COLLEGE 4 202

De bouwplaats M.E.Bakker

UITVOERINGSTECHNIEK WIE DOEN HET ? WIE DOET WAT? HOE GEBEURT HET? WAAR GEBEURT HET?

WIE DOEN HET? 

BOUWBEDRIJF UITVOERENDE DEEL!

BOUWBEDRIJF UITV.DEEL PROJEKTLEIDER AANGESTELD DOOR DE DIREKTIE VAN EEN BOUWBEDRIJF. MOET BINNEN DE GESTELDE TIJD EN BOUWKOSTEN HET WERK REALISEREN. GEMACHTIGDE VAN HET BOUW BEDRIJF 

BOUWBEDRIJF UITV.DEEL UITVOERDER DAGELIJKS LEIDER OP DE BOUWPLAATS VERANTWOORDELIJK VOOR ALLE WERKZAAMHEDEN OP DE BOUWPLAATS. 

BOUWBEDRIJF UITV.DEEL WERKVOORBEREIDER ALS ONDERSTEUNING VAN DE PROJEKTLEIDER EN DE UITVOERDER VOORBEREIDEN VAN DE WERKZAAMHEDEN. 

BOUWBEDRIJF UITV.DEEL BOUWPLAATSMEDEWERKERS DE VAKLIEDEN DIE WERKZAAMHEDEN UITVOEREN. 

BOUWBEDRIJF UITV.DEEL OPZICHTER, (direktievoerder) GEMACHTIGDE VAN DE OPDRACHTGEVER DIE HET CONTRACT EN DE KWALITEIT CONTROLEERT OP DE BOUWPLAATS. Tegenwoordig door ISO9000 kwaliteietsborging vaak niet nodig. 

WIE DOEN HET? BOUWBEDRIJF/ AANNEMER PROJEKTLEIDER UITVOERDER WERKVOORBEREIDER BOUWPLAATSMEDEWERKERS OPZICHTER 

HOE GEBEURT HET? ANALYSE VOOR DE PLANNING FASERINGEN EN MATERIEELCAPACITEITEN BEPALEN, denk hierbij aan factoren als (grond)water,grond, materialen die verharden, tijdelijke stabiliteit, aantallen 

HOE GEBEURT HET? BOUWFASEN: - Inrichten bouwplaats - grondwerk/leidingen - heiwerk - Bemalingen - Tijdelijke construkties tbv het werk - Het werk zelf - Grond/heiwerk/water - Verwijderen bouwplaats 

WAAR GEBEURT HET? 

OP DE BOUWPLAATS!

WAAR GEBEURT HET? BOUWPLAATS: - DISTRIBUTIEBEDRIJF - TRANSPORTBEDRIJF - ASSEMBLAGEBEDRIJF - ARBEIDSPLAATS - PROJEKTMANAGEMENT 

BOUWPLAATS DISTRIBUTIEBEDRIJF IN HET BEGIN IS ER NIETS GOEDEREN BESTELLEN, AANVOEREN EN OPSLAAN. 

BOUWPLAATS TRANSPORTBEDRIJF MATERIALEN (VAAK ZWAAR EN/OF GROOT) VANAF DE BOUWPLAATS IN HET WERK BRENGEN. 

BOUWPLAATS ASSEMBLAGEBEDRIJF GEPREFABRICEERDE ELEMENTEN OF VERSCHILLENDE MATERIALEN WORDEN SAMENGEVOEGD OP DE BOUWPLAATS. 

BOUWPLAATS ARBEIDSPLAATS MOET VOLDOEN AAN ARBEIDSOMSTANDIGHEDEN OM PERSONEEL OPTIMAAL TE KUNNEN LATEN FUNCTIONEREN CQ PRODUCEREN. MAAR OOK ARBOWET IS VAN TOEPASSING! 

BOUWPLAATS PROJEKTMANAGEMENT ER IS EEN BESTURING NODIG VAN DE BEDRIJFSFUNCTIES EN DE WERKZAAMHEDEN OM TOT EEN GOED RESULTAAT TE KUNNEN KOMEN. 

UITVOERINGSTECHNIEK WIE DOEN HET ? WIE DOET WAT? HOE GEBEURT HET? WAAR GEBEURT HET? DIT IS DUS TERUG TE VINDEN IN DE PLANNING

BOUWPLAATSINRICHTING

BOUWPLAATSINRICHTING 

WELKE SOORTEN KETEN  KEETWAGENS  CONTAINERKETEN  SCHOTTENKEET AFHANKELIJK VAN HET WERK EN DE BOUWTIJD VAN HET WERK.

BOUWPLAATSINRICHTING 

RUIMTEN (MIDDELGROOT PROJEKT)  18 m2 UITVOERDER (TEKENINGEN)  24 m2 PROJEKTLEIDER (VERG.)  3 m2 TOILET/PANTRY  24 m2 BOUWDIREKTIE (OPZICHTER)  MIN. 7,5 m2 SCHAFTRUIMTE <20 PERS. 1,25M2/PERS >20 PERS. 1M2

BOUWPLAATSINRICHTING 

RUIMTEN (MIDDELGROOT PROJEKT)  KLEEDRUIMTE >20 PERS. 0,4 m2/PERS. VLOEROPP. EXCL. KASTRUIMTE (0,45 X 0,30)  WASRUIMTE MIN. 1 WASPLAATS PER PERSOON.

BOUWPLAATSINRICHTING 

RUIMTEN (MIDDELGROOT PROJEKT)  TOILETRUIMTE MIN. 1 TOILET PER 25 PERS. PLUS URINOIRS. PERSONEELS BEZETTING VOLGT UIT DE PLANNING !!!!!!

CONTAINERS OF KETEN? 

KEETWAGENS  KEETWAGENS 2X4 m 21,- /wk  TOILETWAGEN 2X4 m 32,- /wk  KEETWAGEN 2X6 m 35 /wk BOUWTIJD EN GROOTTE VAN HET WERK BEKIJKEN.

CONTAINERS OF KETEN? 

CONTAINERKETEN  BASISCONT. 6X3 m 38,- /wk  UITV.CONT. 6X3 m 50,- /wk  SANITAIRCONT. 6X3 m 60,- /wk  TOILETCONT. 9 m2 40,- /wk BOUWTIJD EN GROOTTE VAN HET WERK BEKIJKEN.

CONTAINERS OF KETEN? 

SCHOTTENKEET  MIN. 5X12M VEELV. 1M  HUUR m2 0.90 EURO M2/wk  AFM. 5X12 6X12 6X14 6X20  MONTAGE/TRANSPORT 24,- EURO/M2  VLOERBEDEKKING 18,- EURO/M2

CONTAINERS OF KETEN? 

SCHOTTENKEET (VERVOLG)  ELEKTRA/VERWARMING 42,- /M2  SANITAIR 18,- /M2  DEMONTAGE/TRANSPORT 14,- /M2  WINDVERBAND 14,- /M1

CONTAINERS 

MAGAZIJNCONTAINER 20 FOOT  AFM. 2,4 X 6 M  KOOP 1800,- EURO  HUUR 25,- / WK  TRANSPORT/MONTAGE 200, TRANSPORT/DEMONTAGE 200,-

NISSENHUT   

AFM. 5 X 11 M OF 7,6 X 11 M HUUR 14.- /WK OF 20.- /WK TRANSPORT 600,- / 800,-

BOUWWEGEN (CONSTR.) T.B.V. VLAKHEID STALEN RIJPLATEN 1 X 5 M, HUUR 0,50 /M1 /WK. REDELIJKE ONDERGROND 

T.B.V. DRUKVERDELING ONDERGROND BED VAN STEENSLAG OF H.O.SLAKKEN EVT. MET GEODOEK CA 1,80 /M2 

BOUWWEGEN (CONSTR.) T.B.V. VLAKHEID EN DRUKVERDELING RIJPLATEN OP EEN ZANDBED MET GEODOEK  ALTERNATIEF STELCONPLATEN OF GEW. BETON INDUSTRIEPLATEN 2X2 M DIK 100MM MET STALEN OMRANDING OP ZANDBED. KOOP/TERUGKOOP 20,- P.ST. VERVANGING 70,- P.ST. 

BOUWWEGEN (CONSTR.) 

vervolg



HOOGSTE KWALITEIT WEGVERHARDING VAN ASFALTBETON AANLEG 70,- PER 3 M2

BOUWFASEN utiliteitsbouw 1. RUWBOUW  AANLOOP INRICHTEN BOUWPLAATS, ONTGRAVEN BOUWPUT, MAKEN PAALFUNDERING,bemaling  ONDERBOUW MAKEN VAN DE FUNDERING T/M DE BEGANEGRONDVLOER

BOUWFASEN (H) 



DRAAGCONSTRUCTIE STAAT OP DE ONDERBOUW EN IS DE BASIS VOOR DE OMHULLING VAN DE GEVEL EN HET DAK GEVEL/DAK VORMEN SAMEN DE OMHULLING VAN HET GEBOUW, WIND EN WATERDICHT.

AANLOOPFASE  

INRICHTEN VAN DE BOUWPLAATS MAKEN VAN DE GRONDSLAG VOOR HET GEBOUW ZELF

INRICHTEN BOUWPLAATS 





AANLEGGEN TIJDELIJKE TRANSPORT ROUTES OPRICHTEN VAN TIJDELIJKE ACCOMODATIES AANLEGGEN VAN TIJDELIJKE INSTALLATIES

PLAATSING ACCOMODATIES    

KRAANBAAN EN OPSTELPLAATS MOBIELE KRAAN BOUWWEGEN MET OPSTELSTROKEN ZONE LANGS DE BOUWWEG ONDER KRAANBEREIK ZONE VOOR OPSLAG ONDER KRAANBEREIK

BOUWINSTALLATIES     

ELEKTRISCHE INSTALLATIE TELECOMMUNICATIE WATERINSTALLATIE GASINSTALLATIE SANITAIRE INSTALLATIE

ZONERING VAN DE BOUWPLAATS      

GBW = GEBOUW GVL = GEVELSTROOK TALUD/STEIGER BWG = BOUWWEG KRB = KRAANBAAN LPK = LOSPLAATS LANGS WEG ONDER KRAAN LPW = LOSPLAATS LANGS WEG

ZONERING VAN DE BOUWPLAATS       

OSK = OPSLAGRUIMTE ONDER KRAAN OSB = OPSLAG RUIMTE BUITEN KRAAN PKT = PERSONEELSKETEN MKT = MANAGEMENTKETEN OKT = ONDERAANNEMERSKETEN MGC = MAGAZIJNCONTAINERS LDS = LOODSEN

INFRASTRUKTUUR BEWEGWIJZERING (BORDJES)  TOEGANGSPOORT BEHEERSING GOEDERENSTROOM EN LOSSEN OP DE GOEDE PLAATS ALLEEN MOGELIJK ALS ER EEN TOEGANGSPOORT IS. REGEL EEN OPSTELSTROOK VOOR VRACHTWAGENS 

INFRASTRUKTUUR TOEGANGSPOORT (VERVOLG) BREEDTE INRIJPOORT AFHANKELIJK VAN DE STRAATBREEDTE EN HET TYPE TOE TE LATEN VRACHTWAGENS. STRAATBREEDTE 6M > ENKELE ACHTERAS, DUBBELE ACHTERAS 6,6M, TREKKER MET OPLEGGER 8,5 M 

INFRASTRUKTUUR BOUWWEGEN NEDERLANDSE WEGEN MAX. 40 TON MET EEN MAX. LENGTE VAN 18 M ZWARE VRACHTWAGENS EEN BINNENSTRAAL VAN 15 M. 

INFRASTRUKTUUR DISTRIBUTIEBEDRIJF BENODIGDE EN BESCHIKBARE OPSLAGCAPACITEIT  TRANSPORTBEDRIJF AFSTEMMING WEGTRANSPORT EN BOUWTRANSPORT TRANSPORTMIDDELEN ZOALS KRANEN. 

BOUWPLAATS

WEG BOUWWERK

BOUWPLAATS

KEET

BOUWPLAATS

TOEGANG

BOUWPLAATS

TOEGANGSWEG MET KEERPLAATS OF RONDOM DE BOUWPLAATS

BOUWPLAATS

OPSTELPLAATS KRAAN

LOOPAFSTANDEN 





AFSTAND BOUWKEET – PERSONEEL IS VAN BELANG VOOR KOSTEN: ELKE PAUZE WORDT ER GELOPEN(EN NIET IN EIGENTIJD!) DUS VAN BELANG OM EVT KLEINE KOFFIE ONDERKOMENS TE PLAATSEN OF IEMAND MET KOFFIE ROND TE LATEN GAAN

waar gevonden? www.bouwweb.nl algemene info over bouwen www.intrabouw.nl www.sbr.nl www.stt.nl www.demeeuw.nl bouwsystemen getoonde plaatjes