Maintenance Projects
Routine Maintenance Routine Maintenance works which are being carried out include Grading, Pothole Patching, and Culvert Cleaning/Desilting, Drain/Ditch Cleaning, Grass Cutting and others.
Periodic Maintenance & Minor Works IDA Projects Of the 28 IDA funded projects that started in 2002, 24 have been completed, and four terminated for non-performance. The four terminated projects have been reawarded and are progressing steadily. KfW Projects Two projects are substantially completed. These are Mankranso – Tepa and Sunyani – Ntotroso –Acherensua, road projects. Works on the remaining projects are going on steadily. The details of the progress of works are shown below: Status of KFW Funded Projects Name of Contractor
Start Date
Completion Date
% Completion
Upgrading of Mankranso – P&W Ghanem Tepa Road (45.1km) Ltd.
2-Jan-02
31-Dec-05
100%
Substantially completed.
Upgrading of Bekwai-Ejusu Ussuya(GH)/J. Kuntunase Road (38.7) Adom J.V
12 Mar. 02
31-Jul-06
95.91%
Works almost completed.
Rehabilitation of Wenchi Bamboi Road (51.7km)
P&W Ghanem Ltd.
30-Oct-02
31-Jul-06
76.8%
Works progressing steadily.
Upgrading of SunyaniUssuya(GH)/J. Ntotroso-Acherensua Road Adom J.V (47.8km)
16 Oct. 02
30-Jun-06
100%
Substantially completed.
3-Oct-02
31-Jul-06
62%
Works progressing steadily.
16 Oct. 02
31-Jul-06
85%
Works progressing steadily.
Contract Name
Regravelling of AframsoSekyedumase-Nkoranza Road (57.6km)
Ussuya(GH)/J.Ad om J.V
Regravelling of Ejura Nkoranza Road (50.4km)
P&W GhanemLtd.
Source: GHA Road Maintenance Division
Remarks
The KFW funding for the project ended on 31st July, 2006. The outstanding works are being executed with GoG funding. GHA has also taken over the supervision of the projects from Kocks Consult GMBH.
GOG (Road Fund & Consolidated Fund) Projects Currently there are three hundred and two on-going Road Fund/GoG projects. The breakdown into various activities is as below: Breakdown of Maintenance Activities No. of Projects
Length (km)
Regravelling
22
332.00
Resurfacing (Partial Reconstruction)
17
207.66
Resealing
10
179.00
Upgrading
99
793.45
Town Roads
40
99.72
-
-
Drainage Structures
104
-
Miscellanous Works Total
10 302
1611.83
Activity
Asphalt Overlay
Source: GHA Road Maintenance Division