FLOW CHART FOR PREPARATION OF MECHANICAL STABILIZED SUB-BASE(G30) Sub grdde will be checked for Compaction and Levels

Pass

Preparation of G30 Sub-base Layer as per Section 3700 of GS Sub-base(G30) will be checked compaction,Layer thicksness and Levels

Fail Layer will be re compacted to achieve compaction at mositures with in +/- 2% of OMC

Mechanical Stabilization involves G15materail+Crusher Waste Material

Fail Pass

Spreading of G15 Material+Crusher Waste material

Corrective actions will be taken

Uniform Mixing of Materials to a depth of 250mm(200mm compacted) with the help of Reclaimer to achieve

Material Wil be checked for complience with Table 3702/5 of GS Fail

Necessary corrective actions will be made.Layer will be re compacted to achieve compaction at mositures with in +/- 2% of OMC,

Pass

Preparation for Granular Base course Layer of Material CBR >80%

Related Documents

Flow Chart
December 2019 41
Flow Chart
November 2019 43
Flow Chart
August 2019 54
Flow Chart
April 2020 23
Flow Chart
June 2020 24

More Documents from "arora_dharmendra7485"