METRO’s Historical Contract – March 4, 2009 – Contract Value $1.46 B
FTA – March 23, 2009
Magaziner Cost Estimates – METRO’s Finance Plan ??
What is METRO’s Finance Plan? Description Total
North Corridor Southeast Corridor (FTA) (FTA) $896,797,000
$911,211,000
Cost per mile
$170,493726
$148,405,000
Length
5.26 miles
6.14 miles
Appox Cost @ $159 mil per mile Total Contract if @ $159 mil per mile
East End (Metro 100%)
Uptown (Metro + Tir 2)
Total Corridor Facility
$159,449,000 3.31 miles
4.32 miles
$527.7 mil*
$688.82 mil* $3.0246 Billion
* Using N/SE cost per mile average ($159 million per mile) on East End, Uptown & University Alignments
Metro Historic Contract (March 4th) Total 4 Corridors $& Facilities: $1.46 Billion Magaziner’s cost estimates (April 6) Total 4 Corridors & Facilities: $3.03 Billion
+ University Alignment 11.04 miles @ $159 mil per mile = $1,755,360.00 (50% FTA Funding ??) Cost: $4.77 Billion Metro: $2.911 Billion ????(61%) FTA: $1.809 Billion ???? (39%)
Approx Total Cost of 5 Alignments $4.78 Billion
Finance Plan?
• What is the total annual debt service on $3 Billion in Metro Borrowing? • What is the annual Expense of operations and maintenance on 37 miles of Light Rapid Transit?
$ _____________Millions