Janno Estimate

  • November 2019
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Janno Estimate as PDF for free.

More details

  • Words: 886
  • Pages: 10
A. COST ESTIMATE ITEM I.

II.

III.

IV.

QTY

UNIT

DESCRIPTION GENERAL REQUIREMENTS 1. Arch./ Eng'g.Documents 2. Permits, bonds and licences 3. Power & Water consumption 4. Workers pass 5. Temporary facilities 6. Mobilization / Demobilization SUBTOTAL I SITE CONSTRUCTION 1. Site preparation a. Clearing & grubbing b. Layout & staking 2. Earthworks a. Excavation b. Backfill c. Earthfill d. Gravel fill 3. Septic tank systems 4. Drainage systems 5. Fences, gates & hardwares 6. Soil Poisoning 7. Landscape 8. Debris hauling SUBTOTAL II CONCRETE WORKS 1. Concrete works 2. Formworks & Scaffolds 3. Reinforcement SUBTOTAL III MASONRY WORKS 1. Perimeter walls 2. Partition walls

UNIT COST MATERIAL LABOR

AMOUNT

included verify verify verify 45,000.00 included 45,000.00

220.00 92.87

s.m. s.m.

22.00 24.20 139.31 9.29 2.00 1.00

c.m. c.m. c.m. c.m. lot lot

750.00 25,000.00 30,000.00

77.91 1.00 2,375.00

c.m. lot kg

2,500.00 165,000.00 32.00

600.00

220.00 44.00

s.m. s.m.

500.00 500.00

65.00 65.00

50.00

50.00 50.00

11,000.00 9,287.00

350.00 250.00 250.00

7,700.00 6,050.00 34,826.25 6,965.25 50,000.00 30,000.00 not included not included not included included 155,828.50

8.00

241,521.00 165,000.00 95,000.00 501,521.00

124,300.00 24,860.00

SUBTOTAL IV V.

VI.

VII.

VIII.

IX.

X.

XI.

149,160.00

METAL WORKS 1. Stair railing 2. Trusses SUBTOTAL V

not included not included

WOODS & PLASTICS 1 . Closets & cabinets 2. Ceiling works (boards and nailers) SUBTOTAL VI

not included not included

THERMAL & MOISTURE PROT. 1. Corr.G.I. sht.Ga.#26 & accessories 2. Roof insulation 3. Water proofing SUBTOTAL VII

not included not included not included

DOORS & WINDOWS 1. Doors 2. Windows SUBTOTAL VIII

not included not included

FINISHES 1. Tileworks 2. Plastering works 3. Painting works SUBTOTAL IX

not included not included not included

PLUMBING WORKS 1. Piping 2. Plumbing Fixtures SUBTOTAL X ELECTRICAL WORKS 1. Roughing - in / wiring 2. Electrical Fixtures 3. Telephone & intercommunication

1.00

lot

38,450.00

19,500.00

57,950.00 not included 57,950.00

1.00

lot

37,775.00

25,265.00

63,040.00 not included

equipment SUBTOTAL XI TOTAL DIRECT COST Overhead / Supervision Contingencies TOTAL INDIRECT COST GRAND TOTAL

not included 63,040.00 972,499.50 116,699.94 82,662.46 199,362.40 1,171,861.90

45,000.00

350.00 250.00 750.00 25,000.00 30,000.00

35,000.00

165,000.00 95,000.00

duplex single

BILL OF MATERIALS ITEM

DESCRIPTION SITE CONSTRUCTION 1. Site preparation a. Clearing & grubbing b. Layout & staking 2. Earthworks a. excavation b. earthfill c. back fill d. gravel fill 3. Septic tank systems 4. Drainage systems 5. debris hauling 6. soil poisoning SUBTOTAL CONCRETE WORKS 1. Concrete works a. Footing b. Column c. Slab on fill 2. Formworks & Scaffolds 3. Reinforcement a. Footing (15-10mm rebars ) b. Column ( 4-10mm) c. Slab on fill SUBTOTAL MASONRY WORKS 1. Perimeter walls 2. Partition walls

QTY

UNIT

220.00 92.87

s.m. s.m.

22.00 24.20 139.31 9.29 2.00 2.50 1.00

c.m. c.m. c.m. c.m. lot lot lot s.m.

UNIT COST MATERIAL LABOR

75.00

AMOUNT

50.00 50.00

11,000.00 11,608.75

350.00 250.00 250.00

7,700.00 6,050.00 34,826.25 6,965.25 50,000.00 75,000.00 35,000.00

750.00 25,000.00 30,000.00 10.00

238,150.25

9.9 4.32 396 1

220.00 44.00

c.m. c.m. c.m. lot kg. kg. kg. kg.

s.m. s.m.

500.00 500.00

65.00 65.00

124,300.00 24,860.00

SUBTOTAL METAL WORKS 1. Stair railing 2. trusses THERMAL & MOISTURE PROT. 1. Waterproofing DOORS & WINDOWS 1. Doors (door installation) 2. Windows (window installation) SUBTOTAL FINISHES 1. Tileworks(vynil & ceramic tiles) 2. Plastering works 3. Painting works SUBTOTAL ROOFING WORKS PLUMBING WORKS 1. Piping 2. Plumbing Fixtures SUBTOTAL ELECTRICAL WORKS 1. Roughing - in / wiring 2. Electrical Fixtures SUBTOTAL TOTAL COST

149,160.00 kg.

l.m l.m.

s.m. s.m. s.m. s.m.

COST ESTIMATE ITEM I

II

III

SCOPES OF WORKS

QTY

UNIT

UNIT COST Material Labor

TOTAL COST Material Labor

GENERAL REQUIREMENTS 1.0 Permits and licences 2.0 Mobilization and demobilization 3.0 Temfacil 4.0 Power & water 5.0 Worker's pass Sub total I SITE CONSTRUCTION 1.0 Site preparation a. Clearing & grubbing b. Layout & staking 2.0 Earthworks a. Excavation b. Gravel fill c. Backfill 3.0 Construction debris hauling 4.0 Scaffolds Sub total II

TOTAL AMOUNT verify verify verify verify verify

380.12 380.12

s.m. s.m.

206.20 38.01 257.75 1.00 1.00

c.m. c.m. c.m. lot lot

CONCRETE 1.0 Rebar works a. Column footing 2,033.96 b. Wall Footing ,ramp, steps on grade, 2,809.09 slab on fill c. Suspended slab & stair 7,832.86 d. Beams & Columns d25 bars 14,390.80 d16 bars 3,791.59 d10 bars 4,671.61 2.0 Concrete works a. Column footing 36.40 b. Wall Footing ,ramp, steps on grade, 57.02 slab on fill c. Suspended slab & stair 110.22

50.00 150.00

28,509.00

19,006.00 57,018.00

19,006.00 85,527.00

800.00

300.00 150.00 50.00

30,409.60 -

61,860.00 5,701.80 12,887.50

61,860.00 36,111.40 12,887.50 16,000.00 75,000.00 306,391.90

kg. kg. kg.

42.00 42.00 42.00

16.80 16.80 16.80

85,426.32 117,981.65 328,980.18

34,170.53 47,192.66 131,592.07

119,596.85 165,174.30 460,572.25

kg. kg. kg.

42.00 42.00 42.00

16.80 16.80 16.80

604,413.60 159,246.78 196,207.62

241,765.44 63,698.71 78,483.05

846,179.04 222,945.49 274,690.67

c.m. c.m. c.m.

3,750.00 3,750.00 3,750.00

300.00 300.00 300.00

136,500.00 213,817.50 413,319.38

10,920.00 17,105.40 33,065.55

147,420.00 230,922.90 446,384.93

75.00

d. Beams & Columns 3.0 Formworks a. Suspended slab & stair b. Beams & Columns 4.0 Miscellaneous concrete works Sub total III IV

MASONRY 1.0 verify wall material Sub total IV

89.89

c.m.

3,750.00

300.00

337,087.50

26,967.00

364,054.50

734.79 1,100.44 1.00

s.m. s.m. lot

200.00 200.00

250.00 250.00

146,958.00 220,088.00

183,697.50 275,110.00

330,655.50 495,198.00 22,000.00 4,125,794.43

s.m.

-

Note: quantity shown in red letters will vary if steel decking will be used for slabs.

Total Direct Cost

4,432,186.33

Related Documents

Janno Estimate
November 2019 19
Estimate
November 2019 38
Janno Resume
November 2019 7
Estimate
November 2019 29
Estimate
July 2020 20
Estimate
June 2020 17