LEON, GTO. 9 DE OCTU AT'N : ARQ. ADALID SANCHEZ

PRESENTAMOS PRESUPUESTO DE TRABAJOS DE URBANIZACION EN SU OBRA DENOMINADA "FRACC. R

CATALOGO PAVIMENTOS Y BANQUETAS GUANAJUATO TERRACERIAS PARTIDA

CONCEPTO

1

1.1

TRAZO Y LIMPIEZA CON APARATOS DE PRECISION P.U.O.T.

1.2

1.3

1.4

1.5

1.6

1.7

DESCRIPCION

UNIDAD

P.U.

M2

2.89

EXCAVACION DE MATERIAL TIPO II CON MEDIOS MECANICOS EN UN ESPESOR DE O-2 MTS. DE PROFUNDIDAD (MEDIDO EN BANCO),INCLUYE MATERIALES, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION, P.U.O.T.

M3

14.84

CAPA RENIVELADORA DE TEPETATE CON VRS=60% EN UN ESPESOR NECESARIO COMPACTADO AL 95% ZONA GRANULOMETRICA I O II DE SU P.V.S.M. LIMITE LIQUIDO 25% MAXIMO, 0% DE PORCENTAJE DE EXPANSION EN CAPAS NO MAYORES DE 15 CMS. INCLUYE MATERIALES, MANO DE OBRA, Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION P.U.O.T.

M3

126.93

CARGA Y ACARREO DE MATERIAL PRODUCTO DE LA EXCAVACION POR MEDIOS MECANICOS INCLUYE 30% DE ABUNDAMIENTO.

M3

17.34

ACARREO EN CAMION, DE MATERIAL PRODUCTO DE EXCAVACION Y/O DEMOLICION, INCLUYE EL 30% DE ABUNDAMIENTO, SOBRE PAVIMENTO, KM. SUBSECUENTE AL BANCO (TIRADERO AUTORIZADO) P.U.O.T. (14.0 KMS)

M3-KM

TRATAMIENTO DE TERRENO NATURAL EN CAPA DE 20 CM CON 10 KG /M2 DE CAL. (INCLUYE AFINE Y COMPACTACION AL 95% DE SU P.V.S.M.)

M2

SUB-BASE HIDRAULICA CON VRS=80% EN UN ESPESOR DE 20.0 CMS COMPACTADO AL 95% ZONA GRANULOMETRICA I O II DE SU P.V.S.M. LIMITE LIQUIDO 25% MAXIMO, 0% DE PORCENTAJE DE EXPANSION EN

M3

3.15

24.17

188.62

1.8

1.9

RIEGO DE IMPREGNACION CON EMULSION ASFALTICA RR2K EN PROPORCION 1.20 LT/M2, INCLUYE MATERIALES, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION P.U.O.T.

M2

9.67

POREO CON ARENA PARA SELLADO DE BASE HIDRAULICA, INCLUYE MATERIALES, MANO DE OBRA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION P.U.O.T.

M2

3.27 TOTAL TERRACERIAS

PAVIMENTOS PARTIDA

2

CONCEPTO

DESCRIPCION

UNIDAD

P.U.

2.1

TRAZO Y NIVELACION, DE TERRENO NATURAL CON APARATOS DE PRECISION P.U.O.T.

M2

2.89

2.2

GUARNICION SEMINTEGRAL EN FORMA PECHO DE PALOMA DE 15.0 X 65.0 X 50.0 CMS DE SECCION INCLUYE ACABADO ESCOBILLADO, COLADO CON CONCRETO PREMEZLCLADO F'c = 200.0 KG/CM2, T.M.A. = 1 1/2", REV. 8., INCLUYE MATERIALES, MANO DE OBRA, CIMBRA Y

ML

45.55

CURADO DE CONCRETO EN GUARNICIONES CON MEMBRANA DE CURADO EMULSIONADO BLANCO BASE DE AGUA MCA. FESTER O SIMILAR, INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRRAMIENTA, P.U.O.T.

M2

4.89

PIEDRA BOLA EN SUPERFICIE DE RODAMIENTO CON ESPESOR PROMEDIO DE 20 CM, ASENTADA SOBRE UNA CAMA DE 15 CM DE MORTERO BASTARDO CEMENTO-CALARENA EN PROPORCION 1:4:12, CALAFATEADO CON MORTERO HIDRAULICO 1:5 CEMENTO-ARENA, INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRRAMIENTA,

M2

HUELLAS DE RODAMIENTO EN BASE A CONCRETO HIDRAULICO SIMPLE f´c= 200 kg/cm2, ESPESOR DE 20 CM Y ANCHURA DE 50 CM, INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRRAMIENTA, P.U.O.T.

M2

43.24

CURADO DE CONCRETO EN HUELLAS DE RODAMIENTO CON MEMBRANA DE CURADO EMULSIONADO BLANCO BASE DE AGUA MCA. FESTER O SIMILAR, INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRRAMIENTA,

M2

4.89

2.3

2.5

2.6

2.7

TOTAL PAVIMENTO

BANQUETAS PARTIDA

3

CONCEPTO

3.1

DESCRIPCION TRAZO Y NIVELACION, DE TERRENO NATURAL CON APARATOS DE PRECISION P.U.O.T.

UNIDAD

M2

P.U.

2.89

EXCAVACION PARA ABRIR CAJA EN MATERIAL TIPO "II" POR MEDIOS MECANICOS MEDIDO EN BANCO. (ESPESOR DE 30.0 CMS A RASANTE DE BANQUETA) INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRRAMIENTA,

M3

14.84

CAPA RENIVELADORA DE TEPETATE CON VRS=60% EN UN ESPESOR NECESARIO COMPACTADO AL 95% ZONA GRANULOMETRICA I O II DE SU P.V.S.M. LIMITE LIQUIDO 25% MAXIMO, 0% DE PORCENTAJE DE EXPANSION EN CAPAS NO MAYORES DE 15 CMS.

M3

132.93

3.4

CARGA Y ACARREO DE MATERIAL PRODUCTO DE LA EXCAVACION POR MEDIOS MECANICOS INCLUYE 30% DE ABUNDAMIENTO.

M3

17.34

3.5

ACARREO EN CAMION, DE MATERIAL PRODUCTO DE EXCAVACION, INCLUYE EL 30% DE ABUNDAMIENTO, SOBRE PAVIMENTO, KM. P.U.O.T. (14.0 KMS)

M3

3.15

3.6

AFINE Y COMPACTACION DE TERRENO NATURAL AL 90% PVSM, POR MEDIOS MECANICOS. P.U.O.T.

M2

6.37

3.7

SUBRASANTE DE TEPETATE MEZCLADO Y HOMOGENEIZADO CON AGUA, COMPACTADO AL 90% PVSM, ELABORADA CON MEDIOS SEMI MECANICOS, PARA BANQUETA P.U.O.T. (20.0 CMS DE ESPESOR), INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRRAMIENTA, P.U.O.T.

M3

153.23

BANQUETA DE CONCRETO PREMEZCLADO F'C=150 KG/CM2 DE 9 CMS. TMA 3/4" DE ESPESOR, ACABADO ESCOBILLADO, INCLUYE: MATERIALES, MANO DE OBRA, CIMBRA Y VIBRADO, P.U.O.T.

M2

35.23

CURADO DE CONCRETO CON MEMBRANA DE CURADO EMULSIONADO BLANCO BASE AGUA., INCLUYE: MATERIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA,

M2

4.89

M2

3.87

3.2

3.3

3.8

3.9

3.10

LIMPIEZA GENERAL DE LA OBRA P.U.O.T.

TOTAL BANQUETAS

TOTAL DE PAVIMENTOS Y BANQUETAS NOTA :

1.- ESTOS PRECIOS NO INCLUYEN IVA. DE LOS TRABAJOS, Y EL RESTO EN ESTIMACIONES SEMANALES. 3.- ESTOS VOLUMENES FUERON PROPORCIONADOS POR USTEDES, POR LO QUE AL FINALIZAR LOS TRABAJOS SE HARAN LAS MEDICIONES REALES. 4.- LOS PRECIOS DE LOS MATERIALES QUE SON DERIVADOS DEL PETROLEO, SERAN RESPETADOS DURANTE EL MES QUE SE ESTA COTIZANDO YA QUE ESTOS, SE ESTAN INCREMENTANDO CADA MES, ESTOS INCREMENTOS SE HARAN TAMBIEN AL PRECIO UNITARIO. 5.- NO INCLUYE SUMINISTRO DE CONCRETOS. 6.- EL MATERIAL QUE SE ESTA CONSIDERANDO PARA LA EXCAVACION ES TIPO II.

ATENTAMENTE

________________________________________ ING. J. REFUGIO LOPEZ SANCHEZ GERENTE DE URBANIZACION

LEON, GTO. 9 DE OCTUBRE DEL 2008

A DENOMINADA "FRACC. RESIDENCIAL CAMPESTRE PRIVADA LOS EUCALIPTOS" UBICADA EN LA CARRETERA GU

S GUANAJUATO

CANTIDAD

IMPORTE

4932.48

14,254.86

2555.53

37,924.07

6394.64

811,671.90

3322.19

57,606.76

46510.65

146,508.55

4932.48

119,217.95

986.50

186,072.73

4932.48

47,697.04

4932.48

16,129.20

AL TERRACERIAS

1,437,083.05

CANTIDAD

IMPORTE

4212.47

12,174.02

1334.35

60,779.45

667.17

3,262.48

2883.79

-

1328.68

57,452.12

1328.68

6,497.24

140,165.31

AL PAVIMENTO

CANTIDAD

IMPORTE

1171.91

3,386.82

524.26

7,780.07

1812.12

240,885.76

2355.76

40,848.92

32980.67

103,889.12

1171.91

7,465.08

234.38

35,914.40

1171.91

41,286.44

1171.91

5,730.65

6771.56

26,205.94

AL BANQUETAS

MENTOS Y

481,456.60

2,058,704.96

___

Related Documents

Presupuesto Gto
October 2019 7
Gto
November 2019 6
Presupuesto
May 2020 39
Presupuesto
June 2020 28
Presupuesto
May 2020 24
Presupuesto
November 2019 48