CLIENT: PROJECT NO: DATE: PHASE: CHECKER:
SHEET 1 of 2
INFORMATION REQUIRED FOR CHECKING IFA
IFR
IFE
IFC P&ID’s PFD's Equipment List Vendor Drawings PEM 4207 Client Design Guide if available Project SOW Preliminery site data for potential project area Plant Survey Drawing As-Built survey information As Built Drawing of Existing Plant
BASIC DRAWING INFORMATION IFA
IFR
IFE
IFC Title Block - Title, Project Number and Drawing Number Designer / Checker Initials and Date Revision Number and Date Scale
CHECK LIST IFA
IFR
IFE
IFC
IFA
IFR
IFE
IFC
Plant Boundary (CONFIRM WITH CIVIL) Plant Datum location referenced to UTM coordinates (CONFIRM WITH CIVIL) Plant North / True North and Prevailing Wind Direction Identified (CONFIRM WITH CIVIL) Maintenance Access & Walkways Locations of Roads, Trenches, Pipe racks Etc. Major process equipment shown
Buildings, including non process buildings Drainage ditches and runoff ponds Plant grid and plant coordinates
SHEET 2 of 2
CLIENT: PROJECT NO: DATE: PHASE: CHECKER:
SHEET 1 of 2
INFORMATION REQUIRED FOR CHECKING Location of Existing Underground Lines & Cables Future Equipment Space Requirements Equipment Spacing complies with regulatory, IMV and client guidelines. Process - Proximity Of Associated Pieces Of Equipment Access roads for maintenance, construction and operations Plot plan Equipment and Building List Constructability Architectural - Location of access stairways and access doors Above ground pipe racks Tank farm containment areas Easements and Right Of Ways Soil stockpile areas Bundle pulling areas Fire Fighting stations Plant ESD station Construction Laydown areas COMMENTS