HKIA – M629 Reconfiguration of Commercial Counters at H1 Buffer Hall

Hoarding Arrangement at Buffer Halls for Phase I Works.

Date : 12 August, 2008 Revision : A

Hoarding Arrangement at Buffer Halls for Phase I Works

Pg.1

HKIA – M629 Reconfiguration of Commercial Counters at H1 Buffer Hall

1. Introduction According to the ERI no. 03 item 1 and 2, the hoarding layout & the construction period for Phase 1 works at Buffer Halls are revised to suit the new requirements.

2. Working Portion Plan In order to reduce the interference to passenger, SFK will divide the works in phase 1 into 2 portions (A & B). The working period for Portion A is from 1 September 08 to 6 October 08. For the portion B, the working period is from 4 October, 08 to 17 November, 08. The detail is shown on the Appendix A.

3. Hoarding Arrangement 3.1 Hoarding Arrangement for Portion A The overall hoarding arrangement for Portion A is shown on Appendix B. The wall, floor finishes and new counters will be completed before hoarding removal. However, due to several long-lead materials installed at the ceiling still may not be delivered on time, therefore; fire resistant sheet will be provided to cover the dismantled ceiling areas until completion of ceiling works.

3.2 Hoarding Arrangement for Portion B The overall hoarding arrangement for Portion B is shown on Appendix C

4. Type of Hoarding There has two type of hoarding; one is 3.2m height hoarding which will be installed outside the buffer hall areas. For the 2.4m height hoarding with fire resistant sheet, it will install within the buffer areas. The outlook of the hoarding is shown on the appendix D & E. For the detailed hoarding design & calculation, it will be submitted separately.

Hoarding Arrangement at Buffer Halls for Phase I Works

Pg.2

HKIA – M629 Reconfiguration of Commercial Counters at H1 Buffer Hall

5. Counters Relocation 5.1 Under Potion A Works According to the given comments on the rev. 0, the relocation of the MTR counter can be referring to the appendix B.

5.2 Under Portion B Works 5.2.1 MTR Counter When the portion A is completed, the new counter will be installed. We propose MTR to use the new counter in order to reduce the congestion of the remaining area. 5.2.2 HKTB Counter & AA Information Directory According to the given comments on the rev. 0, the HKTB counter and AA information directory can be referring to the appendix C.

Hoarding Arrangement at Buffer Halls for Phase I Works

Pg.3

Fire Resistant Sheet

Fire Resistant Sheet

Fire Resistant Cover with Aluminium Frame at the Back