Master Scheduling And Rough-cut Capacity Planning

  • May 2020
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Master Scheduling And Rough-cut Capacity Planning as PDF for free.

More details

  • Words: 1,747
  • Pages: 7
Unit 3 Scheduling Operations

Chapter 12: Aggregate Planning Lesson 39- MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING Learning Objectives After reading this lesson you would be able to understand Master production plan Master schedule Rough cut capacity planning

Well, my friends, let’s get started. As we all very well know, the production plan represents a firm's aggregate measure of manufacturing output. Once this plan is made, it is the responsibility of marketing to sell it and production to implement it. To do so requires a desegregation of the production plan into individual products. Recall that the master production schedule (MPS) is a statement of how many finished items are to be produced. Typically the master schedule is developed for weekly time periods over 6-12 months horizon. An example of partial MPS is shown in figure 7.

1 A B

X Totals (Aggregate production plan)

2

3

200 10 150 0

4 200 19 0

75

5

6

7

8

350 120

75 75

60

500 800 350 600 280 750 420

300

FIGURE .7 A portion of a master production schedule Master scheduling is generally a complex problem, especially for products with large number of operations For example, in Dow Corning there are 12 MPS, who are responsible for scheduling 400 packed products over a 26-week time horizon. In process

industries with only a few different operations, master production scheduling is somewhat easier. In order to illustrate the basic concepts of master production scheduling and rough-cut capacity planning, let us turn to an example Developing a Master Schedule Let us suppose that Gulden’s management has decided to use the production plan in Table 8. Since the company produces two products, Golden Brew and Golden Delight,' the master scheduler must translate the aggregate production plan into a weekly schedule for each product. Gulden’s beer is produced in cases of twenty-four 16-ounce cans (3 gallons). Each barrel consists of 32 gallons; the product mix, which is determined by historical sales data, is relatively constant, a 70-30 percent split between Golden Brew and Golden Delight. With this information, we can project the monthly production for each product for the first 6 months is shown in Table 9.

Table 8 Alternate Production Inventory Plan MONTH PRODUCTION INVENTORY Jan Feb Mar April May June July August Sept Oct Nov Dec

1500 1500 1500 2800 2800 2800 2800 2800 2200 2200 2200 1500

1000 1500 1100 1300 1300 1000 600 4000 600 1800 2200 1500

LOST SALES 0 0 0 0 0 0 0 0 0 0 0 0

CUMULATIVE PRODUCTION 2500 4000 5500 8300 11100 13900 16700 19500 21700 23900 26100 2700

Table 9 AGGREGATE PRODUCTION MONTH

January

BARRELS 1500

PRODUCT MIX

GOLDEN BREW CASES (CASES) 16,000 11,200

GOLDEN DELIGHT (CASES) " 4800

February

1500

16,000

11,200

4800

Average Weekly Production Requirements for Golden Breweries WEEK 1500 16,000 11,200 4800 2800 29,867 20,907 8960 2800 29,867 20,907 8960 2800 29,867 20,907 8960 2800 29,867 20,907 8960

March April May June July

A Master Schedule for Golden Breweries

To simplify our calculations, we assume there are 4 weeks in each month. Then the average weekly production required is given in Table 10. At Gulden’s plant, only one product at a time can be produced, since they share common facilities such as mixing equipment, bottling, capping, and case packing. Using a master schedule as determined by Table 10 would probably not be economical, since there would be frequent changeovers of products and thus high setup costs. One method of reducing the number of product changeovers is to produce in large batch sizes. Table 11shows a possible master schedule in which products are alternated on a weekly basis. Table 12 A Feasible Master Production Schedule for Golden Breweries We have not determined whether there is sufficient capacity available on a short-term basis to be able to achieve this schedule. We previously stated that under normal conditions, the plant has a capacity of 2200 barrels per month, or 5867 cases per week. With overtime, the capacity can be increased) to 2800 barrels per month, or 7467 cases per week. These restrictions are due to the physical limitations of the production equipment. From Table 11, we see that up to week 12, we are able to produce within capacity. Beyond this, the planned schedule for Golden Brew cannot be achieved within PROD UCT Golden Brew

1 2

3

4

2800 2800 2800 2800

5

6

7

' \ 2800 2800 2800 2800

8

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 2800 2800 2800 2800

5227 522 522 522 522 522 522 522 522 522 5227 7 7 7 7 7 7 7 7 7

Golden

1200 120 120 1200 1200 12 120 120 129 120 2240 224 224 224 224 224 224 224 224 224 1200 0 0 1200 00 0 0 0 0 2240 0 0 0 0 0 0 0 0 0 the limitation of 7467 cases per week. We would therefore say that this master

Delight

Table 10

PROD UCT Golde n Brew

1

2

3

4

5

6

7

8

9

560 0 5600 0 5600 0 5600 0 5600 0

1 11 12 13 14 15 16 17 18 19 20 21 22 23 0

0 5600

0 746 7

0

597 746 746 4 1 7

Golde n Deligh 0 149 0 2400 0 2400 0 2400 0 2400 0 2400 0 7467 t 3892 3 Table 12 A feasible Master Schedule for Golden Breweries

0

0

0 5974

74 746 67 7

746 1493 0 7

0

0

597 4

746 149 7 3

WEEK PRO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 DUCT Golde n 10,45 0 560 0 0 0 0 0 10,454 0 10,454 0 10,454 0 10,45 Brew 0 5600 0 5600 4 10,454 0 5600' 5600 5600 Golde n Deligh 0 0 240 0 0 0 2400 0 2400 0 2400 0 0 4480 0 4480 0 4480 0 4 t 2400 2400 0 4480 4480 Schedule is infeasible. This is the essence of rough-cut capacity planning-namely, determining if a master schedule is feasible with respect to capacity limitations. If not, then the master scheduler must revise the MPS to stay within capacity constraints. In some cases, it may even be necessary to revise the aggregate production plan. Table 12 shows a feasible master schedule, developed by trial and error, which. meets the capacity limitations in each month. Note that as in Table 11, two product changeovers each month must be made. For example, in weeks 14 and 15, Golden Delight will be produced and. early in week 15, a changeover will be made to Golden Brew. This will be produced until week 18, when a changeover to Golden Delight will be made, and so on. It is a good idea to check planned inventory levels in relation to an MPS. We may use Equation 1 on a weekly basis to do this. Equation 1 = Beginning inventory +Production – Projected sales – ending inventory. Using the projected demand from Table 13 and translating this into cases per week, we arrive at Table 14., which shows the projected short-term fluctuations in Inventory for both products and can be used in assessing the feasibility of the master schedule from the viewpoint of safety stock.

Table 13 Demand forecast for Golden Breweries. e Month Jan Feb Mar April May June July August Sept Oct Nov Dec

Demand ( Barrels) 1500 !000 1900 2600 2800 3100 3200 3000 2000 1000 1800 2200 26100

Cumulative Demand 1500 2500 4400 7000 9800 12900 16100 19100 21100 22100 23900 26100

Inventory Analysis for Golden Breweries' Master Production Schedule GOLDEN BREW GOLDEN DELIGHT PRODUCT INVENTOR DEMAN PRODUCTI WEEK DEMAND INVENTORY. ION Y. D ON 1 2800 5600 10,267 1200 0 2000 2 2800 0 7,467 2400 3200 1200 3 2800 5600 10,267 1200 0 2000 2400 4 2800 0 7,467 1200 3200 5 1867 5600 11,200 800 0 2400 6 1867 0 9,333 800 2400 4000 7 1867 5600 13,066 800 0 3200 8 1867 0 11,199 800 2400 4800 1520 0 3280 9 3547 5600 13,252 10 3547 0 9,705 1520 2400 4.160 11 3547 5600 11,758 1520 0 2640 12 3547 0 8,211 1520 3892 5012 13 4853 7467 10,825 2080 0 2932 14 4853 0 5,972 2080 7467 8319 15 4853 5974 7,093 2080 1493 7732 16 4853 7467 9,707 2080 0 5652 17 5227 7467 11,947 2240 0 3412 18 5227 0 6,720 2240 7467 8639 19 5227 5974 7,467 2240 1493 7892 20 5227 7467 9,707 2240 0 5652 21 5787" 7467 11,387 f480 0 3172 22 5787 0 5,600 2480 7467 8159 23 5787 5974 5,787 2480 1493 7172 24 5787 7467 7,467 2480 0 4692 25 5973 7467 8,961 2560 0 2132 26 5973 0 2,988 2560 7467 7039 ,. .Initial inventory = 1000 barrels (7467 cases of Golden Brew and 3200 cases of Golden Delight) TABLE 14.

Using the Master Schedule It is clear from this simple example that master scheduling can be a complicated process. Let us summarize some of the observations we made through the Golden Breweries example. First, the master production schedule should relate to the aggregate production plan; that is, the planned monthly schedule

should equal the aggregate plan when totaled over all products. Second, rough-cut capacity planning assists the master scheduler in developing a feasible schedule by determining potential production bottlenecks. Often, the master schedule must be revised several times until it is feasible. Third, other ways of evaluating a master production schedule include the and cost of setups or product changeovers and short-term inventory fluctuations. The master schedule is important, since it forms the basis for future production-planning activities. Therefore, it must be adaptive to changes in the environment. Seldom will forecasted demands be realized or production plans be adhered to perfectly. As each week passes, operations managers must compare scheduled production with actual results. This may result in changes to the MPS-master scheduling is a full time job! Too many changes, however, indicate that master scheduling is not being performed correctly and can result in poor productivity and low levels of customer service. With that, we have come to the end of today’s discussions. I hope it has been an enriching and satisfying experience. See you around in the next lecture. Take care. Bye.

Related Documents