Microsoft Office Project - Proposed Office & Amenity Block

  • Uploaded by: Beth Maxwell
  • 0
  • 0
  • July 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Microsoft Office Project - Proposed Office & Amenity Block as PDF for free.

More details

  • Words: 2,278
  • Pages: 18
Proposed Office Building ID

Task Name

1

Design Lead in

2 3

Duration

Start

Finish

20 days

Mon 04/01/10

Fri 29/01/10

Receipt of Order

1 day?

Mon 04/01/10

Mon 04/01/10

Place Order for Steel

1 day?

Mon 04/01/10

Mon 04/01/10

4

Place Order for Long lead in items

1 day?

Mon 04/01/10

Mon 04/01/10

5

Site clearance, removal of client materials 3 days

Tue 05/01/10

Thu 07/01/10

6

Site investigation for old services/CAT 1Scan day?of area Thu 07/01/10

7

Set up site

Fri 08/01/10

Wed 13/01/10

8

Breaking up of existing pavings to construct 14 daysnew Thu car park 14/01/10

Tue 02/02/10

9

Ground improvement works

10 days

Wed 03/02/10

Tue 16/02/10

10

Setting out of site

10 days

Wed 17/02/10

Tue 02/03/10

11

Excavation works to reduce levels, for10foundations days Wed / ground 03/03/10 beamsTue 16/03/10

12

Install new drainage

10 days

Wed 17/03/10

Tue 30/03/10

13

Foundations for steel frame

10 days

Wed 31/03/10

Tue 13/04/10

14

Erection of steel frame

5 days

Wed 14/04/10

Tue 20/04/10

15

Intumescent Paint to Steel

5 days

Wed 21/04/10

Tue 27/04/10

16

Install Bison Beams

5 days

Wed 28/04/10

Tue 04/05/10

17

Erect Scaffold for Bricklayers

5 days

Wed 05/05/10

Tue 11/05/10

18

Construction of external walls To Building 12 days

Wed 12/05/10

Thu 27/05/10

19

Form Ground Floor slab/Power float

2 days

Fri 28/05/10

Mon 31/05/10

20

Construct internal walls/Partitions

5 days

Tue 01/06/10

Mon 07/06/10

21

Screed to Floors

2 days

Tue 08/06/10

Wed 09/06/10

22

Fire protection to all voids/ penetrations 5 days

Thu 10/06/10

Wed 16/06/10

23

Plaster to internal walls/partitons

3 days

Thu 17/06/10

Mon 21/06/10

24

Adapt scaffold for roof works

3 days

Tue 22/06/10

Thu 24/06/10

25

Construction of roof/rainwater Pipes 10 days

Fri 25/06/10

Thu 08/07/10

26

Install man safe system to roof

2 days

Fri 09/07/10

Mon 12/07/10

27

Mechanical and Electrical first fix

20 days

Tue 13/07/10

Mon 09/08/10

28

Adapt scaffold for windows and curtain7walling days

Tue 10/08/10

Wed 18/08/10

29

Curtain walling / windows and doors 8 days

Thu 19/08/10

Mon 30/08/10

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

4 days

09 W

T

F

S

S

07 Dec '09 M T W

T

F

S

S

Thu 07/01/10

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 1

14 Dec '09 M T W

T

F

S

S

21 Dec '09 M T W

T

F

S

S

Proposed Office Building ID

Task Name

Duration

Start

Finish

30

Drop scaffold

2 days

Tue 31/08/10

Wed 01/09/10

31

Canopy to front entrance

5 days

Thu 02/09/10

Wed 08/09/10

32

Spiral stair case to side elevation

3 days

Thu 09/09/10

Mon 13/09/10

33

Install ceilings

3 days

Tue 14/09/10

Thu 16/09/10

34

Demountable partitions

3 days

Fri 17/09/10

Tue 21/09/10

35

Painting to all walls / skirtings / ceilings5 days

Wed 22/09/10

Tue 28/09/10

36

Floor coverings

5 days

Wed 29/09/10

Tue 05/10/10

37

Internal fixtures, fitting, finishes

11 days

Wed 06/10/10

Wed 20/10/10

38

Install kitchen units

3 days

Thu 21/10/10

Mon 25/10/10

39

Tiling to all areas

4 days

Tue 26/10/10

Fri 29/10/10

40

Mechanical and Electrical 2nd fix

6 days

Mon 01/11/10

Mon 08/11/10

41

New drainage to building

5 days

Tue 09/11/10

Mon 15/11/10

42

New services to building

5 days

Tue 16/11/10

Mon 22/11/10

43

Final fix Electrical & Mechanical

4 days

Tue 23/11/10

Fri 26/11/10

44

Install Lift

3 days

Mon 29/11/10

Wed 01/12/10

45

Form new car park

7 days

Thu 02/12/10

Fri 10/12/10

46

New drainage to car park

3 days

Mon 13/12/10

Wed 15/12/10

47

Finish to Car Park/White Lining

5 days

Thu 16/12/10

Wed 22/12/10

48

Brickwork retaining walls, steps and paving 3 days works Mon 03/01/11

Wed 05/01/11

49

Install new entry gates

3 days

Thu 06/01/11

Mon 10/01/11

50

External works / Planting

3 days

Tue 11/01/11

Thu 13/01/11

51

Blockwork to externals / Remedials

5 days

Fri 14/01/11

Thu 20/01/11

52

Commisioning

2 days

Thu 21/01/10

Fri 22/01/10

37 days

Wed 01/12/10

Thu 20/01/11

09 W

T

F

S

S

07 Dec '09 M T W

T

F

S

S

53 54

Client fit out / Training

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 2

14 Dec '09 M T W

T

F

S

S

21 Dec '09 M T W

T

F

S

S

Proposed Office Building 28 Dec '09 M T W

T

F

S

S

04 Jan '10 M T W

T

F

S

S

11 Jan '10 M T W

T

F

S

S

18 Jan '10 M T W

T

F

S

S

25 Jan '10 M T W

T

F

S

S

04/01 04/01 04/01

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 3

01 Feb '10 M T W

T

F

S

S

08 Feb '10 M T W

T

F

S

S

Proposed Office Building 28 Dec '09 M T W

T

F

S

S

04 Jan '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

11 Jan '10 M T W

T

F

S

S

18 Jan '10 M T W

T

F

S

S

25 Jan '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 4

01 Feb '10 M T W

T

F

S

S

08 Feb '10 M T W

T

F

S

S

Proposed Office Building 15 Feb '10 M T W

T

F

S

S

22 Feb '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

01 Mar '10 M T W

T

F

S

S

08 Mar '10 M T W

T

F

S

S

15 Mar '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 5

22 Mar '10 M T W

T

F

S

S

29 Mar '10 M T W

T

F

S

S

Proposed Office Building 15 Feb '10 M T W

T

F

S

S

22 Feb '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

01 Mar '10 M T W

T

F

S

S

08 Mar '10 M T W

T

F

S

S

15 Mar '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 6

22 Mar '10 M T W

T

F

S

S

29 Mar '10 M T W

T

F

S

S

Proposed Office Building 05 Apr '10 M T W

T

F

S

S

12 Apr '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

19 Apr '10 M T W

T

F

S

S

26 Apr '10 M T W

T

F

S

S

03 May '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 7

10 May '10 M T W

T

F

S

S

17 May '10 M T W

T

F

S

S

Proposed Office Building 05 Apr '10 M T W

T

F

S

S

12 Apr '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

19 Apr '10 M T W

T

F

S

S

26 Apr '10 M T W

T

F

S

S

03 May '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 8

10 May '10 M T W

T

F

S

S

17 May '10 M T W

T

F

S

S

Proposed Office Building 24 May '10 M T W

T

F

S

S

31 May '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

07 Jun '10 M T W

T

F

S

S

14 Jun '10 M T W

T

F

S

S

21 Jun '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 9

28 Jun '10 M T W

T

F

S

S

05 Jul '10 M T W

T

F

S

S

Proposed Office Building 24 May '10 M T W

T

F

S

S

31 May '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

07 Jun '10 M T W

T

F

S

S

14 Jun '10 M T W

T

F

S

S

21 Jun '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 10

28 Jun '10 M T W

T

F

S

S

05 Jul '10 M T W

T

F

S

S

Proposed Office Building 12 Jul '10 M T W

T

F

S

S

19 Jul '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

26 Jul '10 M T W

T

F

S

S

02 Aug '10 M T W

T

F

S

S

09 Aug '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 11

16 Aug '10 M T W

T

F

S

S

23 Aug '10 M T W

T

F

S

S

Proposed Office Building 12 Jul '10 M T W

T

F

S

S

19 Jul '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

26 Jul '10 M T W

T

F

S

S

02 Aug '10 M T W

T

F

S

S

09 Aug '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 12

16 Aug '10 M T W

T

F

S

S

23 Aug '10 M T W

T

F

S

S

Proposed Office Building 30 Aug '10 M T W

T

F

S

S

06 Sep '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

13 Sep '10 M T W

T

F

S

S

20 Sep '10 M T W

T

F

S

S

27 Sep '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 13

04 Oct '10 M T W

T

F

S

S

11 Oct '10 M T W

T

F

S

S

Proposed Office Building 30 Aug '10 M T W

T

F

S

S

06 Sep '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

13 Sep '10 M T W

T

F

S

S

20 Sep '10 M T W

T

F

S

S

27 Sep '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 14

04 Oct '10 M T W

T

F

S

S

11 Oct '10 M T W

T

F

S

S

Proposed Office Building 18 Oct '10 M T W

T

F

S

S

25 Oct '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

01 Nov '10 M T W

T

F

S

S

08 Nov '10 M T W

T

F

S

S

15 Nov '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 15

22 Nov '10 M T W

T

F

S

S

29 Nov '10 M T W

T

F

S

S

Proposed Office Building 18 Oct '10 M T W

T

F

S

S

25 Oct '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

01 Nov '10 M T W

T

F

S

S

08 Nov '10 M T W

T

F

S

S

15 Nov '10 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 16

22 Nov '10 M T W

T

F

S

S

29 Nov '10 M T W

T

F

S

S

Proposed Office Building 06 Dec '10 M T W

T

F

S

S

13 Dec '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

20 Dec '10 M T W

T

F

S

S

27 Dec '10 M T W

T

F

S

S

03 Jan '11 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 17

10 Jan '11 M T W

T

F

S

S

17 Jan '11 M T W

T

F

S

S

Proposed Office Building 06 Dec '10 M T W

T

F

S

S

13 Dec '10 M T W

Project: Proposed Office & Amenity Bl Date: Wed 02/12/09

T

F

S

S

20 Dec '10 M T W

T

F

S

S

27 Dec '10 M T W

T

F

S

S

03 Jan '11 M T W

T

F

S

S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 18

10 Jan '11 M T W

T

F

S

S

17 Jan '11 M T W

T

F

S

S

Related Documents

Microsoft Office
December 2019 45
Microsoft Office
November 2019 48
Microsoft Office
November 2019 47
Office Project
April 2020 2
Office Project
May 2020 3

More Documents from ""