screw 50 grs solvent ct. Allow for scaffolding Plumber labours mason labours Over head Per 24.0 L.ft Per L.ft Say Per L.ft Per .L.m Say Per .L.m Description Drains, pvc 400 type 4" laid on cement concrete 6" thick upto 2'-0" depth of invert including excavation and cement concrete haunching (1:3:6 - 1" metal). Per 100 L.ft. Excavation & refilling concrete bed 16"x6" comes from item 2/13 Cement concrete(1:3:6) 1"as per item 2c/16 Concrete (1:2:4) 3/4"

Analysis 1st half - Mullaitivu

38.5 44.8 164 51.5 9.2 107 43 31.5 100 475 325

943.25 44.80 82.00 77.25 156.40 107.00 43.00 94.50 100.00 118.75 81.25

416 47.25 64 64 5 9.5 31.5 43

832.00 47.25 128.00 128.00 20.00 38.00 20.79 64.50 16.25 118.75 81.25 118.75 81.25

475 325 475 325

Unit Rate

545.63

Rate

2,728.13

18,731.00 12,549.77 21,645.00 2,164.50

1,848.20 258.75 2,106.95 87.79 88.00 287.95 288.00

1,694.79 237.27 1,932.06 80.50 81.00 264.05 264.00 Amount

Page 120

1 1/2 1.5

day day

1/2 1/2 100

day day L.ft

Add 50% on Labour as item 5/16 214 Plumber 257 Mate (labour) Allow for solvent cement 214 Plumber 257 Mate (labour) 169 pvc 4" pipe (400 type) including transport Over heads Per 100 L.ft. Per No Say Lft Per Lm Say Lm

311a/244 24

L.ft

168

4 4

Hrs Hrs

214 257 413

13/246

PVC 4" ( 600 type ) pipe supplied and fixed on walls Per 24 L.ft PVC 4" ( 600 type ) pipe 48.5 Add 25% for specials & clips , plugs etc. Plumber 475 Labourer 325 Allow for solvent cement 50 Allow for scaffolding Over heads Per 24 L.ft Per L.ft Say Rs Per L.m Say Rs

1,164.00 291.00 1,900.00 1,300.00 50.00 65.00

31,329.90 4,386.19 35,716.08 357.16 357.00 1,171.49 1,171.00

4,770.00 667.80 5,437.80 226.58 227.00 743.17 743.00

Gulley pvc 6" supplied & fixed including gulley box. 1 1/4 2 2

No 18/247

1,537.50 1,537.50 475 712.50 325 487.50 50 50.00 475 237.50 325 162.50 107 10,700.00

no hour hour hour

90 257 214 257 413

Qty

Unit Code

1/2 250 6

day Nos. C.ft

6" Gulley box Labourer Mason Labourer Allow for cement,metal & sand Over heads Per No Say Rs

Description Manhole 2'x2' and upto 2'-0" deep, 9" thick brick in cement 1:3 walls & cement rendered 1/2" (1:2) with 6" cement conc. foundation 1:3:6 (1" metal) including forming channels but without cover.

257 Labourer digging & transporting surplus 41 Bricks 136 1" Metal

Analysis 1st half - Mullaitivu

290 325 475 325 50

Unit Rate

325 5.7 8470

290.00 10.16 118.75 81.25 50.00

Rate

162.50 1,425.00 508.20

550.16 77.02 627.18 627.00

Amount

Page 121 10 2 1 2

C.ft cwt day day

197 46 214 257

19/247

2100 520 475 325

210.00 1,040.00 475.00 650.00

325 5.7 8470 2100 520 475 325

325.00 2,850.00 847.00 357.00 1,690.00 712.50 975.00

325 5.7 8470 2100 520 475 325

325.00 4,987.50 847.00 546.00 2,340.00 1,187.50 1,625.00

4,470.70 625.90 5,096.60 5,097.00

Manhole 3'6"x2'3" & 2'0" to 4'0" deep - do - do -. 1/2 500 0.10 0.17 3 1/4 1 1/2 3

day Nos. Cube Cube Cwt day day

257 41 136 197 46 214 257

1 875 0.1 0.26 4 1/2 2 1/2 5

day No Cube Cube Cwt day day

257 41 136 197 46 214 257

Qty

Unit Code

Description Manhole cover reinforced concrete 3" thick 2'-0x2'-0" approx. supplied & fixed reinforced with 1/4" dia M.S.rods at 3" centres both ways.

1 1/2 0.20 0.05

C.ft C.ft Cwt cwt

metal ( 3/4") Sand Cement Steel rods

20/248

No 23/248

Sand Cement Mason Labourer Over heads Per No. Say Rs

138 197 46 249

2 Labourers digging & transporting soil Bricks 1" Metal Sand Cement Mason Labourer Over heads Per no Say Rs Manhold 3' 6" x 2' 3" & 4' to 6' deep 9" thick -do -do2 labours digging & transporting soil Bricks 1" Metal Sand Cement Mason Labourer Over heads Per no Say Rs

Unit Rate

8830 2100 520 4330

Analysis 1st half - Mullaitivu

Rate

88.30 10.50 104.00 216.50

7,756.50 1,085.91 8,842.41 8,842.00

11,858.00 1,660.12 13,518.12 13,518.00

Amount

Page 122

1/2 2 2

hour hour hour

413 214 257 214

26/249

50 475 325 475

50.00 29.69 81.25 118.75

60 475

60.00 14.84

367.5 475 325 50

367.50 29.69 20.31 50.00

698.99 97.86 796.85 797.00 797.00 199.25 199.00

Wire dome for 2" pipe supplied and fixed 1 0.25

No Hrs

270 Dome for 2" pipe 214 Plumber Over heads Per no Say Rs

1/D

74.84 10.48 85.32 85.00

110mm PVC inspection joint supplied and fixed 1 0.5 0.5

No Hrs Hrs

2/D 1 0.5 0.5

No Hrs Hrs

3/D 1 0.5 0.5

No 4/D

Allow for binding wire use of moulds etc. Smith Mate (labour) Mason Over heads Per No Say Rs Per 4 sq.ft (per no) Per sq.ft Say Rs

No Hrs Hrs

162 214 257 413

110mm PVC inspection joint Plumber Labourer Allow for solvent cement Over heads Per No Say Rs

110mm PVC inspection "Y" joint supplied and fixed 163 110mm PVC "Y" inspection joint 436 214 Plumber 475 257 Labourer 325 Allow for solvent cement 50 Over heads Per No Say Rs 110mm PVC Bend ( 11 Deg.) supplied and fixed 164 110mm PVC Bend ( 11 Deg.) 115.5 214 Plumber 475 257 Labourer 325 Allow for solvent cement 50 Over heads Per No Say Rs

Qty

Unit Code

1 0.5 0.5

No Hrs Hrs

Description Unit Rate 110mm PVC Bend ( 22 Deg.) supplied and fixed

165 110mm PVC Bend ( 22 Deg.) 214 Plumber 257 Labourer Allow for solvent cement Over heads Per No Say Rs

Analysis 1st half - Mullaitivu

119 475 325 50

436.00 29.69 20.31 50.00

115.50 29.69 20.31 50.00

Rate

119.00 29.69 20.31 50.00

467.50 65.45 532.95 533.00

536.00 75.04 611.04 611.00

215.50 30.17 245.67 246.00 Amount

219.00 30.66 249.66 250.00

Page 123

5/D

110mm PVC Bend ( 60 Deg.) supplied and fixed 1 0.5 0.5

No Hrs Hrs

166 110mm PVC Bend ( 60 Deg.) 214 Plumber 257 Labourer Allow for solvent cement Over heads Per No Say Rs

6/D No Hrs Hrs

167 110mm PVC Bend ( 88 Deg.) 214 Plumber 257 Labourer Allow for solvent cement Over heads Per No Say Rs

7/D

325.5 475 325 50

325.50 29.69 20.31 50.00

552.5 475 325 50

552.50 29.69 20.31 50.00

525 475 325 50

525.00 29.69 20.31 50.00

299.50 41.93 341.43 341.00

425.50 59.57 485.07 485.00

110mm PVC "T" Junction supplied and fixed 1 0.5 0.5

No Hrs Hrs

364 110mm PVC "T" Junction 214 Plumber 257 Labourer Allow for solvent cement Over heads Per No Say Rs

8/D

652.50 91.35 743.85 744.00

110mm PVC "Y" Joint supplied and fixed 1 0.5 0.5

10/D

199.50 29.69 20.31 50.00

110mm PVC Bend ( 88 Deg.) supplied and fixed 1 0.5 0.5

No 9/D

199.5 475 325 50

No Hrs Hrs

365 110mm PVC "Y" Joint 214 Plumber 257 Labourer Allow for solvent cement Over heads Say Rs

Qty

Unit Code

Description 50mm Bottle trap supplied and fixed 366 50mm Bottle trap 214 Plumber 257 Labourer Allow for solvent cement Over heads Say Rs

1 0.5 0.5

No Hrs Hrs

Unit Rate

110mm PVC Inspection bend supplied and fixed

Analysis 1st half - Mullaitivu

165 475 325 50

Rate 165.00 29.69 20.31 50.00

625.00 87.50 713.00

Amount

265.00 37.10 302.00

Page 124

1 0.5 0.5

No Hrs Hrs

367 110mm PVC Inspection Bend 214 Plumber 257 Labourer Allow for solvent cement Over heads Say Rs

11/D

388.5 475 325 50

388.50 29.69 20.31 50.00

0 475 325 25

0.00 29.69 20.31 25.00

301 475 325 50

301.00 29.69 20.31 50.00

488.50 68.39 557.00

63mm PVC "Y" Joint supplied and fixed 1 0.5 0.5

No Hrs Hrs

63mm PVC "Y" Joint 214 Plumber 257 Labourer 414 Allow for solvent cement Over heads Say Rs

12/D

75.00 10.50 86.00

110mm PVC Elbow supplied and fixed 1 0.5 0.5

No Hrs Hrs

369 214 257 413

110mm PVC Elbow Plumber Labourer Allow for solvent cement Over heads Say Rs

401.00 56.14 457.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU MISCELLANEOUS No 6/251

Qty

Unit Code

100

L.ft

Description Fence barbed wire ,14 gauge, 4 points, 3" sparts, supplied and fixed in existing timber posts with G.I staples. Per 100.0 L.ft.

20 Barbed wire

Unit Rate

2.5

Analysis 1st half - Mullaitivu

Rate

250.00

Amount

Page 125 1 1 1

Doz Hr Hr

225 Staples 214 Fitter 257 Labourer 14% Over Heads Per 100.0 L.ft Per L.ft Say Rs. Per L.m Say Rs.

15/253

1 0.5 0.25 0.04 0.5 1 1 2

Cu.ft Cu.ft Cwt cwt Ibs hr hr hrs

0.5

hr

138 197 46 140 31 214 214 257 414 414 257

1.25 0.625 0.34 0.04 0.75

C.ft C.ft Cwt cwt Ibs

138 197 46 140 31

16/253

No 17/253

Qty

Unit Code

7 3.25 6 1.75 0.32

Cu.ft Cu.ft Cu.ft Cwt Cwt

135 138 197 46 140

Intermediate fence posts or structs, cement concrete 1:1 1/2:3(3/4") reinforced with 4 Nos. 1/4 dia. M.S.rods 5'-7" high square section 4" to 6" fixed complete as per drawing No.68 of 22.07.1936. Per Post 3/4" Metal Sand Cement 1/4" rods 14 B.W.G wire Black smith cutting rods and bind wire Mason, cleaning moulds filling and removing Labourer assisting mason Allow for moulds Allow for curing Fixing in ground 2 labours 14% Over heads Per Post Say Rs - do - - do 7'6" high - do -. Per Post. 3/4" Metal Sand Cement 1/4" rods 14 B.W.G wire Labour & mould etc as in item 15 14% Over heads Per Post Say Rs

Description End post and strut for Type barbed wire fence fixed complete in cement concrete as per Drg. 68 of 1936. Per set 1 1/2" Metal 3/4" Metal Sand Cement M.S.rods

Analysis 1st half - Mullaitivu

20 475 325

20.00 59.38 40.63

8830 2100 520 4240 40 475 475 325 25 25 325

88.30 10.50 130.00 169.60 20.00 59.38 59.38 81.25 25.00 25.00 40.63

8830 2100 520 4240 40 290.63

110.38 13.13 176.80 169.60 30.00 290.63

Unit Rate

8020 8830 2100 520 4240

Rate

561.40 286.98 126.00 910.00 1,356.80

370.00 51.80 421.80 4.22 4.20 13.84 13.80

709.03 99.26 808.29 808.00

790.53 110.67 901.20 901.00

Amount

Page 126

No 18/254

1 3 3 6

Ib hrs hrs hrs

31 214 214 257 414 414 257 214 257

1/3 2 4

hrs hrs hrs

Qty

Unit Code

14 B.W.G wire Black smith Mason Labourer Allow for moulds Allow for curing Labour - excavation foundation Mason Labour - planning posts 14% Over heads Per Post Say Rs

Description Fence barbed wire, 7 strands 14 B.W.G with 4 points at 3" centres and R.C.C posts (1:2:4) 3/4" metal reinforced with 4 Nos. 1/4 rods with 14 B.W.G stirrups at 8" centres including post to be fixed at 8'-0 crs' excavation cement concrete foundation '1:3:6(1 1/2") metal to corner posts and 'structs and straining bolts, all as per type 'plan 68 of

Analysis 1st half - Mullaitivu

40 475 475 325 25 25 325 475 325

Unit Rate

40.00 178.13 178.13 243.75 25.00 25.00 13.54 118.75 162.50

Rate

4,225.97 591.64 4,817.60 4,818.00

Amount

Page 127 22.07.1936 structs to be 'reinforced with 4 Nos. 3/8" rods and 'corner posts with 4 Nos. 1/2" rods. ( including white washing 2 coats) Per 100.0 L.ft (with corner post).

12 700 75 1 1

Nos. L.ft Nos. day day

20 76a 214 257

0.1 1 2/5 1 0.44

cwt Cu.ft Ibs Cu.ft Cu.ft Cwt

140 138 31 135 197 46

0.5 0.5 7 1.5

hr hr Nos. Sqr

214 257 224

1

18A/254

No 19/254

20 224 76a 257

End post and strut as in item 17 Intermediate post - do - 15 Barbed wire G.I.Hook bolts Fitter 2 Labourers add for 1 strut. Steel 3/4" Metal Wire 14 BWG 1 1/2" Metal Sand Cement Labourer and moulds as in Item 15 Mason 2 Labourers Straining bolts White washing 14% Over heads Per 100.0 L.ft Per L.ft Say Rs Per L.m Say Rs - Do - do - do - 8 Strands - do - do - do Per 100 L.ft As in Item no 18 Barbed wire Straining balts G I hooks Labourer Overheads Per 100 L.ft Per L.ft Say Rs Per L.m Say Rs

4,225.97 8,508.30 1,750.00 487.50 475.00 650.00

4240 8830 40 8020 2100 520 290.63 475 325 112 104.90

424.00 88.30 16.00 80.20 21.00 228.80 290.63 29.69 40.63 784.00 157.35

18,257.35 2,556.03 20,813.38 208.13 208.00 682.68 683.00

- do - do - do -

100 1 11 2.5

L.ft No No Hrs

Qty

Unit Code

Description Straining Bolts 1/2" dia made and fixed 18" long (Approx).

0.01 1 2 2

cwt No hrs hrs

1/2" rods 1/2" Nut & Washers Blacksmith Labour Allow for coal etc. 14% Over heads

249 264 215 257 417

4,225.97 709.03 2.5 6.5 475 325

Analysis 1st half - Mullaitivu

18,257.35 18,257.35 2.5 250.00 112 112.00 6.5 71.50 325 101.56

Unit Rate

4330.00 3.00 475.00 325.00 10.00

Rate

43.30 3.00 118.75 81.25 10.00

18,792.42 2,630.94 21,423.36 214.23 214.00 702.69 703.00 Amount

256.30 35.88

Page 128 Per No Say Rs 21/255

3

hrs

292.18 292.00

Well, bailing out water 5' to 7' dia. Upto 20' depth including cleaning well. Say 5'-0" depth of water 257 4 Labourers (1 1/2 day ) 14% Over heads Per 5 L.ft Per L.ft depth Say Rs

325.00

487.50

487.50 68.25 555.75 111.15 111.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU ANGLE IRON No 1/A

Qty

Unit Code

Description Unit Rate Supplying and fixing 50mmx50mmx6mm thick Angle iron purlin fixed to wall at not exeeding 900mm centres and joints should be bolted with 2Nos 12mm dia bolts and nuts other site welding with cleats minimum length 450mm in next reduced angle iron including two coats of Anticorrosive paint

Analysis 1st half - Mullaitivu

Rate

Amount

Page 129

100 7.5

L.ft l.ft

0.25 0.25 10 10

Day Day Nos Nos

0.5 0.5 0.70

Day Day Sqr

2/A

No 3/A

100 7.5

L.ft l.ft

0.25 0.25 10 10

Day Day Nos Nos

0.5 0.5 0.9

Day Day Sqr

Qty

Unit

100 7.5

L.ft l.ft

3 3 10 10

Hrs. Hrs. Nos. Nos.

as directed & including anchoring purlins with 2 nos 10mm tor steel welded to purlins where ever necessary and with 1:2:4 concreting. Per 100 L.ft 344 2"x2"x1/4" Angle iron 85 8,500.00 345 1'-6" long 1 1/2"x1 1/2"x1/4" Angle iron 56.5 423.75 Cutting 215 Blacksmith 475 118.75 257 Labourer 325 81.25 352 1/2"x1" Bolts & Nuts with washer 6 60.00 348 Making holes 20 200.00 Hoisting & Placing 215 Blacksmith 475 237.50 257 Labourer 325 162.50 Two coats of Anticorrosive paint 540.51 378.35 413 Transport and Scaffolding cost 50 50.00 Welding charge with electricity 300.00 Allow for concreting etc(25% of men) 100.00 14% Overheads Per 100 L.ft Per L.ft Say Rs Per L.m Say Rs 62.5mmx62.5mmx6mm Angle iron purlin -'do-doPer 100 L.ft 346 2 1/2"x2 1/2"x1/4" Angle iron 102.5 10,250.00 344 1'-6" long 2"x2"x1/4" Angle iron 85 637.50 Cutting 215 Black smith 475 118.75 257 Labourer 325 81.25 352 1/2"x1" Bolts & Nuts with washer 6 60.00 348 Making holes 20 200.00 Hoisting & Placing 215 Black smith 475 237.50 257 Labourer 325 162.50 Two coats of Anticorrosive painting 540.51 486.45 413 Transport and scaffolding cost 50 50.00 Allow for concreting etc(25% of men) 100.00 Welding charge with electricity 300.00 14% overheads Per 100 L.ft Per L.ft Say Rs Per L.m Say Rs Code Description Unit Rate Rate 75mm x 75mm x 6mm Angle Iron purlin -do-do347 75mmx75mmx6mm Angle Iron 125 12,500.00 346 1" -6" long 62.5mmx62.5mmx6mm Angle Iron 102.5 768.75 Cutting 215 Black Smith 475 178.13 257 Labourer 325 121.88 352 1/2" x 1" Bolts & Nuts with washer 6 60.00 348 Making holes 20 200.00

Analysis 1st half - Mullaitivu

10,612.10 1,485.69 12,097.80 120.98 121.00 396.81 397.00

12,683.95 1,775.75 14,459.71 144.60 145.00 474.28 474.00 Amount

Page 130

0.5 0.5 1.0

Day Day Sqr.

Hoisting & placing 215 Black smith 257 Labourer Two coats of Anticorrosive painting 413 Transport and Scaffolding cost Allow for concreting etc(25% of men) 411 Welding charge cost with electricity Add 14% Per 100 l.ft cost Per L.ft. Say Rs. Per L.m. Say Rs.

4/A

14 0.02 2.25

L.ft. cwt L.ft.

344 249 344

0.25 0.25

Day Day

215 257

0.1

Sqr. 413 411

No 5/A

475 325 540.51 50 300

End Truss-2/50mm x 50mm x 6mm Per 7'-0" including 1:2:4(3/4) concreting 2nos 12mm dia 9" long welded to end truss with 2 coats of anticorrosive paint 2/7' -0" - 50mm x 50mm x 6mm Angle iron 85 12mm dia 9" long Tor steel rods. 4330 0'-9" long cleats 50mm x 50mm x 6mm 85 Cutting Black Smith 475 Labourer 325 Hoisting & Placing Allow for hoisting 60 Two coats of Anticorrosive painting 540.51 Transport and Scaffolding cost 50 Welding charge cost with electricity 300 allow for 1:2:4(3/4") con. Etc 100 Add 14% Per 7 L.ft cost Per L.ft Say Rs. Per L.m Say Rs.

Description Unit Rate End Truss-2/62.5mm x 62.5mm x 6mm -do-doPer 7'-0" 346 2/7' -0" - 62.5mm x 62.5mm x 6mm Angle iron 102.5 As in Item no 4/A 1,041.90 Add 14% Per 7 L.ft cost Per L.ft Say Rs.

237.50 162.50 540.51 50.00 100.00 300.00

1,190.00 86.60 191.25 118.75 81.25 60.00 54.05 50.00 300.00 100.00

Qty

Unit Code

Rate

14

L.ft.

1,435.00 1,041.90

Analysis 1st half - Mullaitivu

15,219.26 2,130.70 17,349.95 173.50 173.00 569.08 569.00

2,231.90 312.47 2,544.37 363.48 363.00 1,192.22 1,192.00

Amount

2,476.90 346.77 2,823.67 403.38 403.00

Page 131 per l.m Say Rs. 6/A

14

L.ft.

End Truss-2/75mm x 75mm x 6mm -do-doPer 7'-0" 347 2/7' -0" - 75mm x 75mm x 6mm Angle iron As in Item no 4/a Add 14% Per 7 L.ft cost Per L.ft Say Rs. Per L.m Say Rs.

7/A

125 1,041.90

1,750.00 1,041.90

15

750.00

475 325

237.50 162.50

300 50 540.51 5.00

300.00 50.00 54.05 250.00

22.00 1054.05

1,100.00 1,054.05

2,791.90 390.87 3,182.77 454.68 455.00 1,491.35 1,491.00

25mm x 6mm - Flat Iron - 1'-0" long weld to end purlin as bracket to fix valance board with two coats of anticorrosive paint & bolts & nuts Per 50 Nos. 50

l.ft

0.5 0.5

Day Day

0.1 50

Sqr. nos

8/A

50

No 9/A

1,323.09 1,323.00

l.ft

351 1'-0" long 1"-1/4" flat iron Cutting and making holes 215 Black Smth 257 Labourer Hoisting & Placing Welding charge including electricity Transport and scaffolding cost Two coats of Anticorrosive painting allow for bolts & nuts Add 14% Per 50 Nos. cost Per No. Say Rs. 31mm x 6mm - Flat Iron - 1'-0" long - do-doPer 50 Nos. 374 1'-0" long 1 1/4"x1/4" flat iron As in Item No 7/A Add 14% Per 50 Nos. cost Per No. Say Rs.

Qty

Unit Code

40

L.ft

Description Unit Rate 2/3" x 3" x 1/4"(2/75mm x 75mm x 6mm) angle iron slope beam including 1:2:4(3/4") concreting with 2 nos 16mm 9" long with 2 coats of anticorrosive painting rag bolt fixed to base plate 9"x9"x10mm & 9" long necessary cleats Per 20'

347 (2/20'-0") double Angle Iron ( 75 x 75 x 6 )

Analysis 1st half - Mullaitivu

125

Rate

5,000.00

1,804.05 252.57 2,056.62 41.13 41.00

2,154.05 301.57 2,455.62 49.11 49.00

Amount

Page 132 3.5 2 4

l.ft Nos. Nos.

0.5 0.5

Day Day

0.5 1.50

Day Sqr.

347 0'-6" long cleats 3" x 3" x 1/4" 376 9" x 9" 3/8" M.S.base plate 96a 16 mm 9" Rag bolt Cutting 215 Black Smith 257 Labourer Hoisting & Placing 257 Labourer Two coats of Anticorrosive paint Transport and scaffolding cost Welding charge cost with electricity Add 14% Per 20 l.ft cost Per L.ft Say Rs. Per L.m Say Rs.

10/A

No 11/A

125 110 140

437.50 220.00 560.00

475 325

237.50 162.50

325 540.51 50.00 300

162.50 810.76 50.00 300.00

#N/A

#N/A

475 86.00

1,425.00 258.00

325 300 540.51

81.25 300.00 216.20

7,940.76 1,111.71 9,052.46 452.62 453.00 1,484.60 1,485.00

Supplying & fixing 'H' iron 6" x 3" 6mm with necessary cleats to housing props including 2 coats of anticorrosive painting Per 16'-0" 19.5

L.ft

H' Iron Cutting and welding cleasts 215 Black Smith 257 Labourer Hoisting & placing 257 2 'Labourer Welding charge with electricity Two coats of Anticorrosive painting Add 14% Per 16 L.ft cost Per l.ft Say Rs. Per L.m Say Rs.

3 3

hr hr

0.25

Day

0.40

Sqr.

Qty

Unit Code

19.5

L.ft.

0.5 0.5

Day Day

Description Supplying & fixing ' H ' Iron 8" x 4" (6mm) with necessary cleats -do Per 16'-0" 350 H ' Iron Cutting and welding 215 Black smith 257 Labourer Hoisting & placing

Analysis 1st half - Mullaitivu

Unit Rate

Rate

0

0.00

475 325

237.50 162.50

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Amount

Page 133 0.25

Day

0.5

Sqr.

257 2 'Labourer Welding charge with electricity Two coats of Anticorrosive painting Add 14% Per 16 L.ft cost Per L.ft Say Rs. Per L.m Say Rs.

325 300 540.51

162.50 300.00 270.25

1,132.75 158.59 1,291.34 80.71 81.00 264.72 265.00

GATE WITH PILLARS No 12/A

Qty

Unit Code

Description

Unit Rate

Rate

Amount

G.I. Gate with 12'-0" x 4'-6" hight 2 Nos sashes made out of 1 1/2" dia G.I. heavy quality frame with 6mm M.S. rod welded 3" c/c both ways all as per Drg. No. 409853 fixed with 9" x 9" RCC pillar in 1:2:4(3/4") concrete 4Y12 reinforced and R6 at 6" crs. stirrups rate include for Excavation base concrete footing R/F with Y10 @ 8" c/c both way 5/8" thick 1:4 plastering 4 Nos. pintol and stirrups locking divice barrel bolt etc. and 2 coats Anticorrosive paint and 2 coats enamel paint & 2 coats ofwhite washing to pillers as directed Per Pillar

0.32 0.13 0.04 0.07 0.36 0.17 0.34 0.09 0.36 0.36

Cube Sqr. Cube Cube Sqr. Cwt. Cwt. Cwt. Sqr. Sqr.

Excavation Lean concrete 1:3:6 (1") Footing concrete 1:2:4 (3/4") Column concrete 1:2:4 (3/4") Shuttering Footing 10mm tor steel Shaft 12mm tor steel Reinforcement (M.S. Rods) Plastering Colour washing

622.00 5,338.25 25,416.00 25,416.00 5,979.78 6,159.00 6,387.00 6,275.00 1,681.00 208.00

199.04 693.97 1,016.64 1,779.12 2,152.72 1,047.03 2,171.58 564.75 605.16 74.88 10,304.89 10,305.00 20,610.00 700.00 300.00

per pillars 2 Nos. Pillars Allow for 'Painting Allow'Fixing Charges Gate sash (12'-0" x 4'-6") 14% Overheads for Gate only

0.00 *

0.00 21,610.00

say per 2 pillars Say Rs.

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU ALUMINIUM WORK No

Qty

Unit Code

Description Labour Distribution for aluminium work Per 10 S.ft 215 Sp.skilled Labourer 257 Un skilled labourer Per 10 S.ft Labour rate per S.ft

0.75 1

Day Day

Analysis 1st half - Mullaitivu

Unit Rate

Rate

475 325

356.25 325.00

Amount

681.25 68.13

Page 134

1/AL

Aluminium Partition

39.6 8.8 27.5 32 52.8 52.8 35.2 35.2 17.6 19.8

L.ft L.ft L.ft S.ft S.ft S.ft L.ft L.ft L.ft L.ft

385 399 400 405 406 407 388 387 398 397

15.4 3.3 3.3 3.3 7.7 7.7 7.7 9.9 13.2 19.8 1.0

L.ft L.ft L.ft L.ft L.ft L.ft L.ft S.ft S.ft S.ft No

384 401 383 382 379 380 381 406 405 407 403

77

No 2/AL

Qty

20.9 10.45 41.8 41.8 24.2

Sft

Labourer Overheads Per 77 Sq.ft Per Sq.ft Say per S.ft Say per m2

Unit Code

L.ft L.ft L.ft L.ft S.ft

Size 11' 0" x 7' 0" = 77 S.ft Mian frame 70S-3002-1 Mild frame PT-5157 2" x 1" Box iron P-1113 5mm Tintaed glass 6mm Plywood (Marin) Formica sheet Glass beading 100D - 1917 Glass beading 100D - 1914 Beading bottom PT - 5154 M.Channel beading PT - 5153 Door Vertical frame 70S - 1704 - A Mild frame 80S-1801 Bottom Horri 70S - 1503 - A Top Horri 70S -1402 - 1 Top rail 70S - 1002 -1 Bottom rail 70S - 1102 - 1 Lock vertical rail 70S - 1202 - 1 6mm plywood sheet 5mm Tinted glass Formica sheet Lock alfa Allow for rubber gacscut reverd brass screws, celicone sealent etc. 10%

394 395 396 387 405

85 56.3 40.75 60 20.85 18 32.8 24.3 30.5 12.8

3,366.00 495.44 1,120.63 1,920.00 1,100.88 950.40 1,154.56 855.36 536.80 253.44

79.4 57.85 78.1 52.9 64.6 44.5 46.4 20.85 60 18 750

1,222.76 190.91 257.73 174.57 497.42 342.65 357.28 206.42 792.00 356.40 750.00 1,690.16

68.13

Description Aluminium Casement with project Size 4' 0"x5' 6" = 22 S.ft Side frame CA - 1001 Midle frame CA - 1002 Sash frame CA-2001-A Beading 100D-1914 Tinted glass 5mm Allow for bar hinges, selicone rubber gasscut brass screws riveres etc. 10%

Analysis 1st half - Mullaitivu

Unit Rate

84.3 134.2 88.9 24.3 60

5,245.63

Rate

1,761.87 1,402.39 3,716.02 1,015.74 1,452.00 934.80

23,837.42 3,337.24 27,174.66 352.92 353.00 3,797.00

Amount

Page 135 22

S.ft

Labourer Overheads Per 22 S.ft Per S.ft Say Per S.ft Say per m2

3/AL

68.13

1,498.75

85 24.3

1,589.50 267.30 185.68 356.25 243.75

Aluminium Door frame only

18.7 11.0

L.ft L.ft

0.75 0.75

Day Day

Size 7'-0" x 3'-0" = 21 S.ft 70S - 3002 - 1 70D - 1910 Allow for revert 10% 215 Sp.skilled Labourer 257 Un skilled Labourer

385 Side frame 386 Beading

475 325

14% Overhead Per 21 Sft Per Sft Say per S.ft Say per m2

4/AL

No 5/AL

11,781.57 1,649.42 13,430.99 610.50 610.00 6,569.00

2,642.48 369.95 3,012.43 143.45 143.00 1,544.00

Aluminium door fully glazed double hung

14.3 14.3 5.5 5.5 5.5 50.6 1.0 2 2 35.75 19.8 19.8

L.ft L.ft L.ft L.ft L.ft L.ft No Pair No S.ft L.ft L.ft

392 393 391 390 389 387 403 402 404 405 385 386

32.5

S.ft

Qty

Unit Code

14.3 14.3 5.5 5.5 5.5 50.6

L.ft L.ft L.ft L.ft L.ft L.ft

392 393 391 390 389 387

Size 6' 6"x 5' 0" = 32.5 Sq.ft Side vertical member 100D - 3502 Vertical lock member 100D - 3503-A Bottom rail member 100D-3207 Top rail member 100D-3203 Mid lock rail 100D-3004-A Beading 100D-1914 Lock Handle Door closer 5mm glass Door frame 70S - 3002 - 1 Beading 70D - 1910 Allow 10% Labourer 14% Overhead Per 32.5 S.ft Per S.ft Say per S.ft Say per m2

Description Al Double hung Door with panneled and glazed Size 6' 6" x 5' 0" = 32.5 Sq.ft Side vertical member (sash) 100D - 3502 Vertical lock member 100D - 3503 A Bottom rail 100D - 3207 Top rail 100D - 3203 Mild Lock rail 100D - 3004 A Bead 100D - 1914

Analysis 1st half - Mullaitivu

148.7 160.9 169 129.1 124.5 24.3 750 350 1645 60 85 24.3 68.13

Unit Rate

148.7 160.9 169 129.1 124.5 24.3

2,126.41 2,300.87 929.50 710.05 684.75 1,229.58 750.00 700.00 3,290.00 2,145.00 1,683.00 481.14 1,703.03 2,214.06

Rate

2,126.41 2,300.87 929.50 710.05 684.75 1,229.58

20,947.39 2,932.63 23,880.03 734.77 735.00 7,906.00

Amount

Page 136 1.0 2 2 19.25 16.5 33 19.8 19.8

No Pair No S.ft S.ft S.ft L.ft L.ft

32.5

S.ft

403 402 404 405 406 407 385 386

6/AL

Lock (alpha) Handle Door closer 2 nos. 5mm glass tinted 6mm plywood Formica Door frame 70S - 3002 - 1 Beading 70D- 1910 Allow for rivets, gasscut, rubber brass screws Doorhinges silicone tie rods etc.( 10%) Labourer 14% Overheads Per 32.5 Sq.ft. Per S.ft Say per S.ft Say per m2

750 350 1645 60 20.85 18 85 24.3

750.00 700.00 3,290.00 1,155.00 344.03 594.00 1,683.00 481.14

68.13

1,697.83 2,214.06

20,890.22 2,924.63 23,814.85 732.76 733.00 7,885.00

Al single hung Door with fully glazed Size 6' 6" x 3' 3" = 21.12. Sq.ft.

No 7/AL

7.15 7.15 3.57 3.57 3.57 28.6 1 1 1 23.24 17.87 17.87

L.ft L.ft L.ft L.ft L.ft L.ft No Pair No S.ft L.ft L.ft

21.12

S.ft

392 393 391 390 389 387 403 402 404 405 385 386

Qty

Unit Code

7.15 7.15 3.57 3.57 3.57 28.6

L.ft L.ft L.ft L.ft L.ft L.ft

392 393 391 390 389 387

Side vertical member (sash) 100D - 3502 Vertical lock member 100D - 3503 A Bottom rail 100D - 3207 Top rail 100D - 3203 Mid Lock rail 100D - 3004 A Bead 100D - 1914 Lock (alpha) Handle Door closer 5mm glass tinted Door frame 70S - 3002 - 1 Beading 70D- 1910 Allow 10% for rivets, gascut, rubber brass screws Labour 14% Overheads Per 21.12 Sq.ft. Per Sft Say per S.ft Say per m2

Description Al Single hung Door with panneled and glazed Size 6' 6" x 3' 3" = 21.12. Sq.ft. Side vertical member (sash) 100D - 3502 Vertical lock member 100D - 3503 A Bottom rail 100D - 3207 Top rail 100D - 3203 Mild Lock rail 100D - 3004 A Bead 100D - 1914

Analysis 1st half - Mullaitivu

148.7 160.9 169 129.1 124.5 24.3 750 350 1645 60 85 24.3 68.13

Unit Rate

148.7 160.9 169 129.1 124.5 24.3

1,063.21 1,150.44 603.33 460.89 444.47 694.98 750.00 350.00 1,645.00 1,394.40 1,518.95 434.24 1,050.99 1,438.80

Rate

1,063.21 1,150.44 603.33 460.89 444.47 694.98

12,999.68 1,819.96 14,819.64 701.69 702.00 7,550.00

Amount

Page 137 1 1 1 12.51 10.72 21.45 17.87 17.87

No Pair No S.ft S.ft S.ft L.ft L.ft

21.12

S.ft

49 7

403 402 404 405 406 407 385 386

Lock (alpha) Handle Door closer 2 nos. 5mm glass tinted 6mm plywood Formica Door frame 70S - 3002 - 1 Beading 70D- 1910 Allow for rivets, gasscut, rubber brass screws Doorhinges silicone tie rods etc.( 10%) Labourer 14% Overheads Per 21.12 Sq.ft. Per S.ft Say per S.ft Say per m2

750 350 1645 60 20.85 18 85 24.3

750.00 350.00 1,645.00 750.60 223.51 386.10 1,518.95 434.24

68.13

1,047.57 1,438.80

12,962.08 1,814.69 14,776.77 699.66 700.00 7,528.00

Channels 2" semi-circular, formed in cement concrete floors and 1/2" cement rendered 1:2 (extra over concrete floors). Per 10 L.ft. 2 1

Hour Hour

214 Mason 257 Labourer Allow for cement and sand Over heads

Analysis 1st half - Mullaitivu

475.00 325.00

118.75 40.63 100.00

259.38 36.31

Page 138 Per 10 L.ft Per L.ft Say per L.ft. Per L.m. Say per L.m.

50 8

295.69 29.57 30.00 98.40 98.00

:- 23/10 :- 76/=

Channels 4" - do -

- do - do -.

Per 10 L.ft. 4 2

Hour Hour

51 10

214 Mason 257 Labourer Allow for cement, sand etc Over heads Per 10 L.ft Per L.ft Say per L.ft. :- 34.80 Per L.m. Say per L.m. :- 114/=

475.00 325.00

237.50 81.25 100.00

418.75 58.63 477.38 47.74 48.00 157.44 157.00

Curb in cement concrete 1:2:4 (3/4") 9" heigh and 3" thick, cement rendered 1/2" thick including excavation. Per 10.0 L.ft 2 1/8

Cu.ft Cwt

1 1

Day Day

97 3

Materials for concrete as in Item 47 46 Cement for 7 1/2 S.ft rendering Allow for sand for rendering 214 Mason 257 Labourer Allow for shuttering, excavation,curing etc Over heads Per 10 L.ft Per L.ft Say per L.ft. :- 125/= Per L.m Say per L.m. :- 410/=

184.10 520.00 100.00 475.00 #N/A 150.00

368.20 65.00 100.00 475.00 #N/A 150.00

5.7 2100 520 475 325

1,995.00 315.00 884.00 950.00 1,300.00

#N/A #N/A #N/A #N/A #N/A #N/A #N/A

Floors, brick paved, 3" thick, set in lime mortar 2:5 and cement rendered 1/2", 1:2. Per Sqrs. 350 0.15 1.7 2 4

No 41 Bricks Cube 200 Sand Cwts 46 Cement Day 214 Mason Day 257 Labourer Over heads Per square

Analysis 1st half - Mullaitivu

5,444.00 762.16 6,206.16

Page 139 Say per Sqrs = Per m2 Say per m2 :-

6,206.00 668.03 668.00

471/=

SECOND HALF OF 2001 IN MANNAR ELECTRICAL. 1

Main switch (3 phase, 30 amp.). 1 40 2 2 2 0.5 1/2

No m

131 1000 35 Nos. 339 Nos. 340 Meter 52a day 257 day 214

2

Main switch 30 amp. 7/.044 single core wire, 40m Board Brass Screws 2"x10 Brass Screws 1"x6 Conduit pipe 1" Labour Electrician Over heads Per No Say Rs

1 82.00 50 #REF! #REF! #REF! 325 475

1.00 32.80 50.00 #REF! #REF! #REF! 162.50 237.50

1 #REF! 50 #REF! #REF! #REF! 325 475

1.00 #REF! 50.00 #REF! #REF! #REF! 162.50 237.50

#N/A 43 #N/A

#N/A 43.00 #N/A

#REF! #REF! #REF! #REF!

Main switch (60 Amp, 3 phase). 1 40 2 2 2 1/2 1/2

No m

132 1001 35 Nos. 339 Nos. 340 Meter 52a day 257 day 214

3

Main switch 60 Amp English 7/0.064 Single core wire 40m Board Brass Screws 2"x10 Brass Screws 1"x6 Conduit pipe labourer Electrician Over heads Per No Say Rs

#REF! #REF! #REF! #REF!

Earth wire 15 1 1/2

m No day

10 plug points 321 Earth pipe 2"x5' Electrician labourer Over heads Per No Say Rs

Analysis 1st half - Mullaitivu

#N/A #N/A #N/A #N/A

Page 140

4

Main switch single phase 30 Amp. 1 10 1 2 2 2 1/2

no Meter Nos. Nos. Nos. Meter day

131 1000 35 339 340 52a

5

Main switch 30 Amp English 7/0.044 wire 10m Board Screws 2"x10 Screws 1"x6 Conduit pipe Electrician labourer Over heads Per No Say Rs

1 #REF! 50 #REF! #REF! #REF! #N/A

1.00 #REF! 50.00 #REF! #REF! #REF! #N/A

43 43 #REF! 43 #REF! 43 43 #REF! #N/A

43.00 1,075.00 #REF! 43.00 #REF! 645.00 43.00 #REF! #N/A

43 43 43 43 #REF! 90 43 43 90 43 #REF! 43 475

43.00 43.00 43.00 43.00 #REF! 90.00 43.00 43.00 90.00 1,075.00 #REF! 43.00 237.50

43 #REF! #REF!

43.00 #REF! #REF!

#REF! #REF! #REF! #REF!

15 Amp. Plug. 1 25 2 1 2 15

no m No no No m

2 1/2

m day

322 323 336 324 337 326 327 52a

6

Plug with switch (clipsal) 3/.036 wire, 25 meters Brass Screws (1 1/2"x6), Sunk box Brass Screws 1 1/2"x10" Earth wire 7/.029 Wiring clips and panel pins (Allow) Conduit pipe Electrician labourere Over heads Per No Say Rs

#REF! #REF! #REF! #REF!

Light Fitting. 1 1 1 1 2 1 1 1 1 25 2

no no no m No No no no No m m

1/2

day

7

328 329 330 331 336 40a 333 324 334 52a 327 214

Round plug Ceiling rose Holder Flexible wire Brass Screw 1/2"x6 Brass Screw 1 1/2" Switch clipsal Sunk box Brass screw 2" 1/.044 wire Conduit pipe Wiring clips & pannel pins Electrician Over heads Per No Say Rs

5 Amp. Plug. 1 2 1

Nos. Nos. Nos.

322 Plug with switch (Clipsal) 336 Brass screws (1 1/2"x6) 335 Sunk box

Analysis 1st half - Mullaitivu

#REF! #REF! #REF! #REF!

Page 141 2 25 15

Nos. m m

1 1/2

m day

8

337 334 326 327 52a 214

Brass screws (1 1/2"x10) 1/.044 wire Earth wire 7/.029 Wiring clips & panel pins Conduit pipe Electrician Over heads Per No Say Rs

#REF! 43 43 43 #REF! 475

#REF! 10.75 6.45 43.00 #REF! 237.50

#N/A #N/A #N/A 475

#N/A #N/A #N/A 237.50

#N/A #N/A #N/A #N/A #N/A #N/A #REF! #N/A 475

#N/A #N/A #N/A #N/A #N/A #N/A #REF! #N/A 237.50

#REF! #REF! #N/A #N/A #N/A #N/A 475

#REF! #REF! #N/A #N/A #N/A #N/A 237.50

#N/A #N/A #N/A #N/A #REF!

#N/A #N/A #N/A #N/A #REF!

#REF! #REF! #REF! #REF!

Ceiling Fan (USHA). 1 1 1 1/2

no no no day

9

Ceiling fan 56" Hooks Light point 214 Electrician Over heads Per No Say Rs

#N/A #N/A #N/A #N/A

Calling Bell. 1 1 1 3 1 25 2

no no no Nos. no m m

1/2

day

10 5 2 2 2 1 1 1/2

Bell Bell bush - Clipsal Round block Brass screws 1 1/2" Sunk box 1/.044 wire 52a Conduit pipe Wiring clips & panel pins 214 Electrician Over heads Per No Say Rs

ABC box 500 Type. m 1000 7/.044 wire m 52a Conduit pipe Nos. Brass Screws 2"x10 Nos. Brass Screws 1 1/4"x6 Nos. ABC box 500 type Nos. Board 10"x10" day 214 Electrician Over heads Per No Say Rs

11

Trip switch (Single phase). 1 1 2 2 2

No No Nos. Nos. m

Trip switch crab tree Board Brass Screws 2"x10 Brass Screws 1 1/4"x6 52a Conduit

Analysis 1st half - Mullaitivu

#N/A #N/A #N/A #N/A

#REF! #REF! #REF! #REF!

Page 142 1/2

day

12

214 Electrician Over heads Per No Say Rs

475

237.50

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A

#N/A #N/A #N/A #N/A

Pendent lamp / Battern lamp. 1 1

No No

13

Light point Bulb Over heads Per No Say Rs

#N/A #N/A #N/A #N/A

Water light lamp. 1 1

No No

14

Light point Water tight lamp Over heads Per No Say Rs

#N/A #N/A #N/A #N/A

Flourscent lamp 4'-0". 1 1

No No

15

Light point 4'-0" Flourscent set Over heads Per No Say Rs

#N/A #N/A #N/A #N/A

Flourscent Lamp 2'-0". 1 1

No No

16

Light point Flourscent set Over heads Per No Say Rs

#N/A #N/A #N/A #N/A

Hood lamp. 1 1

No No

17

Light point Hood lamp Over heads Per No Say Rs

#N/A #N/A #N/A #N/A

Wall bracket lamp. 1 1

No No

Light point Bracket lamp Over heads Per No

Analysis 1st half - Mullaitivu

#N/A #N/A #N/A

Page 143 Say Rs

18

#N/A

ABC Box 700 type. As per Item 10 Less 500 type Add 700 type 14% Over Heads Per No Say Rs

19

#REF! #N/A

#REF! #REF! #REF! #REF!

ABC Box 900 type. As per Item 10 Less 500 type Add 900 type 14% Over Heads Per No Say Rs

286 ??

#REF! #N/A

#REF! #N/A

#REF! #REF! #REF! #REF!

Lanka ceremic (Dulex white) Low level white comode with trap Cistern only Fittings Seat cover Brackets Flash band Brackets Allow for Transport Labourer as in Item 34 Over heads Per No Say Rs

287 34

#REF! #N/A

1,843.00 1,375.00 350.00 375.00 54.00 35.50 26.00 100.00

4,158.50 800.00 582.19 4,740.69 4,741.00

Closet pedestal with cistern - do -. Indian make.

??? 1

1843 1375 350 375 54 35.5 26 100

No

1

no

1 1

day day

306 Low level closet suite Allow for transport 227 1/2" stop cock Brass Cement, Metal, Sand etc. (Item 31) 214 Plumber 257 Labourer Over heads Per No Say Rs

Analysis 1st half - Mullaitivu

0 50

0.00 50

105 50 475 325

105.00 50.00 475.00 325.00

955.00 133.70 1,088.70 1,089.00

Page 144

289

Squatting closet 14% Indian made. 1

no

290 1

No

222 Squatting pan & trap Allow for transport as per Item 35 less closet Over heads Per No Say Rs Squatting closet square type. As per Item 288 less squatting pan 307 Square type pan Over heads Per No Say Rs

1

700 50 1,073.33

700.00 50.00 1,073.33

1,073.33 0

1,073.33 0.00

BARBED WIRE FENCE Intermediate fence posts or structs, cement concrete 1:2 1/2:3 (3/4") reinforced with 4 Nos. 1/4 dia. M.S.rods 5'-7" high square section 4" to 6" fixed complete as per drawing No. 68 of 22.07.1936. Per Post

1 0.5 0.25 4 0.5 1 1 2

C.ft. C.ft. Cwt. Hrs. Lbs. Hr. Hr. Hrs.

138 3/4" Metal 197 Sand 46 Cement 1/4" Rods 31 14 B.W.G. Wire 214 Black Smith, cutting rods and tieying wire 214 Mason, cleaningmoulds filing and removing 257 Labourer assisting Mason

Analysis 1st half - Mullaitivu

8830 2100 520 #N/A 40 475 475 325

88.30 10.50 130.00 #N/A 20.00 59.38 59.38 81.25

1,823.33 255.27 2,078.60 2,079.00

1,073.33 150.27 1,223.60 1,224.00

Page 145

0.5

hrs

2

Allow for Moulds Allow for curing 257 Fixing in ground 2 Labourers 1/2 Hr. 14% Overheads Total cost Say Rs.

30 30 325

30.00 30.00 40.63

8020 8830 2100 520 4240 40 475 325 30 30 325

561.40 331.13 126.00 910.00 1,356.80 40.00 178.13 243.75 30.00 30.00 40.63

#N/A #N/A #N/A

End post and struct for Type barbed wire fence fixed complete in cement concrete as per Drg. Of 68 of 1936

7 3.75 6 1.75 0.32 1 3 6

C.ft. C.ft. C.ft. Cwt. Cwt. Lb. Hrs. Hrs.

0.5

Hrs.

3

135 1 1/2" Metal 138 3/4" Metal 197 Sand 46 Cement 140 M.S. Rods 31 14 B.W.G.Wire 214 Black Smith 257 Labourer Allow formoulds Allow for curing 257 Excavation foundation & Planting post 1/2 Hrs. 2 Lab Overheads Total cost Say Rs.

Fence barbed wire 5 strands 12 1/2 B.W.G. with 4 points at 3" centres and R.C.C. posts (1:2:4)3/4" metal reinforced with 4 Nos. 1/4 rods with 14 B.W.G. stirrups at 8" centres post to be fixed at 8'-0" crs. including excavation, cement concrete foundation 1:3:6(1 1/2") metal to corner posts and struts, and straining bolts, all as per type plan 68 of 22.36 structs to be reinforced with 4 Nos. 3/8" rods and corner posts with 4 Nos. 1/2" rods. Per 100 L.ft. (with corner post)

12 500 55

No. L.ft. No.

3/4 3/4

Day Day

11 1 2/5 1 0.44

Lbs. C.ft. Lbs. C.ft. Cwt.

End post and strut as in item 2 Intermediate post - do - 1 31 Barbed wire 76a G.I. Hook bolts 214 Fitter 257 2 Labourers Add for strut Steel 138 3/4" Metal 31 Wire 135 1 1/2" Metal 46 Cement Labour and moulds Concrete foundation

Analysis 1st half - Mullaitivu

3,847.83 #N/A 40 6.5 475 325 #N/A 8830 40 8020 520

3,847.83 538.70 4,386.52

Page 146 1/2 1/2 5 1

Hr. Hr. Nos. Sqr.

29 38

Mason 2 Labourers Straining bolts White washing 2 coats Overheads Per 100 L.ft. Per L.ft. Say Rs. Per L.m. Say Rs.

#N/A #N/A #N/A #N/A

Waterproof Treatment of hot bitumen taken off from flat roof and debris cleared away. Per Sqrs. 2

Day

11 28

257 Labourer Over heads Per square Say per square Per m2 Say per m2

:-

502/=

:-

54/-

325.00

650.00

18 325

54.00 40.63

18 325

270.00 81.25

650.00 91.00 741.00 741.00 79.76 80.00

Tiles, Calicut pattern, flat supplied and laid up to 5 tiles in Buildings of more than 1 storey. Per 3 tiles. 3 1

Nos. Hour

12 29

70 Tiles 257 Labourer Over heads Per 3 tiles Per tiles Say Rs :- 23/-

94.63 13.25 107.87 35.96 36.00

Tiles, Calicut pattern, flat, supplied and laid above 5 and up to 25 in Buildings of more than 1 storey. Per 15.0 tiles. 15 2

208

Nos Hour

70 Tiles. 257 Labourer Over heads Per 15 tiles Per tiles Say per tile

:- 16/-

Painting new wood work with approved

Analysis 1st half - Mullaitivu

351.25 49.18 400.43 26.70 27.00

Page 147 26

primer 1 coat.

0.756 5

Lit Hour

190 Primer 214 Painter preparing surface and painting Allow for brushes etc Over heads Per square Say Rs :- 606/Say per m2

Analysis 1st half - Mullaitivu

1560 475 20

1,179.36 296.88 20.00

1,496.24 209.47 1,705.71 1,705.00 151.00

Page 148

Analysis 1st half - Mullaitivu

Page 149

Analysis 1st half - Mullaitivu

Page 150

Analysis 1st half - Mullaitivu

Page 151

Analysis 1st half - Mullaitivu

Page 152

Analysis 1st half - Mullaitivu

Page 153

Analysis 1st half - Mullaitivu

Page 154

Analysis 1st half - Mullaitivu

Page 155

Analysis 1st half - Mullaitivu

Page 156

Analysis 1st half - Mullaitivu

Page 157

Analysis 1st half - Mullaitivu

Page 158

Analysis 1st half - Mullaitivu

Page 159

Analysis 1st half - Mullaitivu

Page 160

Analysis 1st half - Mullaitivu

Page 161

Analysis 1st half - Mullaitivu

Page 162

Analysis 1st half - Mullaitivu

Page 163

Analysis 1st half - Mullaitivu

Page 164

Analysis 1st half - Mullaitivu

Page 165

Analysis 1st half - Mullaitivu

Page 166

Analysis 1st half - Mullaitivu

Page 167

Analysis 1st half - Mullaitivu

Page 168

Analysis 1st half - Mullaitivu

Page 169

Analysis 1st half - Mullaitivu

Page 170

Analysis 1st half - Mullaitivu

Page 171

Analysis 1st half - Mullaitivu

Page 172

Analysis 1st half - Mullaitivu

Page 173

Analysis 1st half - Mullaitivu

Page 174

Analysis 1st half - Mullaitivu

Page 175

Analysis 1st half - Mullaitivu

Page 176

Analysis 1st half - Mullaitivu

Page 177

Analysis 1st half - Mullaitivu

Page 178

Analysis 1st half - Mullaitivu

Page 179

Analysis 1st half - Mullaitivu

Page 180

Analysis 1st half - Mullaitivu

Page 181

Analysis 1st half - Mullaitivu

Page 182

Analysis 1st half - Mullaitivu

Page 183

Analysis 1st half - Mullaitivu

Page 184

Analysis 1st half - Mullaitivu

Page 185

Analysis 1st half - Mullaitivu

Page 186

Analysis 1st half - Mullaitivu

Page 187

Analysis 1st half - Mullaitivu

Page 188

Analysis 1st half - Mullaitivu

Page 189

Analysis 1st half - Mullaitivu

Page 190

Analysis 1st half - Mullaitivu

Page 191

Analysis 1st half - Mullaitivu

Page 192

Analysis 1st half - Mullaitivu

Page 193

Analysis 1st half - Mullaitivu

Page 194

Analysis 1st half - Mullaitivu

Page 195

Analysis 1st half - Mullaitivu

Page 196

Analysis 1st half - Mullaitivu

Page 197

Analysis 1st half - Mullaitivu

Page 198

Analysis 1st half - Mullaitivu

Page 199

Analysis 1st half - Mullaitivu

Page 200

Analysis 1st half - Mullaitivu

Page 201

Analysis 1st half - Mullaitivu

Page 202

Analysis 1st half - Mullaitivu

Page 203

Analysis 1st half - Mullaitivu

Page 204

Analysis 1st half - Mullaitivu

Page 205

Analysis 1st half - Mullaitivu

Page 206

Analysis 1st half - Mullaitivu

Page 207

Analysis 1st half - Mullaitivu

Page 208

Analysis 1st half - Mullaitivu

Page 209

Analysis 1st half - Mullaitivu

Page 210

Analysis 1st half - Mullaitivu

Page 211

Analysis 1st half - Mullaitivu

Page 212

Analysis 1st half - Mullaitivu

Page 213

Analysis 1st half - Mullaitivu

Page 214

Analysis 1st half - Mullaitivu

Page 215

Analysis 1st half - Mullaitivu

Page 216

Analysis 1st half - Mullaitivu

Page 217

Analysis 1st half - Mullaitivu

Page 218

Analysis 1st half - Mullaitivu

Page 219

Analysis 1st half - Mullaitivu

Page 220

Analysis 1st half - Mullaitivu

Page 221

Analysis 1st half - Mullaitivu

Page 222

Analysis 1st half - Mullaitivu

Page 223

Analysis 1st half - Mullaitivu

Page 224

Analysis 1st half - Mullaitivu

Page 225

Analysis 1st half - Mullaitivu

Page 226

Analysis 1st half - Mullaitivu

Page 227

Analysis 1st half - Mullaitivu

Page 228

Analysis 1st half - Mullaitivu

Page 229

Analysis 1st half - Mullaitivu

Page 230

Analysis 1st half - Mullaitivu

Page 231

Analysis 1st half - Mullaitivu

Page 232

Analysis 1st half - Mullaitivu

Page 233

Analysis 1st half - Mullaitivu

Page 234

Analysis 1st half - Mullaitivu

Page 235

Analysis 1st half - Mullaitivu

Page 236

Analysis 1st half - Mullaitivu

Page 237

Analysis 1st half - Mullaitivu

Page 238

Analysis 1st half - Mullaitivu

Page 239

h983

Analysis 1st half - Mullaitivu

Page 240

Analysis 1st half - Mullaitivu

Page 241

Analysis 1st half - Mullaitivu

Page 242

Analysis 1st half - Mullaitivu

Page 243

Analysis 1st half - Mullaitivu

Page 244

Analysis 1st half - Mullaitivu

Page 245

Analysis 1st half - Mullaitivu

Page 246

Analysis 1st half - Mullaitivu

Page 247

Analysis 1st half - Mullaitivu

Page 248

Analysis 1st half - Mullaitivu

Page 249

Analysis 1st half - Mullaitivu

Page 250

Analysis 1st half - Mullaitivu

Page 251

Analysis 1st half - Mullaitivu

Page 252

Analysis 1st half - Mullaitivu

Page 253

Analysis 1st half - Mullaitivu

Page 254

Analysis 1st half - Mullaitivu

Page 255

Analysis 1st half - Mullaitivu

Page 256

Analysis 1st half - Mullaitivu

Page 257

Rate

Amount

0

Analysis 1st half - Mullaitivu

Page 258

0 0 211

Analysis 1st half - Mullaitivu

Page 259

Analysis 1st half - Mullaitivu

Page 260

Analysis 1st half - Mullaitivu

Page 261

Analysis 1st half - Mullaitivu

Page 262

Analysis 1st half - Mullaitivu

Page 263

Analysis 1st half - Mullaitivu

Page 264

Analysis 1st half - Mullaitivu

Page 265

Analysis 1st half - Mullaitivu

Page 266

Analysis 1st half - Mullaitivu

Page 267

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 268

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 269

Analysis 1st half - Mullaitivu

Page 270

Analysis 1st half - Mullaitivu

Page 271

Analysis 1st half - Mullaitivu

Page 272

Analysis 1st half - Mullaitivu

Page 273

Analysis 1st half - Mullaitivu

Page 274

Analysis 1st half - Mullaitivu

Page 275

Analysis 1st half - Mullaitivu

Page 276

Analysis 1st half - Mullaitivu

Page 277

Analysis 1st half - Mullaitivu

Page 278

Analysis 1st half - Mullaitivu

Page 279

Analysis 1st half - Mullaitivu

Page 280

Analysis 1st half - Mullaitivu

Page 281

Analysis 1st half - Mullaitivu

Page 282

Analysis 1st half - Mullaitivu

Page 283

Analysis 1st half - Mullaitivu

Page 284

Analysis 1st half - Mullaitivu

Page 285

Rate

Amount

Analysis 1st half - Mullaitivu

Page 286

Rate

Amount

Analysis 1st half - Mullaitivu

Page 287

Analysis 1st half - Mullaitivu

Page 288

Analysis 1st half - Mullaitivu

Page 289

Analysis 1st half - Mullaitivu

Page 290

Analysis 1st half - Mullaitivu

Page 291

Analysis 1st half - Mullaitivu

Page 292

Analysis 1st half - Mullaitivu

Page 293

Analysis 1st half - Mullaitivu

Page 294

Analysis 1st half - Mullaitivu

Page 295

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 296

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 297

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 298

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 299

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 300

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 301

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 302

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 303

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 304

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 305

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 306

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 307

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 308

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 309

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 310

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 311

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 312

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 313

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 314

Rate

Add 14%

Analysis 1st half - Mullaitivu

Page 315

Analysis 1st half - Mullaitivu

Page 316

Analysis 1st half - Mullaitivu

Page 317

Analysis 1st half - Mullaitivu

Page 318

Analysis 1st half - Mullaitivu

Page 319

Analysis 1st half - Mullaitivu

Page 320

Analysis 1st half - Mullaitivu

Page 321

Analysis 1st half - Mullaitivu

Page 322

Analysis 1st half - Mullaitivu

Page 323

Analysis 1st half - Mullaitivu

Page 324

Analysis 1st half - Mullaitivu

Page 325

Analysis 1st half - Mullaitivu

Page 326

Analysis 1st half - Mullaitivu

Page 327

Analysis 1st half - Mullaitivu

Page 328

Analysis 1st half - Mullaitivu

Page 329

Analysis 1st half - Mullaitivu

Page 330

Analysis 1st half - Mullaitivu

Page 331

Analysis 1st half - Mullaitivu

Page 332

Analysis 1st half - Mullaitivu

Page 333

Analysis 1st half - Mullaitivu

Page 334

Analysis 1st half - Mullaitivu

Page 335

Analysis 1st half - Mullaitivu

Page 336

Analysis 1st half - Mullaitivu

Page 337

Analysis 1st half - Mullaitivu

Page 338

Analysis 1st half - Mullaitivu

Page 339

Analysis 1st half - Mullaitivu

Page 340

Analysis 1st half - Mullaitivu

Page 341

Analysis 1st half - Mullaitivu

Page 342

Analysis 1st half - Mullaitivu

Page 343

Analysis 1st half - Mullaitivu

Page 344

Analysis 1st half - Mullaitivu

Page 345

Analysis 1st half - Mullaitivu

Page 346

Analysis 1st half - Mullaitivu

Page 347

Analysis 1st half - Mullaitivu

Page 348

Analysis 1st half - Mullaitivu

Page 349

Analysis 1st half - Mullaitivu

Page 350

Analysis 1st half - Mullaitivu

Page 351

Analysis 1st half - Mullaitivu

Page 352

Analysis 1st half - Mullaitivu

Page 353

Analysis 1st half - Mullaitivu

Page 354

Analysis 1st half - Mullaitivu

Page 355

Analysis 1st half - Mullaitivu

Page 356

Analysis 1st half - Mullaitivu

Page 357

Analysis 1st half - Mullaitivu

Page 358

Analysis 1st half - Mullaitivu

Page 359

Analysis 1st half - Mullaitivu

Page 360

Analysis 1st half - Mullaitivu

Page 361

Analysis 1st half - Mullaitivu

Page 362

Analysis 1st half - Mullaitivu

Page 363

Analysis 1st half - Mullaitivu

Page 364

Analysis 1st half - Mullaitivu

Page 365

Analysis 1st half - Mullaitivu

Page 366

PRICE LIST Description

Code No

Unit

Rate

1

1 1 1/2" dia. Pvc pipe 1000 type

L.ft

42.00

2

2 1 1/2" dia. Pvc pipe 600 type

L.ft

27.00

3

3 1 1/4" dia. Pvc pipe 1000 type

L.ft

28.00

4

4 1 1/4" dia. Pvc pipe 600 type

L.ft

20.00

5

5 1" dia. Pvc pipe 1000 type

L.ft

19.00

6

6 1" dia. Pvc pipe 600 type

L.ft

11.00

7

7 1/2" dia. Pvc pipe 1000 type

L.ft

7.00

8

8 2" dia. Pvc pipe 1000 type

L.ft

73.00

9

9 2" dia. Pvc pipe 600 type

L.ft

44.00

10

10 3/4" dia. Pvc pipe 1000 type

L.ft

12.00

11

11 4" dia. Sewerage (SS) 250 type

L.ft

53.00

12

12 4" dia. Sewerage (SS) 400 type

L.ft

82.00

13

13 Asbestoes flat sheet 1.2m x 1.2m

S.ft

18.00

14

14 Asbestoes ridges

Pairs

363.00

15

15 Asbestos corr. Sheet

S.ft

29.00

16

19 Coconut rafters(each 10' )

no

300.00

17

20 Barbed wire

L.ft

2.50

21 wooden block

no

5.00

18

22 Barrel bolt 4" Brass oxidised

no

79.00

19

23 Barrel bolt 6" Brass oxidised

no

120.00

20

24 Basket

no

52.50

21

25 Beading

L.ft

4.00

26 Beading 2"x1/2"

l.ft

4.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page 367

22

31 Binding wire 14 B.W.G.

lbs

40.00

23

32 Bitumen

Gal

347.00

24

35 Board 1" thick Valance (10")

S.ft

50.00

25

36 Brass Bib Tap 1/2"

No

145.00

26

41 Bricks

No

5.70

27

44 Castm. stays h. qual 10" brass oxidised

No

90.00

28

45 Castm.fast. Brass oxi. H. qlty ,mort.plate

No

90.00

29

46 Cement

CWT

520.00

30

47 Center pivot hinges br.oxi.h.qual. ( 4 pieces )

Set

45.00

31

50 Closet low level pedestal type (complete ceremic)No

4100.00

32

57 Rubber shuttering planks

33

sq.ft

20.00

60 Draw rings 1 1 /2 dia.

no

25.00

34

61 Earth ( Gravel Filling)

Cube

1850.00

35

63 Emulsion Paint ( Weather shield )

gal

1790.00

64 EMulsion Paint

Gal

1415.00

37

65 Enamel Paint

Gal

1785.00

38

66 Fanlight catch Brass oxi. Heavy qality

No

30.00

39

70 Calicut pattern flat tiles

No

18.00

40

73 G.I 20 B.W.G Sheets

S,ft

75.00

41

74 G.I. 22 B.W.G.Flat sheet

Sft

55.00

42

77 Ginisappu timber 3/4" thick

S.ft

50.00

43

81 Glass panes obscured(3mm)

S.ft

50.00

44

85 Glue

lbs

86.00

45

90 Gulley Box PVC 6"

no

290.00

46

91 Half round tiles

No

6.50

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page 368

47

94 Hinges 4"x3" Brass oxidised

Pair

136.00

48

95 Hinges 4"x4" Brass oxidised

Pair

205.00

97 Hire of mixtur, vibrator, wages of operator

Day

4500.00

49

98 Hold fast

no

17.50

50

117 Skelton bolt 10" brass

Doz

136.00

51

119 Iron T.hinges 10"

No

58.00

120 Brass T hinges 10"

Pair

0.00

123 Joists Class II 4" x 2"

L.ft

40.00

Bushel

257.00

126 Lime -Slaked 52

127 Limpet washers

No

53

135 Metal 1 1/2"

Cube

8020.00

54

136 Metal 1"

Cube

8470.00

55

137 Metal 2"

Cube

7850.00

56

138 Metal 3/4"

cube

8830.00

57

139 Metal 6" to 9"

cube

5715.00

58

140 Mild steel

cwt

4240.00

59

141 Mirror with fittings

no.

520.00

60

142 Mortice Lock Concord

No

525.00

61

143 Mortice Lock Vinion double

No

790.00

62

144 Lock Night Latch Bird

No

290.00

63

145 Mortice lock Union English single leaver

No

1575.00

64

146 Mortice lock Union English double leaver

no.

2795.00

65

147 Mould oil

gal

100.00

66

150 Nails 2" (GI)

Ibs

34.00

67

153 Nails 3/4" (GI)

lbs

34.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

1.00

Page 369

68

157 P.V.C. end cap (Gutter Cap)

no

44.80

69

158 P.V.C. gutter joint

no

51.50

70

159 P.V.C. metre joint

no

164.00

71

160 P.V.C. running head

no

107.00

72

161 P.V.C.gutter 6"

L.ft

38.50

73

162 P.V.C.Inspection joint 4" (110mm)

No

367.50

74

163 P.V.C.Inspection "Y" joint 4" (110mm)

no.

436.00

75

164 P.V.C.Bend (11Deg) - 4" (110mm)

no.

115.50

76

165 P.V.C.Bend (22Deg) - 4" (110mm)

no.

119.00

77

166 P.V.C.Bend (60Deg) - 4" (110mm)

no.

199.50

78

167 P.V.C.Bend (88 Deg) - 4" (110mm)

no.

325.50

79

168 P.V.C.Pipe 4" 600 type

L.ft.

48.50

80

169 P.V.C.Pipe 4" 400 type

L.ft.

107.00

81

171 Paint oil Enamel

gal

1785.00

82

181 Planks 1 1/4" special upper

Sft

135.00

83

182 Planks 1" Class II (Ginnisappu)

s.ft

50.00

84

183 Plastic cistern low level (Plastic )

no

1265.00

85

184 Plugs

no.

2.00

86

186 Plywood door 2"-3" x 6'-9"

no.

0.00

87

187 Plywood door 2'-3" x 6'-9" ( Mackply)

no

1848.00

88

188 Plywood door ord 2'-9" x 6'-9"

no

1765.00

89

189 Pressed Tiles 8" x 8"

no.

32.00

90

190 Primer

gal

1560.00

91

191 Pudlo cement

lbs

32.00

92

192 Red cement

kg

342.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page 370

93

193 Reepers (2":1") sp. (Micro)

L.ft

8.00

94

194 Ridge tile

no.

35.00

95

196 Rim lock 6" 2 leaves Brase

No

446.00

96

197 River Sand

Cube

2100.00

97

198 Drive screws and washers

no.

6.00

98

199 Rawl plugs & 2" Screws

No

15.00

99

200 Sand Fine (River sand)

cube

2100.00

100

205 Sash bars 1 1/2"x1 1/2"

L.ft.

19.00

206 Special labour

day

375.00

101

207 Screws 1 1/2"

doz.

0.00

102

211 Sink 24"x15"x8" with waste plug & chain

no

2100.00

103

214 Skilled labour Gr.Il

day

475.00

104

215 Skilled labour Gr.I

day

475.00

105

216 Boild Lime

Bushel

270.00

106

218 Soap tray

no

173.00

107

220 Spur stones

no.

22.50

108

222 Squating pan with trap

no

700.00

109

224 Staining Bolts

no.

112.00

110

225 Staples

Doz

20.00

111

227 Stop cock L.D model 1/2"

no

105.00

112

228 Stop cock L.D model 1 1/4"

no.

0.00

113

232 Tar

Gal

90.00

114

236 Tiles 6" x 6" white

no

0.00

115

245 Timber purlins

c.ft.

1250.00

246 Timber sp.class upper / Kempus

c.ft.

1250.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page 371

116

248 Tooth brush holder cromium plated

no

196.00

117

249 Tor steel

cwt

4330.00

118

250 Towel Trail holder chromium plated

no

275.00

119

255 transport 1 st Mile

120

257 Unskilled labour

day

325.00

121

260 Varnish

gal

1756.00

122

263 Wash basin 22"x16"

no.

1780.00

123

264 1/2" Nut & Washers

No

3.00

124

268 Wood plugs

no

0.00

125

269 Yellow ocare

lbs

0.00

126

270 Wire dome for 2" pipe

No

60.00

127

300 2"X2" Class II Battens

Lft

13.00

128

301 3/8" dia 18" Bolts,Nuts & Washers

No

13.00

129

302 Grey Cement

cwt

393.00

130

303 Rawl Plugs and Screws

No

0.00

304 Culicut Tiles

No

0.00

131

308 gate valve 2"

No

357.00

132

309 Stopcock LD Model 3/4" (Plastic)

No

134.40

133

310 Stopcock LD Model 1" (Plastic)

No

145.60

134

311 Stopcock LD Model 1 1/4" (Plastic)

No

280.00

135

312 Stopcock LD Model 1 1/2" (Plastic)

No

306.00

136

313 Stopcock LD Model 2" (Plastic)

No

372.00

137

314 Jet Shower 3" Chromium plated

No

500.00

138

317 pvc gutter brackets

No

9.20

139

318 Solvent cement 50g

Tin

43.00

1 mile

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

0.00

Page 372

140

344 Angle iron 2"x2"x1/4"

L.ft

85.00

141

345 Angle iron 1 1/2"x1 1/2"x1/4"

L.ft

56.50

142

346 Angle iron 2 1/2"x2 1/2"x1/4"

L.ft

102.50

143

347 Angle iron 3"x3"x1/4"

L.ft

125.00

144

348 Making holes on angle iron

No

20.00

145

349 H - iron 6"x3" (6mm)

L.ft

0.00

146

350 H - iron 8"x4" (6mm)

L.ft

0.00

147

351 1" x 1/4" Flat iron

L.ft

15.00

148

352 1/2"x1" Bolts & Nuts

No

6.00

149

353 Fillets (Class I local timber for beeding)

L.ft

0.00

150

354 Fillets 1/2" x 1/2"

L.ft

3.25

151

355 Ball valve 1/2"

No

94.50

152

356 Ball valve 3/4"

No

152.25

153

357 Cistern only ceremice

No

1800.00

154

358 Fittings ( For commode & cistern )

Item

367.50

155

359 Seat cover ( Double )

No

420.00

156

360 Brackets (For cistern )

Item

62.00

157

361 Flush bend

No

39.80

159

363 4" Sandcrete Block

No

0.00

160

364 110mm PVC "T" Junction

No

552.50

161

365 110mm PVC "Y" Joint

No

525.00

162

366 50mm Bottle trap

No

165.00

163

367 110mm PVC Inspection Bend

No

388.50

164

368 bends 3.5"

No

64.00

165

369 110mm PVC Elbow

No

301.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page 373

166

370 PVC down pipe 3 1/2"

Length

416.00

167

371 PVC socket 3 1/2"

No

47.25

168

372 PVC elbow 3 1/2"

No

64.00

169

373 PVC clips 3 1/2"

No

9.50

170

374 1 1/4" x 1/4" Flat iron

Lft

22.00

171

375 1/2" (12mm) Bolt & Nut

No

6.50

172

376 9" x 9" 3/8" M.S. plate

No

110.00

173

377 1/2' x 1 1/2" Rag bolt

No

6.00

174

378 2" x 1/4" Flat iron

L.ft

38.00

175

379 70S-1002-1

L.ft

64.60

176

380 70S-1102-1

L.ft

44.50

177

381 70S-1202-1

L.ft

46.40

382 70S-1402-1

L.ft

52.90

178

383 70S-1503-A

L.ft

78.10

179

384 70S-1704-A

L.ft

79.40

180

385 70S-3002-1

L.ft

85.00

181

386 70D-1910

L.ft

24.30

387 100D-1914

L.ft

24.30

182

388 100D-1917

L.ft

32.80

183

389 100D-3004-A

L.ft

124.50

184

390 100D-3203

L.ft

129.10

185

391 100D-3207

L.ft

169.00

186

392 100D-3502

L.ft

148.70

187

393 100D-3503-A

L.ft

160.90

188

394 CA-1001

L.ft

84.30

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page 374

189

395 CA-1002

L.ft

134.20

190

396 CA-2001-A

L.ft

88.90

191

397 PT-5153

L.ft

12.80

192

398 PT-5154

L.ft

30.50

193

399 PT-5157

L.ft

56.30

194

400 P-1113

L.ft

40.75

195

401 80S-1801

L.ft

57.85

196

402 BD-1066 ( Handle )

Pair

350.00

197

403 Lock ALPHA

No

750.00

198

404 Door Closer

No

1645.00

199

405 5mm thick tinted glass

S.ft

60.00

200

406 6mm thick Plywood sheet ( ordinary )

S.ft

20.85

201

407 Formica sheet

S.ft

18.00

202

408 Rubber Beading for Aluminium fittings

L.ft

3.00

203

409 Welded mesh

S.ft

10.00

204

410 Type 1

Sum

125.00

205

411 Type 2

Sum

250.00

206

412 Type 3

Sum

75.00

207

413 Type 4

Sum

50.00

208

414 Type 5

Sum

25.00

209

415 Allowance type 1

Sum

100.00

210

416 Allowance type 2

Sum

150.00

211

417 Allowance type 3

Sum

10.00

1mile

0.00

215 216

1002 transport every additional Miles 12b Anticorrosive paint

gal

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

1139.00

Page 375

217

147a Mouldings

L.ft

4.50

218

181a Planks 1" Sp. Upper Class Timber/Kempus

sft

125.00

219

182b Planks 3/4"

sq.ft.

105.00

220

193a Reepers Cl.II 2"x1"

L.ft

0.00

221

198a Ring 1 1/2" Brass

no

26.25

222

207a Screws 1" brass

Doz

45.00

223

207b Screws 2"

doz

69.00

224

232a Tiles 1'-0"x1'-0" floor

no

85.00

225

236a Tiles 6"x6" colour

no

15.00

226

236b Tiles 4"x4" white

no

0.00

227

236c Tiles 4"x4" colour

no

8.00

228

267a Wire nails 2"

lbs

36.50

229

268a Wood preservative

gal

315.00

230

357a Cistern plastic

No

1265.00

231

40a Brass screws 1 1/2"

Doz

52.50

232

40c Brass screws 3/4"

Doz

31.50

233

40d Brass Screws 1"

Doz

45.00

234

76a G.I.Hook 5/16"x4 1/4"

no

6.50

235

81a Glass Panes Tinted (5mm)

S.ft

80.00

236

91a Bras Sancy 1 1/4"

Doz

45.00

237

91b Cistern ceremic

no

0.00

238

91c Cistern plastic

no

1265.00

239

95a Hinges 4"x2 1/2" Brass oxidised

Pair

115.50

no

140.00

240 96a

16mm 9" Rag bolt

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

Code No

Description

Unit

Rate

1

1 1 1/2" dia. Pvc pipe 1000 type

L.ft

38.50

2

2 1 1/2" dia. Pvc pipe 600 type

L.ft

25.00

3

3 1 1/4" dia. Pvc pipe 1000 type

L.ft

26.00

4

4 1 1/4" dia. Pvc pipe 600 type

L.ft

18.50

Lft

20.00

170

374 1 1/4" x 1/4" Flat iron

5

5 1" dia. Pvc pipe 1000 type

L.ft

17.00

6

6 1" dia. Pvc pipe 600 type

L.ft

10.50

147

351 1" x 1/4" Flat iron

L.ft

13.75

173

377 1/2' x 1 1/2" Rag bolt

No

6.00

171

375 1/2" (12mm) Bolt & Nut

No

6.00

L.ft

6.30

7

7 1/2" dia. Pvc pipe 1000 type

123

264 1/2" Nut & Washers

No

3.00

148

352 1/2"x1" Bolts & Nuts

No

6.00

387 100D-1914

L.ft

24.30

182

388 100D-1917

L.ft

32.80

183

389 100D-3004-A

L.ft

124.50

184

390 100D-3203

L.ft

129.10

185

391 100D-3207

L.ft

169.00

186

392 100D-3502

L.ft

148.70

187

393 100D-3503-A

L.ft

160.90

160

364 110mm PVC "T" Junction

No

526.00

161

365 110mm PVC "Y" Joint

No

500.00

165

369 110mm PVC Elbow

No

287.00

163

367 110mm PVC Inspection Bend

No

370.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

8

8 2" dia. Pvc pipe 1000 type

L.ft

67.00

9

9 2" dia. Pvc pipe 600 type

L.ft

40.50

174

378 2" x 1/4" Flat iron

L.ft

35.00

127

300 2"X2" Class II Battens

Lft

12.00

L.ft

11.30

10

10 3/4" dia. Pvc pipe 1000 type

128

301 3/8" dia 18" Bolts,Nuts & Washers

No

12.00

11

11 4" dia. Sewerage (SS) 250 type

L.ft

48.50

12

12 4" dia. Sewerage (SS) 400 type

L.ft

75.00

159

363 4" Sandcrete Block

No

0.00

162

366 50mm Bottle trap

No

150.00

199

405 5mm thick tinted glass

S.ft

60.00

200

406 6mm thick Plywood sheet ( ordinary )

S.ft

20.85

181

386 70D-1910

L.ft

24.30

175

379 70S-1002-1

L.ft

64.60

176

380 70S-1102-1

L.ft

44.50

177

381 70S-1202-1

L.ft

46.40

382 70S-1402-1

L.ft

52.90

178

383 70S-1503-A

L.ft

78.10

179

384 70S-1704-A

L.ft

79.40

180

385 70S-3002-1

L.ft

85.00

195

401 80S-1801

L.ft

57.85

172

376 9" x 9" 3/8" M.S. plate

No

110.00

209

415 Allowance type 1

Sum

100.00

210

416 Allowance type 2

Sum

150.00

211

417 Allowance type 3

Sum

10.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

141

345 Angle iron 1 1/2"x1 1/2"x1/4"

L.ft

42.75

142

346 Angle iron 2 1/2"x2 1/2"x1/4"

L.ft

79.00

140

344 Angle iron 2"x2"x1/4"

L.ft

55.50

143

347 Angle iron 3"x3"x1/4"

L.ft

99.35

216

12b Anticorrosive paint

gal

1085.00

S.ft

13.30

Pairs

267.00

S.ft

21.35

13

13 Asbestoes flat sheet 1.2m x 1.2m

14

14 Asbestoes ridges

15

15 Asbestos corr. Sheet

151

355 Ball valve 1/2"

No

90.00

152

356 Ball valve 3/4"

No

145.00

17

20 Barbed wire

L.ft

1.45

18

22 Barrel bolt 4" Brass oxidised

no

75.00

19

23 Barrel bolt 6" Brass oxidised

no

115.00

20

24 Basket

no

50.00

Pair

350.00

25 Beading

L.ft

4.00

26 Beading 2"x1/2"

l.ft

4.00

No

61.00

196 21

164

402 BD-1066 ( Handle )

368 bends 3.5"

22

31 Binding wire 14 B.W.G.

lbs

36.00

23

32 Bitumen

Gal

330.00

24

35 Board 1" thick Valance (10")

S.ft

46.30

Bushel

257.00

105

216 Boild Lime

156

360 Brackets (For cistern )

Item

54.00

236

91a Bras Sancy 1 1/4"

Doz

43.00

No

130.00

25

36 Brass Bib Tap 1/2"

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

231

40a Brass screws 1 1/2"

Doz

50.00

233

40d Brass Screws 1"

Doz

39.00

232

40c Brass screws 3/4"

Doz

30.00

120 Brass T hinges 10"

Pair

0.00

No

2.60

26

41 Bricks

188

394 CA-1001

L.ft

84.30

189

395 CA-1002

L.ft

134.20

190

396 CA-2001-A

L.ft

88.90

39

70 Calicut pattern flat tiles

No

11.00

27

44 Castm. stays h. qual 10" brass oxidised

No

90.00

28

45 Castm.fast. Brass oxi. H. qlty ,mort.plate

No

90.00

29

46 Cement

CWT

345.00

30

47 Center pivot hinges br.oxi.h.qual. ( 4 pieces )

Set

45.00

237

91b Cistern ceremic

no

0.00

153

357 Cistern only ceremice

No

1400.00

230

357a Cistern plastic

No

1150.00

238

91c Cistern plastic

no

1150.00

31

50 Closet low level pedestal type (complete ceremic)No

3900.00

16

19 Coconut rafters(each 10' )

198 33 97 34

no

300.00

304 Culicut Tiles

No

0.00

404 Door Closer

No

1645.00

no

25.00

no.

6.00

60 Draw rings 1 1 /2 dia. 198 Drive screws and washers 61 Earth ( Gravel Filling) 64 EMulsion Paint

Cube

590.00

Gal

1345.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

35

63 Emulsion Paint ( Weather shield )

gal

1704.00

37

65 Enamel Paint

Gal

1698.00

38

66 Fanlight catch Brass oxi. Heavy qality

No

30.00

149

353 Fillets (Class I local timber for beeding)

L.ft

0.00

150

354 Fillets 1/2" x 1/2"

L.ft

3.00

154

358 Fittings ( For commode & cistern )

Item

350.00

157

361 Flush bend

No

35.50

201

407 Formica sheet

S.ft

18.00

40

73 G.I 20 B.W.G Sheets

S,ft

65.00

41

74 G.I. 22 B.W.G.Flat sheet

Sft

50.00

234

76a G.I.Hook 5/16"x4 1/4"

no

6.00

131

308 gate valve 2"

No

340.00

42

77 Ginisappu timber 3/4" thick

S.ft

0.00

43

81 Glass panes obscured(3mm)

S.ft

45.00

S.ft

60.00

lbs

86.00

cwt

375.00

235 44 129

81a Glass Panes Tinted (5mm) 85 Glue 302 Grey Cement

45

90 Gulley Box PVC 6"

no

550.00

145

349 H - iron 6"x3" (6mm)

L.ft

0.00

146

350 H - iron 8"x4" (6mm)

L.ft

0.00

No

5.00

Pair

110.00

46 239

91 Half round tiles 95a Hinges 4"x2 1/2" Brass oxidised

47

94 Hinges 4"x3" Brass oxidised

Pair

130.00

48

95 Hinges 4"x4" Brass oxidised

Pair

195.00

97 Hire of mixtur, vibrator, wages of operator

Day

2520.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

49 51

98 Hold fast

no

17.50

119 Iron T.hinges 10"

No

58.00

123 Joists Class II 4" x 2"

L.ft

30.00

Bushel

257.00

126 Lime -Slaked 52 197 62 144

127 Limpet washers

No

1.00

403 Lock ALPHA

No

750.00

144 Lock Night Latch Bird

No

275.00

348 Making holes on angle iron

No

5.00

53

135 Metal 1 1/2"

Cube

3500.00

54

136 Metal 1"

Cube

3750.00

55

137 Metal 2"

Cube

3350.00

56

138 Metal 3/4"

cube

4100.00

57

139 Metal 6" to 9"

cube

2000.00

58

140 Mild steel

cwt

1986.50

59

141 Mirror with fittings

no.

390.00

60

142 Mortice Lock Concord

No

425.00

64

146 Mortice lock Union English double leaver

no.

2660.00

63

145 Mortice lock Union English single leaver

No

1500.00

61

143 Mortice Lock Vinion double

No

750.00

65

147 Mould oil

gal

100.00

217

147a Mouldings

L.ft

4.00

66

150 Nails 2" (GI)

Ibs

30.00

67

153 Nails 3/4" (GI)

lbs

30.00

68

157 P.V.C. end cap (Gutter Cap)

no

38.00

69

158 P.V.C. gutter joint

no

44.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

70

159 P.V.C. metre joint

no

142.00

71

160 P.V.C. running head

no

102.00

75

164 P.V.C.Bend (11Deg) - 4" (110mm)

no.

110.00

76

165 P.V.C.Bend (22Deg) - 4" (110mm)

no.

113.00

77

166 P.V.C.Bend (60Deg) - 4" (110mm)

no.

190.00

78

167 P.V.C.Bend (88 Deg) - 4" (110mm)

no.

310.00

72

161 P.V.C.gutter 6"

L.ft

37.00

74

163 P.V.C.Inspection "Y" joint 4" (110mm)

no.

415.00

73

162 P.V.C.Inspection joint 4" (110mm)

No

350.00

80

169 P.V.C.Pipe 4" 400 type

L.ft.

60.00

79

168 P.V.C.Pipe 4" 600 type

L.ft.

48.50

400 P-1113

L.ft

40.75

81

171 Paint oil Enamel

gal

1698.00

82

181 Planks 1 1/4" special upper

Sft

114.50

83

182 Planks 1" Class II (Ginnisappu)

s.ft

41.70

sft

94.00

sq.ft.

69.00

194

218

181a Planks 1" Special Upper Class Timber

219

182b Planks 3/4"

84

183 Plastic cistern low level (Plastic )

no

1150.00

85

184 Plugs

no.

2.00

87

187 Plywood door 2'-3" x 6'-9" ( Marine)

no

1490.00

86

186 Plywood door 2"-3" x 6'-9"

no.

0.00

88

188 Plywood door ord 2'-9" x 6'-9"

no

1467.00

89

189 Pressed Tiles 8" x 8"

no.

29.00

90

190 Primer

gal

1485.00

397 PT-5153

L.ft

12.80

191

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

192

398 PT-5154

L.ft

30.50

193

399 PT-5157

L.ft

56.30

191 Pudlo cement

lbs

30.00

169

373 PVC clips 3 1/2"

No

9.00

166

370 PVC down pipe 3 1/2"

168

91

Length

317.00

372 PVC elbow 3 1/2"

No

61.00

138

317 pvc gutter brackets

No

9.20

167

371 PVC socket 3 1/2"

No

45.00

98

199 Rawl plugs & 2" Screws

No

15.00

130

303 Rawl Plugs and Screws

No

0.00

92

192 Red cement

kg

325.00

93

193 Reepers (2":1") sp.upper

L.ft

8.00

L.ft

0.00

220

193a Reepers Cl.II 2"x1"

94

194 Ridge tile

no.

23.00

95

196 Rim lock 6" 2 leaves Brase

No

425.00

no

25.00

221 96 202

198a Ring 1 1/2" Brass 197 River Sand

1700.00

L.ft

3.00

sq.ft

16.70

200 Sand Fine

cube

1500.00

100

205 Sash bars 1 1/2"x1 1/2"

L.ft.

14.30

101

207 Screws 1 1/2"

doz.

0.00

222

207a Screws 1" brass

Doz

43.00

223

207b Screws 2"

doz

66.00

No

350.00

32 99

155

408 Rubber Beading for Aluminium fittings

Cube

57 Rubber shuttering planks

359 Seat cover ( Double )

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

137

314 Shower Rose 6"

No

95.00

102

211 Sink 24"x15"x8" with waste plug & chain

no

1810.00

117 Skelton bolt 10" brass

Doz

130.00

104

215 Skilled labour Gr.I

day

500.00

103

214 Skilled labour Gr.Il

day

450.00

106

218 Soap tray

no

164.00

139

318 Solvent cement 50g

Tin

43.00

206 Special labour

day

500.00

107

220 Spur stones

no.

10.00

108

222 Squating pan with trap

no

700.00

109

224 Staining Bolts

no.

40.00

110

225 Staples

Doz

20.00

112

228 Stop cock L.D model 1 1/4"

no.

0.00

111

227 Stop cock L.D model 1/2"

no

77.00

135

312 Stopcock LD Model 1 1/2" (Plastic)

No

291.50

134

311 Stopcock LD Model 1 1/4" (Plastic)

No

213.33

133

310 Stopcock LD Model 1" (Plastic)

No

143.00

136

313 Stopcock LD Model 2" (Plastic)

No

354.20

132

309 Stopcock LD Model 3/4" (Plastic)

No

104.50

113

232 Tar

Gal

0.00

50

224

232a Tiles 1'-0"x1'-0" floor

no

65.00

227

236c Tiles 4"x4" colour

no

5.75

226

236b Tiles 4"x4" white

no

0.00

114

236 Tiles 6" x 6" white

no

0.00

225

236a Tiles 6"x6" colour

no

13.40

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

Page (Page)

115

245 Timber purlins

c.ft.

620.00

246 Timber sp.class upper

c.ft.

920.00

116

248 Tooth brush holder cromium plated

no

100.00

117

249 Tor steel

cwt

2084.00

118

250 Towel Trail holder chromium plated

no

275.00

119

255 transport 1 st Mile

215

1002 transport every additional Miles

1 mile

0.00

1mile

0.00

204

410 Type 1

Sum

125.00

205

411 Type 2

Sum

250.00

206

412 Type 3

Sum

75.00

207

413 Type 4

Sum

50.00

208

414 Type 5

Sum

25.00

120

257 Unskilled labour

day

300.00

121

260 Varnish

gal

1673.00

122

263 Wash basin 22"x16"

no.

1473.00

203

409 Welded mesh

S.ft

10.00

126

270 Wire dome for 2" pipe

No

60.00

228

267a Wire nails 2"

lbs

30.00

124

268 Wood plugs

no

0.00

gal

300.00

no

5.00

lbs

0.00

229

268a Wood preservative 21 wooden block

125

269 Yellow ocare

240

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE

SUMMARY.

NO 1/1

DESCRIPTION OF WORK Brick work in Cement, demolished brick stacked and debris cleared.

2/1

5/2

6/2

7/2

8/2

9/3

11/3

Brick work in lime, demolished brick stacked

m3

Cube m3

Ceiling, existing removed materials stacked

Sqr

and debris cleared.

m2

Cement concrete demolished, and debris

Sqr

cleared away.

m2

Cement concrete, reinforced demolished in suspended floors reinforcement removed and

Sqr

debris cleared.

m2

Corrugated Sheets, Iron, Asbestoes or Aluminium Alloy removed from roof or walls

Sqr

and stacked.

m2

Corrugated sheets iron or asbestos or aluminium alloy

Sqr

removed from roofs or walls of 2 storeyed buildings

m2

Door or Window, size up to 40 S.ft removed No

Doors for window, size over 40 S.ft removed - do -

13/4

Cube

and debris cleared.

from existing walls and door or stacked.

12/3

UNIT

- do -

No

Door or window, sash only, up to 40 S.ft removed from existing walls and stacked.

No

14/4

Door or window, sash only, over 40 S.ft - do -

15/4

16/4

- do -

No

Down pipes, 4" to 6" dia G.I old or decayed,

L.ft

removed from existing building and stacked.

L.m

Drains demolished and debris cleared

L.ft

NO 18/5

19/5

20/6

DESCRIPTION OF WORK

UNIT

Fence uprooted, barbed wire rolled up and all materials stacked (length of fencing to

L.ft

measured).

L.m

Floors brick paved, demolished and debris

Sqr

cleared away.

m2

Gate sash removed and stacked after demolishing cement concrete blocks or removing posts and separating pintols (demolishing brick work where necessary paid for separately).

21/6

22/6

23/6

25/7

26/7

Glass panes in doors, windows and fanlights

No

Sq.ft

removed and stacked.

m2

Gutter, Eaves, removed and stacked from roofs of

L.ft

single story buildings.

L.m

Gutter, Eaves removed from roofs of two storeyed

L.ft

buildings and stracked.

L.m

Partitions removed and stacked at side, including

Sq.ft

making goodnes two walls and floors.

m2

Lime plastering shipped and debris cleared away.

Sqr

27/4

28/8

29/8

30/8

32/9

Rendering cement, chipped and debris cleared away

Sqr

from brick walls and floors.

m2

Rendering cement, chipped and debris cleared away

Sqr

from cement concrete floors and walls.

m2

Roofing removing tiles and timber stacking, serviceable materials and cleaning debris in single storey

Sqr

building.

m2

Roof, removing tiles and timber stacking serviceable

Sqr

material and cleaning debris in two storeyed building.

m2

Rubble masonry in cement, demolished rubble stacked and debris cleared away.

33/9

m3

Rubble masonry in lime demolished rubble stacked and debris cleared away

NO

Cube

Cube m3

DESCRIPTION OF WORK

UNIT

34/9

Tiles glazed demolished and debris cleared away.

Sqr

35/10

Tiles calicut or half round, removed from roof of

Sqr

single storey buildings and stacked.

m2

Tiles calicut of half round removed from

Sqr

roof of 2 storeyed buildings and stacked.

m2

36/10

28

Tiles calicut of half round removed from roof of two storeyed buildings and stacked.

39/11

Sqr

Ceiling asbestoes removing including timber frame work, stacking serviceable materials single storey

Sqr

building (and debris cleared away in single).

m2

40/11

Ceiling asbestos removing including timber frame

Sqr

work,

m2

- do -

- do -

in two

storeyed building. 41/11

42/11

Valance/ Barge boarding removed materials stacked

L.ft

and debris cleared away in single storey building.

L.m

Valance/ Barge boarding removed

L.ft

- do -

- do - in 2 storeyed building.

43/12

L.m

Cement plastering, soffit chipped and debris cleared away.

NO 1/15

m2

DESCRIPTION OF WORK Cement concrete 1:3:6 with 2" metel, above one cube (shuttering paid for seperately).

Sq.ft

UNIT Cube m3

2/15

Cement concrete 1:3:6 (2") upto one cube shuttering paid for seperately.

3/15

Cement concrete 1:2 1/2:5 (1") above one cube (shuttering paid for seperately).

2a/16

Cement concrete 1:3:6 (1 1/2") above 1 cube (shuttering paid for seperately).

2c/16

Cement concrete 1:3:6 (1") above 1 cube (shuttering paid for seperately).

4/16

Cement concrete 1:2 1/2:5 (1") upto one cube (shuttering paid for seperately).

5/16

Cement concrete 1:2:4 (3/4") above one cube (shuttering paid for seperately).

6/16

Cement concrete 1:2:4 (3/4") upto one cube (shuttering paid for seperately).

11/18

Cube m3

Cube m3

Cube m3

Cube m3

Cube m3

Cube m3

Cube m3

Drains, semi circular, in cement concrete 1:3:6 (1") 9" wide and 9" average depth, with 3" thick sides and base

12/19

13/19

14/20

19/22

inclusive of 1/2" cement rendering 1:3 and expansion

L.ft

joints as necessary excavation (without ramp).

L.m

Lintol cement concrete 1:2:4 (3/4") 4 1/2"x6"

L.ft

(Reinforcement paid seperately).

L.m

Lintol cement concrete 1:2:4 (3/4") 9"x6" (Reinforcement

L.ft

paid seperately).

L.m

Lintol cement concrete 1:2:4 (3/4") 9"x9" )Reinforcement

L.ft

paid seperately).

L.m

Padstones, cement concrete 1:2:4 (3/4") precast

or in situ.Size 1-6x1-1 1/2x0-6

19a/22

Padstones, cement concrete 1:2:4 (3/4") precast or in situ.Size 1-6x0-6x0-6

21/23

21a/23

25a/25

No

No

Slabs over drain, cement concrete 3" thick 1:2:4(3/4") reinforced with expended metal and 1/2" cement rendered

S.ft

1:2 (R/F paid for seperately).

m2

Slabs over drain, cement concrete 3" thick 1:2:4(3/4") reinforced with expended metal and 1/2" cement rendered

S.ft

1:2 (R/F paid for seperately).

m2

Cement concrete 1:1 1/2:3 (3/4").

Cube m3

23/24

Supr stone, cement concrete 1:2:4 (3/4") for door posts supplied and fixed.

25/25

Cement concrete 1:2 1/2":5(1") using mixer and vibrator (shuttering paid for seperately).

26/25

Cube m3

Cement concrete 1:2:4(3/4") in column shafts (Reinforcement shuttering and finishes paid for seperately) in guard floor using mixer and vibrator.

27/25

No

Cement concrete as per Item 61 in 1st floor.

Cube m3

Cube m3

28/25

Cement concrete as per Item 61 in 2nd floor.

Cube m3

29/26

Cement concrete 1:2:4 (3/4") in beams in ground floor (reinforcements shuttering and finishes paid for seperately) using mixer and vibrator.

Cube m3

30/26

Cement concrete as per Item 29 in 1st floor.

Cube m3

31/26

Cement concrete as per Item 29 in 2nd floor.

Cube m3

32/26

Shuttering for floor slab concrete and dismantling.

Sqr m2

33/27

33a/27

Shuttering for column shaft and diamantling (for column

Sq.ft

9"x9"x4" 4 ft heigh I.e 4 1/2" ft box).

m2

Shuttering for footing and walls etc.

Sq.ft m2

34/27

Shuttering for beam including dismantling (12"x18" beam 20 ft long).

35/28

m2

Cement concrete 1:2"4(3/4") lintol in ground floor Reinforcement and shuttering paid for seperately using mixer and vobrator.

36/28

Sq.ft

Cube m3

Cement concrete lintols as per Item (71) in 1st floor.

Cube m3

37/28

38/29

4" thick R..C.C 1:2:4 (3/4") in first floor slab (reinforcement

Sqr

and shuttering paid seperately) using mixer and vibrator.

m2

5" thick R.C.C in 1st floor

Sqr

- do -

39/29

- do - do -

Drains semi circular in cement concrete 1:3:6 (1") wide and 9" average depth, 3" thick sides and base, inclusive of

m2

40/29

1/2" cement rendering 1:3 with necessary expension, joints

L.ft

and excavation, but without ramp

L.m

Drains in cement concrete 1:3:6(1") as above

L.ft

But with ramp 2' 6" wide

L.m

BLOCK MASONRY 1

2

Cement sand block in 1:6 mix in cement sand 1:5 mix

m3

4" thick cement sand block 1:6 mix masonry

Sqr

in cement sand 1:5 mix

m2

NO 2/30

DESCRIPTION OF WORK Brick work in cement mortar (1:5) above 1 cube (up to 1st floor level).

3/30

- do -

UNIT Cube m3

up to one cube

- do -

- do -

4/31

Cube

Brick work in cement mortar 1:5 in piers (in ground floor).

Cube m3

Cube m3

6/31

Brick work 4 1/2" thick in cement mortar 1:5 above 1 square.

Sqr m2

7/32

- do -

up to one Sqrs.

Sqr m2

12/33

14/34

19/35

20/35

24/37

Extra over Item 2-5 and 9-11 for brick

Cube

work from 1st floor level up 2nd floor.

m3

Extra over Items 6-8 for brickwork from

Sqrs

1st floor level to 2nd floor.

m2

Coping, brick in cement 1:5 weathered and throated on

L.ft

4 1/2" walls, cement renedered 1/2", 1:3 complete.

L.m

Coping, brick in cement 1:5 weathered throated on 9" walls

L.ft

and 1/2" cement rendered 1:3 complete.

L.m

Doors or window inserted in existing walls including making, No

25/37

Drains brick in cement 1:5,9" average depth 12" wide and cement rendered 1/2" thick 1:3 complete with expansion joints

26/38

as necessary, including necessary excavation (apron paid

L.ft

for seperately).

L.m

Drains brick in cement 1:5,6" average depth 9" wide and cement rendered 1/2" thick 1:3 complete with expansion joints

28/38

30/39

as necessary, including necessary excavation (apron paid

L.ft

for seperately).

L.m

Steps 12" wide and 6" to 9" high masonary or brick work in cement mortar 1:5 rendered 1/2" cement 1:2 with foundation

L.ft

6" below ground.

L.m

Brick work in cement and sand 1:8 in foundation and upto

Cube

D.P.C.

31/40

m3

Brick work in cement and sand 1:8 in super structure in ground floor.

32/40

- do -

Cube m3

in 1st floor.

Cube m3

33/40

- do -

in 2nd floor.

Cube m3 MASON.

NO 1/41

DESCRIPTION OF WORK Random Rubble Masonary in cement mortar 1:5 above 1 cube.

2/41

UNIT Cube m3

- do -

up to one cube.

Cube m3

NO 1/43

2/43

5/44

12/46

DESCRIPTION OF WORK

UNIT

Exapansion joints in brick floors, filled with bitumen

L.ft

and sand.

L.m

Exapansion joints in concrete floors filled with bitumen and

L.ft

sand(to full depth of concrete and rendering).

L.m

Floors, cement concrete 1:2 1/2:5(1") 3" cement rendered 1/2",

Sqr

1:2, with expansion joints filled with cement and sand.

m2

Tiles glazed colour 6"x6" with all specials, supplied and

S.ft

fixed to walls including raking plaster and bedding in

m2

cement mortar 1:2.

12/46

Tiles glazed(colour)6"x6", with all

S.ft

specials, supplied and fixed to walls

m2

including raking plaster and bedding in cement mortar 1:2.

12d/46

Tiles 8"x8", pressed of approved pattern and

S.ft

colour, supplied and fixed.

m2

NO 4/139

DESCRIPTION OF WORK Cracks in wall, plastered in cement 1:3 after chipping 2" to 4" wide

9/141

UNIT L.ft m

Flashing or plaster bands laid over tiles

L.ft

4" to 6" wide on roof in cement and lime

L.m

mortar 1:1:4

14/142

15/142

Rendering cement 1/2", 1:2 above 1

Sqr

Square.

m2

Rendering cement 1/2", 1:2 upto 1 square

Sqr m2

16/143

Rendering cement 1/2", 1:3 above 1 Square.

Sqr m2

17/143

Rendering cement 1/2", 1:3 upto 1 Square

Sqr m2

18/143

19/143

Rendering, cement 3/4", 1:2 above 1

Sqr

Square.

m2

Rendering, cement 3/4", 1:2 upto 1 square

Sqr m2

20/144

21/144

Rendering, cement 3/4", 1:3 above 1

Sqr

Square.

m2

Rendering, cement 3/4", 1:3 upto 1 square

Sqr m2

22/144

25/145

26/145

Rendering, cement, floating coat using Red cement finished smooth with Carborandum

Sqr

stone

m2

Rendering cement 3/4", 1:2 with Pudlo 5lbs

Sqrs

to 100 lbs cement

m2

Skirting in cement mortar 1:3, 1/2"x4"

L.ft

projected or flush with wall, and

L.m

including forming groove.

27/145

Skirting in cement mortar 1:3, 1/2"x6" projected or flush with all finished with

28/146

Red cement floating, including forming

L.ft

groove.

L.m

3/8" thick plastering to RCC beams, slab

Sqrs

soffit in cement sand 1:3 .with lime putty

m2

29/146

29a/146

D.P.C. 3/4" thick in cement, sand 1:2 finished smooth with 2 coats of hot tar.

m2

3/8" thick cement and sand plastering to

Sqrs

column and beam

29b/146

Sqrs

1/2" thick cement plastering 1:4 mix

m2

Sqrs m2

29c/146

5/8" thick cement plastering 1:4 mix

Sqrs m2

29d/146

29e/146

Cracks in wall Plastered in cement 1:3

L.ft

after chipping 2" to 4" wide

L.m

Plinth plastering 1/2" thick 1:3 cement and

Sqrs

sand with red cement floating

m2

NO 5/49

DESCRIPTION OF WORK

UNIT

Corrugated asbestos sheet roofing on special upper cl. Timber/kempas purlines supplied and fixed complete including treating timber with wood preservative two coats (ridging measured seperately).

7/50

Sqrs m2

Corrugated asbestos sheet fixed to roof or wall on existing frame work with necessary coach screws and limpet washers, or hook bolts.& with 2 coats wood

Sqrs m2

Preservative to existing frame work

18/53

19/53

21/54

26/55

Ridging, calicut pattern bedded in Cement and lime mortar 1:1:4, Coloured

L.ft

to match tiles.

L.m

Ridging, Calicut Pattern bedded in cement and lime mortar 1:1:4 coloured

L.ft

to match tiles (tiles available at site)

L.m

Ridging with asbestos cement close fitting ridges fixed complete with

L.ft

roofing screws or hook bolts.

L.m

Tiles, calicut pattern, flat supplied and laid up to 5 tiles in single storey building

27/56

No

Tiles, calicut pattern flat supplied and laid (above 5 and up to 25) in single storey Building.

No

30/56

31/56

43/53

44/59

Tiles calicut pattern supplied and laid

Sqr

in any Building.

m2

Tiles, calicut pattern, laid in any

Sqr

Buildings(tiles available at site).

m2

Shifting and re-laying calicut pattern

Sqr

tiles.

m2

Supplying and laying half round tiles

Sqr

on the existing asbestos roof.

m2

NO 8/63

DESCRIPTION OF WORK

UNIT

Boards, Barge, Valance, Fascia, 3/4" to 1" thick in class.II Local timber fixed complete with necessary Brass screws new or

12/64

3/61A

14/65

renewed above 1 C.ft.( 9" width) with 1 coat

L.ft

primer & 2 coat of enamel painting

L.m

Boardes, Barge, Valance, Facia, available fixed including cutting and

s.ft

minor repairs.with 2 coats enamel painting

m2

Beadings, Class I local timber 1 1/2" to 2"x1/2" plain chamfered, fixed with brass

L.ft

screws

L.m

Ceiling asbestos, flat fixed with clout headed nails to 4"x2" joists at 4'crs & 2"x 2" bearers at 2' crs of spl.upper class. Timber/ kempas including 1 1/2" x 1/2" cover fillets and 2 1/2" x 1/2" coves of Halmills timber. Rate to include 2 coats tarnap to joists and bearers primer and '2 coats of enamel

painting to beadings 'and mouldingd 2 coats of white washing to ceiling. Making holes in wall and fixing joists and bearers 'Per 1.95 Sqrs (15'-0"x13'-0").

Sqr m2

14a/65

Ceiling asbestos, flat in eves fixed with clout headed nails to 2" x 2"& 2"x1" spacer bearers not exceading 2'-0 centrs both ways bearers of spl.upper class/ kempus timber including Aluminium beading 1" wide with Rubber fillets fixed not exceedaing 2'-0" crs bothways Rate to include 2 coats tarnap to

Sqr

timber and 2 coats emulsion

m2

paint to abestos sheet

NO 14b/65

DESCRIPTION OF WORK

UNIT

Ceiling asbestos, flat fixed with clout headed nails to 4"x2" joists 4'-0 crs & 2"x2" bearers of spl.upper class/kempus timber 2'-0" crs and 2"x1" spacer bearers not exceding 2'-0crs including Aluminium beading 1" wide with rubber fillets not exceeding 2'-0 crs fixed bothways

Sqr

Rate to include 2 coats tarnap to timber

m2

and 2 coats emulsion paint to abestos sheet

14c/65

As per Item No.14 with only 2"x2"beares

Sqr

in eaves ceiling.

m2

-do-

-do-

14d/65

14e/65

26/68A

28/69

White washing to ceiling 2 coats and 2 coats of oil paint to beading and

Sqr

moulding.

m2

Ceiling, upper side cleaned and debris

Sqr

cleared away.

m2

Cove mouldings Cl.I 2 1/2"x1 1/2" fixed with brass screws and plugs new or

L.ft

renewed.

L.m

Doors or Windows, ledged, braced and battened with grooved and tongured joint,3 3/4" x 2 3/4" frames in spl upper class / kempas and 3/4" to

30/70

32/70

7/8" thick sashes in class1 timber

S.ft

with brass fittings.

m2

- do -

- do -

Sash only, in class 1 timber

S.ft

fixed with brass furniture.

m2

Doors or Windows, framed and battened, sash 1" to 1 1/8" thick in Special

32a/70

upper Class timber/kempas fixed complete

S.ft

with brass furniture.

m2

Battened sash only 1" to 11/8" thick in sp.

S.ft

upper class timber/kempas fixed completed with

m2

brass fittings

NO 42/74

DESCRIPTION OF WORK

UNIT

Doors or Windows, glazed and/or pannelled with 3 3/4"x2 3/4" frames and 1 1/8" to 1 1/4" sashes in special upper

S.ft

Class I timber/kempas fixed.

44/75

m2

Doors or Windows, glazed or pannelled sash only 1 1/8" to 1 1/4" thick

44a/75

in Special upper class timber/kempas with brass

S.ft

furniture.

m2

Doors pannelled and terllised/B.R.C. weld mesh No. 32 with 3 3/4"x2 3/4" frames and 1 1/8" thick sashes in special

52/78

53/78

upper class timber/kempas, fixed complete with

S.ft

brass furniture.

m2

Doors pannelled with 3 3/4"x2 3/4" frames and 1 - 1 1/8"sashes in Special upper

S.ft

Class timber /kempasfixed.with brass fittings

m2

Door or Window, removing easing and

Per

re-fixing.

sash

54/78

Door or Window, easing only.

55/79

Door or Window frames renewed in

Per sash

short lengths with special upper Class

L.ft

timber/kempas.

L.m

Assume 3'-0" Length of frame renewed

100/92

Reepers 2"x1" in Class I timber supplied

L.ft

and fixed new or renewed with iron

L.m

nails, up to 100 L.ft (shiffting of tiles paid for seperately). re-fixed in new position.

101/92

- do over 100 L.ft.

- do -

L.ft L.m

Per 100 L.ft

107/94

107a/94

Roof with calicut pattern tiles on spl upper class/Kempus frame work complete with ridges,

Sqr

hips etc.

m2

gable end roof - do -

117/97

121/98

135/101

- do -

Sqr

- do -.

m2

Timber available, sorted out, cut to required sizes and fixed in roof and

C.ft

other carpentry work.

m3

Timber special upper Class/kempas fixed or renewed in roof and other carpentry

C.ft

work.

m3

Trellis partition with 1/2"x1/2" laths fixed 2" apart diagonally or horizontally and

S.ft

vertically on 4"x2" Milla timber framing.

m2

Door frame 4"x3" in spl upper class timber/kempas

S.ft

supplied and fixed in position

m2

118/97

Timber fixed or renewed in post and frames

C.ft

140/103

Door 1 1/4" thick plywood ordinary sash

138/102

single (ordinary finish) hung on 4"x3"

140a/103

frame in Special upper class timber/kempas and

S.ft

complete with brass furniture with mortice lock

m2

As per Item No 140 -do- -do- but with marine type

S.ft

2'3"x6'9".

m2

142/104

Supplying and fixing Plywood door 1 1/4" thick

S.ft

single (Ordinary finish) to the existing frame

m2

with brass fittings with mortice lock

143/104

-do-

-do-

plywood Marine type 1 1/4" thick

single hung to existing frame with fitting

NO 13/165

DESCRIPTION OF WORK

ground.

24/168

Per

- do -

Per

- do -.

Letter

Lettering 4" to 5" - do -

23/168

UNIT

Letter

Lettering 2" to 3" - do -

15/166

m2

Lettering 1" to 1 1/2" painted in sinhalese English or Tamil, including painting

14/165

S.ft

- do - do -.

Per Letter

Painting, enamel paint including washing cleaning and smoothing down with sand

Sqr

paper, 1 coat.

m2

Painting enamel paint

- do -

Sqr

- do -

25/168

25a/168

27/169

2 coats.

m2

Painting New wood 1 Coat primer & 2 Coats

Sqr

Enamel paint

m2

Painting new wood work and 2 coats of

Sqr

enamel paint.

m2

Painting Steel work, 1 coat, with

Sqr

Anticrosive paint including removing

m2

scale and wire brushing.

28/169

30/169

30a/169

31/170

31a/170

32/170

32a/170

Painting Steel work, 2 coats, with Red oxide including removing scale and

Sqr

wire brushing.

m2

Painting walls with emulsion paint 1 coat

Sqr

(new coat).

m2

Painting walls with weather shield 1 coat

Sqr

( New work )

m2

Painting walls with Emulsion paint, 2

Sqr

coats (new work).

m2

Painting walls with 2 coats of weather shield paint

Sqr

( New work )

m2

Painting walls with Emulsion paint, 1 coat including preparing surface of old

Sqr

work.

m2

Painting walls with weather shield paint

Sqr

1 coat ( Old work )

m2

33/170

- do 2 coats

33a/170

40/172

41/172

44/173

45/173

49/174

50/174

- do - do -

- do -.

Sqr m2

Painting walls with weather shield paint

Sqr

2 coat ( Old work )

m2

Tarnap or other wood preservative,

Sqr

applied to wood work 1 coat (old work).

m2

Tarnap or other wood preservative,

Sqr

applied to wood work 2 coats (new work).

m2

Varnishing with best copal varnish after

Sqr

washing down and sand papering 1 coat.

m2

- do -

- do -

Sqr

- do -

2 coats.

m2

White or colourwashing walls of single storey buildings 1 coat, including

Sqr

patching and preparing surface.

m2

- do 2 coats

- do -

Sqr

- do -.

m2

Item 4/127

Description

Unit

Bolts barrel 4", brass oxidised heavy quality supplied and fixed with brass screws.

6/128

No

- do -

6"

- do -

18/130

- do - do -

Casement fastner with mortice plate, brass oxidised heavy quality supplied and fixed with brass screws.

19/130

No

Fanlight Catches brass oxidised heavy quality with brass screws fixed complete.

27/132

- do -

4"x4"

- do -

29a/132

- do - do -

31/133

No

But hinges 4"x3" brass oxidised heavy quality supplied and fixed with brass screws complete.

29/132

No

Casement stays 10", brass oxidised heavy quality supplied and fixed.

21/131

No

No

- do - do -

4"x2 1/2"

No

- do - do -

No

Hinges centre pivot (consisting of 2 pieces) brass oxidised heavy quality supplied and fixed with brass screws complete.

31a/133

Set

Rings, brass 1 3/4" to 1 1/2" supplied and fixed to doors and windows with brass screws.

No

51/137

Lock Mortice Vinion /concord single supplied and fixed.

52/137

Lock Mortice Vinion/concord double, supplied and fixed.

53/137

No

Mortice Lock Union ( English) double supplied and fixed.

53a/137

No

Mortice Lock Union ( English) single supplied and fixed.

54/137

No

No

Lock Night Latch supplied and fixed with duplicate keys approved quality

No

63/123

Tor steel rods in reinforcing.

Kg

64/123

Tor steel rods reinforcement in foundation

Kg

63a/123

Mild Steel rods in reinforcing lintols or beams.

Kg

64a/123

Mild Steel rods in Foundation .

Kg

Item 49/119

Description Hinges T, 10" Iron, heavy quality supplied and fixed with iron screws complete.

60/121

Pair

Locks, rim 6" iron, superior quality, heavy type, s/f. with iron screws complete.

67/123

Unit

No

M.S.Bars 5/8" dia supplied & fixed in window frame at 4" cetres & painted

L.ft

with one coat red lead & 2 coats aluminium

L.m

67e/123

1/2" dia

- do -

- do -

L.ft L.m

RATE ANALYSIS SECOND HALF OF 2003 IN TRINCOMALEE TINKER. Item

Description

Unit

9/150

Flashing G.I.22 B.W.G. 1'6" wide, fixed with 6" turned up along, and top edge

29/156

tucked well into wall in cement and

L.ft

lime mortar.

L,m

Gutters, Valley 20 B.W.G 36" wide, renewed on existing board, sheets

34/158

NO

tarred, joints soldered and cement,

L.ft

lime filletting complete.

L,m

-Do-

renewed including 1" thick timber

boarding sheet tarred, joints soldered and

L.ft

cement lime filletting complete.

L,m

DESCRIPTION OF WORK

UNIT

1

Drains, earth, in any soil except rock requiring blasting cut to gradient and shaped as directed soil deposited

cube m3

within site.

2/13

Excavation in any soil except rock requiring blasting part returnfill in and ram, and

cube m3

surplus disposed of within site as directed.

4/14

Filling under floor with gravel or other approved quality of filling, spread,

cube m3

watered and well rammed in 3" layers with available earth.

6/14

Filling under floor with gravel or other

cube

approved quality of filling spread water

m3

and rammed in 3" layers (material not available at site).

7/15

External Filling.(Material not available at site)

cube m3

8/15

External Filling.(Material available at site)

cube m3

Item

Description

Unit

1/179

Ball valve 1/2" supplied and fixed

No

2/179

Ball valve 3/4" supplied and fixed

No

13/181

Wash' Basin, Lavatory, 22"x16" with one tap, water plug, new brackets, supplied & fixed complete. (Additional tap, trap, and outlet pipe paid for seperately).

17/182

Basin, sink or urinal including all fittings removed and walls made good

31/185

No

No

Closet, pedestal type available at site, fixed with cement concrete after breaking concrete floor and making good and connections to soil and flush pipes

32/186

No

Closet, pedestal type, disconnecting and plugging sewer connection and making good all affected walls and floors

34/186

Closet, pedestal type, with low level glazed earthenware flushing cistern flush pipe, double plastic sheet cover, 1/2" stop cork, trap etc. supplied &

No

fixed completed.

35/186

Closet squatting type, with trap supplied & fixed.

36/187

No

No

Closet, squatting type, removed, sewer connections plugged and floor made good.

40/188

Cocks, brass bib 1/2" supplied & fixed (Heavy quality).

66/193

No

Flushing cistern, low level, plastic supplied and fixed complete.

86/197

No

Flushing Cistern fixed complete low level (Ceremics).meterial available

66a/193

No

No

Mirror, bath room type, supplied & fixed to wall with Rawl plugs and plastic frames.

No

147/214

Shower rose, 6" pvc supplied & fixed.

No

153/215

Sink, glazed, earthenware 24"x15"x8" supplied and fixed with waste plug, complete (pedestal paid seperately).

147a/214

Towel rail 2'-0" long 3/4" dia chromium plated.

171/219

173/220

No

No

Soap tray, white porcelain, supplied and fixed to wall with rawl plugs.

No

Stop cocks, 1/2" supplied & fixed

No

Plastic L.D. make).

174/220

Stop cocks, 3/4" supplied and fixed. Plastic L.D. make).

175/220

Stop cocks, 1" supplied and fixed. Plastic L.D. make).

176/220

178a/221

No

Stop cocks, 1 1/2" supplied and fixed. Plastic L.D. make).

178/221

No

Stop cocks, 1 1/4" supplied and fixed. ( Plastic L.D. Model )

177/220

No

No

Stop cocks, 2" supplied and fixed. Plastic L.D. make).

No

As per Item No. 178a (Gate valve 2")

No

English make

178b/221

Non return valve English 2" dia

200/228

Tooth brush holder, chromium plated

No

supplied and fixed to wall with Rawl

292/240

plugs.

No

Pipes pvc 1/2" supplied & fixed.

L.ft L.m

293/240

Pipes pvc 3/4" supplied & fixed.

L.ft L.m

294/240

Pipes pvc 1" supplied & fixed 1000 type.

L.ft L.m

294a/240

pipes pvc 1" supplied & fixed 600 type.

L.ft L.m

295/240

Pipes pvc 1 1/4" supplied & fixed 1000 type.

L.ft L.m

295a/240

Pipes pvc 1 1/4" supplied & fixed 600 type.

L.ft L.m

296/241

Pipes pvc 1 1/2" supplied & fixed.

L.ft

296a/241

pvc pipe 1 1/2" (1000 type) supplied &

L.ft

fixed with out excavation.

L.m

pvc pipe 1 1/2" (600 type) supplied &

L.ft

fixed with excavation.

L.m

pvc pipe 1 1/2" (600 type) supplied &

L.ft

fixed with out excavation.

L.m

Pipes pvc 2" (1000 type) supplied & fixed.

L.ft

With excavation

L.m

pvc pipe 2" (1000 type) supplied &

L.ft

fixed with out excavation.

L.m

pvc pipe 2" (600 type) supplied &

L.ft

fixed with excavation.

L.m

pvc pipe 2" (600 type) supplied &

L.ft

fixed with out excavation.

L.m

Eaves gutters 6" square type pvc fixed

L.ft

with PVC brackets. (1' - 6 " Crs)

L.m

Down Pipe 3 1/2" Dia P.V.C Fixed with

L.ft

Wooden Plug to wall etc.

L.m

296b/241

296c/240

297/241

297a/241

297b/241

297c/241

310/243

311/244

311a/244

PVC 4" ( 600 type ) pipe supplied and fixed on walls

L.ft L.m

5/245

Drains, pvc 400 type 4" laid on cement concrete 6" thick upto 2'-0" depth of

13/246

invert including excavation and cement

L.ft

concrete haunching (1:3:6 - 1" metal).

L.m

Gulley pvc 6" supplied & fixed including gulley box.

18/247

No

Manhole 2'x2' and upto 2'-0" deep, 9" thick brick in cement 1:3 walls & cement rendered 1/2" (1:2) with 6" cement conc. foundation 1:3:6 (1" metal) including forming channels but without cover.

19/247

Manhole 3'6"x2'3" & 2'0" to 4'0" deep - do -

20/248

- do -.

Manhold 3' 6" x 2' 3" & 4' to 6' deep 9" thick -do

23/248

No

No

No

-do-

Manhole cover reinforced concrete 3" thick 2'-0x2'-0" approx. supplied & fixed

no

reinforced with 1/4" dia M.S.rods at 3" centres both ways.

26/249

Wire dome for 2" pipe supplied and fixed

no

1/D

110mm PVC inspection joint supplied and fixed

No

2D

110mm PVC inspection "Y" joint supplied and fixed

No

3D

110mm PVC Bend ( 11 Deg.) supplied and fixed

No

4D

110mm PVC Bend ( 22 Deg.) supplied and fixed

No

5D

110mm PVC Bend ( 60 Deg.) supplied and fixed

No

6D

110mm PVC Bend ( 88 Deg.) supplied and fixed

No

7D

110mm PVC "T" Junction supplied and fixed

No

8D

110mm PVC "Y" Joint supplied and fixed

No

9D

50mm Bottle trap supplied and fixed

No

10D

110mm PVC Inspection bend supplied and fixed

No

11D

63mm PVC "Y" Joint supplied and fixed

No

12D

110mm PVC Elbow supplied and fixed

No

'APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE 'MISCELLANEOUS.. Item 6/251

15/253

Description

Unit

Fence barbed wire ,14 gauge, 4 points, 3" sparts, supplied and fixed in

L.ft

existing timber posts with G.I staples.

L.m

Intermediate fence posts or structs, cement concrete 1:1 1/2:3(3/4") reinforced with 4 Nos. 1/4 dia. M.S.rods 5'-7" high square section 4" to 6" fixed complete as per drawing No.68 of 22.07.1936.

16/253

- do -

- do -

7'6" high

per post

- do -.

per post

17/253

End post and strut for Type barbed wire fence fixed complete in cement concrete as per Drg. 68 of 1936.

18/254

per post

Fence barbed wire, 7 strands 14 B.W.G with 4 points at 3" centres and R.C.C posts (1:2:4) 3/4" metal reinforced with 4 Nos. 1/4 rods with 14 B.W.G stirrups at 8" centres including post to be fixed at 8'-0 crs' excavation cement concrete foundation '1:3:6(1 1/2") metal to corner posts and 'structs and straining bolts, all as per type 'plan 68 of 22.07.1936 structs to be 'reinforced with 4 Nos. 3/8" rods and 'corner posts

18A/254

with 4 Nos. 1/2" rods. ( including

L.ft

white washing 2 coats)

L.m

- Do - do -

6 Strands

- do -

19/254

- do -

- do -

- do -

- do -

L.ft

- do -

L.m

- do -

Straining Bolts 1/2" dia made and fixed 18" long (Approx).

21/255

No

Well, bailing out water 5' to 7' dia. Upto 20' depth including cleaning well.

^ Item 1/A

L.ft

^ANGLE IRON Description Supplying and fixing 50mmx50mmx6mm thick Angle iron purlin fixed to wall at not exeeding

Unit

900mm centres and joints should be bolted with 2Nos 12mm dia bolts and nuts other site welding with cleats minimum length 450mm in next reduced angle iron including two coats of Anticorrosive paint as directed & including anchoring purlins with 2 nos

2/A

3/A

4/A

10mm tor steel welded to purlins where ever necessary and

L.ft

with 1:2:4 concreting.

L.m

62.5mmx62.5mmx6mm Angle iron purlin

L.ft

-DO-

L.m

-DO-

75mm x 75mm x 6mm Angle Iron purlin

L.ft

-DO-

L.m

-DO-

End Truss-2/50mm x 50mm x 6mm

L.ft

Per 7'-0" including 1:2:4(3/4) concreting 2nos

L.m

12mm dia 9" long welded to end truss with 2 coats of anticorrosive paint

5/A

6/A

7/A

End Truss-2/62.5mm x 62.5mm x 6mm

L.ft

-DO-

L.m

-DO-

End Truss-2/75mm x 75mm x 6mm

L.ft

-DO-

L.m

-DO-

25mm x 6mm - Flat Iron - 1'-0" long weld to end purlin as bracket to fix valance board with two coats of anticorrosive paint

8/A

& bolts & nuts

No

31mm x 6mm - Flat Iron - 1'-0" long

No

-DO-

9/A

-DO-

2/3" x 3" x 1/4"(2/75mm x 75mm x 6mm)

L.ft

angle iron slope beam including 1:2:4(3/4")

L.m

concreting with 4 nos 16mm 9" long Rag bolt

with 2 nos 9"x9" 10mm Ms base plate

10/A

Supplying & fixing 'H' iron 6" x 3" 6mm

L.ft

with necessary cleats to housing props

L.m

including 2 coats of anticorrosive painting

11/A

Supplying & fixing ' H ' Iron 8" x 4"

L.ft

(6mm) with necessary cleats

L.m

-do -

12/A

G.I. Gate with 12'-0" x 4'-6" hight 2 Nos sashes made out of 1 1/2" dia G.I. heavy quality frame with 6mm M.S. rod welded 3" c/c both ways all as per Drg. No. 409853 fixed with 9" x 9" RCC pillar in 1:2:4(3/4") concrete 4Y12 reinforced and R6 at 6" crs. stirrups rate include for Excavation base concrete footing R/F with Y10 @ 8" c/c both way 5/8" thick 1:4 plastering 4 Nos. pintol and stirrups locking divice barrel bolt etc. and 2 coats Anticorrosive paint and 2 coats enamel paint & 2 coats ofwhite washing to pillers as directed

per piller

ALUMINIUM WORK Item 1/AL

Description Aluminium Partition with sliding door

Unit S.ft m2

2/AL

Aluminium Casement with project

S.ft m2

3/AL

Aluminium Door frame only

S.ft m2

4/AL

Aluminium door fully glazed double hung

S.ft m2

5/AL

6/AL

Al Double hung Door with panneled and

S.ft

glazed

m2

Al single hung Door with fully glazed

S.ft m2

7/AL

Al Single hung Door with panneled and

S.ft

glazed

m2

APPROVED B.S.R FOR THE FIRST HALF 0F 2003 IN TRINCOMALEE DEMOLISHER. RATE (1st) 973.00 344.00

778.00 275.00

247.00 26.60

1667.00 179.00

2408.00 259.00

281.00 30.20

304.00 33.00

371.00

556.00

57.00

86.00

3.90 12.80

12.00

RATE (1st)

18.00 59.00

278.00 30.00

371.00

16.90 182.00

2.40 7.90

3.60 11.80

14.20 153.00

139.00

416.00 45.00

625.00 67.00

524.00 56.00

719.00 77.00

1216.00 430.00

778.00 275.00

RATE (1st) 741.00

195.00 21.00

292.00 31.00

224.00

931.00 100.00

1125.00 121.00

2.40 7.90

3.60 11.80

542.00 58.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE CONCRETOR. RATE (1st) 20647.00 7296.00

21388.00 7558.00

22842.00 8071.00

20840.00 7364.00

21353.00 7545.00

23583.00 8333.00

24675.00 8719.00

25416.00 8981.00

286.00 938.00

120.00 394.00

162.00 531.00

218.00 715.00

315.00

118.00

111.00 1195.00

79.00 850.00

27551.00 9735.00

29.00

24048.00 8498.00

26830.00 9481.00

27571.00 9742.00

28682.00 10135.00

26700.00 9435.00

27441.00 9696.00

28552.00 10089.00

3988.00 429.00

60.00 646.00

16.00 172.16

43.00 463.00

26678.00 9427.00

27419.00 9689.00

8838.00 951.00

10712.00 1153.00

0.00 0.00

463.00 1518.00

16630.00 5876.00

6081.00 655.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE BRICKLAYER. RATE (1st) 16820.00 5943.00

17690.00 6251.00

18559.00 6558.00

6593.00 710.00

6982.00 752.00

584.00 206.00

195.00 21.00

117.31 384.00

164.00 538.00

4121.00

329.00 1079.00

217.00 712.00

170.00 558.00

15894.00

5616.00

16357.00 5780.00

16941.00 5986.00

18108.00 6399.00

RATE (1st) 15823.00 5591.00

16379.00 5788.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE PAVIOR. RATE (1st) 7.00 23.00

17.00 56.00

7868.00 611.00

107.00 847.00

128.00 1378.00

125.00 1350.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE PLASTERER. RATE (1st) 12.00 39.00

20.00 66.00

1971.00 212.00

2110.00 227.00

1716.00 185.00

1855.00 200.00

2790.00 300.00

2975.00 320.00

2493.00 268.00

2679.00 288.00

587.00 63.00

3228.00 347.00

30.00 98.00

51.00 167.00

2601.00 280.00

3681.00 396.00

2348.00 253.00

1615.00 174.00

1681.00 181.00

13.00 42.00

2303.00 248.00

APPROVED B.S.R FOR THE FIRST HALF 2003 IN TRINCOMALEE ROOFER. RATE (1st)

10298.00 1109.00

4705.00 506.00

78.00 256.00

49.00 161.00

149.00 489.00

28.00

24.00

2750.00 296.00

185.00 20.00

370.00 40.00

2649.00 285.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE. CARPENTER & JOINTER. RATE (1st)

95.00 310.00

42.00 452.00

11.00 36.00

12087.00 1299.68

14211.00 1530.00

RATE (1st)

14911.00 1603.00

10874.00 1171.00

1018.00 109.46

92.00 10.00

16.00 54.00

394.00 4234.00

252.00 2717.00

509.00 5472.00

377.00 4061.00

RATE (1st)

479.00

5155.00

416.00 4474.00

425.00 4568.00

487.00 5244.00

171.00

67.00

304.00 997.12

12.00 41.00

11.00 36.00

14294.00 1539.00

12093.00 1302.00

436.00 15387.00

1861.00 65672.00

504.00 5425.00

239.00 2575.00

2152.00

321.00 3458.00

365.00 3927.00

207.00 2230.00

219.00 2356.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE. PAINTER & DECORATOR. RATE (1st)

42.00

50.00

70.00

741.00 80.00

1415.00

152.00

2114.00 228.00

1405.00 151.00

616.00 66.00

1136.00 122.00

534.00 58.00

607.00 65.00

957.00 103.00

1118.00 120.00

625.00 67.00

698.00 75.00

1049.00 113.00

1210.00 130.00

253.00 27.00

460.00 50.00

867.00 93.00

1507.00 162.00

120.00 12.90

208.00 22.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE BRASS FOUNDER. RATE (1st)

138.00

185.00

170.00

154.00

102.00

300.00

379.00

277.00

128.00

56.00

869.00

1442.00

2066.00

3728.00

601.00

128.00

123.00

126.00

121.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE IRON MONGER. RATE (1st)

298.00

636.00

60.00 199.00

37.00 124.00

RATE (1st)

152.00 498.00

342.00 1121.00

572.00 1875.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003. IN TRINCOMALEE DISTRICT EXCAVATOR. RATE (1st)

529.00 187.00

622.00 220.00

725.00 256.00

3001.00 1060.00

2314.00 818.00

205.00 73.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE PLUMBER. RATE (1st) 165.00

231.00

2979.00

485.00

889.00

612.00

6891.00

2022.00

866.00

232.00

619.00

2061.00

785.00

599.00

2936.00

410.00

293.00

234.00

267.00

280.00

433.00

463.00

538.00

1005.00

#N/A

320.00

13.00 42.00

20.00 65.00

39.00 129.00

28.00 92.00

53.00 175.00

42.00 138.00

73.00

65.00 213.00

47.00 154.00

38.00 126.00

118.00 388.00

110.00 361.00

71.00 233.00

63.00 206.00

88.00 288.00

81.00 264.00

227.00 743.00

357.00 1171.00

627.00

5097.00

8842.00

13518.00

797.00

85.00

533.00

611.00

246.00

250.00

341.00

485.00

744.00

713.00

302.00

557.00

86.00

457.00

RATE (1st)

4.20 13.80

808.00

901.00

4818.00

208.00 683.00

214.00 703.00

292.00

111.00

RATE ANALYSIS FIRST HALF OF 2003 IN TRINCOMALEE RATE (1st)

121.00 397.00

145.00 474.00

173.00 569.00

363.00 1192.00

403.00 1323.00

455.00 1491.00

41.00

49.00

453.00 1485.00

#N/A #N/A

81.00 265.00

21610.00

RATE ANALYSIS FIRST HALF OF 2003 IN TRINCOMALEE

RATE (1st) 353.00 3797.00

610.00 6569.00

143.00 1544.00

735.00 7906.00

733.00 7885.00

702.00 7550.00

700.00 7528.00

Code No

Description

Unit

Rate

1 1 1/2" dia. Pvc pipe 1000 type

L.ft

38.50

2 1 1/2" dia. Pvc pipe 600 type

L.ft

25.00

3 1 1/4" dia. Pvc pipe 1000 type

L.ft

26.00

4 1 1/4" dia. Pvc pipe 600 type

L.ft

18.50

5 1" dia. Pvc pipe 1000 type

L.ft

17.00

6 1" dia. Pvc pipe 600 type

L.ft

10.50

7 1/2" dia. Pvc pipe 1000 type

L.ft

6.30

8 2" dia. Pvc pipe 1000 type

L.ft

67.00

9 2" dia. Pvc pipe 600 type

L.ft

40.50

10 3/4" dia. Pvc pipe 1000 type

L.ft

11.30

11 4" dia. Sewerage (SS) 250 type

L.ft

48.50

12 4" dia. Sewerage (SS) 400 type

L.ft

75.00

gal

1085.00

S.ft

13.30

Pairs

267.00

15 Asbestos corr. Sheet

S.ft

21.35

19 Bamboos

L.ft

120.00

20 Barbed wire

L.ft

1.45

22 Barrel bolt 4" Brass oxidised

no

75.00

23 Barrel bolt 6" Brass oxidised

no

115.00

24 Basket

no

50.00

25 Beading

L.ft

4.00

31 Binding wire 14 B.W.G.

lbs

36.00

32 Bitumen

Gal

330.00

35 Board 1" thick (timber)

S.ft

45.00

36 Brass Bib Tap 1/2"

No

130.00

40a Brass screws 1 1/2"

Doz

50.00

40c Brass screws 3/4"

Doz

30.00

40d Brass Screws 1"

Doz

39.00

41 Bricks

No

2.60

44 Castm. stays h. qual 10" brass oxidised

No

90.00

45 Castm.fast. Brass oxi. H. qlty ,mort.plate

No

90.00

CWT

345.00

47 Center pivot hinges br.oxi.h.qual. ( 4 pieces )

Set

45.00

50 Closet low level pedestal type (complete ceremic)

No

3900.00

57 Distember

Lbs

0.00

60 Draw rings 1 1 /2 dia.

no

25.00

61 Earth ( Gravel Filling)

Cube

590.00

gal

1704.00

12b Anticorrosive paint 13 Asbestoes flat sheet 1.2m x 1.2m 14 Asbestoes ridges

46 Cement

63 Emulsion Paint ( Weather shield )

64 Emulsion Paint

Lit

1345.00

65 Enamel Paint

Lit

1698.00

66 Fanlight catch Brass oxi. Heavy qality

No

30.00

70 Calicut pattern flat tiles

No

11.00

73 G.I 20 B.W.G Sheets

S,ft

65.00

74 G.I. 22 B.W.G.Flat sheet

Sft

50.00

no

6.00

77 Ginisappu timber 3/4" thick

S.ft

50.40

81 Glass panes obscured(3mm)

S.ft

45.00

S.ft

60.00

85 Glue

lbs

86.00

90 Gulley Box PVC 6"

no

550.00

91 Half round tiles

No

5.00

Doz

43.00

76a G.I.Hook 5/16"x4 1/4"

81a Glass Panes Tinted (5mm)

91a Bras Sancy 1 1/4" 91b Cistern ceremic

no

1400.00

91c Cistern plastic

no

1150.00

94 Hinges 4"x3" Brass oxidised

Pair

130.00

95 Hinges 4"x4" Brass oxidised

Pair

195.00

Pair

110.00

Day

2520.00

95a Hinges 4"x2 1/2" Brass oxidised 97 Hire of mixtur, vibrator, wages of operator 98 Hold fast

no

17.50

117 Iron screws 2"

Doz

0.00

119 Iron T.hinges 10"

No

58.00

120 Brass T hinges 10"

Pair

0.00

123 Joists Class II 4" x 2"

L.ft

7.50

126 Lime -Slaked 127 Limpet washers

Bushel No

257.00 1.00

135 Metal 1 1/2"

Cube

3500.00

136 Metal 1"

Cube

3750.00

137 Metal 2"

Cube

3350.00

138 Metal 3/4"

cube

4100.00

139 Metal 6" to 9"

cube

2000.00

140 Mild steel

cwt

1773.00

141 Mirror with fittings

no.

390.00

142 Mortice Lock Concord

No

425.00

143 Mortice Lock Vinion double

No

750.00

144 Lock Night Latch Bird

No

275.00

145 Mortice lock Union English single leaver

No

1500.00

146 Mortice lock Union English double leaver

no.

2660.00

147 Mould oil

gal

100.00

147a Mouldings

L.ft

4.00

150 Nails 2" (GI)

Ibs

30.00

153 Nails 3/4" (GI)

lbs

30.00

157 P.V.C. end cap (Gutter Cap)

no

38.00

158 P.V.C. gutter joint

lb.

44.00

159 P.V.C. metre joint

no

142.00

160 P.V.C. running head

no

102.00

161 P.V.C.gutter 6"

L.ft

37.00

162 P.V.C.Inspection joint 4" (110mm)

No

350.00

163 P.V.C.Inspection "Y" joint 4" (110mm)

no.

415.00

164 P.V.C.Bend (11Deg) - 4" (110mm)

no.

110.00

165 P.V.C.Bend (22Deg) - 4" (110mm)

no.

113.00

166 P.V.C.Bend (60Deg) - 4" (110mm)

no.

190.00

167 P.V.C.Bend (88 Deg) - 4" (110mm)

no.

310.00

168 P.V.C.Pipe 4" 600 type

L.ft.

48.50

169 P.V.C.Pipe 4" 400 type

L.ft.

60.00

171 Paint oil Enamel

gal

1698.00

181 Planks 1 1/4"

Sft

96.00

sft

94.00

s.ft

45.00

sq.ft.

90.00

181a Planks 1" Special Upper Class Timber 182 Planks 1" Class II 182b Planks 3/4" 183 Plastic cistern low level (Plastic )

no

1150.00

184 Plugs

no.

2.00

186 Plywood door 2"-3" x 6'-9"

no.

0.00

187 Plywood door 2'-3" x 6'-9" ( Marine)

no

1490.00

188 Plywood door ord 2'-9" x 6'-9"

no

1467.00

189 Pressed Tiles 8" x 8"

no.

0.00

190 Primer

gal

1485.00

191 Pudlo cement

lbs

30.00

192 Red cement

lbs

148.00

193 Reepers

L.ft

8.00

193a Reepers Cl.II 2"x1"

L.ft

8.00

194 Ridge tile

no.

23.00

196 Rim lock 6" 2 leaves Brase

No

425.00

Cube

1700.00

197 River Sand 198 Drive screws and washers 198a Ring 1 1/2" Brass 199 Rawl plugs & 2" Screws

no.

6.00

no

25.00

No

15.00

200 Sand Fine

cube

1500.00

205 Sash bars 1 1/2"x1 1/2"

L.ft.

8.00

207 Screws 1 1/2"

doz.

0.00

207a Screws 1" brass

Doz

0.00

207b Screws 2"

doz

66.00

211 Sink 24"x15"x8" with waste plug & chain

no

1810.00

214 Skilled labour Gr.Il

day

450.00

215 Skilled labour Gr.I

day

500.00

216 Slacked lime

Bushel

0.00

218 Soap tray

no

164.00

220 Spur stones

no.

10.00

222 Squating pan with trap

no

700.00

224 Staining Bolts

no.

40.00

225 Staples

Doz

20.00

227 Stop cock L.D model 1/2"

no

77.00

228 Stop cock L.D model 1 1/4"

no.

0.00

232 Tar

Gal

0.00

no

65.00

236 Tiles 6" x 6" white

no

0.00

236a Tiles 6"x6" colour

no

13.40

236b Tiles 4"x4" white

no

0.00

236c Tiles 4"x4" colour

no

5.75

245 Timber purlins

c.ft.

1036.00

248 Tooth brush holder cromium plated

no

100.00

249 Tor steel

cwt

2084.00

250 Towel Trail holder chromium plated

no

275.00

232a Tiles 1'-0"x1'-0" floor

255 transport 1 st Mile 1002 transport every additional Miles 257 Unskilled labour

1 mile

0.00

1mile

0.00

day

300.00

260 Varnish

gal

1673.00

263 Wash basin 22"x16"

no.

1473.00

264 1/2" Nut & Washers

No

3.00

267a Wire nails 2"

lbs

30.00

268 Wood plugs

no

0.00

gal

300.00

269 Yellow ocare

lbs

0.00

270 Wire dome for 2" pipe

No

60.00

300 2"X2" Class II Battens

Lft

17.50

301 3/8" dia 18" Bolts,Nuts & Washers

No

12.00

302 Grey Cement

Kg

7.50

303 Rawl Plugs and Screws

No

0.00

304 Culicut Tiles

No

0.00

268a Wood preservative

308 Stopcock LD Model 1/2" (Plastic)

No

0.00

309 Stopcock LD Model 3/4" (Plastic)

No

104.50

310 Stopcock LD Model 1" (Plastic)

No

143.00

311 Stopcock LD Model 1 1/4" (Plastic)

No

213.33

312 Stopcock LD Model 1 1/2" (Plastic)

No

291.50

313 Stopcock LD Model 2" (Plastic)

No

354.20

314 Shower Rose 6"

No

95.00

317 pvc gutter brackets

No

9.20

318 Solvent cement 50g

Tin

43.00

319 Steel Rods 1/4" dia

Lbs

320 Cost of Junction

No

321 Earth Pipe 2"x5'

No

322 Plug with Switch (clipsal)

No

323 3/.036 wire

m

324 Sunk box

No

325 Screws Brass 1 1/2"x10"

No

326 Earth wire 7/.029

m

327 Wiring clips and panel pins

(Allow)

328 Round plug

No

329 Ceiling rose

No

330 Holder

No

331 Flexible wire

m

332 Screw 1/2"x6

No

333 Switch clipsal

No

334 1/.044 wire

m

335 Sunk box

No

336 Brass screws 1 1/2"x6

No

337 Brass screws 1 1/2"x10

No

338 Brass screws 1 1/4"x6 339 Brass screws 2"x10 340 Brass screws 1"x 6 341 Brass screws 2"x10 342 343 344 Angle iron 2"x2"x1/4"

L.ft

55.50

345 Angle iron 1 1/2"x1 1/2"x1/4"

L.ft

42.75

346 Angle iron 2 1/2"x2 1/2"x1/4"

L.ft

79.00

347 Angle iron 3"x3"x1/4"

L.ft

99.35

348 Making holes on angle iron

No

5.00

349 H - iron 6"x3" (6mm)

L.ft

265.00

350 H - iron 8"x4" (6mm)

L.ft

280.00

351 1" x 1/4" Flat iron

L.ft

13.75

352 1/2"x1" Bolts & Nuts

No

6.00

353 Fillets (Class I local timber for beeding)

L.ft

0.00

354 Fillets 1/2" x 1/2"

L.ft

3.00

355 Ball valve 1/2"

No

90.00

356 Ball valve 3/4"

No

145.00

357 Cistern only ceremice

No

1400.00

No

1150.00

357a Cistern plastic 358 Fittings ( For commode & cistern )

Item

350.00

359 Seat cover ( Double )

No

350.00

360 Brackets (For cistern )

Item

54.00

361 Flush bend

No

35.50

362 Tightning hook bolts

No

363 4" Sandcrete Block

No

0.00

364 110mm PVC "T" Junction

No

526.00

365 110mm PVC "Y" Joint

No

500.00

366 50mm Bottle trap

No

150.00

367 110mm PVC Inspection Bend

No

370.00

368 63mm PVC "Y" Joint

No

0.00

369 110mm PVC Elbow

No

287.00

370 PVC down pipe 3 1/2"

Length

317.00

371 PVC socket 3 1/2"

No

0.00

372 PVC elbow 3 1/2"

No

61.00

373 PVC clips 3 1/2"

No

9.00

374 1 1/4" x 1/4" Flat iron

Lft

20.00

375 1/2" (12mm) Bolt & Nut

No

6.00

376 9" x 9" 3/8" M.S. plate

No

110.00

377 1/2' x 1 1/2" Rag bolt

No

6.00

378 2" x 1/4" Flat iron

L.ft

35.00

379 70S-1002-1

L.ft

64.60

380 70S-1102-1

L.ft

44.50

ALUMINIUM MEMBERS

381 70S-1202-1

L.ft

46.40

382 70S-1402-1

L.ft

52.90

383 70S-1503-A

L.ft

78.10

384 70S-1704-A

L.ft

79.40

385 70S-3002-1

L.ft

85.00

386 70D-1910

L.ft

24.30

387 100D-1914

L.ft

24.30

388 100D-1917

L.ft

32.80

389 100D-3004-A

L.ft

124.50

390 100D-3203

L.ft

129.10

391 100D-3207

L.ft

169.00

392 100D-3502

L.ft

148.70

393 100D-3503-A

L.ft

160.90

394 CA-1001

L.ft

84.30

395 CA-1002

L.ft

134.20

396 CA-2001-A

L.ft

88.90

397 PT-5153

L.ft

15.50

398 PT-5154

L.ft

30.50

399 PT-5157

L.ft

56.30

400 P-1113

L.ft

40.75

401 80S-1801

L.ft

57.85

402 BD-1066 ( Handle )

Pair

350.00

403 Lock ALPHA

No

750.00

404 Door Closer

No

1645.00

405 5mm thick tinted glass

S.ft

60.00

406 6mm thick Plywood sheet ( ordinary )

S.ft

20.85

407 Formica sheet

S.ft

18.00

408 Rubber Beading for Aluminium fittings

L.ft

3.00

409 Welded mesh

S.ft

10.00

410 Type 1

Sum

125.00

411 Type 2

Sum

250.00

412 Type 3

Sum

75.00

413 Type 4

Sum

50.00

414 Type 5

Sum

25.00

415 Allowance type 1

Sum

100.00

416 Allowance type 2

Sum

150.00

417 Allowance type 3

Sum

10.00

418 Allowance type 4

Sum

419 Allowance type 5

Sum

Allowing of water