SL 1 in Value Engineering
SL 1 in Value Engineering
1
SL 1 in Value Engineering
Welcome to the court of Emperor Jalaluddin Muhammad Akbar
2
SL 1 in Value Engineering
Noble men! There is a very important matter before the court today.
The raw material price is shooting up. The material cost of a sword has gone up by Rs.10 . And …. We are adding 50,000 soldiers to our army this year.
I want to handle this situation without increasing the taxes. Please give your valuable suggestions as to how we should face this situation.
3
SL 1 in Value Engineering
Your Majesty, I have six ideas which can reduce the cost of a sword by atleast Rs.20 without compromising the functional requirements.
Why everyone’s quiet? Birbal! I am surprised that you too have become silent!!
!!
??
Brilliant!. Tell us those ideas.
!?
4
SL 1 in Value Engineering
Part Count Reduction
Presently, the hilt has 7 parts. The proposed design will have 4 .
Existing Design
New Idea
7 parts
4 parts 5
SL 1 in Value Engineering
Part Commonisatio n For the new hilt, instead of designing exclusive rivets, we can use the rivets of daggers.
x 6
SL 1 in Value Engineering
Benchmarking When the Shah of Persia was our Guest last month , I observed that the hilt in his sword does not have a curved portion. We can design similar hilts for our experienced soldiers.
Existing Design
New Idea
Curved portion 7
SL 1 in Value Engineering
The sheath which houses the blade is made of copper now. We can switch over to Alloy steel which is cheaper.
Alternate Material
Copper
Steel
Sheath Blade
8
SL 1 in Value Engineering
Weight Reduction
Since alloy steel is stronger than copper, we can reduce the thickness by 0.5 mm which will save material
1.5 mm
2 mm
Sheath Blade
9
SL 1 in Value Engineering
Yield Improvement
The curved blade design is yielding only 2 pieces per die. If a straight blade is designed, we can extract 3 pieces per die.
2 Blades
3 Blades
10
SL 1 in Value Engineering
Saheb, there is no doubt that the present sword designed by you for my Grandfather’s army is superior. However, let us test this new design in our barracks.If they pass the tests, we will deploy them in the battle field.
There is an advantage also. I do not have to increase the tax. Your majesty. The present design is being used since the time of Babur without any failure. We should not risk any design change. If the ideas pass the test, we can save atleast Rs. Ten Lakhs this year, thus serving the purpose of cost reduction. 11
SL 1 in Value Engineering
Birbal! I wonder Yes, your Majesty.how you With the help of Functional Analysis developed these System Technique(FAST) anyIsbody ideas! there a can generate such ideas. FAST is away systematic powerful tool usedby in which Value others Engineering (VE) which an be canis also extremely effective system to to trained improve products and services generatefor such cost and productivity improvement. ideas.
If six ideas for the sword itself can save Rs. Ten lakhs , imagine how much money we can save on other weapons like spears, arrows and cannons etc.
12
SL 1 in Value Engineering
Yes, your Majesty.
Birbal! There are four divisions in my army – Infantry, Cavalry,Artillery and Elephant brigade. I want you to teach the engineers in each of these divisions the application of Value Engineering (VE), especially the Functional Analysis System Technique(FAST). Each division should release Armoury Change Requests (ACRs) for the worth of Rs.25 lakh.
13