Progress Report

  • July 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Progress Report as PDF for free.

More details

  • Words: 1,125
  • Pages: 4
Progress reports are common in engineering. As the name suggests, they document ongoing projects. They might be one-page memos or long, formal documents. Such a report is aimed at whoever assigned the project. Its goal is to enable the manager or sponsor of a project to make informed decisions about the future of the project. Usually, progress reports are stressful. The sponsor wants a job done quickly and cheaply; the engineer needs to ensure accuracy and quality. A sponsor might cancel even a quality job if it is behind or overbudget. As the engineer, you need to please the sponsor and do the job well. Yet, any project of size or significance is bound to encounter snags: additional requirements, miscommunications, problems, delays, or unexpected expenses. A progress report must account for those snags.

Organization The original proposal for the project determines the structure: make use of original milestones or the timeline. With this in mind, the simplest structure is as follows: 1.

Introduction

2.

Work Completed

3.

Work Scheduled

4.

Problems But a more comprehensive list of components will give you a clearer structure, even if you return to the simpler structure for the report itself. Beer and McMurrey's [8] Detailed Structure: 1. Introduction 2. Project Description 3. Progress Summary 4. Problems Encountered

5. Changes in Requirements 6. Overall Assessment of the Project This document adds: 7. Report Apparatus (titles, references, etc.)

1.

Introduction

As always, first indicate the purpose of the report and its intended audience. Clearly define the time period covered in the report (see also titles). Then, explain the project's objectives and summarize the major issues. Sometimes the summary 2.

can

be

a

separate

section

Project

from

the

introduction

[2].

Description

In very short reports, the introduction might contain this section, but if it is under its own heading, readers who are familiar with the project can skip it. Someone unfamiliar with the project, however, needs summarized details such as purpose and scope of the project, start and completion dates, and names of parties involved [8]. Often this section can be adapted from a proposal or borrowed from a 3.

previous Progress

progress

report. Summary

This is the substance of the report (so "summary" may be a misnomer). You want to discuss work done, work in progress, and work to be done. You might just use these as subheadings to structure the section. This would be a project-tasks approach. Other approaches are time-periods or a combined approach. •

Project-tasks approach: Focus on the tasks. Defined milestones can logically

organize your discussion into this kind of structure. Also if you are working on a number of semi-independent tasks at the same time, this approach will work well [8]. •

Time-periods approach: Focus on time: the previous period, the current period,

the future. If a timeline (or deadline) is more important than milestones, then use this approach. Also, use it for projects with a simple linear structure. •

Combined approach: The two above approaches could be combined if, for

example, under previous work, you break down what you have done by individual tasks.

Or, under the tasks, you focus on what part is complete, what part is in progress, and what part is yet to come. Your project (and sometimes your sponsor) will determine which of these three you use. If the problems encountered or changes required are time-related, then use the time-periods approach to your advantage; likewise, if the problems or changes relate to specific tasks then use the project-tasks approach. Another item that may be included here is a summary of financial data. This last item could be contained in a table or appendix, or an independent section. 4.

Problems

Encountered

As noted in the opening, snags are expected. Don't hide from them; explain what they are and how they might affect key areas of the job (such as timing, price or quality). If the problem occurred in the past, you can explain how you overcame it. This is least serious; in fact, you look good. If the problem is in front of you (now or in the future), explain how you hope to overcome it, if you can. 5.

Changes

in

Requirements

Here, you record the changes to the project: milestones added, new requirements, or schedule changes (good or bad). Even if these changes have not affected the ultimate goal of the project, you need to tell the sponsor how problems have been accommodated. Note: If changes are a direct result of problems encountered, sections 4 and 5 may be combined. This would lead to a modified organization: first problem and the change it required, then the next problem and change, and so on. 6.

Overall

Assessment

of

the

Project

Since a progress report is not about a finished work, the conclusion needs only to give your professional opinion of how the project is going. Being unrealistically optimistic is as inappropriate as being unduly negative. Beware of promising early completion: a single setback can gobble up much time. Likewise, don't overreact if you are behind schedule. You may also gain time along the way. Far more significant for the engineer is to explain anything that may change the

expected quality of the final product. Keeping in mind your purpose can help you focus here: your goal is to enable the manager or sponsor to make informed decisions. 7.

Report

Apparatus

A long progress report will include all the apparatus of formal reports: letter of transmittal, title page, table of contents, abstract, appendices, references. Only the most common will be addressed here. •

Title: whether on a separate page or merely as a header, the title sends an

important message to the reader. It needs to be clear and concise. Sample good title: PROGRESS

REPORT:

Manufacturing Custom Relief Valve Assemblies XYZ Company Reporting Period: April - July 1997 •

Subtitle: Note that the subtitle in the above example incorporates the dates

covered by the report. This makes handy reference for a reader, particularly on a large project where more than one progress report may be necessary. •

Appendices: In a short report (less than 10 pages) keep appendices to a

minimum. It is always appropriate, however, to lodge financial data in an appendix if it does not fit elsewhere in the report. An important guideline is that it is only worth including an appendix if you mention it in the guts of the report. Otherwise, leave it out altogether. References: Systems of referencing vary widely within engineering disciplines. The University of Toronto's Language Across the Curriculum program has a convenient "bibliography builder" for people using the author-date system. The basics of the format can be seen in the reference list below that contains the references used in producing these pages. See also:

Related Documents

Progress Report
July 2020 10
Progress Report
June 2020 11
Progress Report
July 2020 16
Progress Report
May 2020 12
Progress Report
November 2019 24
Progress Report
July 2020 13