Port Lekki Master Presentation

  • December 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Port Lekki Master Presentation as PDF for free.

More details

  • Words: 1,644
  • Pages: 38
Lekki Port LFTZ Enterprise W e l c o m e T o

port@lekki

Nigeria 2020 (Growth & Infrastructure)

Nigeria - a Country that has 140 million people handles only 600 000 TEU 600,000 TEUs per annum. ---------------------------Mainly due to insufficient capacity at the Ports

Nigeria 2020 (Growth & Infrastructure) Comparative Analysis SR NO

COUNT RY

T EU'S T RAFFIC (2007 NOS)

YEAR (DAT A)

POPULAT ION (NOS)

1

SINGAPORE

27,932,000

2007

4,588,600

2

HONG KONG

23,881,000

2007

7,040,885

3

SOUT H KOREA

13,270,000

2007

49,044,790

4

GERM ANY

13,507,039

2005

82,689,210

5

M ALAYSIA

12 620 000 12,620,000

2007

27 250 370 27,250,370

6

JAPAN

16,777,410

2005

128,084,700

7

EGYPT

4,500,000

2007

74,032,880

8

SOUT H AFRICA

2,867,909

2005

47,431,830

9

NIGERIA

2006

140,000,000

600,000

Data source:- World Port Ranking & World Container country League 2005

Nigeria 2020 (Growth & Infrastructure)

G r o w t h

Ni Nigeria i will ill be b Africa’s Af i ’ Largest L t economy y 2020. by

Double digit growth forecast in port traffic till 2020.

Nigeria 2020 (Growth & Infrastructure)

G r o w t h

Serious Congestion and Melt Down

The forecast is that by 2011 there will be a short fall in terminal capacity of approximately 160 160,,000 TEU’s within Nigerian ports ports.. Without infrastructure the expected growth will be hampered hampered..

Nigeria 2020 (Growth & Infrastructure)

G r o w t h

The additional growth of approximately 160,000 TEU’S due t port@lekki to t@l kki would increase the Nigerian GDP by 8 billion US$ (920 billion Naira). A Assumption ti : Every E additional dditi l 20 foot f t container t i b brought ht into i t Nigeria would add value worth approximately 50 50,,000 US US$ $.

Nigeria g 2020 (Growth ( & Infrastructure))

G r o w t h Nigeria has the potential to be a major transshipment hub for West African countries.

Nigeria 2020 (Growth & Infrastructure) I n f r a s t r u c t u r e

To ssupport pport the double digit growth forecast for Nigeria p and transshipment potential. -------------------------Requires the development of a new port

Introduction to p port@lekki. @

Jointly promoted by: by:--

Other Strategic Investors. Investors

Introduction to p port@lekki. @ L o c a t i o n

The approximate Project Site coordinate are 4˚00’E, 6˚25’ N in Lekki Peninsula, Nigeria.

Concept p & Design g . F e a t u r e s

SALIENT FEATURES:ƒ port@lekki has a 1,500 meters long “Main Breakwater”. ƒ A “Turning Circle” 600 meter in diameter. ƒ “Draft” of 16 to 18 meters. ƒ A 200 meters wide “Approach Channel”. ƒ port@Lekki will be the 1st “Deep Water” port in West Africa to berth larger p g vessels then the current ports can accommodate. ƒ The p port is designed g to berth vessels of 8,000 TEU’s and 160,000 DWT.

Concept p & Design g . F e a t u r e s

Design Vessel Size • Container vessel up 8,000 TEU with a maximum draft of 14.5 m and length of 335 m. • Suez Max and Aframax Tankers of 160,000 DWT and with maximum draft of 17.1 m and length of 310 m. m Dredge Channel • Will be 16.0 to 19.5 m deep. • 7.4 km long, g, 150 to 200 m wide. • Volume of capital dredging – 22 million cubic meters. • Dredged D d d material t i l will ill be b used d for f reclamation. l ti

Concept p & Design g . F e a t u r e s

Breakwaters “Main Breakwater” of 1,500 m length oriented to avoid wave p penetration and facilitating g natural sediment bye-pass & designed for 1:100 year return period storm.

Channel Length g 7.4 KM Dredged to 19.5m Width 150m - Widening to 200m

Concept p & Design g . T e r m i n a l D e s i g n

VEHICULAR ENTRANCE TO THE TERMINAL

Concept p & Design g . T e r m i n a l D e s i g n

VIEW FROM NORTH

Concept p & Design g . T e r m i n a l D e s i g n

VIEW FROM SOUTH

Concept p & Design g . T e r m i n a l D e s i g n

VIEW FROM EAST

Concept p & Design g . T e r m i n a l D e s i g n

VIEW FROM WEST

Concept p & Design g . T e r m i n a l D e s i g n

1

3

600m

2 6 = Berths

Concept p & Design g . M a r I t i m e F l e e t

Maritime Services Fleet With the Approval and assistance of the Nigerian Ports Authority y Lekki Ports LFTZ Enterprise p Will operate and manage its own Maritime Services Fleet of Vessels and Trained Pilots. Pilots.

Fast Pilot Launches

Tug Boats of 50 ton + Bollard Pull

Latest Navigational Aids will be Installed

Concept p & Design g . Key ey Container Co ta e Handling a d g Equipment qu p e t E q u i p m e n t

TYPE

NOS.

STS CRANES

8

TERMINAL BUMP CARTS REACH STACKERS FORKLIFT

114 4

TYPE

NOS.

RTG’S

28

TERMINAL TRACTORS EMPTY STACKER

85 4

11

The latest state of the art terminal handling equipment together with international productivity standards will make Lekki Port the most efficient port in West Africa,

Concept p & Design g . E q u i p m e n t

STS (SHIP TO SHORE) CRANES

Concept p & Design g . E q u i p m e n t RTG’S (RUBBER TYRED GANTRY CRANES)

Concept p & Design g . E q u i p m e n t

REACH & EMPTY STACKER

Concept p & Design g . E q u i p m e n t

TERMINAL TRACTORS BUMP CARTS AND FORK LIFTS

Work Already y Undertaken. C u r r e n t S t a t u s

The following g studies have been completed p ::-•

• • • • • • •

Oceanographic Studies Bathymetry Environmental Offshore Geotechnical Investigation Model Studies p Sediment Transport Nautical Simulation (Maritime Maneuvering & Berthing) 2D & 3D Break Water Testing and Simulation

Work Already y Undertaken. C u r r e n t S t a t u s

2D Tests: 2D Tests for Caisson portion ti off th the M i Main Breakwater conducted.

Work Already y Undertaken. Environmental Impact Assessment :

C u r r e n t

• EIA completed and clearance obtained to construct the Port@Lekki from Federal Ministry of Environment.

S t a t u s

• No significant environmental issues h have b been ffound d th thatt would restrict the expansion & operation of the Port

Work Already y Undertaken. C u r r e n t S t a t u s

Nautical Simulation:

A Tanker of 160,000 dwt A Container Vessel of 8,000 teus

Nautical Simulation undertaken by Alkyon of Holland to determine the criteria necessary to ensure safe berthing of vessels at Lekki Port

Work Already y Undertaken. C u r r e n t S t a t u s

Port Infrastructure already in place

Work Already y Undertaken. C u r r e n t S t a t u s

Port Infrastructure already in place

Office space in warehouse - I

Work Already y Undertaken. C u r r e n t S t a t u s

Port Infrastructure already in place

Development of Corporate Headquaters

Work Already y Undertaken. C u r r e n t S t a t u s

Provisional construction approval from NPA. On the 3rd June 2008 2008, “Lekki Lekki Port LFTZ Enterprise” obtained “Provisional Construction Approval” From “The The Nigerian Port Authority”

W ki Working closely l l in i cooperation ti with ith Nigerian Port Authorities

Work Already y Undertaken. C u r r e n t S t a t u s

Port project team in place ƒ Managing Director ƒ Project Director. ƒ Finance Director. ƒ Project Development Manager. Manager ƒ Admin Manager. ƒ Site Manager. ƒ Civil Engineer – Port ƒ Civil Engineer – Buildings & Infrastructure ƒ Civil Engineer g – Utilities. ƒ Chief Security Officer.

Activity y Schedule. C u r r e n t S t a t u s

ƒ August 2008 - Invitation to Bid Document will be released to prospective construction companies. ƒ October 2008 – Bid Documents will be received. ƒ October 2008 – Financial Closure will be achieved. ƒ November 2008 – Bid Documents will be scrutinised and evaluated. l t d ƒ December 2008 – Construction contract will be awarded. ƒ January J 2009 – Mobilsation M bil ti off Construction C t ti contractor. t t

Activity y Schedule. C u r r e n t S t a t u s

ƒ March 2009 – Quayy wall and Onshore construction to commence. ƒ March 2009 – Dredging of Inner Basin will commence. ƒ July 2009 – Channel Dredging operations will commence. ƒ July 2010 – Part of Berth will be ready for receiving terminal equipment equipment. ƒ March 2011 – Expected date when the terminal will be completed to allow the berthing of container vessels, vessels break bulk vessels and project cargo ashore.

Expansion p Plan. C u r r e n t S t a t u s

To cope with the expected demand, more land will be required in order to cater for the increase in containers traffic and bulk cargoes.. cargoes

Lekki Port LFTZ Enterprise

THANK YOU

Related Documents

Port
November 2019 44
Port.
December 2019 35