Radiogram No. 4724u Form 24 for 02/19/07 COMMANDING САУП ОНА [HIGH-GAIN ANTENNA AUTOMATIC DRIVE CONTROL SYSTEM] FROM POSITION 1 TO POSITION 2. DC1-ТКГ LEAK CHECK GMT CREW ACTIVITY 02:00-02:10 .
Morning inspection
02:10-02:40 .
Post-sleep
02:40-03:30 .
BREAKFAST
03:30-04:00 .
Prep for Work
04:00-04:15 .
Daily Planning Conference (S-band)
04:15-04:45 CDR,FE-2 Conference to brief the crew on 13A Prepack Operations (S-band) 05:10-05:15 CDR
Connect DCP power cable
05:10-05:30 FE-2
MELFI - ICEPAC Insertion into a Box Module
05:15-06:15 CDR
Physical Exercise (RED)
05:30-05:50 FE-2
IMS update
06:15-07:45 CDR
Physical Exercise (TVIS + CEVIS)
06:15-06:20 FE-2
Payload status check /
06:20-07:20 FE-2
EarthKAM: setup, activation
06:35-06:45 FE-1
Soyuz 219 Gas Analyzer deactivation
06:45-08:15 FE-1
Physical Exercise (TVIS), day 3
07:20-08:20 FE-2
Physical Exercise (RED)
07:45-08:15 CDR
Multi-Use Tether (MUT) Modification
08:15-08:30 CDR,FE-1 Fresnel lens install in Orlan 08:30-09:30 .
Review Airlock Ops Procedure per RODF "EVA from DC1". Tagup with specialists (VHF+S-band)
09:30-10:30 .
LUNCH
10:30-10:40 FE-1
PLANTS-2. Photography
10:30-11:30 FE-2
DOUG Software Review
10:40-11:20 FE-1
Filling EDV [KOB] (separation) for Elektron
10:50-10:55
Configure Cameras for 2B Solar Array Wing Survey
10:55-11:10 CDR
Removal of sealing cover from window #13 in SM ПхО during survey of SA 2В.
11:10-11:40
Photo/TV 2B Solar Array Wing Survey
11:20-11:50 FE-1
СОЖ Maintenance
11:30-12:30 FE-2
SSRMS checkout
11:50-12:50 FE-1
Physical Exercise (VELO + RED) day 3
12:30-14:00 FE-2
Physical Exercise (CEVIS)
12:45-13:15 CDR
Photo/TV 2B Solar Array Wing Survey
13:00-13:20 FE-1
Testing КВД [Pressure Equalization Vlv] from ПОВ panels in ПхО and in DC1 DC1 Comm Config
13:15-13:30 CDR
Installation of sealing cover on window #13 in SM ПхО after survey of SA 2В
13:30-13:40 FE-1
Medical Kit config for EVA
13:45-14:45 CDR,FE-1 Install Progress 359 Docking Mechanism 14:00-15:30 FE-2
SSRMS checkout
14:45-15:30 FE-1
Progress 359 activation, air duct dismantling
14:50-15:30 CDR
Portable Repress Tank (БНП) set up in РО (Working Compartment) (#3 п.1, 001473R, СМ1ПхО_4)
15:30-15:50 CDR,FE-1 Removal of quick-release screw clamps from DC1 15:30-15:35 15:35-16:15
FE-2
Transfer TVIS/RED/CEVIS/HRM data to MEC Evening work prep
15:50-16:10 CDR,FE-1 DC1-Progress transfer hatch closure 16:10-17:10 FE-1
DC1-СУ and СУ-Progress hatch leak check
16:10-16:20 CDR
Daily Food Prep
16:15-16:40 FE-2
Daily Food Prep
16:20-16:35
Private Family Conference (S + Ku-band)
16:35-16:40
CDR
Daily Food Prep
16:40-17:10 CDR,FE-2 DINNER 17:10-17:25 .
Daily Planning Conference (S-band)
17:25-17:55 FE-1
DINNER
17:25-18:30 FE-2
Pre-sleep
17:25-17:55 CDR
Installation of additional Portable Repress Tank (БНП) in DC1 In-flight comm procedures
17:55-18:30 CDR,FE-1 Pre-sleep 18:30-03:00 . Task List
FE-1
SLEEP ТБУ (Universal Bioengineering Thermostat). Temperature check
PLANTS-2. Payload status check Note: See OSTP for references to US activities. End of Radiogram