Lekki Port LFTZ Enterprise W e l c o m e T o
port@lekki
Nigeria 2020 (Growth & Infrastructure)
Nigeria - a Country that has 140 million people handles only 600 000 TEU 600,000 TEUs per annum. ---------------------------Mainly due to insufficient capacity at the Ports
Nigeria 2020 (Growth & Infrastructure) Comparative Analysis SR NO
COUNT RY
T EU'S T RAFFIC (2007 NOS)
YEAR (DAT A)
POPULAT ION (NOS)
1
SINGAPORE
27,932,000
2007
4,588,600
2
HONG KONG
23,881,000
2007
7,040,885
3
SOUT H KOREA
13,270,000
2007
49,044,790
4
GERM ANY
13,507,039
2005
82,689,210
5
M ALAYSIA
12 620 000 12,620,000
2007
27 250 370 27,250,370
6
JAPAN
16,777,410
2005
128,084,700
7
EGYPT
4,500,000
2007
74,032,880
8
SOUT H AFRICA
2,867,909
2005
47,431,830
9
NIGERIA
2006
140,000,000
600,000
Data source:- World Port Ranking & World Container country League 2005
Nigeria 2020 (Growth & Infrastructure)
G r o w t h
Ni Nigeria i will ill be b Africa’s Af i ’ Largest L t economy y 2020. by
Double digit growth forecast in port traffic till 2020.
Nigeria 2020 (Growth & Infrastructure)
G r o w t h
Serious Congestion and Melt Down
The forecast is that by 2011 there will be a short fall in terminal capacity of approximately 160 160,,000 TEU’s within Nigerian ports ports.. Without infrastructure the expected growth will be hampered hampered..
Nigeria 2020 (Growth & Infrastructure)
G r o w t h
The additional growth of approximately 160,000 TEU’S due t port@lekki to t@l kki would increase the Nigerian GDP by 8 billion US$ (920 billion Naira). A Assumption ti : Every E additional dditi l 20 foot f t container t i b brought ht into i t Nigeria would add value worth approximately 50 50,,000 US US$ $.
Nigeria g 2020 (Growth ( & Infrastructure))
G r o w t h Nigeria has the potential to be a major transshipment hub for West African countries.
Nigeria 2020 (Growth & Infrastructure) I n f r a s t r u c t u r e
To ssupport pport the double digit growth forecast for Nigeria p and transshipment potential. -------------------------Requires the development of a new port
Introduction to p port@lekki. @
Jointly promoted by: by:--
Other Strategic Investors. Investors
Introduction to p port@lekki. @ L o c a t i o n
The approximate Project Site coordinate are 4˚00’E, 6˚25’ N in Lekki Peninsula, Nigeria.
Concept p & Design g . F e a t u r e s
SALIENT FEATURES: port@lekki has a 1,500 meters long “Main Breakwater”. A “Turning Circle” 600 meter in diameter. “Draft” of 16 to 18 meters. A 200 meters wide “Approach Channel”. port@Lekki will be the 1st “Deep Water” port in West Africa to berth larger p g vessels then the current ports can accommodate. The p port is designed g to berth vessels of 8,000 TEU’s and 160,000 DWT.
Concept p & Design g . F e a t u r e s
Design Vessel Size • Container vessel up 8,000 TEU with a maximum draft of 14.5 m and length of 335 m. • Suez Max and Aframax Tankers of 160,000 DWT and with maximum draft of 17.1 m and length of 310 m. m Dredge Channel • Will be 16.0 to 19.5 m deep. • 7.4 km long, g, 150 to 200 m wide. • Volume of capital dredging – 22 million cubic meters. • Dredged D d d material t i l will ill be b used d for f reclamation. l ti
Concept p & Design g . F e a t u r e s
Breakwaters “Main Breakwater” of 1,500 m length oriented to avoid wave p penetration and facilitating g natural sediment bye-pass & designed for 1:100 year return period storm.
Channel Length g 7.4 KM Dredged to 19.5m Width 150m - Widening to 200m
Concept p & Design g . T e r m i n a l D e s i g n
VEHICULAR ENTRANCE TO THE TERMINAL
Concept p & Design g . T e r m i n a l D e s i g n
VIEW FROM NORTH
Concept p & Design g . T e r m i n a l D e s i g n
VIEW FROM SOUTH
Concept p & Design g . T e r m i n a l D e s i g n
VIEW FROM EAST
Concept p & Design g . T e r m i n a l D e s i g n
VIEW FROM WEST
Concept p & Design g . T e r m i n a l D e s i g n
1
3
600m
2 6 = Berths
Concept p & Design g . M a r I t i m e F l e e t
Maritime Services Fleet With the Approval and assistance of the Nigerian Ports Authority y Lekki Ports LFTZ Enterprise p Will operate and manage its own Maritime Services Fleet of Vessels and Trained Pilots. Pilots.
Fast Pilot Launches
Tug Boats of 50 ton + Bollard Pull
Latest Navigational Aids will be Installed
Concept p & Design g . Key ey Container Co ta e Handling a d g Equipment qu p e t E q u i p m e n t
TYPE
NOS.
STS CRANES
8
TERMINAL BUMP CARTS REACH STACKERS FORKLIFT
114 4
TYPE
NOS.
RTG’S
28
TERMINAL TRACTORS EMPTY STACKER
85 4
11
The latest state of the art terminal handling equipment together with international productivity standards will make Lekki Port the most efficient port in West Africa,
Concept p & Design g . E q u i p m e n t
STS (SHIP TO SHORE) CRANES
Concept p & Design g . E q u i p m e n t RTG’S (RUBBER TYRED GANTRY CRANES)
Concept p & Design g . E q u i p m e n t
REACH & EMPTY STACKER
Concept p & Design g . E q u i p m e n t
TERMINAL TRACTORS BUMP CARTS AND FORK LIFTS
Work Already y Undertaken. C u r r e n t S t a t u s
The following g studies have been completed p ::-•
• • • • • • •
Oceanographic Studies Bathymetry Environmental Offshore Geotechnical Investigation Model Studies p Sediment Transport Nautical Simulation (Maritime Maneuvering & Berthing) 2D & 3D Break Water Testing and Simulation
Work Already y Undertaken. C u r r e n t S t a t u s
2D Tests: 2D Tests for Caisson portion ti off th the M i Main Breakwater conducted.
Work Already y Undertaken. Environmental Impact Assessment :
C u r r e n t
• EIA completed and clearance obtained to construct the Port@Lekki from Federal Ministry of Environment.
S t a t u s
• No significant environmental issues h have b been ffound d th thatt would restrict the expansion & operation of the Port
Work Already y Undertaken. C u r r e n t S t a t u s
Nautical Simulation:
A Tanker of 160,000 dwt A Container Vessel of 8,000 teus
Nautical Simulation undertaken by Alkyon of Holland to determine the criteria necessary to ensure safe berthing of vessels at Lekki Port
Work Already y Undertaken. C u r r e n t S t a t u s
Port Infrastructure already in place
Work Already y Undertaken. C u r r e n t S t a t u s
Port Infrastructure already in place
Office space in warehouse - I
Work Already y Undertaken. C u r r e n t S t a t u s
Port Infrastructure already in place
Development of Corporate Headquaters
Work Already y Undertaken. C u r r e n t S t a t u s
Provisional construction approval from NPA. On the 3rd June 2008 2008, “Lekki Lekki Port LFTZ Enterprise” obtained “Provisional Construction Approval” From “The The Nigerian Port Authority”
W ki Working closely l l in i cooperation ti with ith Nigerian Port Authorities
Work Already y Undertaken. C u r r e n t S t a t u s
Port project team in place Managing Director Project Director. Finance Director. Project Development Manager. Manager Admin Manager. Site Manager. Civil Engineer – Port Civil Engineer – Buildings & Infrastructure Civil Engineer g – Utilities. Chief Security Officer.
Activity y Schedule. C u r r e n t S t a t u s
August 2008 - Invitation to Bid Document will be released to prospective construction companies. October 2008 – Bid Documents will be received. October 2008 – Financial Closure will be achieved. November 2008 – Bid Documents will be scrutinised and evaluated. l t d December 2008 – Construction contract will be awarded. January J 2009 – Mobilsation M bil ti off Construction C t ti contractor. t t
Activity y Schedule. C u r r e n t S t a t u s
March 2009 – Quayy wall and Onshore construction to commence. March 2009 – Dredging of Inner Basin will commence. July 2009 – Channel Dredging operations will commence. July 2010 – Part of Berth will be ready for receiving terminal equipment equipment. March 2011 – Expected date when the terminal will be completed to allow the berthing of container vessels, vessels break bulk vessels and project cargo ashore.
Expansion p Plan. C u r r e n t S t a t u s
To cope with the expected demand, more land will be required in order to cater for the increase in containers traffic and bulk cargoes.. cargoes
Lekki Port LFTZ Enterprise
THANK YOU