Our Ref:
DCB/05/09 Item 7.03
14th April 2009
Planning Department Cayman Islands Government
P.O Box 235 Cayman Brac KY2-2101 Cayman Islands 1-345-948-2222
John Ball Oasis Land Development Ltd C/o Cayman Survey Associates P.O. Box 2313 Grand Cayman KY1-1106
Re: Proposed Major Subdivision, CBE Block 110A Parcel 12 Rem 1 Dear Mr. Ball,
At a meeting held on the 30th March 2009, the Board resolved to approve your requested amendments to the above referenced application. You are not required toinstall sidewalks and you are not required to install a sewage treatment plant. The Board suggests that you consider phasing the development to be able to utilize a sewage treatment plant as opposed to septic tanks on individual lots. The following requirements (DCB/25/08, 3rd November 2008) shall continue to apply:
1) 2) 3)
The road shall be constructed and paved to PWD and NRA standards. All utility poles shall be installed. The surveyor’s drawing shall be submitted to the Planning Office for approval prior to registration of the lots.
Respectfully yours, Andrea L. Stevens Executive Secretary For Development Control Board Pc:
Bodden & Bodden Attorneys at Law
Phone: (345)-244-4422 Facsimile: (345)-948-2422 Web: www.planning.gov.ky Email: