PROJECT NAME:
KALBARYUHAN 16th & 17th of April, 2019
DATE OF PRODUCTION: Director:
Jay Manoos
Below is my suggested timetable for the upcoming project.
TIMETABLE DATE February 25 – March 2
DESCRIPTION Casting, Locked Script, Location, Final Crew List st 1 week of March (4, Monday to Saturday) Script Reading, Workshop of Cast. (location and time to be discussed) nd 2 week of March (11 - 16) Rehearsal of Cast (location and time to be discussed) rd 3 week of March (18 - 22) Rehearsal of Cast and Crew Production Design + Start of Dubbing (location and time to be discussed) th 4 week of March (25 – 30) Priority Dubbing st 1 week of April (1 – 7) Rest Day of Cast, Set Design and Props making for crew. Finalizing Lights. Equipment. nd 2 week of April (8 – 12) General Production April 15 Company Call April 16 evening 1st act April 17 morning 2nd act