Oakland–Macomb Interceptor Drain Rehabilitation State Revolving Fund – Project Plan Overview Public Meeting – June 10, 2009

What is the OMI? • The OMI is the Oakland Macomb Interceptor Sewer. • The OMI transports much of the sanitary sewage from Oakland and Macomb Counties to the Detroit Water & Sewerage Department (DWSD) for treatment. • The OMI is a 21 mile long pipe tunnel. • The OMI is between 3’ 0” and 12’ 9” in diameter (mostly over 8’) • The OMI is buried up to 100 ‘ deep. • The OMI serves about 830,000 people.

Oakland–Macomb Interceptor Drain Rehabilitation

What is the OMI Service Area?

Oakland–Macomb Interceptor Drain Rehabilitation

Who does the OMI Service? • • • • • • • • • • • •

City of Auburn Hills City of Clarkston City of Rochester City of Rochester Hills Independence Township Oakland Township Orion Township Oxford Township West Bloomfield Township Waterford Township Village of Lake Orion Village of Oxford

• • • • • • • • • • •

City of Fraser City of Sterling Heights City of Utica Chesterfield Township Clinton Township Harrison Township Lenox Township Macomb Township Shelby Township Washington Township Village of New Haven

Oakland–Macomb Interceptor Drain Rehabilitation

Where is the OMI located? • Begins at Dequindre and Avon Roads – An arm follows M-59 • Follows Clinton River and Utica Road to Dodge Park Road. • Follows Dodge Park Rd. to 15 Mile Road. • Follows 15 Mile Rd, to the ITC (Edison) Corridor • Follows the ITC Corridor to 9 Mile Road. • Follows the Railroad ROW to just south of Eight Mile Road.

What is the History of the OMI? • Built in the early 1970s by Detroit Water and Sewerage Department • Series of Construction Contracts • Included the 15 Mile and Romeo Arms in Macomb County • Three Collapses on15 Mile – 1978, 1980, 2004 • Major Disruption Occurred – Loss of Service – Environmental Impairment – Surface Disruption • $200,000,000 in Repair Costs (current dollars)

• INSERT FIG 4

What Disruption is Caused by a Collapse?

Oakland–Macomb Interceptor Drain Rehabilitation

What is the OMI’s Current Condition? • The OMI was inspected in 2007 and 2008. • Visual inspection was conducted by staff and by using CCTV. • Much of the pipe exhibited moderate to severe deterioration. • Voids were detected above the pipe in a number of areas. • Infiltration through cracks will continue to deteriorate the pipe.

Projecting Reinforcing Steel 

Crown of Pipe Severely Deteriorated

Oakland–Macomb Interceptor Drain Rehabilitation

Why is the Project Needed? • The OMI was constructed using the same design, materials and contractors in the same soil conditions and at the same time as the 15 Mile Road Interceptor. • The 15 Mile Road Interceptor has failed three times with catastrophic results. • Rehab will prevent environmental impairment. • Rehab of the OMI will prevent collapse at costs far less than future repairs.

Where are the Problem Areas? • High Distress Areas – – – – – –

Avon Arm (M-59) – 2 areas 15 Mile west of corridor Corridor south of 15 Mile Corridor at I-696 Corridor at 10 ½ Mile Corridor south of 10 Mile

• Medium Distress Areas – – – – –

Utica south of M-59 Dodge Park south of 18 Mile Dodge Park south of 16 Mile Corridor north of 12 Mile Corridor south of 11 ½ Mile

• Localized Distress Throughout

• INSERT FIG 8

What are the Alternatives? Three Alternatives were analyzed • The first is the “No Action” Alternative • The second is the “Replacement” Alternative • The third is the “Rehabilitation” Alternative

Oakland–Macomb Interceptor Drain Rehabilitation

What is the No Action Alternative? • THE OMI would remain in service with no repair or rehabilitation. • Structural defects would remain and expand. • Pipe failure – collapse – could be anticipated at some unknown time. • Initial Capital cost would be Zero. • Additional user cost would be Zero. • Future Repair cost could be Significant. • Potential Environmental Impact is Severe.

Oakland–Macomb Interceptor Drain Rehabilitation

What is the Replacement Alternative? • The existing pipe would be replaced in a tunnel roughly paralleling the current route. • Construction would disrupt many neighborhoods. • Initial Capital Cost would be $499,000,000. • Additional User Cost would be about $103 per year per customer over 20 years.

• INSERT FIG 7

What is the Rehabilitation Alternative? • Control Structures would be constructed to allow work inside the tunnel while maintaining service to customers. • Structural lining would be constructed in severely deteriorated areas. • Cracks and leaks would be sealed to prevent further deterioration. • Initial Capital Cost would be about $160,000,000. • Additional User Cost would be about $35 per year per customer over 20 years.

Oakland–Macomb Interceptor Drain Rehabilitation

How do the Alternative Costs Compare? Estimated Capital Cost SRF Interest Rate Term - in years Estimated Annual Payment

ALTERNATIVES No Action Replacement Rehabilitation $ - $ 499,000,000 $ 160,068,220 2.50% 2.50% 2.50% 20 20 20 $ - $ 32,009,417 $ 10,267,917

Estimated Annual O&M Cost

$ 832,529 $

Estimated Total Annual Cost

$ 832,529 $ 32,841,946 $ 11,100,446

Service Area Population Average Household Size Number of Customers Estimated Annual Cost per Customer over 20 years

832,902 2.61 319,120 $

832,529 $

832,902 2.61 319,120

832,529

832,902 2.61 319,120

2.61

plus potential repair costs

$

Oakland–Macomb Interceptor Drain Rehabilitation

102.91 $

34.78

What Alternative has been selected? • The Rehabilitation Alternative provides for construction leading to a tunnel with a useful life of at least 20 years. • The alternative does not require area-wide disruption that Replacement would. • The alternative will protect against catastrophic collapse that is a potential of No Action. • The annual user cost of about $35.00 (over 20 years) will be much less than potential repair costs and is a reasonable addition to current rates.

Oakland–Macomb Interceptor Drain Rehabilitation

When will the Work Take Place? Design Efforts: Year Quarter Q1 Project Component Hydraulic Study Modify Corridor Gate Supplimental Geotech PCI-5 Gate PCI-5 Rehab PCI-5 Grouting PCI-8 New Gate PCI-9 Temp fix of hole PCI-8 New Access Shaft PCI-8 Rehab PCI-7 Corridor Bypass PCI-7 Rehab PCI-7 Grouting PCI-11A Rehab PIC-6 New Gate PCI-6 Rehab PCI-6 Groutimg PCI-9 Control Structure PCI-9 Rehab PCI-10B Rehab PCI-10A Rehab

Construction Efforts:

2009 Q2

Q3

2010 Q4

Q1

Q2

Q3

2011 Q4

Q1

Q2

Oakland–Macomb Interceptor Drain Rehabilitation

Q3

1012 Q4

Q1

Q2

Q3

2013 Q4

Q1

Q2

Q3

Q4

What are the Social & Environmental Impacts? • Without Replacement or repair collapse of the OMI could cause up to 83 million gallons of raw sewage to be discharged by tributary communities per day. • During Rehabilitation surface disruption to open-space and parkland may take place that will be mitigated upon completion. • Minor construction related impacts will also occur. These impacts include additional noise, dust, sediment and traffic. These will be minimized by staging construction and implementing best management practices. • No Historical or Archeological sites will be disturbed as part of the Rehabilitation. Oakland–Macomb Interceptor Drain Rehabilitation

Any Questions or Comments?

Oakland–Macomb Interceptor Drain Rehabilitation

Thank You for Your Interest !

Oakland–Macomb Interceptor Drain Rehabilitation