CONTRACT NO. 391/2006 WORK PROGRAMME FOR TESTING WORKS AT BUKIT MINYAK DESCRIPTION
AUGUST 2007 1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
SEPTEMBER 2007 18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
STAGE 1 1 Multicore Cable Check Plan Actual
100 % COMPLETED
2 DC System Checks Plan Actual
100 % COMPLETED
3 AC System Checks Plan Actual
100 % COMPLETED
STAGE 2 4 132kV CT Test Plan Actual
100 % COMPLETED
5 132kV CVT Test Plan Actual
100 % COMPLETED
6 132kV SA Test Plan Actual
100 % COMPLETED
7 132kV BBISO Test Plan Actual 8 132kV LISO Test Plan Actual
O/T : CONTACT RESISTANCE & TIMING WILL BE CARRIED OUT DURING OUTAGE
100 % COMPLETED
9 132kV Capacitor Test Plan Actual
100 % COMPLETED
10 132kV Reactor Test Plan Actual
100 % COMPLETED
11 132kV CB Test by AREVA Specialist Plan Actual
100 % COMPLETED
12 SCA FOR 132kV CB & RTU Plan Actual
100 % COMPLETED( PASS )
13 132kV CB Test - Timing Test,Contact Resistance Check & Insulation Test Plan Actual
100 % COMPLETED
- SF6 Dew Point & Purity Test Plan Actual 14 132kV MetersTest Plan Actual
100 % COMPLETED
100 % COMPLETED
15 132kV Secondary Injection Relays Plan Actual
100 % COMPLETED
16 Earthing System Plan Actual
100 % COMPLETED
17 132kV RTU Local Test Plan Actual
100 % COMPLETED
STAGE 3 18 Primary Injection of Relay & Meters Plan Actual
100 % COMPLETED
19 Functional & Interlocking Test Plan Actual
100 % COMPLETED
20 Facia / Alarm Indication Test Plan Actual
100 % COMPLETED
21 Remote Operation Plan Actual 22 Live Transfer ,Voltage Selection, Synchronising Scheme Test Plan Actual
100 % COMPLETED WILL BE CARRIED OUT BEFORE THE OUTAGE FOR BUSBAR STABILITY
23 132kV RTU Test With NLDC Plan Actual STAGE 4 25 Installation of Fly Bus ( Blue Phase ) Plan Actual
cancelled 100 % COMPLETED
6
7
8
9
10
11
12
13
14
15
25 Tripping Test
WILL BE CARRIED OUT BEFORE THE OUTAGE FOR BUSBAR STABILITY
26 Busbar Stability Outage For Main Busbar On 08/092007 ( Reference Bay PRAI NO.1) Outage For Reserve On 09/09/2007 ( Reference Bay PRAI NO.1) 27 Pre PIAT - on 11/09/2007 28 PIAT & RSV - on 14/09/2007 29 Commissioning
cancelled cancelled cancelled cancelled
CONTRACT NO. 391/2006 WORK PROGRAMME FOR TESTING WORKS AT PRAI INDUSTRIAL ESTATE SUBSTATION DESCRIPTION STAGE 1 1 To obtain PTW From TNB AM Plan Actual 2 Multicore Cable Check Plan Actual 3 DC System Checks Plan Actual 4 AC System Checks Plan Actual STAGE 2 5 Earthing System Plan Actual 6 132kV SA Test Plan Actual 7 132kV Reactor Test Plan Actual 8 132kV CT Test Plan Actual 9 132kV CVT Test Plan Actual 10 132kV BBISO Test Plan Actual 11 132kV LISO Test Plan Actual 12 132kV Capacitor Test Plan Actual 13 132kV CB Test Plan Actual 14 132kV MetersTest Plan Actual 15 132kV Secondary Injection Relays Plan Actual
JANUARY 2008 7
8
9
10
11
12
13
14
15
16
17
18
19
20
FEBRUARY 2008 21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
16 132kV RTU Local Test Plan Actual STAGE 3 17 Primary Injection of Relay & Meters Plan Actual 18 Functional & Interlocking Test Plan Actual 19 Facia / Alarm Indication Test Plan Actual 20 Remote Operation Plan Actual 21 Live Transfer ,Voltage Selection, Synchronising Scheme Test Plan Actual 22 132kV RTU Test With NLDC Plan Actual STAGE 4 23 Tripping Test 24 Busbar Stability Outage For Main Busbar On 19/012008 ( Reference Bay Existing Capbank ) Outage For Reserve On 20/01/2008 ( Reference Bay Existing Capbank ) 25 Pre PIAT - on 21/01/2008 Plan Actual 26 PIAT & RSV - on 24/01/2008 Plan Actual 27 Commissioning - on 26/01/2007 Plan Actual