Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

METHOD OF STATEMENT FOR BOX UP AND PIPE SLEEVE INSTALLATION

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

THAI POLYCONS PUBLIC COMPANY LIMITED CHEVRON THAILAND AVIATION CONSOLIDATION PROJECT TPOLY DOCUMENT NO. : TPOLY-MOS-30-100-00 REVISION : 00 TITLE : Box up and pipe sleeve installation

AUTHORISATION Prepared By:

Reviewed By:

Approved By:

Name:

Name:

Name:

M Ch i W Mr.Chaiya W.

Mr.Chawalit M Ch lit M M.

Mr.Chanwit M Ch it Ch Chaleoiad l id

M&E Project Engineer

M&E Project Manager

Project Manager

Signature:

Signature:

Signature:

Date:

Date:

Date:

NOTE :

Effective Date

Issue No.

A CONTROLLED copy is valid only if stamped "C" in red, Uncontrolled copy will Not be updated or amended. Please refer to a controlled copy or check for amendments before use.

AMENDMENT / RELEASE RECORD Issue No. Issue Type

Description

Effective Date

Approved By

Type of Issuing: "A" For Acknowledgement & Information & Reference "R" For Internal Review & Comment "C" F E l C t&A l "U" F U i d/ l i th i ti

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

CONTENT Subject

Page No.

1. General

1

2. Material

1

3. Equipment & Tool

2

4. Box up and pipe sleeve installation procedures

3

5. Quality Assurance

4

6. Appendix

5

6.1

Flow chart

6

6.2

Illustation.

8

63 6.3

D t il drawing Details d i off Box B up andd sleeve l installation i t ll ti

9

6.4

Schedule

11

6.5

Resources

15

6.5.1 Equipment schedule

16

6.5.2 Man Power schedule

19

6.6

Inspection and Test Plan

22

6.7

Check list of Work

24

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

METHOD STATEMENT FOR COLD WATER PIPE INSTALLATION AND TESTING

1. General This method statement is to describe the intended work method and control measures for the pipe sleeve installation which is carried out for this project.

2. Material 2.1

Material of Pipe Sleeve

Item

1 2 3

2.2

Description Black steel pipe Black iron wire Rebar 2-db mm.

Material of Box Up Item

1 2 3 4

Description Ply wood minimum of thickness is 5/16” (8 mm) Nail Black iron wire REBAR 2-DB MM.

Page 3

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

4. Box up and pipe sleeve installation Procedure 4.1Setting out Survey 4.1.1 From the survey, the issued drawings will be marked up detailing all containment location and proposed materials and equipment to be installed for approval. Actual commencement of the installation works would be agreed with the client and main parties, which would also depend on the working areas being made available. The installation system will be installed in accordance with the safety policy using plan and equipment to suit the application. 4.2 Check Location of working areas. 4.2.1 The working area will be cleared and being made available. 4.3 Installation 4.3.1 Project specification, all works/operations will be carried out in accordance with all proven methods and industry standards. 4.3.2 On completion of the installation, all of the location and position will be followed in the referential drawing 4.4 Inspection 4.4.1 Materials shall supply to the Consulting Engineer's for his approval certificates from the manufacturer, showing that the materials have been tested according to the relevant specification or standard. 4.4.2 The Project Engineer and supervisor will make the visual inspection of the location and position also others. Then request to the Consulting Engineer's inspector to inspected and approved. The Inspection must continuity in accordance with Approved M&E inspection check list to ensure that all sleeves or box up were immovable. And work properly. 4.4.3 If inspection or tests show defects, such defective work or material shall be replaced and Inspection and tests shall be repeated.

Page 3

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

3.Equipment and Tool Basic equipment for the mark will be as follows. Item

Equipment / Tool

1

Cutter

2

Pincers

3

Cut off machine for 14" cutting discs

4

Hammer

5

Saw

Page 2

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

5. Quality Assurance All works will conform to the standards set out. Material on site approval by DEC. the work procedu

corresponds with visual method of statement. The proposed inspection and test plans (ITP) are shown in the appendix.The proposed Inspection and Test Plans (ITP) are shown in the Appendix.

Page 4

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6. APPENDIX

Page 5

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.1 FLOW CHART

Page 6

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

FLOW CHART FOR BOX AND SLEEVE INSTALLATION

Page 7

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.2 ILLUSTRATION

Page 8

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.3 DETAILS DRAWING OF BOX UP AND SLEEVE INSTALLATION

Page 9

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

Page 10

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.4 SCHEDULE

Page 11

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

Box up and Sleeve (Work Schedule) Item

Description

1 Water Treatment Plant (Pump Room) 1.1 Setting out survey 1.2 Check Location of working areas 1.3 Installation 1.4 Inspection

Item

Description

2 S,W,V System ground floor 2.1 Setting out survey 2.2 Check Location of working areas 2.3 Installation 2.4 Inspection 3 Cold Water Supply System ground floor 3.1 Setting out survey 3.2 Check Location of working areas 3.3 Installation 3.4 Inspection

Duration

Start

Finish

3 days 1 day 1 day 1 day 1 day

2/11/09 2/11/09 2/11/09 3/11/09 4/11/09

4/11/09 2/11/09 2/11/09 4/11/09 4/11/09

Duration

Start

Finish

3 days

3/1/10

5/1/10

3 days

10/1/10

12/1/10

Box up and sleeve schedule For November 2009 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Box up and sleeve schedule For January 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Page 12

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

Box up and Sleeve (Work Schedule) Item

Description

4 S,W,V System second floor 4.1 Setting out survey 4.2 Check Location of working areas 4.3 Installation 4.4 Inspection 5 Fire protection ground floor work 5.1 Setting out survey 5.2 Check Location of working areas 5.3 Installation 5.4 Inspection 6 Air conditioning system ground floor 6.1 Setting out survey 6.2 Check Location of working areas 6.3 Installation 6.4 Inspection Item

Description

7 Fire protection ground floor work (Pump Room) 7.1 Setting out survey 7.2 Check Location of working areas 7.3 Installation 7.4 Inspection

Duration

Start

Finish

3 days

10/1/10

12/1/10

3 days

10/1/10

12/1/10

3 days

10/1/10

12/1/10

Duration

Start

Finish

3 days

6/2/10

8/2/10

Box up and sleeve schedule For January 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Box up and sleeve schedule For Febuary 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Page 13

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

Box up and Sleeve (Work Schedule) Item

Description

Duration

Start

Finish

Item

Description

Duration

Start

Finish

3 days

10/2/10

12/2/10

3 days

10/2/10

12/2/10

3 days

25/1/10

27/1/10

2 days

1/2/10

2/2/10

8 Fire protection second floor work 8.1 Setting out survey 8.2 Check Location of working areas 8.3 Installation 8.4 Inspection 9 Cold Water Sypply System second floor 9.1 Setting out survey 9.2 Check Location of working areas 9.3 Installation 9.4 Inspection 10 Air conditioning system second floor 10.1 Setting out survey 10.2 Check Location of working areas 10.3 Installation 10.4 Inspection 11 Air conditioning system roof floor 11.1 Setting out survey 11.2 Check Location of working areas 11.3 Installation 11.4 Inspection

Box up and sleeve schedule Box up and sleeve schedule For Febuary 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Page 14

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.5 RESOURCES

Page 15

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.5 RESOURCES 6.5.1 Equipment Schedule Location 1. Water Treatment Plant (Pump Room) (1 Place) Item

Description

Cutter Pincers Cut Off Machine for 14" Cutting Discs Hammer Fishing Line Steel tape Saw Total Location 2. Cold Water Supply System ground floor 3. S,W,V System second floor 4 .Fire protection ground floor work 5. Air conditioning system ground floor (4 Places) a b c d e f g

Item a b c d e f g

1 2 1 3 1 1 1 3 1 11

3 1 3 1 1 1 3 1 11

Box up and sleeve schedule For November 2009 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 3 1 1 1 3 1 11

Description Cutter Pincers Cut Off Machine for 14" Cutting Discs Hammer Fishing Line Steel tape Saw

1 2 3 4 5 6 7 8 9 10 4 12 1 4 4 12 2 39

11 4 12 1 4 4 12 2 39

Box up and sleeve schedule For December 2009 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 4 12 1 4 4 12 2 39 Page 16

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

7.1 RESOURCES 6.5.1 Equipment Schedule (cont.) Location 6. S,W,V System ground floor (1Place) Item a b c d e f g

Description Cutter Pincers Cut Off Machine for 14" Cutting Discs Hammer Fishing Line Steel tape Saw

1 2 3 1 3 1 1 1 3 1 11

4 1 3 1 1 1 3 1 11

Box up and sleeve schedule For January 2010 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 3 1 1 1 3 1 11

Location 7. Fire protection ground floor work (Pump Room) (1 Place) Item a b c d e f g

Description Cutter Pincers Cut Off Machine for 14" Cutting Discs Hammer Fishing Line Steel tape Saw

1 2 3 4 5 6 1 3 1 1 1 3 1 11

7 1 3 1 1 1 3 1 11

Box up and sleeve schedule For Febuary 2010 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 3 1 1 1 3 1 11

Page 17

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.5 RESOURCES 6.5.1 Equipment Schedule (cont.) Location 8. Fire protection second floor work 9. Cold Water Sypply System second floor 10. Air conditioning system second floor (3 Places) Item a b c d e f g

Description Cutter Pincers Cut Off Machine for 14" Cutting Discs Hammer Fishing Line Steel tape Saw

1 2 3 4 5 6 7 8 9 10 3 9 1 3 3 9 2 30

11 3 9 1 3 3 9 2 30

Box up and sleeve schedule For Febuary 2010 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 3 9 1 3 3 9 2 30

Location 11.Air conditioning system roof floor (1 place) Item a b c d e f g

Description Cutter Pincers Cut Off Machine for 14" Cutting Discs Hammer Fishing Line Steel tape Saw

Box up and sleeve schedule For Febuary 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 1 3 3 1 1 1 1 1 1 3 3 1 1 10 10

Page 18

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.5 RESOURCES (Cont.) 6.5.2 Man Power Schedule Location 1. Water Treatment Plant (Pump Room) (1 Place) Item

a b c d e

Description Manpower Project Engineer M&E Super Visor Headman General labour Safety Officer Total

Box up and sleeve schedule For November 2009 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 1 1 3 1 7

1 1 1 3 1 7

1 1 1 3 1 7

Location 2. Cold Water Supply System ground floor 3. S,W,V System second floor 4 .Fire protection ground floor work 5. Air conditioning system ground floor (4 Places) Item a b c d e

Description Project Engineer M&E Super Visor Headman General labour Safety Officer

1 2 3 4 5 6 7 8 9 10 1 1 2 12 1 17

11 1 1 2 12 1 17

Box up and sleeve schedule For December 2009 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 1 2 12 1 17

Page 19

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.5 RESOURCES (Cont.) 6.5.2 Manpower Schedule (cont.) Location 6. S,W,V System ground floor (1Place) Item

a b c d e

Description

Box up and sleeve schedule For January 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Manpower Project Engineer M&E Super Visor Headman General labour Safety Officer

1 1 1 3 1 7

1 1 1 3 1 7

1 1 1 3 1 7

Location 7. Fire protection ground floor work (Pump Room) (1 Place) Item a b c d e

Description Project Engineer M&E Super Visor Headman General labour Safety Officer

1 2 3 4 5 6 1 1 1 3 1 7

7 1 1 1 3 1 7

Box up and sleeve schedule For Febuary 2010 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 1 1 3 1 7

Page 20

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

7.1 RESOURCES (Cont.) 7.1.2 Manpower Schedule Location 8. Fire protection second floor work 9. Cold Water Sypply System second floor 10. Air conditioning system second floor (3 Places) Item a b c d e

Description Project Engineer M&E Super Visor Headman d General labour Safety Officer

1 2 3 4 5 6 7 8 9 10 1 1 1 9 1 13

11 1 1 1 9 1 13

Box up and sleeve schedule For Febuary 2010 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 1 1 9 1 13

Location 11.Air conditioning system roof floor (1 place) Item a b c d e

Description Project Engineer M&E Super Visor Headman General labour Safety Officer

Box up and sleeve schedule For Febuary 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 1 3 3 1 1 1 1 1 1 7 7

Page 21

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.6 INSPECTION AND TEST PLAN

Page 22

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

6.7 CHECK LIST OF WORK

Page 24

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

Check List for Box Up and Pipe Sleeve Installation Location

Doc No.:

: :

Date

TPOLY-CHV-M&E-0001-00

Specific Location : Attach Drawing No. : Check List Serial No. :

Purpose Of Inspection :

Electrical and Communication System

Air Conditioning and Ventilation System

Plumbing System

Compressed Air Supply System

Fire Protection System

Others

Remark Item

Criteria / Chk. Methood

Item Check

No. of Inspection Acceptable #1

#2

Not Acceptable Signature

Visual

1

Approved brand/make of material used

2

Location

Measure

3

Size And Dimension

Measure

4

All sleeves or box up is immovable.

Visual

5

Housekeeping

Visual

Above installation is acceptable Above installation is not acceptable

Note :

Prepared by:

Date:

Checked by:

(TPOLY Tech/Supervisor)

Verified by:

Date: (DEC Inspector)

Date: TPOLY Engineer

Approved by:

Date: DEC Engineer

Page 25

Project: Chevron Thailand Aviation Consolidation Owner: Chevron Thailand Exploration and Production Limited Consultant: Dynamic Engineering Consultant Contractor: Thai Polycons Public Company Limited

INSPECTION AND TEST PLAN FOR CHEVRON THAILAND AVIATION CONSOLIDATION PROJECT Inspection and test required Item

Reference

Description Test method

Frequency

Standard

Inspection and Test plan Acceptance Criteria

Specification

Quality record Form No.

Vender

Subcon

TPOLY

ERA

M&E

Box Up And Sleeve Installation

Symbol

H W/O

-Material : Black Steel Pipe

Manufacture'S Certificate

-Approved Before Use -Every Delivery

TIS

N/A

-Install Box Up And Sleeve

Measurement

Everytime

Method Visual

Chapter 7,8,19

Legend

As Specification

Symbol

N/A

N/A

I

I

Technical Specifications for the Aviation Consolidation Project Doc.No.5T0142/RFP/0066/MP/BKK

N/A

SI

I

I

TPOLY-CHV-M&E-0001-00

Legend

Mandatory Hold Point - Hold Unit Approved

D

Document or Record Required

Witness Point - Optional

SI

Subcontractor Inspection

W

Witness Point

I

Inspection

S

Surveillance Point - Random / Each Quantity