Radiogram No. 4636u

Form 24 for 02/04/07

USOS EVA-7 GMT

CREW

ACTIVITY

08:30-09:00

CDR,FE-2 BREAKFAST

08:30-08:35

FE-1

PLASMA CRYSTAL-3 PLUS. Turbo-pump activation

08:35-08:40

FE-1

Morning inspection

08:40-09:10

FE-1

Post-sleep

09:00-10:10

CDR,FE-2 EVA - Hygiene Break/Prebreathe

09:10-09:30

FE-1

BREAKFAST

09:30-09:40

FE-1

Comm config for EVA

09:40-10:10

FE-1

EVA - Hygiene Break/Prebreathe

10:10-10:20

FE-1

DCS 760 EVA Camera Hatch Close Configuration

10:10-10:20

CDR,FE-2 Post-sleep ops

10:20-12:10

.

EVA Prep

12:10-12:25

.

EMU purge

12:25-13:25

.

EMU prebreathe

13:25-13:55

.

Crew Lock depress

13:55-14:00

.

Terminate prebreathe

14:00-17:15

FE-1

EVA-7 IV Support, LUNCH

14:00-14:30

CDR,FE-2 Crewlock Egress and EVA 7 Setup

14:30-16:45

FE-2

Liquid Loop B QD Connections (port)

14:30-16:45

CDR

Loop B Electrical Connections (starboard)

16:45-17:20

CDR,FE-2 Aft radiator prep

17:15-17:25

FE-1

17:20-17:35

CDR,FE-2 Retraction of the aft radiator

17:25-18:05

FE-1

17:35-18:25

CDR,FE-2 Aft radiator cinch

18:05-18:35

FE-1

18:25-18:55

CDR,FE-2 Early Ammonia Sytem (EAS) Fluid Line Preparation including Jumper Relocate

18:35-20:05

FE-1

Physical Exercise (TVIS), day 4

18:55-19:00

CDR

Retrieve APFR (Foot Restraint) From PMA1

18:55-19:45

FE-2

Installation of ISS/Shuttle power cable

19:00-19:50

CDR

Installation of ISS/Shuttle power cable

19:45-19:50

FE-2

Retreive Long Cutters

19:50-20:05

CDR,FE-2 EVA Cleanup

20:05-20:20

.

Crew Lock Ingress

20:20-20:25

.

Crew Lock Repress

20:25-20:35

.

Crew Lock Repress

20:35-21:55

.

Post-EVA ops

21:55-22:05

FE-1

СТТС reconfig for nominal ops

21:55-22:00

CDR

DCS 760 camera config for the next EVA

Video tape change out АОК ГАНК-4М calibration and readings СОЖ maintenance

22:00-22:30

CDR,FE-2 DINNER

22:05-22:20

FE-1

Post-EVA Pille dosimeter reading

22:20-22:50

FE-1

22:30-23:00

CDR,FE-2 Daily Food Prep

DINNER

22:50-23:00

FE-1

Daily Food Prep

23:00-23:55

FE-1

Pre-sleep

23:00-00:00

CDR,FE-2 Pre-sleep

23:55-00:00

FE-1

PLASMA CRYSTAL-3 PLUS. Turbo-pump deactivation

00:00-08:30

.

SLEEP ТБУ temperature check

Task List

FE-1

PLANTS-2. Payload status check Search for CO2 Filter Unit

Note: See OSTP for references to US activities. End of Radiogram