REKAPITULASI PERKIRAAN HARGA PEKERJAAN Program

: PEMBANGUNAN JALAN DAN JEMBATAN

Kegiatan

: KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

Prop / Kab / Kodya : RIAU

No. Divisi

Jumlah Harga Pekerjaan (Rupiah)

Uraian

1

Umum

2

Drainase

3

Pekerjaan Tanah

4

Pelebaran Perkerasan dan Bahu Jalan

5

Perkerasan Berbutir dan Perkerasan Beton Semen

6

Perkerasan Aspal

7

Struktur

8

Pengembalian Kondisi dan Pekerjaan Minor

9

Pekerjaan Harian

10

Pekerjaan Pemeliharaan Rutin

(A)

Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan )

(B)

Pajak Pertambahan Nilai ( PPN ) = … % x (A)

(C)

JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)

Terbilang :

……………………, 2019 Penawar, PT/CV ……………………………. Tanda tangan, cap

(………………………………) nama jelas

DAFTAR KUANTITAS DAN HARGA SPESIFIKASI 2010 Revisi 3 PROGRAM

: PEMBANGUNAN JALAN DAN JEMBATAN

KEGIATAN

: KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

PROVINSI

: RIAU

Uraian

No. Mata

Satuan

Pembayaran

Perkiraan Kuantitas

a

b

c

d

DIVISI 1. UMUM 1.2 1.8.(1) 1.20.(1)a

Mobilisasi

LS

1,00

Manajemen dan Keselamatan Lalu Lintas

LS M1

1,00 120,00

M3

747,00

Pengeboran, termasuk SPT dan Laporan (untuk Konstruksi Jalan)

Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 2. DRAINASE 2.1.(1)

Galian untuk Selokan Drainase dan Saluran Air

Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 3. PEKERJAAN TANAH 3.1.(1a)

Galian Biasa

M3

1.443,00

3.2.(1a)

Timbunan Biasa dari sumber galian

M3

4.800,00

3.2.(2a)

Timbunan Pilihan dari sumber galian

M3

3.243,00

3.3.(1)

Penyiapan Badan Jalan

M2

24.000,00

Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN

Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 5. PERKERASAN BERBUTIR 5.1.(2)

Lapis Pondasi Agregat Kelas B

M3

3.397,00

5.3.(1)

Perkerasan Beton Semen

M3

6.300,00

3

2.220,00

200,00

5.3.(3)

Lapis Pondasi bawah Beton Kurus

M

Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 6. PERKERASAN ASPAL

Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

7.1 (7) a

DIVISI 7. STRUKTUR Beton mutu sedang fc’20 Mpa

M3

7.1 (8)

Beton mutu rendah fc’15 MPa

M3

226,00

7.3 (1)

Baja Tulangan U 24 Polos

Kg

11.898,00

M2

855,00

Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 8.4.(1)

Marka Jalan Termoplastik

Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 9. PEKERJAAN HARIAN

Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN

Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan)

Harga

Jumlah

Satuan

Harga-Harga

(Rupiah)

(Rupiah)

e

f = (d x e)

ITEM PEMBAYARAN NO. JENIS PEKERJAAN

: 1.2 : MOBILISASI

% TERHADAP TOTAL BIAYA PROYEK =

No.

URAIAN

%

SATUAN

VOL.

A.

Sewa Tanah

Ls

-

B.

PERALATAN Periksa lembar 1.2-2

Ls

1

FASILITAS KONTRAKTOR Base Camp Kantor dan fasilitas / perlengkapan Barak Bengkel Gudang dan lain-lain

Ls Ls Ls Ls Ls

1 1 1 1 1

Ls

1

C. 1 2 3 4 5

F.

DEMOBILISASI

Total Biaya Mobilisasi

HARGA SATUAN (Rp.)

Lembar 1.2-1 JUMLAH HARGA (Rp.)

ITEM PEMBAYARAN NO. JENIS PEKERJAAN

No.

: 1.2 : MOBILISASI

JENIS ALAT

1. B. I 1 2 3 4 5 6

2. PERALATAN Diangkut dengan Trailler : MOTOR GRADER >100 HP WHEEL LOADER 1.0-1.6 M3 TANDEM ROLLER 6-8 T. VIBRATORY ROLLER 5-8 T. EXCAVATOR CONCRETE PAVER SCREED

II

Diangkut dengan Flad Bed Truck 1

CONCRETE VIBRATOR

1 2 3 4

Berjalan Sendiri : DUMP TRUCK 6 Ton DUMP TRUCK (Tronton) WATER TANKER TRUCK MIXER (AGITATOR)

III

Total untuk Item B pada Lembar 1

KODE ALAT

SATUAN

KUAN TITAS

3.

4.

5.

E13 E15 E17 E19

Unit Unit Unit Unit Unit Unit

1 1 1 1 1 1

E13

Unit

1

E23

unit unit unit unit

2 6 1 8

JARAK ASAL ALAT (KM) 6.

KOE FI SIEN 7.

HARGA DASAR ALAT (Rp.) 8.

Lembar 1.2-2 JUMLAH HARGA (Rp.) 9=7x8

Analisa El - 18

ANALISA HARGA SATUAN ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

No.

: 1.8. : Manajemen dan Keselamatan Lalu Lintas : Lump Sum

URAIAN

A. 1 2 3 4 5

B. 1 2 3 4 5

DATA DAN ASUMSI Panjang Lokasi Pekerjaan Total Masa Pelaksanaan Kegiatan Masa Mobilisasi Periode Pekerjaan Perkerasan Jalan Panjang zona kerja Perkerasan Jalan

PERKIRAAN KUANTITAS

KM Bulan Bulan Bulan M

3,00 7,00 2,00 4,00 500,00

Buah M' Buah Buah Buah Buah Buah Buah M' M2 Set Ls

2,00

URUTAN KERJA Penyedia menyiapkan perlengkapan keselamatan jalan selama periode konstruksi sesuai ketentuan Buat rencana kerja manajemen lalu-lintas sesuai schedule pekerjaan dan koordinasikan dengan seluruh personil yang terkait Kelompok kerja pengatur lalu-lintas selama konstruksi menggunakan tenaga pengatur dan flagman dengan 3 shift Pengalihan arus lalu-lintas harus ijin PPK dan pihak terkait Semua rambu harus jelas dan terbaca oleh Pengguna Jalan

C. 1 2 3 4 5 6 7 8 9 10 11 12

PERALATAN KESELAMATAN LALU LINTAS Rambu panah berkedip Rambu suar berkedip portabel Rambu tetap informasi pengalihan/pengaturan lalu lintas Rambu portabel informasi pengalihan/pengaturan lalu lintas Rambu penghalang lalu-lintas jenis plastik Rambu penghalang lalu-lintas jenis beton Rambu Peringatan Rambu Petunjuk Pagar jaring pengaman termasuk perlengkapannya Marka jalan sementara (jika diperlukan) Peralatan komunikasi dan Lainnya Alat Bantu

D.

TENAGA / PERSONIL

E

SATUAN

4,00 8,00 15,00 8,00 8,00

2,00 1,00

1

Pekerja (Flagman)

OB

12,00

2

Koordinator / Pengatur

OB

8,00

TOTAL BIAYA MANAJEMEN DAN KESELAMATAN LALU LINTAS

HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

Analisa El - 1201 FORMULIR STANDAR UNTUK PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

No.

URAIAN

A. 1 2

3

B.

4

1 2 2 3 4 5 6 7

PERALATAN DAN PELAKSANAAN PENGEBORAN Estimasi kedalaman boring per titik Peralatan Pengeboran lengkap Mobilisasi dan Demobilisasi Peralatan Pengeboran lengkap Pelaksanaan Pekerjaan Pengeboran dilapangan Pengambilan SPT interval 2 meter Pengambilan benda uji tanah interval 2 meter Pengujian Laboratorium untuk benda uji lengkap Laporan hasil pengeboran dan pengujian Alat Bantu

1 2 3

TENAGA/PERSONIL Estimasi kedalaman boring per titik Tenaga Ahli Pengeboran Tenaga Pendukung Mobilisasi dan Demobilisasi Tenaga

2

3

C.

D.

SATUAN

PERKIRAAN KUANTITAS

M Unit Ls M Sampel Sampel Sampel Ls Ls

40,00 1,00 1,00 40,00 20,00 20,00 20,00 1,00 1,00

M OH OH Ls

40,00 3,00 9,00 1,00

DATA DAN ASUMSI Pengeboran untuk penyelidikan tanah dilokasi kegiatan termasuk pembuatan laporan hasil penyelidikan Jasa pengeboran termasuk sewa peralatan yg digunakan, personil yang melakukan pengeboran, biaya pengujian laboratorium dan pembuatan laporan Penentuan lokasi pengeboran harus seijin direksi

URUTAN KERJA Penyedia memobilisasi peralatan pengeboran kelokasi yang telah disetujui oleh PPK Pengeboran dilakukan dengan mengambil SPT dan sampel tanah terganggu (Disturb) dengan interval mak.2 meter atau setiap ada perubahan strata tanah Benda uji diambil dan dilakukan pengujian laboratorium Pengeboran dilakukan hingga mencapai tanah keras atau SPT hingga nilai >40 Dibuat laporan hasil pengujian

1

E F G H

: 1.20.(1)a : Pengeboran, termasuk SPT dan Laporan (untuk Konstruksi Jalan) : M'

TOTAL BIAYA PENGEBORAN TERMASUK LAPORAN OVERHEAD & PROFIT (...% x E) TOTAL HARGA PEKERJAAN ( E + F ) HARGA SATUAN PENGEBORAN DAN LAPORAN PER METER

HARGA SATUAN (Rp.)

JUMLAH HARGA (Rp.)

Analisa EI-211

ANALISA HARGA SATUAN

PROGRAM KEGIATAN

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU : 2.1.(1) PERKIRAAN VOL. PEK. : : Galian untuk Selokan Drainase TOTAL HARGA (Rp.) : : M3 dan Saluran Air % THD. BIAYA PROYEK :

PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2.

Pekerja Mandor

(L01) (L03)

HARGA SATUAN (Rp.)

jam jam

JUMLAH HARGA TENAGA B.

BAHAN

JUMLAH HARGA BAHAN C.

PERALATAN

1. 2. 3.

Excavator Dump Truck (6 ton) Alat Bantu

(E10)

jam Ls Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

747,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-311a

ANALISA HARGA SATUAN

PROGRAM KEGIATAN

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

: RIAU : 3.1.(1a) : Galian Biasa : M3

NO.

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2.

Pekerja Mandor

PERKIRAAN VOL. PEK. TOTAL HARGA (Rp.) % THD. BIAYA PROYEK

(L01) (L03)

HARGA SATUAN (Rp.)

Jam Jam

JUMLAH HARGA TENAGA B.

BAHAN

JUMLAH HARGA BAHAN

C.

PERALATAN

1. 2. 3.

Excavator Dump Trcuk (6 ton) Alat Bantu

(E10)

Jam Ls Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

: : :

1.376,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-321

ANALISA HARGA SATUAN

PROGRAM KEGIATAN PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU : 3.2.(1a) PERKIRAAN VOL. PEK. : : Timbunan Biasa Dari Sumber Galian TOTAL HARGA (Rp.) : : M3 % THD. BIAYA PROYEK :

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2.

Pekerja Mandor

(L01) (L02)

HARGA SATUAN (Rp.)

Jam Jam

JUMLAH HARGA TENAGA B.

BAHAN

1.

Bahan timbunan (M08)

M3

JUMLAH HARGA BAHAN C. 1. 2. 3. 4 5. 6

PERALATAN Excavator Dump Truck (Tronton) Motor Grader Vibro Roller Water tank truck Alat Bantu

(E15) (E08) (E13) (E19) (E23)

Jam Jam Jam Jam Jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

4.800,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-322

ANALISA HARGA SATUAN

PROGRAM KEGIATAN PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU : 3.2.(2a) PERKIRAAN VOL. PEK. : : Timbunan Pilihan Dari Sumber Galian TOTAL HARGA (Rp.) : : M3 % THD. BIAYA PROYEK :

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2.

Pekerja Mandor

(L01) (L03)

HARGA SATUAN (Rp.)

Jam Jam

JUMLAH HARGA TENAGA B.

BAHAN

1.

Bahan pilihan (M09)

(M09)

M3

JUMLAH HARGA BAHAN C. 1. 2. 3. 3. 4. 5.

PERALATAN Excavator Dump Truck (Tronton) Motor Grader Tandem Water Tanker Alat Bantu

(E15) (E08) (E13) (E17) (E23)

Jam Jam Jam Jam Jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

3.176,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-322

ANALISA HARGA SATUAN

PROGRAM

: PEMBANGUNAN JALAN DAN JEMBATAN

KEGIATAN

: KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

PROP / KAB / KODYA

: RIAU

ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

: 3.3.(1) : Penyiapan Badan Jalan : M2

NO.

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2.

Pekerja Mandor

PERKIRAAN VOL. PEK. TOTAL HARGA (Rp.) 0 % THD. BIAYA PROYEK

(L01) (L02)

HARGA SATUAN (Rp.)

jam jam

JUMLAH HARGA TENAGA B.

BAHAN

JUMLAH HARGA BAHAN C. 1. 2. 3

PERALATAN Motor Grader Vibro Roller Alat Bantu

(E13) (E19)

jam jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

: : :

24.000,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-512

ANALISA HARGA SATUAN

PROGRAM KEGIATAN

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU : 5.1.(2) PERKIRAAN VOL. PEK. : : Lapis Pondasi Agregat Kelas B TOTAL HARGA : : M3 % THD. BIAYA PROYEK :

PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2.

Pekerja Mandor

(L01) (L03)

HARGA SATUAN (Rp.)

jam jam

JUMLAH HARGA TENAGA B.

BAHAN

1.

Aggregat B

M27

M3

JUMLAH HARGA BAHAN C. 1. 2. 3. 4. 5. 6.

PERALATAN Wheel Loader Dump Truck (Tronton) Motor Grader Tandem Roller Water Tanker Alat Bantu

(E15) (E08) (E13) (E17) (E23)

jam jam jam jam jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

3.397,00 0,00 0,00

JUMLAH HARGA (Rp.)

ANALISA HARGA SATUAN Analisa El-531

PROGRAM KEGIATAN

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

: RIAU : 5.3.(1)

NO.

A. 1. 2. 3.

PERKIRAAN VOL. PEK. : TOTAL HARGA (Rp.) : % THD. BIAYA PROYEK :

: Perkerasan Beton Semen : M3

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

TENAGA Pekerja Tukang Mandor

(L01) (L02) (L03)

HARGA SATUAN (Rp.)

jam jam jam JUMLAH HARGA TENAGA

B. 1. 2 3 4 5 6 7 8 9 10

BAHAN Semen Pasir Agregat Kasar Baja Tulangan Joint Sealent Cat Anti Karat Expansion Cap Polytene 125 mikron Curing Compound Additive

(M12) (M01a) (M03) (M39a) (M94) (M95) (M96) (M97) (M98) (M67a)

Kg M3 M3 Kg Kg Kg M1 Kg Ltr Ltr

19,2592

JUMLAH HARGA BAHAN C. 1 2 3 4 5 6 7 8

PERALATAN Wheel Loader Batching Plant Truck Mixer Con. Vibrator Water Tank Truck Conc. Paver Screed Formwork Plate/Acuan Plat Baja Alat Bantu

D. E. F. G.

JUMLAH HARGA PERALATAN JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E ) HARGA SATUAN PEKERJAAN / M3

E15 E43 E49 E20 E23 E42

jam jam jam jam jam jam Ls Ls

6.300,00 0,00

JUMLAH HARGA (Rp.)

ANALISA HARGA SATUAN Analisa El-533

PROGRAM KEGIATAN

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

: RIAU : 5.3.(3)

NO.

A. 1. 2. 3.

: Lapis Pondasi bawah Beton Kurus : M3

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

TENAGA Pekerja Tukang Mandor

(L01) (L02) (L03)

PERKIRAAN VOL. PEK. : TOTAL HARGA (Rp.) : % THD. BIAYA PROYEK :

HARGA SATUAN (Rp.)

jam jam jam JUMLAH HARGA TENAGA

B. 1. 2 3 4 5 6

BAHAN Semen Pasir Agregat Kasar (kerikil) Multiplex 12 mm Kayu Acuan Paku

(M12) (M01a) (M03) (M73) (M99) (M18)

Kg M3 M3 Lbr M3 Kg

JUMLAH HARGA BAHAN C. 1 2 3 4 5 6

PERALATAN Wheel Loader Batching Plant Truck Mixer Con. Vibrator Water Tank Truck Alat Bantu

D. E. F. G.

JUMLAH HARGA PERALATAN JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E ) HARGA SATUAN PEKERJAAN / M3

E15 E43 E49 E20 E23

jam jam jam jam jam Ls

2.220,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-717a

ANALISA HARGA SATUAN

PROGRAM KEGIATAN PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU :7.1 (7) a PERKIRAAN VOL. PEK. :Beton mutu sedang fc’= 20 Mpa TOTAL HARGA (Rp.) :M3 % THD. BIAYA PROYEK

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2. 3.

Pekerja Biasa Tukang Mandor

(L01) (L02) (L03)

HARGA SATUAN (Rp.)

jam jam jam JUMLAH HARGA TENAGA

B.

BAHAN

1. 2. 3. 4. 5.

Semen Pasir beton Agregat Kasar Kayu Perancah

Paku

(M12) (M01a) (M03) (M19) (M18)

Kg M3 M3 M3 Kg JUMLAH HARGA BAHAN

C.

PERALATAN

1. 2. 3. 4.

Batching Plant Truck Mixer Water Tanker Alat Bantu

E43 E49 E23

jam jam jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

: : :

200,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-718

ANALISA HARGA SATUAN

PROGRAM KEGIATAN PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU :7.1 (8) PERKIRAAN VOL. PEK. :Beton mutu rendah fc’= 15 MPa TOTAL HARGA (Rp.) :M3 % THD. BIAYA PROYEK

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2. 3.

Pekerja Tukang Mandor

(L01) (L02) (L03)

HARGA SATUAN (Rp.)

jam jam jam JUMLAH HARGA TENAGA

B.

BAHAN

1. 2. 3. 4. 5.

Semen Pasir beton Agregat Kasar (kerikil) Kayu Perancah

Paku

(M12) (M01a) (M03) (M19) (M18)

Kg M3 M3 M3 Kg JUMLAH HARGA BAHAN

C.

PERALATAN

1. 2. 3. 4.

Batching Plant Truck Mixer Water Tanker Alat Bantu

E43 E49 E23

jam jam jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

: : :

0,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-731

ANALISA HARGA SATUAN

PROGRAM KEGIATAN PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A 0 : RIAU : 7.3 (1) PERKIRAAN VOL. PEK. :Baja Tulangan U 24 Polos TOTAL HARGA (Rp.) : Kg % THD. BIAYA PROYEK

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2. 3.

Pekerja Biasa Tukang Mandor

(L01) (L02) (L03)

HARGA SATUAN (Rp.)

jam jam jam JUMLAH HARGA TENAGA

B.

BAHAN

1. 2.

Baja Tulangan (Polos) U24 Kawat Beton

(M39a) (M14)

Kg Kg

JUMLAH HARGA BAHAN C.

PERALATAN

1.

Alat Bantu

Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

: : :

11.898,00 0,00 0,00

JUMLAH HARGA (Rp.)

Analisa EI-841

ANALISA HARGA SATUAN

PROGRAM KEGIATAN PROP / KAB / KODYA ITEM PEMBAYARAN NO. JENIS PEKERJAAN SATUAN PEMBAYARAN

NO.

: PEMBANGUNAN JALAN DAN JEMBATAN : KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A : RIAU : 8.4.(1) PERKIRAAN VOL. PEK. : : Marka Jalan Termoplastik TOTAL HARGA (Rp.) : : M2 % THD. BIAYA PROYEK :

PERKIRAAN SATUAN KUANTITAS

KOMPONEN

A.

TENAGA

1. 2. 3.

Pekerja Biasa Tukang Mandor

(L01) (L02) (L03)

HARGA SATUAN (Rp.)

jam jam jam JUMLAH HARGA TENAGA

B.

BAHAN

1. 2. 3.

Cat Marka Thermoplastic M17b Minyak Pencair (Thinner M33 Glass Bead M34

Kg Liter Kg

JUMLAH HARGA BAHAN C.

PERALATAN

1. 2. 3.

Compressor Dump Truck Alat Bantu

E05 E08

Jam Jam Ls

JUMLAH HARGA PERALATAN D. E. F.

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) OVERHEAD & PROFIT % x D HARGA SATUAN PEKERJAAN ( D + E )

855,00 0,00 0,000

JUMLAH HARGA (Rp.)

HARGA DASAR SATUAN UPAH No.

1. 2. 3. 4. 5. 6. 7. 8. 9. 10.

URAIAN

Pekerja Tukang Mandor Operator Pembantu Operator Sopir / Driver Pembantu Sopir / Driver Mekanik Pembantu Mekanik Kepala Tukang

KODE

SATUAN

(L01) (L02) (L03) (L04) (L05) (L06) (L07) (L08) (L09) (L10)

Jam Jam Jam Jam Jam Jam Jam Jam Jam Jam

HARGA SATUAN ( Rp.)

KETERANGAN

DAFTAR HARGA DASAR SATUAN BAHAN No.

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63

URAIAN

Pasir Pasang (Sedang) Pasir Beton (Kasar) Pasir Halus (untuk HRS) Pasir Urug (ada unsur lempung) Batu Kali Agregat Pecah Kasar untuk Beton Agregat Halus Agregat Lolos # 1 " Lolos screen1 ukuran ( 0 - 5) Lolos screen2 ukuran ( 0 - 5) Lolos screen2 ukuran ( 5 - 9,5) Lolos screen2 ukuran ( 9.5 - 19,0) Filler Agregat Kasar (Kerikil) Gravel Bahan Tanah Timbunan Bahan Pilihan Aspal Kerosen / Minyak Tanah Semen / PC (50kg) Semen / PC (kg) Besi Beton Kawat Beton Kawat Bronjong Sirtu Cat Marka (Non Thermoplas) Cat Marka (Thermoplastic) Paku Kayu Perancah B e n s i n / Pertalite Solar Minyak Pelumas / Olie Plastik Filter Pipa Galvanis Dia. 1.6" Pipa Porus Agr.Base Kelas A Agr.Base Kelas B Agr.Base Kelas C Agr.Base Kelas C2 Agr.Base Kelas S Geotextile Aspal Emulsi Gebalan Rumput Thinner Glass Bead Pelat Rambu (Eng. Grade) Pelat Rambu (High I. Grade) Rel Pengaman Beton K-250 Baja Tulangan (Polos) U24 Baja Tulangan (Ulir) D32 Kapur Chipping Chipping (kg) Cat Pemantul Cahaya (Reflector) Pasir Urug Arbocell Baja Bergelombang Beton K-125 Baja Struktur Tiang Pancang Baja Tiang Pancang Beton Pratekan Kawat Las

KODE

SATUAN

M01b M01a M01c M01d M02

M3 M3 M3 M3 M3 M3 M3 M3 M3 M3 M3 M3 Kg M3 M3 M3 M3 KG LITER Zak Kg Kg Kg Kg M3 Kg Kg Kg M3 LITER LITER LITER M2 Batang M' M3 M3 M3 M3 M3 M2 Kg M2 LITER Kg BH BH M' M3 Kg Kg M3 M3 Kg Kg Bh. M3 Kg. Kg M3 Kg M' M3 Dos

M05 M06 M07 M08 M09 M10 M11 M12 M12 M13 M14 M15 M16 M17a M17b M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28 M29 M29 M30 M31 M32 M33 M34 M35a M35b M36 M37 M39a M39b M40 M41 M41kg M42 M43 M44 M45 M46 M47 M48 M49 M50 M51

HARGA SATUAN ( Rp.)

KETERANGAN

No.

64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134

URAIAN

Pipa Baja Minyak Fluks Bunker Oil Asbuton Halus Baja Prategang Baja Tulangan (Polos) U32 Baja Tulangan (Ulir) D39 Baja Tulangan (Ulir) D48 PCI Girder L=17m PCI Girder L=21m PCI Girder L=26m PCI Girder L=32m PCI Girder L=36m PCI Girder L=41m Beton K-300 Beton K-175 Cerucuk Elastomer Bahan pengawet: kreosot Mata Kucing Anchorage Anti strpping agent Bahan Modifikasi Beton K-500 Beton K-400 Ducting (Kabel prestress) Ducting (Strand prestress) Beton K-350 Multipleks 12 mm Elastomer jenis 1 Elastomer jenis 2 Elastomer jenis 3 Expansion Tipe Joint Asphaltic Plug Expansion Join Tipe Rubber Expansion Join Baja Siku Marmer Kerb Type A Paving Block Mini Timber Pile Expansion Joint Tipe Torma Strip Bearing Joint Socket Pile 35x35 Joint Socket Pile 16x16x16 Mikro Pile 16x16x16 Matras Concrete Assetilline Oxygen Batu Bara Pipa Galvanis Dia 3" Pipa Galvanis Dia 1,5" Agregat Pecah Mesin 0-5 mm Agregat Pecah Mesin 5-10 & 10-20 mm Agregat Pecah Mesin 20-30 mm Joint Sealent Cat Anti Karat Expansion Cap Polytene 125 mikron Curing Compound Kayu Acuan Additive Casing Pasir Tailing Polimer Batubara Kerb jenis 1 Kerb jenis 2 Kerb jenis 3 Bahan Modifikasi Aditif anti pengelupasan Bahan Pengisi (Filler) Tambahan Asbuton yang diproses

KODE

SATUAN

M52 M53 M54 M55 M56 M57a M39c M39d M58a M58b M58c M58d M58e M58f M59 M60 M61 M62 M63 M64 M65 M66 M67 M68 M69 M70 M71 M72 M73 M74a M74b M74c M75d M75e M75f M76 M77 M78 M79 M80 M81 M82 M83 M84 M85 M86 M87 M88 M24a M24b M91 M92 M93 M94 M95 M96 M97 M98 M99 M67a M100

Kg Liter Liter Ton Kg Kg Kg Kg Buah Buah Buah Buah Buah Buah M3 M3 M buah liter buah buah Kg Kg M3 M3 M' M' M3 Lbr buah buah buah M M M Buah Buah Buah Buah M1 Buah Set Set M1 Buah Botol Botol Kg M M M3 M3 M3 Kg Kg M1 Kg Ltr M3 0 M2 M3 kg Buah Buah Buah Kg Kg Kg Kg

HARGA SATUAN ( Rp.)

KETERANGAN

DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA BIAYA

No.

URAIAN

KO DE

HP

KAP.

HARGA ALAT

SEWA ALAT/JAM (di luar PPN)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

ASPHALT MIXING PLANT ASPHALT FINISHER ASPHALT SPRAYER BULLDOZER 100-150 HP COMPRESSOR 4000-6500 L\M CONCRETE MIXER 0.3-0.6 M3 CRANE 10-15 TON DUMP TRUCK 6 TON DUMP TRUCK 10 TON EXCAVATOR 80-140 HP FLAT BED TRUCK 3-4 M3 GENERATOR SET MOTOR GRADER >100 HP TRACK LOADER 75-100 HP WHEEL LOADER 1.0-1.6 M3 THREE WHEEL ROLLER 6-8 T TANDEM ROLLER 6-8 T. TIRE ROLLER 8-10 T. VIBRATORY ROLLER 5-8 T. CONCRETE VIBRATOR STONE CRUSHER WATER PUMP 70-100 mm WATER TANKER 3000-4500 L. PEDESTRIAN ROLLER TAMPER JACK HAMMER FULVI MIXER CONCRETE PUMP TRAILER 20 TON PILE DRIVER + HAMMER CRANE ON TRACK 35 TON WELDING SET BORE PILE MACHINE ASPHALT LIQUID MIXER TRONTON COLD MILLING ROCK DRILL BREAKER COLD RECYCLER HOT RECYCLER AGGREGAT (CHIP) SPREADER ASPHALT DISTRIBUTOR CONCRETE PAVER SCREED CONCRETE PAN MIXER CONCRETE BREAKER ASPAHLT TANKER CEMENT TANKER CONDRETE MIXER (350) VIBRATING RAMMER TRUK MIXER (AGITATOR) BORE PILE MACHINE CRANE ON TRACK 75-100 TON BLENDING EQUIPMENT

53

ASPHALT LIQUID MIXER

54

BATCHING PLANT GRASS CUTTER

54

BAR BENDER

55

BAR CUTTER

56

BREAKER

57

GROUTING PUMP

58 59 60

JACK HIDROLIC MESIN LAS PILE DRIVER LEADER, 75 kw

61 62 63 64

PILE HAMMER PILE HAMMER, 2,5 Ton STRESSING JACK WELDING MACHINE, 300 A

KET.

MATA PEMBAYARAN PEKERJAAN UTAMA

PROGRAM

: PEMBANGUNAN JALAN DAN JEMBATAN

KEGIATAN

: KEGIATAN PENINGKATAN JALAN DALU-DALU - MAHATO (DAK) A

PROPINSI

: RIAU

MATA PEMBAYARAN

JENIS PEKERJAAN

SATUAN

JUMLAH HARGA PEKERJAAN (Rp)

1

2

3

4

5.3.(1)

Perkerasan Beton Semen

M3

5.3.(3)

Lapis Pondasi bawah Beton Kurus

M3

5.1.(2)

Lapis Pondasi Agregat Kelas B

M3

% TERHADAP JUMLAH HARGA KETERANGAN PEKERJAAN 5

……………………, 2019 Pekanbaru, Februari 2019 Penawar, PT/CV ……………………………. DITETAPKAN OLEH : PEJABAT PEMBUAT KOMITMEN Tanda tangan, cap (PPK)

(………………………………) nama jelas YUNANNARIS, ST., MT NIP. 19670607 199803 1 007

6