Sign Up To Qanet.gm

  • December 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Sign Up To Qanet.gm as PDF for free.

More details

  • Words: 419
  • Pages: 2
ARCHI TECTS, ENGI NEERS &SURVEYORS TOTAL DESIGN STUDIO 71 ATLANTIC RD. FAJARA; P.O. BOX& 2001, FAJARA; T EL: 396869 ARCHITECTS, ENGINEERS SURVEYORS 16 Fillan St. Serrekunda, The Gambia 16B F ILLAN ST REET , SERREKUNDA; TEL: 391750 Telephone: 4373722

email: [email protected] Ref: TSR/MR/01

3rd. March 2008

REPORT ON STRUCTURAL SURVEY CARRIED OUT ON ST. MARIE RIVIER SCHOOL BUILDING BLOCK AT BRIKAMA (KITTY) IN WESTERN REGION. The building comprises two floors with six classrooms on each. The ground floor is complete and work on the first floor is on-going. A physical inspection was carried out on all structural elements (columns, beams, suspended slab/cantilever, stairs and blockwork cladding). Information on elements like the column pad foundations which have since been complete, were obtained from the Contractor. Generally, the design and construction are sound and workmanship has been good. Substructure : The substructure has been properly constructed to specification. There is a 200mm thick concrete strip and 300mm thick reinforced column pad footings. The concrete ground slab is 150mm thick. There are no ‘settlement cracks’ on the building, or ground slab, indicating that the foundation and general substructure are fine. Superstructure: The superstructure is robust and comprises 250X200 reinforced concrete columns and ring beams to the underside of openings and above lintel height. Cladding consists of sandcrete blocks. The structural elements are properly built and are fine. There are a few hairline cracks on some wall panels and two columns on the ground floor. These cracks are not due to structural defects but are confined to the plasterwork over the columns and on blockwork cladding. The defects are cosmetic and the contractor will make good all such defects as contractually bound to do. Suspended slab, cantilever & stairs: These have been properly built and exhibit no signs of defect. The slab is 150mm thick and is reinforced with 10mm diameter high yield steel bars at 150mm centres, each way. There is no sagging or deflection and the elements were constructed to proper lines and levels. GENERAL OBSERVATIONS: The site is well organised and the contractor is doing a good job. The defective cracks are mainly due to lack of finishing skills on the part of the workforce. RECOMMENDATIONS: 1. Contractor to be sending out samples of concrete and blockwork to materials laboratories (at DTS, GTTI or CSE) for strength testing.

2. Import skilled labour from Senegal to complete the plasterwork although this is not crucial unless the client is really concerned with having a near perfect finish. SIGNED..............................................................................

Bevan Mendy (Civil/Structural Engineer)

Related Documents

Sign Up To Qanet.gm
December 2019 14
Presentation Sign-up Sheet
October 2019 23
Parent Sign Up Sheet
November 2019 30
Midterm Sign-up Sheet
June 2020 17
Volunteer Sign-up Sheet1
April 2020 13
Vbs Sign Up Sheet
May 2020 8