Permit to work system Different types
of Maintenance of Power Plant and its cost effectiveness Maintenance Planning Power Plant Operation
Permit to Work System PTW
is a printed form and issued to employee before they may work on specified equipment. Objective is to ensure safety of employee PTW is Guarantee of Safety
Steps/ Arrangement while issuing PTW PTW
should be issued only against the presentation of an isolation request by maintenance Department Except in case of emergency. Person presenting himself to collect PTW should be fully familiar with the job and details of work to be done All Copies of PTW must be signed both at Receipt and Clearance Receipt and Clearance signature must be made in presence of Shift Charge Engineer/ Unit incharge PTW should be signed for clearance by the person who signed for receipt
Steps/ Arrangement while issuing PTW …….contd Whenever a job is permanently transferred
from one person to another, the permit should be cancelled and reissued. The PTW is cancelled and reissued when change in isolation become necessary Work on medium/ low voltage equipments should be done when they are dead. At least two isolation should be in service in case of electrical Permit “Do Not Operate” caution board should be put on desk on control station of equipments under PTW
Steps/ Arrangement while issuing PTW …….contd An emergency Job Card should be opened by
operation department giving details of work in case of Emergencies Operation representative has to deliver the equipment to maintenance section ensuring all safety Operation representative must ensure that job has been carried out properly before taking back the PTW. Operation representative must ensure that there is no danger before charging the equipment/ System
At Work Maintenance person should must ensure
that PTW has been issued for their own safety It is responsibility of all persons on site to ensure that they do not start work on equipments for which a PTW is necessary untill PTW is issued.
Role of Operation Engineer Safety of equipment Safety of Persons Generation of Electricity at economic cost Keeping generation within the declared
schedule Start up and shut down of equipments in safe and systematic manner
Role of Operation Engineer ….Contd. Maintaining the parameters within
prescribed limit Physical Inspection of equipment to observe Noise, Vibration etc. Prompt Decision Making Cost Effectiveness in Present Scenario (ABT - UI)
Grid Discipline Grid Discipline is given a priority in ABT Incentive and penalty in form of UI to
maintain Grid Frequency Penalty when actual generation is less than scheduled Incentive when actual generation is more than scheduled generation when frequency is less It is a new challenge for operation engineer
U I Rate Each
0.02 Hz step is equivalent to 8.0 paise/kwh in the range of 49.8-50.5 Hz Penalty is 18.0 paise/kwh in the range of 49.049.8 Hz for each 0.02 Hz step Incentive is 18.0 paise/kwh in the range of 49.8-49.66 Hz for each 0.02 Hz step below 49.66 is fixed UI rate is capped at 49.66 when actual generation exceeds the scheduled generation UI rate goes up to Rs 10.0 per Kwh when actual generation is below scheduled generation
STEPS Pre Start Up/Light Up Checks Starting Auxiliaries Light Up Rolling and Soaking Synchronization Loading Off Loading Shut Down
Type of Start Cold Start Hot Start
Auxiliaries
Boiler Auxiliaries Milling
System Draft System ESP
Turbine Auxiliaries Pumps Feed Heaters Dearator
Generator Auxiliaries Seal
Oil System Hydrogen Cooling System Stator Water Cooling System
START UP PROCEDURE FOR STAGE-I AND II UNITS 0. RELAY RESETTING. 1. START ID AND FD 1.1 Deaerator tank Heating/AS-57 etc 1.2 SCRAPPER/SLAG CRUSHER IN SERVICE 1.3 BIGGER SIZE OIL GUN TIPS 2. BOILER LIGHTUP 2.1 START PA FANS : FLUE GAS TEMP>350 2.11 START MILLING SYS AND PC FEEDER 2.2 START SEAL AIR FAN 3. MAINTAIN TOTAL AIR FLOW >30% 4. DRUM PR =5 KSC CLOSE BOILER VENTS
START UP PROCEDURE FOR STAGE-I AND II UNITS
5. CLOSE SH HDR DRAINS 6. OPERATE BOILER LPDS AT 10 KSC DRUM PRESS. 6.1 START COND VACC PULLING 6.2 CHARGE SEALING STEAM ; 150 mm Hg Take GSC-1 7. CHARGE HP/LP BYPASS/APRDS MS 30 KSC/330 CELSIUS 7.1 READY RESPECTIVE BAY FROM S/YARD 7.2 UAT BREAKERS SERVICE REMOTE 7.3 AC/DC FIELD FLASHING SUPPLIES ON 8. TPL HEATING DRAINS OPEN 8.1 STG-I MS-9,10 OR BYPASS ESV 60% OPEN 8.2 STG-II LOCK IV OPEN ESV=60% MS-5,6 OPEN
START UP PROCEDURE FOR STAGE-I AND II UNITS 9. STOP TPL HEATING/NORMALISE LOCKING 10. MANNING OF SEAL OIL SYSTEM 10.1 LINEUP FOR FLANGE/STUD HTNG 10.2 OPEN HPC AND IPC CYL DRAINS 11. START ROLLING 500 RPM 12. ROLLING 1100 RPM 13. ROLLING 3000 RPM 13.1 STOP SOP 13.2 START CW BOOSTER PUMP
START UP PROCEDURE FOR STAGE-I AND II UNITS 14. SYNCHRONISE THE UNIT 15. OPEN MS-1,2 OR 9,10 AND ISOLATE HP/LP BYPASS OR PRDS 15.1 RAISE LOAD TO 50 MW : TAKE UATS IN SERVICE 15.2 OPEN AS-30 STG-I 15.3 CHARGE LPHS START DRIP PUMP STG-I 15.4 NORMALISE DEAERATOR EXT –IN ;HTNG –STOP 15.5 CLOSE ALL TURBINE SIDE DRAINS 15.6 PUT ALL PROT IN SERVICE
START UP PROCEDURE FOR STAGE-I AND II UNITS 16. START SECOND BFP RAISE LOAD 17. CHARGE HPHS AT 100 MW 18. TAKE AS-49/11 ATA IN SERVICE 19. CHARGE ESP ZONES 20. ISOLATE FLANGE/STUD HEATING/STARTING EJECTOR
PLANNED SHUTDOWN OF STAGE-1 UNITS 1. 2. 3. 4. 5. 6. 7.
REDUCE THE LOAD ALONGWITH OIL GUNS TO 30-35 MW ISOLATE LPHs FROM STEAM AND WATER SIDE STOP DRIP PUMP UAT CHANGEOVER /MAINTAIN PC LEVEL TRIP THE UNIT AROUND 20 MW/MS TEMP=480-450. START SOP .LATER ON C/O TO AC LOP AND AC SEAL OIL PUMP CLOSE AS-30 SPINDLE LEAKOFF TO D/A
PLANNED SHUTDOWN OF STAGE-1 UNITS PUT TG SET ON B/GEAR. CLOSE SYPHON FILLING V/V KILL THE COND VACUUM.CLOSE AS-9 AND D/A DOME HEATING V/V 3. 4. 5.
BOILER LPD OPERATION AT 10 KSC DRUM PRESS RACK OUT UAT BRKR ,OPEN BAY ISOLATOR SWITCH OFF AC/DC FIELD FLASHING SUPPLIES
PLANNED SHUTDOWN OF STAGE-1 UNITS 2. 3. 4. 5. 6.
TAKE LOCAL TG SET ECC. START TSI LOGGING SWITCH OFF EP ZONES CLOSE FO-1 ISOLATE 11ATA V/V AND OPEN DRAINS OPEN SH/DRUM VENTS AND STOP SLAGCRUSHERS.
PLANNED SHUTDOWN OF STAGE-2 UNITS
REDUCE LOAD AS FAR AS POSSSIBLE WITH 4 MILL W/OUT OIL NORMALISE TURBINE SEALING (IF ADJUSTED) CONTROL TSI PARAMETERS CLOSE ALL FUEL /AUX AIR DAMPERS TAKE OIL AND CUT OFF LOWER MILLS TO MAINTAIN MS TEMP REDUCE LOAD TO 100 MW
PLANNED SHUTDOWN OF STAGE-2 UNITS
ISOLATE HPH HEATERS. DO UAT CHANGEOVERS MAINTAIN TOTAL AIR FLOW> 30 % STOP ONE FD TO CONTROL OXYGEN/FURNACE HUNTING REDUCE LOAD FURTHER TO 30-40 MW .STOP ONE BFP TRIP THE UNIT.START SOP.CHECK COASTING TREND OF TG ISOLATE EXTRACTIONS .Give tripping commands to tripped brkr ENGAGE B/GEAR TAKE LOCAL TG ECC
PLANNED SHUTDOWN OF STAGE-2 UNITS
KILL THE COND VACUUM..CLOSE AS-61 BOX UP THE BOILER. SWITCH OFF EP ZONES. OPERATE BOILER LPD AT 15 KSC DRUM PRESS OPEN BOILER/SH VENTS AT 5 KSC DRUM PRESS RACK OUT UAT BRKRS AND OPEN BAY ISOLATOR SWITCH OFF AC/DC FIELD FLASHING SUPPLY STOP LDO PUMP. ISOLATE 16 ATA AND OPEN DRAINS START LOGGING OF TSI /DRUM METAL TEMP
PLANNED SHUTDOWN OF STAGE-2 UNITS PRECAUTIONS: BOILER DRAININGAT DRUM METAL
TEMP<120 STOPPING OF B/GEARHPT T/B TEMP<120 APPROX 129 HRS GEN CASING DEPRESSURISED.SEAL OIL ISOLATED STOP CW PUMPS AT EXHAUSTHOOD TEMP<60
Frequency
UI Rate (+)
UI Rate (-)
Variable Charges
49.0
406
1000
130.168
49.1
406
910
130.168
49.2
406
820
130.168
49.3
406
730
130.168
49.4
406
640
130.168
49.5
406
550
130.168
49.6
406
460
130.168
49.66
406
406
130.168
49.7
370
370
130.168
49.8
280
280
130.168
49.9
240
240
130.168
50.0
200
200
130.168
50.1
160
160
130.168
50.2
120
120
130.168
50.3
80
80
130.168
50.4
40
40
130.168
50.5
0
0
130.168